IR 05000369/2023001
| ML23118A014 | |
| Person / Time | |
|---|---|
| Site: | McGuire, Mcguire |
| Issue date: | 05/01/2023 |
| From: | Eric Stamm Division Reactor Projects II |
| To: | Pigott E Duke Energy Carolinas |
| References | |
| IR 2023001 | |
| Download: ML23118A014 (12) | |
Text
SUBJECT:
MCGUIRE NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000369/2023001 AND 05000370/2023001
Dear Edward Pigott:
On March 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at McGuire Nuclear Station. On April 12, 2023, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Eric J. Stamm, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 05000369 and 05000370 License Nos. NPF-9 and NPF-17
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000369 and 05000370
License Numbers:
Report Numbers:
05000369/2023001 and 05000370/2023001
Enterprise Identifier: I-2023-001-0025
Licensee:
Duke Energy Carolinas, LLC
Facility:
McGuire Nuclear Station
Location:
Huntersville, North Carolina
Inspection Dates:
January 1, 2023, to March 31, 2023
Inspectors:
C. Safouri, Senior Resident Inspector
F. Young, Resident Inspector
D. Ray, Reactor Inspector
M. Schwieg, Senior Reactor Inspector
Approved By:
Eric J. Stamm, Chief
Reactor Projects Branch 1
Division of Reactor Projects
Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at McGuire Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 1 operated at or near 100 percent rated thermal power (RTP) for the entire inspection period.
Unit 2 began the inspection period at or near 100 percent RTP. On February 18, 2023, the unit was shut down for the remainder of the inspection period for a scheduled refueling outage (M2R28).
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Impending Severe Weather Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather tornado watch, tornado warning, and severe thunderstorm warning, on January 12, 2023.
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Unit 2 train B emergency diesel generator (EDG) while Unit 2 train A EDG was out of service for planned maintenance, on January 10, 2023
- (2) Unit 2 train A and train B spent fuel cooling system, on March 6, 2023
- (3) Unit 1 train A nuclear service water system (RN), on March 14, 2023
- (4) Unit 2 low temperature overpressure protection system while Unit 2 was in mode 4, on March 29, 2023
Complete Walkdown Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated system configurations during a complete walkdown of the Unit 2 train A and train B residual heat removal (ND) system while the reactor coolant system was in lowered inventory, on February 23, 2023.
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Standby shutdown facility, on January 30, 2023
- (2) Unit 2 safety-related emergency switchgear and associated HVAC rooms, on February 1, 2023
- (3) Units 1 and 2 auxiliary building elevation 733' vital battery area, on March 8, 2023
- (4) Unit 1 train A and train B EDG rooms, on March 17, 2023
- (5) Unit 2 upper containment building, on March 28, 2023
- (6) Unit 2 lower containment building, on March 28, 2023
Fire Brigade Drill Performance Sample (IP Section 03.02) (2 Samples)
- (1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill, on January 8, 2023. The fire scenario involved a fire in the Unit 1 lube oil purifier in the Unit 1 turbine building basement.
- (2) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill, on January 12, 2023. The fire scenario involved a fire in the Unit 2 generator seal oil pump system.
71111.07A - Heat Exchanger/Sink Performance
Annual Review (IP Section 03.01) (1 Sample)
The inspectors evaluated readiness and performance of:
- (1) PT/2/A/4403/007, "RN Train A Flow Balance," on March 9, 2023
71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)
The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:
- (1) Ultrasonic Examination
reactor head thermal sleeve inspection Visual Examination
reactor head bare metal inspection Welding Activities
cold leg check valves 2NI-21 and 2NI-349 PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection
Activities (IP Section 03.02) (1 Sample)
The inspectors verified that the license conducted the following vessel upper head penetration inspections and addressed any identified defects appropriately:
- (1) reactor head bare metal inspection
reactor head thermal sleeve inspection PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)
The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:
- (1) threaded fittings associated with flow transmitter 2-NI-FT-5450, action request (AR) 2419116
threaded fitting associated with flow transmitter 2-FW-FT-5250, AR 2424371
packing gland associated with valve 2-NV-VA-0060, AR 2437743
containment boric acid walkdown
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)
- (1) The inspectors observed and evaluated licensed operator performance in the control room during reactor shutdown and plant cooldown for Unit 2 refueling outage, on February 18, 2023.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated just in time training associated with refueling outage preparations, specifically on startup and zero power physics testing, on February 9, 2023.
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Emergent work and protected equipment plan associated with the failure of the 120VAC nonsafety-related auxiliary control power panelboard inverter (KXA), on January 4, 2023
- (2) Equipment protection plan for Unit 1 train A component cooling water (KC) during preventive maintenance on Unit 1 train B KC auxiliary building non-essential header isolation valve (1KC-53B), on January 5, 2023
- (3) Equipment protection plan for Unit 2 while in yellow shutdown risk for decay heat removal and inventory control due to lowered inventory, on February 23, 2023
- (4) Unit 2 high risk evolution associated with core fuel offload during the refueling outage, on February 26, 2023
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Nuclear condition report (NCR) 02454406, Unit 2 upper airlock volumetrics failure - Airlock Operability Test (PT/2/A/4200/020A) failed acceptance criteria, on January 18, 2023
- (2) NCR 02458167, oil leak on the isolation valve for Unit 2 train B steam generator power operated relief valve (2SV-28), on January 24, 2023
- (3) NCR 02457570, water found in Unit 1 train B diesel fuel oil storage tank, on January 26, 2023
- (4) NCR 02462518, several ice condenser baskets weighed less than expected during end of cycle surveillance, on February 27, 2023
- (5) NCR 02463633, thermal sleeve wear discovered on locations F06 and K10, on March 6, 2023
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Engineering change 101501, implementation of an alternative wiring method for the close torque bypass switch on Rotork actuators for Unit 2 train A ND reactor coolant system (NC) isolation valve (2ND-19A), on January 17, 2023
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)
(1)
(Partial)
The inspectors evaluated Unit 2 refueling outage (M2R28) activities from February 18, 2023, to March 31, 2023. The inspectors completed inspection procedure Sections 03.01.a through 03.01.c
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (PMT) (IP Section 03.01) (3 Samples)
- (1) PT/1/A/4350/002B, "Diesel Generator 1B Operability Test," following Unit 1 train B EDG governor booster servomotor replacement, on January 3, 2023
- (2) PT/0/A/4350/030, "Nordberg Diesel Engine 6 year Periodic Maintenance," on Unit 2 train B EDG, on March 14, 2023
- (3) PT/2/A/4200/008B, "NC Pressure Isolation Valve Test," following repairs on safety injection to Unit 2 train A cold leg check valve (2NI-171), on March 31, 2023
Surveillance Testing (IP Section 03.01) (4 Samples)
- (1) IP/1/A/3000/006C, "OTDT Channel Calibration Protection III," on January 11, 2023
- (2) PT/1/A/4201/001A, "RWST Level Auto-Switchover Analog Channel Operational Test,"
on January 24, 2023
- (3) PT/2/A/4200/009A, Engineered Safety Features Actuation Periodic Test Train A, Section 12.3, Unit 2 train A EDG load testing and engineered safety features valve stroking upon safety injection, phase A isolation, phase B isolation, and blackout signals, on February 19, 2023
- (4) PT/2/A/4200/009A, Engineered Safety Features Actuation Periodic Test Train A, Section 12.4, Unit 2 train A EDG response testing with offsite power available upon safety injection signal, on February 19, 2023
Inservice Testing (IST) (IP Section 03.01) (2 Samples)
- (1) PT/0/A/4250/037, "Main Steam Safety Valve Setpoint Test Using Set Pressure Verification Device (SPVD)," on Unit 2 valves 2SV-8, 2SV-9, 2SV-10, 2SV-11, and 2SV-12, on February 15, 2023
- (2) PT/2/A/4204/004C, "A and B ND Pump Head Curve Verification," on February 27, 2023
Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)
- (1) PT/2/A/4200/001C, "Isolation Valve Leak Rate Test," Enclosure 13.11, "Test Sheet for Penetration M-278 (NI)," for Unit 2 train B emergency core cooling system sump piping drain reservoir and associated isolation valves, on February 28, 2023
Reactor Coolant System Leakage Detection Testing (IP Section 03.01) (1 Sample)
- (1) PT/1/A/4150/001B, "Reactor Coolant Leakage Calculation," due to Unit 1 elevated NC unidentified leakage, on January 6, 2023
71114.06 - Drill Evaluation
Drill/Training Evolution Observation (IP Section 03.02) (2 Samples)
The inspectors evaluated:
- (1) A simulator exam consisting of a failure of an intermediate range instrumentation; inadvertent start of the turbine driven auxiliary feedwater pump; and steam generator tube rupture requiring a reactor trip and safety injection, on January 20, 2023
- (2) A technical support center qualification tabletop drill consisting of a failure of all three fission product barriers, on January 23,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===
- (1) Unit 1 (January 1, 2022, through December 31, 2022)
- (2) Unit 2 (January 1, 2022, through December 31, 2022)
IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (2 Samples)
- (1) Unit 1 (January 1, 2022, through December 31, 2022)
- (2) Unit 2 (January 1, 2022, through December 31, 2022)
IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (2 Samples)
- (1) Unit 1 (January 1, 2022, through December 31, 2022)
- (2) Unit 2 (January 1, 2022, through December 31, 2022)
71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
- (1) NCR 02462518, several ice condenser baskets weighed less than expected during end of cycle surveillance, on February 27,
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On March 6, 2023, the inspectors presented the Unit 2 inservice inspection results to Edward Pigott and other members of the licensee staff.
On April 12, 2023, the inspectors presented the integrated inspection results to Edward Pigott and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
RP/0/A/5700/006
Natural Disasters
Procedures
RP/0/B/5700/027
Severe Weather Preparation
MCFD-2551-
2.00
Flow Diagram of Chemical and Volume Control System (NV)
MCFD-2554-
01.02
Flow Diagram of Chemical and Volume Control System (NV)
MCFD-2554-
03.00
Flow Diagram of Chemical and Volume Control System (NV)
MCFD-2554-
03.01
Flow Diagram of Chemical and Volume Control System (NV)
Drawings
MCFD-2561-
01.00
Flow Diagram of Residual Heat Removal (ND)
OP/2/A/6200/004
Residual Heat Removal System
2
Procedures
OP/2/A/6350/002
Diesel Generator
119
Corrective Action
Documents
Resulting from
Inspection
Nuclear Condition
Report(s)
2456811
Fire Plans
CSD-MNS-PFP-
AB-0733-001
Auxiliary Building Elevation 733 Pre-Fire Plan
Procedures
AD-OP-ALL-0207
Fire Brigade Administrative Controls
Procedures
PT/2/A/4403/007
RN Train 2A Flow Balance
2
NDE-NE-ALL-
7301
VT-3 VISUAL EXAMINATION
Procedures
TE-MN-PWR-
0006
INSPECTION, ASSESSMENT, AND CLEANUP OF BORIC
ACID ON PLANT MATERIALS
Licensed Operator - Just in Time Training - Startup -
Simulator Exercise Guide
2/24/2021
Miscellaneous
Licensed Operator - Just in Time Training - Simulator
Exercise Guide - Initial Criticality and Zero Power Physics
Testing
09/01/2020
Procedures
OP/2/A/6100/003
Controlling Procedure for Unit Operation
203
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
Nuclear Condition
Report(s)
2454401, 02467113
Corrective Action
Documents
Resulting from
Inspection
Nuclear Condition
Report(s)
2462559
AD-OP-ALL-0201
Protected Equipment
Procedures
AP/1/A/5500/15
Loss of Vital of Aux Control Power
Corrective Action
Documents
Nuclear Condition
Report(s)
2457570, 02406930, 02401057, 02458167
MCS-1593.SM-
00-0001
Design Basis Specification for the SM, SV and SB Systems
Miscellaneous
MCTC-1593-
SM.V006-01
SG PORV Isolation 1/2SV-25, -26, -27 and -28, Testing and
Acceptance Criteria, Units 1 & 2
MCSRD - NI System Reactor building
Drawings
MCSRD - NI System Reactor Building (Sh. 3 of 3)
Miscellaneous
AD-OP-ALL-0106
2NI-171 Repair - Freeze Seal - Conduct of Infrequently
Performed Tests of Evolutions
03/30/2023
AD-OP-ALL-0200
Clearance and Tagging
IP/1/A/3000/006C
OTDT Channel Calibration Protection III
PT/0/A/4250/037
Main Steam Safety Valve Setpoint Test Using Set Pressure
Verification Device (SPVD)
PT/0/A/4350/030
Nordberg Diesel Engine 6 Year Periodic Maintenance
PT/1/A/4150/001B
Reactor Coolant Leakage Calculation
105
PT/1/A/4150/055
NC System Unidentified Leakage OAC Point Determination
PT/2/A/4200/008B
NC Pressure Isolation Valve Leak Test
PT/2/A/4204/004C
2B ND Pump Comprehensive Test
Procedures
TE-MN-ALL-0410
Freeze Seals
Procedures
CSD-EP-MNS-
0101-01
EAL Technical Basis Document
Corrective Action
Documents
Resulting from
Inspection
Nuclear Condition
Report(s)
2457706