IR 05000369/1990019
| ML20058A301 | |
| Person / Time | |
|---|---|
| Site: | McGuire, Mcguire |
| Issue date: | 10/04/1990 |
| From: | Blake J, Newsome R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML20058A296 | List: |
| References | |
| 50-369-90-19, 50-370-90-19, NUDOCS 9010250391 | |
| Download: ML20058A301 (10) | |
Text
W9:: }p
-
y.
g vy
'
}
a-3:.
'
a r
,,
.
.
,
a
..
s
,
..
.
,
,-i V~ 8,7 [
p,';
.,
'
Sm na!f-7 '
LNITE3 STATES.
+'
.
NUCLEAR REGULATORY COMMIS$10N
,
-
REGION 11
'.;'c f
'
',.
'i,,;f =
'
101 MARIETTA STREET,N.W.
,
,
,
' '
!
- ATLANTA, GEORGIA 30323 -
%
-
'
.
y(, *****
,
,
.
,
,
.
,
'
"
,7n s
i
'
i ts y
_
,
- p A-
.,
-
,..
_
Report Nos.:. 50-369/90-19 and 50-370/90-19
,
s
,
,
j'
Licensee: _. Duke Power Company
,
422' South Church Street y
/ Charlotte, NC = 28242 Docket Nos.: <50-369 and 50-370'
License'Nos.: 'NPF-9 and NPF-17.
Facility Namei McGuire l'and 2'
-
'
-Inspection Conducted:
September 24-28, 1990
'
taf /
Inspectors:[R.
<< eu <-
/4-3 - 90 (
'Date Signed ews e
,
. Approved by:
do u-
.
'J J/ Blake, Chief
,
Date Signed.
tgrial:r and Processes Section
,
. ngineering Branch--
l
Division of Reactor Safety
+
SUMMARY Scope
.;
..
This' routine,> announced: inspection was conducted on-site in.the' areas --of-
Inservice Inspection- (ISI).
The inspection included a review of the ~ISI
Jprogram..and ' the Unit 1 2-' inspection plan for this : outage;- reviews of
't nondestructive examination(NDE) procedures; observations of in-progress 'NDE
!
examinations; independent examination verifications; reviews of NDE personnel
qualifications; reviews-of NDE material certification documentation; and, a
.j review 'of completed NDE examination data.
Also, previously opened NRC items
-)
.
_
i were addressed.
'
Results-
"
'
In the areas' inspected, violations or deviations were not identified.
i All ~ areas -inspected' -indicated adequate control and implementation of the inservice inspection program.
,
r 9010250391 901010 ADOCK0500g9 DR
'
,,
...
.i
,
,
.
.
--
y
-
=
.
,
y
.<
-
,
.,.
'
<
,
I.'
Y
!
REPORT DETAILS
- i ip
1.
Persons Contacted-
-
!
Licensee Employees J.Baumann, Supervisor,EddyCurrent(EC) Examination
,
- S. Carter, Outage Maintenance Coordinator
- G. Gilbert, Superintendent, Technical Services
- W. Goodman, Quality Assurance (QA) Technical Support Manager L. Keith, QA/ISI
- M. Kimray, Integrated Scheduling, Outage Manager
- L. Kunka, Compliance Engineer
- R. Sharpe, Manager, Compliance Other -licensee employees contacted during this inspection included
[
craf tsmen, engineers. -technicians, and administrative personnel.
q NRC Resident Inspectors
,
K. Van Doorn, Senior Resident Inspector
- S. Vias, Resident Inspector I
- Attended exit interview Acronyms and initialisms used throughout this ' report are-listed in the last paragraph..
-
2.
Inservice Inspection The inspector observed examination activities and reviewed documents and records as indicated below, +.o determine whether 'ISI.was being conducted-in accordance with applicable procedures, regulatory requirements, and ~
licensee commitments. The. applicable code for ISI is the American Society of Mechanical Engineers Boiler and Pressure Vessei (ASME B&PV) Code,Section XI,1980 -edition with addenda through Winter 1980.
Duke Power Company (DPC) NDE personnel are performing the NDE examinations except Eddy Current examinations.
Both Babcock and Wilcox (B&W)- and DPC personnel are collecting the Steam Generator -(SG) tubing eddy current
- examination data with B&W personnel performing the primary data analysis and DPC personnel performing a secondary data-evaluation.
a.
ISI Program Review, Units 1 and 2 (73051)
,
The' inspector reviewed the following documents relating to the ISI program to determine whether the plan had been approved by the licensee and to assure that procedures and plans had been established
.-
a
.
D a
,
,,
,..
(
2:
i j
<
'(written, reviewed.. approved and. issued) to control and accomplish a
-
the following applicable. activities:
organizational structure'
.
'
including qualifications,-' training, - responsibilities. and duties of personnel responsible for ISI; audits including procedures, frequency.. and-qualification of personnel; general quality assurance.
requirements including examination reports,- deviations from-
.
previously. established program, material certifications, and.
'
identification of L components to be covered; work and inspection procedures; control of processes including suitably controlled work conditions, special methods, and use of qualified personnel;
-
corrective action; document control; control of examination equipment; quality records including documentation of indications and NDE findings, review of documentation, provisions to assure.
a
-
legibility and retrievability, and corrective action; scope of the inspection including description of areas to be examined, examination category, method of inspection, extent of examinations. and justifi-
<
cation for any exception; definition. of inspection interval and-o extent of e'xamination; qualification of NDE personnel; and, controls-i of generation,- approval, custody, storage and maintenance of' NDE i
records.
Inservice Inspection Plan McGuire Nuclear Station
-
Unit 2, Refueling Outage #6, Revision 12 QCL-5 (R11)
Control Of Preservice And Inservice
-
Inspection Activities QAB-1(R29)
Control Of Measuring And Test Equipment And
-
Calibration Standards NDE-B-(R16)
Training, Qualification And Certification Of
-
NDE Personnel b.
Review of NDE Procedures, Units 1 and 2 (73052)
(1) The inspector reviewed the procedures listed below to. determine
>
whether these procedures were consistent with regulatory
!
requirements and licensee commitments. The procedures were also l
. reviewed in the areas of procedure approval, requirements for
'
qualification of NDE personnel, and compilation of required-records; and, if. applicable, division.of responsibility between
- the licensee and contractor personnel if contractor personnel are involved in the ISI effort.
l
-
L
'
i
[\\
,
%
,
i
]
7."
,
,
t f
1-
- :
.
,b
.
3"
.I51-119(R12)
Ultrasonic Examination Of Stainless:
-
'
Steel And Nickel-Base Alloy Weld Seams.
1S1-120(R25)
Ultrasonic Examination Of Pipe And
-
with CA-CAT-90-001 Vessel Welds Joining Similar And-Dissimilar Materials NDE-35(R13)
Liquid Penetrant Examination.
-
NDE-25 (R14)
Magnetic Particle Examination
-
Procedure And Techniques NDE-12(R8)
General Radiography Procedure For
-
Preservice And Inservice Inspection QCL-14 (RIO)
ISI Visual Examination, VT-3 And VT-4
-
I QAL-16(R9)
Procedure For The Inspection Of ASME.
o
-
Section XI Field Piping Welds Eddy Current Analysis Guidelines For McGuire Nuclear
-
-
Station Unit 2, (RI)
,
l All procedures listed above have been reviewed during previous NRC inspections.
Only current revisions were reviewed during
]
this inspection.
'
(2) The inspector reviewed ~ the Ultrasonic procedures to ascertain whether they had been reviewed and approved in accordance with y
the licensee'_s established QA procedures.
The procedures were also reviewed for technical adequacy and conformance with ASME,Section V, Article 5 and other licensee commitments / requirements in the following areas:
type of apparatus used; extent of f
coverage 'of weldment; calibration requirements; search units; j
beam angles; DAC curves; reference level for monitoring
discontinuities; method for demonstrating penetration; limits i
for evaluating and recording indications; recording significant
!
'
indications; and, acceptance limits.
(3) The inspector reviewed the Liquid Penetrant procedure to ascertain whether it had been reviewed and approved in accordance with the licensee's established QA procedures.
The procedures were also ' reviewed for technical adequacy and conformance with ASME,Section V, Article 6, and other licensee
'
requirements in the following areas:
specified method;
'
penetrant material identification; penetrant materials analyzed for sulfur; penetrant materials analyzed for total halogens; surface temperature; acceptable pre-examination surface conditioning; method used for pre-examination surface cleaning; surface drying time prior to penetrant application; method of t-t
y
- - -
-
,
,
u
,
L
.:
'-
- ' '
,
,
- j
?
penetrant-application; penetrant dwell time; method"used for f
excess penetrant ~_ removal; surface drying prior _- to developer
~
application, if applicable; -type of developer; examination
technique; evaluation techniques; and, procedure-requalification.
-(4) The inspector reviewed the Magnetic Particle procedure to ascertain whether it had been reviewed and approved in accordance with the licensee's established QA procedures; 'The
,
procedure was reviewed for technical adequacy and' for.
.conformance with the ASME Code Section V, Article 7, and other licensee commitments / requirements in the following areas:
examination methods; contrast of dry powder particle color. with l
-
background; surface temperature; suspension medium and surface temperature requirement for wet Iarticles; viewing conditions;-
examination overlap and directiols; pole or prod spacing;
current or lif ting power (yoke); ind, acceptance criteria, j
(5) The inspector reviewed the Radiocraphic procedure to determine whether it contained sufficient Information to assure that the following -parameters were specif sed and controlled within the limits permitted by the applirable code, or any other specification requirement:
type of material to be radiographed;
. material and weld surface condition requirements; type of.
radiation source, effective focal spot or effective source size; film brand or type; number of films in cassette; minimum source
,
to film distance; type and thickness of intensifying screens and filters; quality of radiographs; film density and contrast for single and composite viewing; use of densitometers for assuring compliance with film density requirements; system of radiograph identification; use of location markers; methods of reducing and testing ~ for back-scatter; selection of penetrameters including penetrameter placement; number of' penetrameters; shimi under penetrameters; radiographic technique for double wall <iewing; and, evaluation and disposition of radiographs.
(6) The. inspector reviewed the Visual examination proceduret to determine whether they contained sufficient instructions to
- '
assure that the following parameters were specified and
controlled within the limits permitted by the applicable coac,
'
standard, or any other specification requirement:
method -
direct visual, remote visual or translucent visual; application
- hydrostatic testing, fabrication procedure, visual examination of welds, leak testing, etc.; how visual' examination is to be performed; type of surface condition available; method or implement used for surface preparation, if any; whether-direct or remote -viewing is used; sequence of performing examination,
'
when applicable; data to be tabulated, if any; acceptance criteria is specified and consistent with the applicable code L
section or controlling specification; and, report form comple-tion.
l J
\\
u ~ f. [ ' 1 ~
l U
j
,
p:
c'(
j :
'
'
'(7): The inspector' reviewed the Eddy Current procedure for content relative to:
multichannel examination indication equipment is
-
specified, examination sensitivity,J method of examination, method of calibration and calibration. sequence, and acceptance criteria.
All procedures reviewed appeared to contain the necessary elements t
'
for conducting the specific examination.
r c.
-Observation of Work and Work Activities, Unit 2(73753)
The inspector-observed in-process examination activities. - conducted independent verification examinations, reviewed certification records of NDE materials, and reviewed NDE personnel qualifications-for personnel that had been utilized during the reauired ISI examinations
during this - outage.
The observations, independent examination verifications, and reviews _ conducted by the inspector are documented-below.
(1) The_ inspector observed calibration activities and the in-process
,
ultrasonic (UT) ~ examinations being conducted on 4 Main Steam System welds.
These observations were compared. with. the
.
applicable procedures and the ASME B&PV Code in the following areas: availability of and compliance with approved NDE procedures;. use of knowledgeable ' NDE personnel;. use of NDE personnel qualified to the proper level; type of apparatus used; calibration requirements; scarch units; beam angles; DAC curves; reference. level for monitoring discontinuities; method of
demonstrating penetration; extent of weld / component examination
_
coverage; limits of evaluating and recording indications;-
recording significant indications; and, acceptance limits.
The inspector conducted an independent ultrasonic verification examination, using DPC equipment, on portions of 2 of the Main Steam. welds. previously observed being examined.
These examinations were conducted in order to evaluate the technical adequacy of the ultrasonic examination procedure being used by the licensee and to assess the validity of_the information being reported by the ultrasonic examiners.
,
The verification ultrasonic examinations conducted by the inspector indicated that the procedure being used to conduct the examinations is adequate and the verification examination results compared favorably with the information being reported by the ultrasonic examiners.
The following listed ultrasonic equipment and materials certification records were reviewed:
Ultrasonic Instruments 31501-875 and 1244 i
y
- 4 4 f
'l
'
'
a.
>
...
j
t
Ultrasonic Couplant Batch Number.8981 The inspector reviewed spectrum-analysis data for the ultrasonic transducers listed below:
'
Serial No.
Size
' Frequency i
E30938 IX1 2.25 MHz G12908
'lX1 2.25 MHz 32233 1"Dia.
2.25 MHz-K05231 1"Dia..
2.25 MHz (2) The inspector observed the in-process magnetic particle-(MT)
examinations of 4 Main Steam system circumferential pipe-welds.
The observhtions were compared-with the applicable procedures and the Code.-in the following areas:
examination methods; contrast of dry powder particle color with background; surface temperature; suspension medium for wet particles,-.if applicable; viewing conditions; examination overlap and directions; pole or
,
prod spacing; current or lifting power (yoke); and acceptance criteria.
The inspector conducted MT verification examinations, using DPC equipment, on portions of 2 of the welds previously observed i
being examined.
The examinations were conducted in order to evaluate the technical adequacy of the examination' procedure being used by the licensee to perform examinations and to assess.
the validity of the information being reported by the MT examiners.
The information reported by the MT examiners compared favorably with the verification examinations.
The inspector reviewed documentation indicating that a 10 pound l
lift test had been performed on magnetic particle alternating-
-
'
current yoke MCQA-2 The certification record for the lift. test plate that was used to conduct the test, MCQUA-26041, was:
reviewed to confirm the weight of the test plate.
A review of the magnetic particle material certification record for batch _ numbers 84E010 and 890030 indicated the particles met the applicable specifications requirements.
!
(3) The inspector evaluated 24 radiographic films for RHR Heat Exchanger weld 2RHR-2A-2-3, that had been radiographed under the-licensee's ISI program, in order to determine if the radiographic quality was.in accordance with the applicable procedure and ASME Code requirements and to specifically verify the following: penetrameter type, size, and placement; penetrameter sensitivity; film density and density variation;
'
y
- 77
,
>-
-t
.:
a
~
'
7-
e
? t.
k film ' identification; film quality; weld coverage; ~ and,=
,
'
disposition of the welds radiographed.
-(4) Steam Generator Tubing Eddy Current Examination The inspector observed the EC activities indicated below., The
observations were compared with the-' applicable procedures and the Code'in the following areas: ' method for maximum sensitive is applied; method of examination has been recorded;. examination equipment has been calibrated in accordance with'the applicable performance reference; amplitude and. phase angle have been calibrated with the proper. calibration reference and.is recalibrated at predetermined frequency; required coverage of
!
steam generator. tubes occurs during the examination; acceptance criteria is specified or referenced and is consistent with the procedure or the ASME Code; and, results are consistent'with the
-
acceptance criteria.
(a)
In-process tube-data acquisition, including calibration
. confirmation and tube location verifications, was observed for 29 SG-C tubes and 15 SG-D tubes.
r (b)
In-process eddy current data evaluation, including
',
calibration confirmation, was observed for 27 SG tubes.
Primary data-analysis, being conducted by B&W, was observed i
for 11 SG tubes. ' Secondary data analysis, being conducted-by DPC, was observed for 17 SG tubes.
!
(c)
In-process eddy current data evaluation resolution of differences in analysis for reported indications noted by the primary and secondary analysts was observed for 2 steam-generator C tubes.
The inspector co-evaluated' 12' of the SG tubes during the -
,
observations of the primary and secondary analysts evaluations, 10 in SG-C, and-2 in SG-D.
The sanple of evaluations, some having reportable indications and some with no reported indications, was conducted in order to confirm the validity of the reported tubing condition.
The co-evaluation 'analyris conducted by the inspector agreed well with the reported results.
Certification records for EC calibration standards Z-7590 and Z-7877 were reviewed for material type, correct fabrication, and artificial flaw location and size.
!
(5) The inspector reviewed personnel qualification documentation for 28;NDE personnel which included DPC and B&W EC data collection and'EC data evaluation personnel. These personnel qualifications were reviewed in the following areas:
employer's name; person certified; activity qualified to perform; CJrrent period of
.-
-
.-.
' ' *
sg
-. -
,r
.
?.1
,
. 8 g
i:
'
,
certification; signature of employer's desig'nated'
representative; basis used for certificatior; and, annual visual?
'
c acuity, color vision examination, and perionic recertification.
All personnel qualification documentation reviewed indicated that the examiners were qualified for the examinations -being conducted.
d.
Data Review and Evaluation,. Unit 1 (73755)~
(1)' Records of 52 completed ISI nondestructive examinations were selected and reviewed to ascertain whether:
the methods (s),
technique, and. extent of the examination complied with the ISI l
plan 'and, cpplicable NDE procedures; findings were properly j
-
recorded and evaluated by qualified personnel; programmatic j
deviations were recorded as required; personnel, instruments,
calibration blocks, and NDE materials (penetrants, ccuplants)
were designated.
(2) The inspector reviewed the eddy current data analysis results.
.
and a -sample of associated completed records for over 800 SG tubes,'. approximately 200 tubes from each of the four steam
generators.
The reviews were compared with the applicable
<
procedures and the ASME B&PV Code in the following areas:.the multichannel' eddy current examination equipment has' been identified; material permeability has been recorded; method of examination has been recorded; and, results are consistent with acceptance criteria.
'
All 'of the examination reports reviewed appeared to contain the-l required examination information including disposition of
'
indications,-if any.
'In the areas inspected,' violations or deviations were not identified.-
3.
Licensee Action on Previously Opened Items (Closed) Inspector Followup Item 50-369, 370/89-15-01, Walking In Cable Trays.
This item resulted from NRC inspectors observing plant personnel using cable. trays as pathways and subsequent discussions with those penonnel which indicated that not all plant personnel are cognizant of '.ianagement's position that using cable trays as a pathway is unacceptable.
The inspector reviewed documents and attendance sign in sheets which indicated that management had transmitted to plant personnel, through memorandum, bulletins, and standup. safety meetings, that the practice of using cable trays as pathways by plant personnel is unacceptable.
Based on the review of the above, this item is considered closed.
.
)
'
- p ;<.
L i:
'
,
'-
1.
_..
- L.
Exit Interview'
-
'
.The inspection scope-and results were summarized on September 28, 1990, with-those persons iidicated in paragraph 1.
The inspector described the areas inspected and discussed in detail the inspection.results.
Dissenting comments we.e not received from the licensee.
'
.5.
Acronyms and Initialisms American Society of Mechanical Engineers.
-
B&PV Boiler and Pressure Vessel'
-
B&W.
Babcoci: and Wilcox
-
Change Authorization-CA
-
,
Distance Amplitude Curve DAC
"
-
DIA Diameter
-
Duke Pover Company-DPC
-
Eddy Current EC
-
'
Inservics Inspection ISI
-
Megahertz MHz
-
Magnetic Particle
.MT
-
NDE Nondestructive Examination
-
Nuclear Regulatory Commission NRC
-
Quality Assurance.
-
R Revision
-
,
-
Steam Generator DSG -
-
UT Ultrasonic
-
VT.
Visual
-
i
,
m.
m m
..
.