|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs ML20216C2601998-03-0606 March 1998 Insp Repts 50-254/97-28 & 50-265/97-28 on 971224-980210. Violations Noted.Major Areas Inspected:Operations,Maint & Engineering ML20202G3071998-02-13013 February 1998 Insp Repts 50-254/97-22 & 50-265/97-22 on 971027-1121. Violations Noted.Major Areas Inspected:Hpci Sys Operational Performance for Operations,Maintenance & Engineering ML20202B0501998-02-0505 February 1998 Insp Repts 50-254/98-02 & 50-265/98-02 on 980112-16. Violations Noted.Major Areas Inspected:Review of ALARA Planning,Radiation Work Permits & Observations of Radworker Performance ML20198T5071998-01-21021 January 1998 Insp Repts 50-254/97-26 & 50-265/97-26 on 971103-1223. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19970241998-01-13013 January 1998 Insp Repts 50-254/97-24 & 50-265/97-24 on 971124-1202.No Violations Noted.Major Areas Inspected:Licensed RO & SRO Requalification Training Programs ML20197F5741997-12-23023 December 1997 Insp Repts 50-254/97-27 & 50-265/97-27 on 971103-07 & 1204. Violations Noted.Major Areas Inspected:Maint & Engineering ML20197B2641997-12-16016 December 1997 Insp Repts 50-254/97-14 & 50-265/97-14 on 970729-0922.NOV & Deviations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support Re Troubleshooting Resulting in Discovery of Long Standing Problem W/Fire Pump IR 05000254/19970251997-12-0909 December 1997 Insp Repts 50-254/97-25 & 50-265/97-25 on 971103-07.No Violations Noted.Major Areas Inspected:Respiratory Protection Plan,Source Term Reduction Efforts & Follow Up on Several Open Items IR 05000254/19970211997-12-0909 December 1997 Insp Repts 50-254/97-21 & 50-265/97-21 on 970923-1103.No Violations Noted.Major Areas Inspected:Operation,Maint, Engineering & Plant Support IR 05000254/19970191997-11-18018 November 1997 Insp Repts 50-254/97-19 & 50-265/97-19 on 971006-10.No Violations Noted.Major Areas Inspected:Ep Program IR 05000254/19970181997-11-10010 November 1997 Insp Repts 50-254/97-18 & 50-265/97-18 on 970922-25. Violations Noted.Major Areas Inspected:Maintenance & Engineering IR 05000254/19970161997-11-0505 November 1997 Insp Repts 50-254/97-16 & 50-265/97-16 on 970825-29. Violations Noted.Major Areas Inspected:Fire Protection Program & Several App R Issues 1999-09-09
[Table view] Category:UTILITY
MONTHYEARIR 05000254/19900141990-10-0404 October 1990 Insp Repts 50-254/90-14 & 50-265/90-14 on 900805-0915. Violations Noted.Major Areas Inspected:Ler Review,Regional Request,Followup on TMI Action Items,Operational Safety Verification,Esf Sys & Monthly Maint Observations IR 05000254/19900101990-08-14014 August 1990 Insp Repts 50-254/90-10 & 50-265/90-10 on 900605-0802. Violations Noted.Major Areas Inspected:Allegation That 1/2 Emergency Diesel Generator Cooling Pump Could Not Fulfill Cooling of Diesel & ECCS Room Coolers IR 05000254/19900111990-07-13013 July 1990 Insp Repts 50-254/90-11 & 50-265/90-11 on 900611-14.No Violations or Deviations Noted.Major Areas Inspected: Licensee Radwaste Mgt Program,Including Solid,Liquid & Gaseous Wastes & Audits & Assessments IR 05000254/19890161989-08-28028 August 1989 Insp Repts 50-254/89-16 & 50-265/89-16 on 890625-0819. Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Safety Assessment/ Quality Verification,Emergency Preparedness & Security IR 05000254/19890181989-08-24024 August 1989 Physical Security Insp Repts 50-254/89-18 & 50-265/89-18 on 890814-18.No Violations Noted.Major Areas Inspected:Mgt Support,Security Program Plans,Audits,Protected & Vital Area Physical Barriers & Detection & Assessment Aids ML20246C4001989-08-15015 August 1989 Partially Deleted Insp Repts 50-272/89-19,50-311/89-17 & 50-354/89-15 on 890710-14 (Ref 10CFR73.21).Major Areas Inspected:Followup on Actions Taken in Response to Regulatory Effectiveness Review on 890410-14 ML20246Q0301989-08-10010 August 1989 Insp Repts 50-029/89-14 & 50-271/89-10 on 890717-21.No Violations or Deviations Noted.Major Areas Inspected: Corporate Engineering & Offsite Support for Plants & Implementation of Mods IR 05000254/19890121989-07-17017 July 1989 Insp Repts 50-254/89-12 & 50-265/89-12 on 890514-0624.One licensee-identified Violation & Two Unresolved Items Noted. Major Areas Inspected:Licensee Actions on Previous Items, Plant Operations,Emergency Preparedness & Security ML20246C3471989-06-29029 June 1989 Safety Insp Repts 50-254/89-13 & 50-265/89-13 on 890522-0608.No Violations,Deviations or Open Items Noted. Major Areas Inspected:Maint & Inservice Testing of Pumps & Valves,Including Actions in Response to NRC Bulletin 85-003 IR 05000254/19890151989-06-28028 June 1989 Insp Repts 50-254/89-15 & 50-265/89-15 on 890619-21.No Violations Noted.Major Areas Inspected:Radwaste Mgt Program, Including Solid,Liquid & Gaseous Radwastes,Audits & Assessments & Unplanned Liquid Radwaste Release IR 05000254/19890141989-06-27027 June 1989 Insp Repts 50-254/89-14 & 50-265/89-14 on 890605-09.No Violations or Deviations Noted.Major Areas Inspected: Implementation of NRC Bulletin 88-010 Requirements Re molded-case Circuit Breakers IR 05000254/19890101989-05-22022 May 1989 Insp Repts 50-254/89-10 & 50-265/89-10 on 890402-0513.No Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness,Security & Engineering/Technical Support ML20247B6651989-05-0909 May 1989 Mgt Meeting Rept on 890307 & 0413.Major Areas Discussed: Status of Plant,Training & Safety Programs & Self Assessment Programs IR 05000254/19890041989-04-13013 April 1989 Insp Repts 50-254/89-04 & 50-265/89-04 on 890205-0401.No Violations Noted.Major Areas Inspected:Plant Operations, Radiological Controls,Maint/Surveillance,Emergency Preparedness & Security IR 05000321/19880371989-03-0909 March 1989 Partially Withheld Insp Repts 50-321/88-37,50-366/88-37 & 50-424/88-53 on 881102-890106 (Ref 10CFR2.790(d) & 73.21). Violations Noted.Major Areas Inspected:Physical Security Operational Activities & Safeguards Matl Handling IR 05000254/19890061989-03-0707 March 1989 Insp Repts 50-254/89-06 & 50-265/89-06 on 890214-17.No Violations Noted.One Potential Contamination Control Weakness Noted.Major Areas Inspected:Radiation Protection Program,Including Organization & Mgt Controls & ALARA IR 05000254/19890051989-02-27027 February 1989 Insp Repts 50-254/89-05 & 50-265/89-05 on 890206-10.No Violations Noted.Major Areas Inspected:Chemistry Program, Including Procedures,Organization & Training & Radiological Environ Monitoring Program & Qc/Qa Program in Lab IR 05000213/19880211988-11-15015 November 1988 Physical Security Insp Repts 50-213/88-21,50-245/88-22, 50-336/88-25 & 50-423/88-21 on 881017-21.No Noncompliance Noted.Major Areas Inspected:Safeguards Info Program - Corporate Ofcs IR 05000280/19880401988-10-26026 October 1988 Insp Repts 50-280/88-40,50-281/88-40,50-338/88-28 & 50-339/88-28 on 880926-30.No Violations or Deviations Noted. Major Areas Inspected:Control Room Habitability & Insp Followup Items IR 05000254/19880201988-10-13013 October 1988 Insp Repts 50-254/88-20 & 50-265/88-20 on 880807-0930.No Violations or Deviations Noted.Major Areas Inspected: Operations,Maint,Surveillance,Ler Review,Routine Repts, Temporary Instructions,Radiation Control & Info Notices IR 05000254/19880211988-10-0505 October 1988 Insp Repts 50-254/88-21 & 50-265/88-21 on 880222-0901. Violations Noted.Major Areas Inspected:Compliance W/App R to 10CFR50 & Review of Fire Protection Program Requirements IR 05000254/19880191988-09-22022 September 1988 Insp Repts 50-254/88-19 & 50-265/88-19 on 880830-0902.No Violations Noted.Weakness & Four Open Items Identified.Major Areas Inspected:Annual Exercise IR 05000254/19880251988-09-20020 September 1988 Insp Repts 50-254/88-25 & 50-265/88-26 on 880908-14.No Violations Noted.Major Areas Inspected:Licensee Written Practice for Nondestructive Exam Pertaining to 25% Rule Described in SNT-TC-1A ML20154L9461988-09-14014 September 1988 Insp Rept 50-265/88-24 on 880826.No Violations Noted. Major Areas Inspected:Weakness Identified in Verification of Component Operability as Documented in Insp Repts 50-254/88-15 & 50-265/88-15 ML20154L7701988-09-14014 September 1988 Corrected Pages 13 & 14 to Insp Repts 50-254/88-15 & 50-265/88-15 IR 05000254/19882001988-09-0707 September 1988 Emergency Operating Procedures Insp Rept 50-254/88-200 on 880613-30.Inadequacies & Deficiencies Noted.Major Areas Inspected:Determination If Procedures Technically Correct & Whether Procedures Could Be Carried Out & Performed IR 05000254/19880181988-07-29029 July 1988 Partially Withheld Physical Security Insp Repts 50-254/88-18 & 50-265/88-18 on 880718-21 (Ref 10CFR73.21).Noncompliances Noted.Major Areas Inspected:Security Plan & Implementing Procedures & Mgt Effectiveness IR 05000254/19880171988-07-14014 July 1988 Insp Repts 50-254/88-17 & 50-265/88-17 on 880706-07.No Violations Noted.Major Areas Inspected:Emergency Preparedness Program Areas,Including Actions on Previously Identified Items & Initiatives to Improve Program IR 05000254/19880161988-07-0101 July 1988 Insp Repts 50-254/88-16 & 50-265/88-16 on 880607-15. Violations Noted.Major Areas Inspected:Containment Integrated Leak Rate Test Procedure,Performance & Results, Local Leak Rate Test Results & LER Followup IR 05000254/19880121988-06-28028 June 1988 Insp Repts 50-254/88-12 & 50-265/88-06 on 880310-0411-12,18, 21,26-29 & 05-10,17-18 & 0601 & 20.No Violations Noted.Major Areas Inspected:Inservice Insp Activities,Including Review of Programs 73051,Procedures 73052 & Observation of Work ML20195H1591988-06-21021 June 1988 Insp Repts 50-254/88-11 & 50-265/88-12 on 880422-0601. Violations Noted.Major Areas Inspected:Maint Activities & Followup on Previous Identified Insp Items Using Selected Portions of Listed Insp Modules IR 05000254/19880131988-06-15015 June 1988 Insp Repts 50-254/88-13 & 50-265/88-13 on 880510-20. Violation Noted.Major Areas Inspected:Radwaste Mgt & Radiation Protection Programs During Refueling & Maint Outage Including Organization & Mgt Controls IR 05000254/19880091988-06-0707 June 1988 Insp Repts 50-254/88-09 & 50-265/88-10 on 880403-0604.No Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Temporary Instructions & Administrative Controls Affecting Quality IR 05000254/19880101988-06-0606 June 1988 Insp Repts 50-254/88-10 & 50-265/88-11 on 880418-29.No Violations Noted.Major Areas inspected:safety-related Piping Weldments,Components & Supports Selected from Plant Mod Packages & Inservice Insp Plan IR 05000454/19880081988-05-27027 May 1988 Insp Repts 50-454/88-08,50-455/88-08 & 50-456/88-16 on 880509-19.No Violations or Deviations Noted.Major Areas Inspected:Review of Action on Previous Insp Items & Followup on SER Items IR 05000254/19880071988-05-0404 May 1988 Errata to Insp Repts 50-254/88-07 & 50-265/88-08 ML20151Z6211988-04-28028 April 1988 Insp Repts 50-254/88-07 & 50-265/88-08 on 880328-0407.No Violations Noted.Major Areas Inspected:Hpci/Rcic History & Mgt Activities,Root Cause Determination & Corrective Action & Maint Activities Re HPCI & RCIC IR 05000254/19880881988-04-27027 April 1988 Insp Repts 50-254/88-88 & 50-265/88-09 on 880404-08.No Violations Noted.Major Areas Inspected:Qa & Confirmatory Measurements for in-plant Radiochemical Analyses & Verification of TLD Collocation IR 05000254/19880041988-04-12012 April 1988 Insp Repts 50-254/88-04 & 50-265/88-04 on 880207-0402. Violations Noted.Major Areas Inspected:Operations,Maint, Surveillance,Ler Review,Routine Repts,Temporary Instructions & Administrative Controls Affecting Quality IR 05000254/19880061988-03-31031 March 1988 Insp Repts 50-254/88-06 & 50-265/88-07 on 880315-17.No Violations Noted.Major Areas Inspected:Licensee Actions on Previously Identified Items,Emergency Plan Activations, Review of Licensee Initiatives to Improve Program IR 05000272/19880061988-03-18018 March 1988 Partially Withheld Physical Security Insp Repts 50-272/88-06,50-311/88-06 & 50-354/88-04 on 880201-05 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected: Procedures,Security Organization & Mgt Effectiveness ML20151U8781988-03-0404 March 1988 Partially Withheld Insp Repts 50-259/88-01,50-260/88-01, 50-296/88-01,50-327/88-01 & 50-328/88-01 on 880106,07 & 13. (Ref 10CFR2.790(d) & 73.21).Major Areas Inspected:Corrective Measures in Response to Unresolved Item IR 05000254/19870331988-02-24024 February 1988 Insp Repts 50-254/87-33 & 50-265/87-33 on 871206-880206. Violations & Deviations Noted.Major Areas Inspected: Operations,Maint & Surveillance,Ler Review,Routine Repts & Administrative Controls Affecting Radiation Control IR 05000254/19880031988-02-0404 February 1988 Partially Withheld Physical Security Insp Repts 50-254/88-03 50-265/88-03 on 880111-14 (Ref 10CFR73.21).No Violations Noted.Major Areas Inspected:Mgt Effectiveness Security Program Audits,Records & Repts IR 05000254/19880021988-01-27027 January 1988 Insp Repts 50-254/88-02 & 50-265/88-02 on 880105-07.No Violations or Deviations Noted.Major Areas Inspected:Items Identified in Nov 1987 Insp & Initial Review of Licensee Initiatives to Improve Emergency Preparedness Program IR 05000254/19870241987-12-29029 December 1987 Insp Repts 50-254/87-24 & 50-265/87-24 on 870913-1208.No Violations or Deviations Noted.Major Areas Inspected: Containment Integrated Leak Rate Test (Cilrt) Procedure, Cilrt Performance Witnessing & Cilrt Results IR 05000254/19870201987-12-21021 December 1987 Safety Insp Rept 50-254/87-20 on 870901-1209.No Violations Noted.Major Areas Inspected:Inservice Insp Activities, Including Review of Programs,Procedures,Observation of Work Activities,Data Review & IE Bulletin Evaluation IR 05000254/19870301987-12-17017 December 1987 Insp Repts 50-254/87-30 & 50-265/87-30 on 871026-1105.One Violation Noted.Major Areas Inspected:Licensee Action on Previous Insp Findings,Implementation of QA Program in Areas of Design Changes & Mod & Maint IR 05000254/19870271987-12-16016 December 1987 Insp Repts 50-254/87-27 & 50-265/87-27 on 871001-1205.No Violations Noted.Major Areas Inspected:Maint,Operations, Surveillance,Ler Review,Routine Repts & Administrative Controls Affecting Quality & Radiation Control IR 05000254/19870321987-12-0404 December 1987 Insp Repts 50-254/87-32 & 50-265/87-32 on 871102-06.No Violations or Deviations Noted.Major Areas Inspected: Chemistry Program,Including Procedures,Organization & Training & Qa/Qc Program in Lab 1990-08-14
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000254/19990011999-10-0707 October 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990721-0908.No Violations Noted.Major Areas Inspected:Initiating Events, Mitigating Sys & Barrier Integrity IR 05000254/19990171999-09-15015 September 1999 Insp Repts 50-254/99-17 & 50-265/99-17 on 990823-27.No Violations Noted.Major Areas Inspected:Pilot Baseline Insp for Annual Review of Changes to Safety Analysis Rept & Biennial Review Permanent Plant Mod IR 05000254/19990161999-09-0909 September 1999 Errata to Insp Repts 50-254/99-16 & 50-265/99-16 Conducted on 990819.Administrative Error Was Corrected on Page 8 of Subj Rept.One Open Item Was Deleted & re-numbering of Two Other Items Were Identified IR 05000254/19990151999-08-25025 August 1999 Insp Repts 50-254/99-15 & 50-265/99-15 on 990816-20.No Violations Noted.Major Areas Inspected:Maint Rule Implementation IR 05000254/19990101999-08-20020 August 1999 Insp Repts 50-254/99-10,50-265/99-10,50-454/99-09, 50-455/99-09,50-456/99-10 & 50-457/99-10 on 990628-0721. Major Areas Inspected:Licensee C/A Approach & Implementation of Configuration Control Processes at Each Site ML20211D2031999-08-19019 August 1999 Insp Repts 50-254/99-16 & 50-265/99-16 on 990719-22. Violations Noted.Major Areas Inspected:Physical Protection Cornerstone,Including Review of Access Authoization Program & Changes to Security Plan IR 05000254/19990121999-08-13013 August 1999 Insp Repts 50-254/99-12 & 50-265/99-12 on 990628-0716. Violations Noted.Major Areas Inspected:Corrective Action Process Which Included Methods Used for Identification, Cause Investigation & Correction of Quality Related Items IR 05000254/19990111999-08-13013 August 1999 Insp Repts 50-254/99-11 & 50-265/99-11 on 990601-0720.NCVs Noted.Major Areas Inspected:Performance in Initiating Events,Mitigating Sys,Barrier Integrity Cornerstones & Performance Indicator Verification IR 05000254/19990141999-07-30030 July 1999 Insp Repts 50-254/99-14 & 50-265/99-14 on 990713-15.One Violation Noted & Treated as Ncv.Major Areas Inspected: Heat Sink Performance,Which Covers Inspectable Area Under Initiating Events & Mitigation Sys IR 05000254/19990131999-07-29029 July 1999 Insp Repts 50-254/99-13 & 50-265/99-13 on 990628-0702.No Violations Noted.Major Areas Inspected:Public Radiation Safety & Review of Gaseous & Liquid Radiological Effluents & of Radiological Environmental Monitoring Program IR 05000254/19990091999-06-23023 June 1999 Insp Repts 50-254/99-09 & 50-265/99-09 on 990421-0531.One Violation of NRC Requirements Occurred & Being Treated as non-cited Violation.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000254/19990061999-05-14014 May 1999 Insp Repts 50-254/99-06 & 50-265/99-06 on 990307-0420.Three Violations Noted & Being Treated as non-cited Violations. Major Areas Insptected:Aspects of Licensee Operations,Maint, Engineering & Plant Support IR 05000254/19990081999-05-11011 May 1999 Insp Repts 50-254/99-08 & 50-265/99-08 on 990419-23.No Violations Noted.Major Areas Inspected:Adequacy of Licensee Programs,Procedures,Training & Supporting Documentation IR 05000254/19990031999-04-0909 April 1999 Insp Repts 50-254/99-03 & 50-265/99-03 on 990308-12.No Violations Noted.Major Areas Inspected:Maint & Engineering ML20205J2951999-04-0101 April 1999 Insp Repts 50-254/99-01 & 50-265/99-01 on 990121-0306. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19990071999-03-31031 March 1999 Radiation Protection Insp Repts 50-254/99-07 & 50-265/99-07 on 990309-12.No Violations Noted.Major Areas Inspected:Solid Radwaste Processing & Control Program & Radioactive Matls Shipping Program IR 05000254/19980211999-03-0505 March 1999 Insp Repts 50-254/98-21 & 50-265/98-21 on 981112-1218. Violation Noted:Major Areas Inspected:Isi Activities at Plant During Refueling Outage 15 ML20207G1771999-03-0505 March 1999 Notice of Violation from Insp on 99112-1218.Violation Noted:Licensee Had Not Included in Revised ISI Program,Basis for Determination That Code Required Exam Was Impractical For,Unit 2 Reactor Pressure Vessel Nozzle Weld Nsb IR 05000254/19990041999-02-26026 February 1999 Insp Repts 50-254/99-04 & 50-265/99-04 on 990201-05.No Violations Noted.Major Areas Inspected:Emergency Prepardeness Program as Aspect of Plant Support IR 05000254/19990021999-02-25025 February 1999 Insp Repts 50-254/99-02 & 50-265/99-02 on 990125-29.No Violations Noted.Major Areas Inspected:Radiation Protection & Chemistry Program Included Water Chemistry Control, Instrument Quality Control & internal-lab Comparison ML20199E9431999-01-14014 January 1999 Partially Withheld Security Insp Repts 50-254/98-24 & 50-265/98-24.Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Quad Cities Facility.Details Withheld (Ref 10CFR2.790) IR 05000254/19980221998-12-28028 December 1998 Insp Repts 50-254/98-22 & 50-265/98-22 on 981130-1204.No Violations Noted.Major Areas Inspected:Radiation Protection Staff Preparation for Q1R15 Refueling Outage,Including Review of ALARA Planning & Work Plan Integration IR 05000254/19980201998-12-28028 December 1998 Insp Repts 50-254/98-20 & 50-265/98-20 on 981014-1201.No Violations Noted.Major Areas Inspected:Operations,Maint & Plant Support IR 05000254/19980191998-12-18018 December 1998 Insp Repts 50-254/98-19 & 50-265/98-19 on 981019-1106. Violations Noted.Major Areas Inspected:Effectiveness of Engineering & Technical Support Provided to Plant in Performance of Routine & Reactive Site Activities ML20198G2901998-12-18018 December 1998 Notice of Violations from Insp on 981019-1106.Violations Noted:As of 980327,performance of Listed Test Procedures Did Not Demonstrate Equipment Could Perform Satisfactorily Under Design Conditions IR 05000254/19980171998-11-0505 November 1998 Insp Repts 50-254/98-17 & 50-265/98-17 on 980902-1014.No Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support IR 05000254/19980181998-10-15015 October 1998 Partially Withheld Insp Repts 50-254/98-18 & 50-265/98-18 on 980914-18 (Ref 10CFR73.71).No Violations Identified.Major Areas Inspected:Review of Plant Support Activities,Security Activities Re Onsite Personnel Access & Communications IR 05000254/19980131998-09-22022 September 1998 Insp Repts 50-254/98-13 & 50-265/98-13 on 980716-0901.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support IR 05000254/19980141998-09-17017 September 1998 Insp Repts 50-254/98-14 & 50-265/98-14 on 980825-28.No Violations Noted.Major Areas Inspected:Evaluation of Licensee Performance During Plant Biennial Exercise of Emergency Plan ML20154G4301998-09-11011 September 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:As of 970926,licensee Failed to Provide Alternate Shutdown Capability for Some Fire Areas of Facility Containing Safe Shutdown Equipment ML20195D1951998-09-0808 September 1998 EN-98-057B:on 980911,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based on One Severity Level II Problem Involving Very Significant Inadequacies in Comm Ed Capability to Shut Down IR 05000254/19980161998-09-0404 September 1998 Insp Repts 50-254/98-16 & 50-265/98-16 on 980810-14.No Violations Noted.Major Areas Inspected:Radiation Protection Program Included External & Internal Exposure Control,Whole Body Counting & Contamination & Survey Monitoring Program ML20237D6671998-08-11011 August 1998 Notice of Violation from Insp on 980529-0716.Violation Noted:On 980622,while Performing Quad Cities Operating Surveillance Procedure 6600-01,rev 24,operator Failed to Position Throttle Air Box Drain Valve One Turn IR 05000254/19980121998-08-11011 August 1998 Insp Repts 50-254/98-12 & 50-265/98-12 on 980529-0716. Violations Noted.Major Areas Inspected:Operations, Engineering,Maintenance & Plant Support ML20195D2341998-08-11011 August 1998 EN-98-057:on 980814,notice of Proposed Imposition of Civil Penalty in Amount of $143,000 Issued to Licensee.Action Based on One Severity Level II Problem & One Severity Level III Violation IR 05000254/19980151998-07-31031 July 1998 Insp Repts 50-254/98-15 & 50-265/98-15 on 980721-24.No Violations Noted.Major Areas Inspected:Aspects of Licensee Corrective Actions & Engineering Involvement in Corrective Actions Process IR 05000254/19980091998-07-0202 July 1998 Insp Repts 50-254/98-09 & 50-265/98-09 on 980401-0529. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support ML20236M0831998-07-0202 July 1998 Notice of Violation from Insp on 980401-0529.Violation Noted:On 980501,Interim Procedure 98-0035 Was Not Implemented When Change Was Made to Personnel Out-of Svc Number 98-512 Which Was Not Reviewed & Approved IR 05000254/19980111998-07-0202 July 1998 Insp Repts 50-254/98-11 & 50-265/98-11 on 980504-22. Violations Noted.Major Areas Inspected:Quad Cities Safe Shutdown Analysis & Supporting Procedures ML20248L7951998-06-0505 June 1998 Notice of Violation from Investigation on 970530.Violations Noted:Licensee Provided to Commission on 960825,operability Determination Checklist.Info Inaccurate Because Supporting Calculations Showed FICs to Be Excess of 1.0 ML20237E7051998-06-0505 June 1998 EN-98-043:informs Commission That Staff Intends to Exercise Enforcement Discretion Per Section VI.B.6 of Enforcement Policy & Not Issue NOV to Util for Failure to Provide Complete & Accurate Info to NRC ML20247P4551998-05-15015 May 1998 Notice of Violation from Insp on 971014-980415.Violation Noted:On 971215,inspector Identified That Licensee Failed to Provide Training of Personnel Performing Activities Affecting Quality IR 05000254/19980081998-05-11011 May 1998 Insp Repts 50-254/98-08 & 50-265/98-08 on 980407-09 & 14-17. No Violations Noted.Major Areas Inspected:Maint,Quality Assurance & Engineering IR 05000254/19982011998-05-0606 May 1998 Insp Repts 50-254/98-201 & 50-265/98-201 on 980216-0327.No Violations Noted.Major Areas Inspected:Evaluation of Capability of Selected Sys to Perform Safety Functions Required by Design Bases IR 05000254/19980101998-05-0606 May 1998 Insp Repts 50-254/98-10 & 50-265/98-10 on 980413-17.No Violations Noted.Major Areas Inspected:Liquid & Gaseous Effluent Programs,Annual Effluent Rept,Continuous Air & Area Radiation Monitors ML20217G2341998-04-23023 April 1998 Notice of Violation from Insp on 980216-0326.Violation Noted:Between 971006 & 10,work Package 970104149-03 Replaced 2A Recirculation Loop Sample Pci Valve AO-2-0220-44,activity Affecting Quality,Prepared & Installed Prior to 971014 ML20217G2481998-04-23023 April 1998 Insp Repts 50-254/98-05 & 50-265/98-05 on 980216-0326. Violations Noted.Major Areas Inspected:Engineering,Including Allowances for Development of Emergency & Immediate Mods ML20217G3101998-04-23023 April 1998 Notice of Violations from Insp on 980211-0331.Violations Noted:On 980314,non-licensed Operators Performing Plant Operating Procedure 6600-7,rev 6,attachment H,Failed to Charge Breaker Closing Spring for Unit 2 ML20217G3401998-04-23023 April 1998 Insp Repts 50-254/98-04 & 50-265/98-04 on 980211-0331. Violations Noted.Major Areas Inspected:Operations, Engineering,Maint & Plant Support IR 05000254/19980071998-04-22022 April 1998 Insp Repts 50-254/98-07 & 50-265/98-07 on 980330-0403.No Violations Noted.Major Areas Inspected:Plant Support Activities Re Physical Protection of Plant,Adequacy of Security Procedures & Event Logs 1999-09-09
[Table view] |
Text
{{#Wiki_filter:- _ _ _ _ - _ _ _ - _ _ '
\
.
02&& *
.
U. S.. ATOMIC ENERGY COMMISSION DIRECTORATE OF REGULATORY OPERATIONS
REGION III
RO Inspection Report No. 050-265_/72-09 RO Inspection Report No. g 254/72- M Litensee Conunonwealth Edison Company P. O. Box 767
, Chicago, 113inois 60690
<
Quad-Cities Nuclear Power Station License Nos. DPR-29 Units 1 and 2 and DPR-30 Cordova, Illinois Category: B R #
*- GE (BWR) 809 Hve, 2511 Mwt Type of Licensee:
Type of Inspection: Special, Unannounced Dat es of Inspection: August 25 - 27, September 7 and 28, 1972 Dates of Previous Inspection: August 10 - 11, 16 and 17, 1972 Principal Inspector ~ /8 o 7 '(Da(e)
Accompanying Inspectors: None Other Accompanying Personnel: None Reviewed By:
.b N D. M. Hunnicutt, Chief M/bO/71 Reactor Testing and Startup Branch '(Datd)
.
8709280158 870921 PDR FOIA MENZ87-111 PDR
.
_ _ _ _ _ _ _ _ - _ _ - - - - _ - _ _ - _ - - _ _ _ _ _ _ _ - _ _ _ - _ - _ - - - _ _ _ _ - - _ - _ _ _ _ - _ _ - _ _ _ _ _ _ _ - _ _ _ - _ - _ _ _ - ___
s
.
l
.,
e l
-
.
~ '
SUMMARY OF FINDINGS
!
. I J
Enforcement Action: None j Licensee Action on Previously Identified Enforcement Matters: None i
Design Changes None j Unusual Occurrenc3s Jet Pump Failure on August 20. 1972 l
An unbalance in recirculation loop flow was detected about 11 August 20, 1972, during a restart of recirculation pump "B". Investiga-tien by the licensee revealed abnormal flow indication on jet pump N . An orderly shutdown of Unit 2 reactor was started at 12:45 August 21, 1972. The reactor has remained shutdown since this occurrence for investigation and correction of the jet pump failur The . licensee has found that jet pump No.17 had been displaced from its normal position due to loosening of the beam bolt assembly which normally holds the pump in position. The beam bolt loosening has been attributed to inadequate tack welds and/or improper tensioning of the beam assembly during installatio (Paragraphs 1 - 12) ;
The licensee has inspected all Unit 2 jet pumps and has initiated repairs and measures to prevent similar failures. The licensee presently schedules restart for the week of October 9, 197 Other Significant Findings Current Findings Although detection and analysis of the jet pump failure appeared to be timely, the licensee's surveillance procedure and the Technical Specifications were found to be inadequate to identify a jet pump failure such as occurred August 20, 1972. (Paragraph 3) Results lof jet pump inspections (Paragraph 7) indicate inade-quate quality assurance (tack nelds and beam tensioning) during i
,
jet pump assembl . Analysis of ef fects of unrecovered disc and retainer upon reactor safety was incomplet (Paragraph 8)
-2-(
,
h L _ .____________________-_____________-__D
, . .l l
. '
,,
* '
. , Jet pumps.Nos. 10, 11, 32,'14 16, and 17 repairs were incomplet p" (Paragrapli 9) } l
' . Vibration instrumentation on jet pumps' Nos.11 and 12 may be j damaged during jet pump repairs. (Paragraph 9) .
B. . Status of Previously Reported Unresolved Items: N/A
-
-
q Management Interview
.
'
.t A .' - Auaust 26. 1972 I The inspector discussed the findings of the vessel inspection
'
.
.
(Paragraph 4) and the detection of the jet pump failure (Paragraph 2)?
with Mr. Palme September 7. 1972 The inspector' discussed the jet pump inspection results (Paragraph 7)
and the initial installation records (Paragraph 6) .with Messr ,
Palmer and Stephenson. The inspector stated that the differences
' between the inspection results and the installation records appeared to illustrate inadequacies in the construction quality assurance program. . The inspector asked the licensee to consider additional surveillance test measures to assure Unit 'l jet pump operability in
-
view of the' nature of Unit 2 failure (Paragraph 12) Mr. Palmer
, agreed to consider additional surveillance measure September 28, 1972 " The inspector discussed jet pump repairs (Paragraph 9) with Messr Palmer and Stephenson. .The inspector. stated concern regarding unrecovered components.(Paragraph 8). Mr. Palmer stated that a safety analysis of unrecovered components would be completed before .
Unit 2 operation is resumed. The inspector stated concern regarding
. probable loss of jet pump 11 and 12 vibration instrumentation
,
(Paragraph 9). Mr. Palmer stated that every effort was being made to preserve the sensors but assurance of jet pump integrity was evaluated by CE to be more important than additional vibration' test dat !
,
i
.
d b
{ .
.
.
f REPORT DETAILS
. Persons Contacted Commonwe.alth Edison Company (CE)
F. Palmer, Operations Superintendent B. Stephenson, Assistant Operations Superintendent V. Schlosser, Plant Maintenance Engineer N. Kalivianakis, Operating Engineer K. Houseman, Technical Staff Engineer R. Newkirk, Technical Staff Supervisor General Electric Company (GE)
R. Murkowski, Jet Pump Design Engineer (San Jose)
J. Macpherson, Reactor Internals Engineer (San Jose)
R. Leasburg, Project Manager Jet Pump Failure. August 20. 1972 Reactor Status Precedina Occurrence Review of strip chart recorder tracas and control room logs showed Unit 2 was operating at approximately 80% of full power preceding a "2B" recirculation pump trip at 6:20 p.m. on October 20, 197 The pump was restarted and the load was returned to- 650 Mwe by 7:15 p.m. A second "2B" pump trip occurred at 7:52 p.m. In both pump trips, the recirculation flow decayed normally with no flow increase. The pump trip was found to be caused by an erroneous high oil temperature indication in the hydraulic speed control unit. A licensee representative stated that the temperature sensors have been replaced since this occurrenc . Detection of Jet P sp Failure Recirculation pump "2B" was restarted at 10:15 p.m. following the second trip. The . circulation flows were found to be unbalanced at the same pump speed during flow increase in " local manual" control. The licensee switched from "B" to "A" GMAC for reactor level control due to noisy behavior of the "B" level control GMA (Noisy behavior was later attributed to upward flow through diffuser and transition piece.) The licensee was found to have reduced power with the recirculation system at 12:00 a.m. (midnight)
-4-
,:
a __ ___ ___________._____-___--.-___________1__ ___.___ _
_- - _ , _ . ___ _ _ _ _ _ _ . .__ _ _ _ _
;
*
.
l'
l
<
<
i October 20 to check for possible jet pump failure. Rod insertion
'
was begun'at 12:25 a.m. October 21. The turbine generator was tripped at 2:42 a.m. and the mode switch was manually positioned to " shutdown" by 5:14 a.m. October 21. The indications of jet pump failure are listed in the attached Table 1. The licensee confirmed that jet pump No.17 apparently had f ailed by observing individual jet pump flow indication during a recirculation pump 2B trip. All "B" loop jet pump flow indications, except jet pump No.17, were observed to drop toward zero as flow reversal occurre This additional information indicated jet pump No.17 to be apparently flowing in reverse even when recirculation pump "B" was runnin . Jet Pump Surveillance ' Testing
'
Review of the records of jet pump surveillance testing which was performed on October 21, 1972, indicated inadequacies in both the licensee's procedure and the Technical Specifications. The pro-cedure requirerients and Technical Specifications Section 4. daily surveillance requirements state that if recirculation loop
'
flow imbalance > 15% and indicated core flow compared with core flow derived from loop flow is > 10% and individual jet pump A p varies, from the reau of all jet pump 4 p by > 10% simultaneously, then the jet pump is inoperable. Ccuparisen of drive flows in Table 1 shows loop B 23% greater than loop A, extrapolation o total driving flow of 58 x 103 gym from licensee's data gave a core flow of - 73 x 106 lb/hr, hence the jet pumps are operable according to the procedure requirements and Technical Specifications Section 4.6.G which requires the three conditions simultaneousl The dynamic behavior of the recirculation system was found to cause one or more jet pumps to vary from the mean flow rate by more than i 4.88% flow (i 10% o p) especially at lower pump speed l i-5-I i
,
. ._
J
-
. -- a
.
I
* .
.
'
-
. .
,
,
I
'
.
In spite of the inadequacy of the surveillance requirements, the-licensee personnel assessed the jet pump No.17 failure correctly and took appropriate actions. . Licensee represes:atives have pro-vided an interim surveillance test procedure to replace the pro- i cedure in use at the-time of the occurrence. (Paragraph 11) The licensee states that chaages to the existing Technical Specifications were being proposed to make the jet pump operability testing more meaningfu The licensee stated that consideration was being given to a sur-veillance test which would compare each test with a baseline or
, initial set of test dat i
* Reactor Internals Examination Access to the reactor vessel was available follewing steam dryer i separation removal on August 26, 1972. The inspector examined reactor internals with licenses representatives the same dsy. Jet pump No.17 (Figure 1) was found to be leaning against jet pump No. 16, exposing the riser pipe transition piece and the diffuser section opening ! Cause of Failure
, - Subsequent inspections and investigation by the licensee attributed 1 the f ailure to inadequate beam bolt keeper tack welds and/or improper i tensioning of the been bolt assembly during installation.- The beam bolt assembly vertically restrains the jet pump (Figure 2). Following failure of the tack welds between the keeper and the lock plate (Figure 3)'the beam bolt apparently loosened until during the trip on August 20, 1972, the beam disengaged from the transition piece stanchions allowing the pump to rise until interference of the
' diffuser with the restrainer- restricted upward notion of the pum ,
'
The mode of weld failure was determined by metallurgical examinations by GE at San Jose to be metal fatigue. RO:HQ personnel reviewed the metallurgical test results at San Jos .
~ Initial Installation Records The inspector examined records of initial installation of jet pumps for both Units 1 and 2 which included verification for each pump that the following installations and tack welds were completed and
-
inspected:
Jet pump throat restrainer adjusting screw field weld Unit 1, 8-17-70, Unit 2, 2-12-71-6-
!
I e
r- +
l
- _ _ - _ _ _ . _ - _ _ _ _ _ _ _ _
'
... ,
l h *
-
k ,
<
a
~'
Jet pump top inlet retainer bolt shop weld Unit 1. 8-15-70, n
. Unit 2, 5-7-71
,
Jet: pump throat restrainer keeper tack weld Unit 1,8-15-70, Unit 2, 2-12-71 L Jet pump hold,down (beam bolt) keeper tack weld, tensioner ,
) .(3965 + 25' psi), bolt torque (50 ft 1b) Unit 1, 8-13-70, l, Unit 2, 5-6-71- l No discrepancies were found in the initial installation records although details of verification of two welds on each beam bolt ~
or specific tension-for each pump was omitte . Results of Jet Pump' Inspections l The inspector reviewed current inspection records consisting of procedures, individual phap inspection checklists and selected
'
!
videotapes of underwater television inspection. The checkpoints I for each pump were found to have been videotaped and the tapes were viewed by GE and CE engineers who filled out the checklist ~
l>
.. !
!
The seven inspection points for each pump are shown on Figures 2, 3, and 4 as circled numbere which correspond to inspection points listed below:
1 Beac bolt keeper tack weld-
.2 Second tack weld on bsam bolt ,
3 Restrainer gate keeper tack weld 4 Second restrainer gate bolt keeper tack weld 5' Beam-pocket fit i 6 Restrainer gate wedge penetration 7 Besa bolt retainer bolt tack weld q
)
Beam bolt and restrainer gste keeper welds were found by the f
'
licensee to be inadequate as listed below:
. 1
)
_y_
.?
. .
f
. .
_ _ _ _ _ - . _ _ . . - _ _ _ - - - -
-__-__ __-_
.
-
b
,
-
l the retainer plate (Figure 5) which dropped into the jet pump No. 17 )
diffuser during attempted recovery. The retainer plate was subse-quently "found" on the vessel bottom by a television camera which was lowered through jet pu.ap No. 17 diffuser but recovery attempts ;
were unsuccessful and the plate is no longer visible. Licensee i representatives stated that a safety analyses of operation with the j unrecovered disc and retainer are underway and vill be completed j be' era Unit 2 operation is resume The inspector was advised during a telephone conversation with licensee representatives on October 9, 1972, that two additional objects had accidentally been broken off of the keeper welding .
rig during removal and censistad of cne-half of a cadalum plated- I carbon steel compression nut and a neoprene bukhing. The licensee l representative stated that analyses would be provided for operation (
vith the two objects described above preceding resumption of Unit 2 {
operatio . Inspection of Jet Pump No. 17 l
Licensee representatives stated that jet pump Ns.17 had received only minor surface scratches during the occurrence and would be reinstalled. Surface radiation dose rates were stated by licensee i representatives to be in the. order of 400 mram/br upon removal from the reactor ~veese . Repair Procedures and Status The licensee was found to have prepared and approved procedures which required breaking all biam bolt keeper tack wolds, (except jet pump No. 20 which was installed by the licensee following a jet pump blackage incident oc April 29,3972) retensioning each beam, retorquaing each beam bolt and installing four tack welds on each beam bolt keeper. The procedures also require application of a 300 ft/lb torque clockwise and counterclockwise upon the conopleted beam bolt and a reinspection of the tack welds after the torque application. The defective restrainer gate keeper tack welds (Paragraph 7) were r4 quired to be repaire The inspector reviewed records of repairs as of September 28, 1972, and found no discrepancies in the documentatio ".'he jet pump repairs were decumented as complete as of September 28, 1972, except for jet pump Nos. 10, 11, 12, 14, 16, and 17 which had not yet been retensioned and tack welded. The tack welds on jet i-9-l
-
.
f
_ - _ _ _ . __ __--____A
. .
.
.
_ . - - - -
,
,
i J~ ,
.
. . . - ,
f pump Nos. = 10,14 and 16 did not break when deten.sioned, with' 300 j ft/lbs.of torque applied. The licensee was found to have fabricated d a special tool to cut the tack weld. Provisions were made t collect metal chips with an underwater vacuum. Jet pump No.-20
- beam was detensioned and the tack welds could not be broken 'with 360 f t/lbs of' torque. - Jet pump No. 20 will be lef t as is following addition .of two' tack welds on the beam bolt keeper. Jet pump No 'and '12 have vibration test instrumentation installed. to measure
.' displacement at the jet pump elbow relative to the reactor. vesse i
'
The licensee removed the sensor from jet pump No.11 to permit recensioning and tack welding. The sensor. assembly was reinstalled
. following the repa tre but continuity tests presently indicate the .;
sensor to be inoperable. The licensee has decided to also attempt 1 jet. pump No. 12 repairs based upon the licensee's position that the
-
Unit 2 90% power jet pump elbow vibration test data can be extra- !
polated to the 10C% power condition and potential failure of jet; pump No.12 due te improper tensioning or tack welding represents
.
,
the greater threat to operational safet ' 1 Personnal Radiation Protection i
The inspector observed work in progress in the reactor cavit Personnel were dressed in full protective clothing as required !
'
by procedures. Stepoff pads with monitoring provisions were .in use at the boundary of the roped off area. The licensee was j
. found to be-keeping, the steam dryer and separator wet with sprays ,
to prevent possible airborne contaminatio . Increased Unit 1 Jet Pump Operability Surveillance j
The inspector reviewed Unit 1 jet pump operability surveillance j '
testing records, control room logs and Station Review Board Minutes
.after the Unit 2 jet pump failure on August 20, 1972. The Station Review Board (SRB) on September 5, 1972, was found to have recom-mended, and station management implemented, a procedure requiring a jet pump operability test immediately following any Unit i recirculation pump trip in addition to the daily test. The SRB also requested an analysis .of the effects of a jet pump failure upon core floodability and recommended c spot check of Unit 1 jet pump welds during the outage' presently planned for April 1973. On September 8, 1972, the SRB approved recording Unit I recirculation system readings hourly and jet pump operability once each shif On September 11, 1972, the SRB recommended, and station management 3 implemented, hourly jet pump flow readings in addition to the
-
existing surveillance test ;
j l
- 10 - l i
f l
K
'
i-l L Q ria .' AAlp e .= ,
,' *
.
.
,,
*' .
..
V
'
No deficiencies were found in'the Unit 1 jet pump surveillance test records. The inspector noted .that the Unic I master flow controller
. presently maintains an offset in speed between the two pumps o approximately 5%. Licensee representatives stated that'the offset-was due to the control. system and was under investigation. The inspector also noted one pump. motor watt-meter was reading incor-rectly. Operating personnel; stated that a work request on the
-
,
.watt-meter had been initiate .
Attachments:
L Table 1 l Figures 1.thru 5 l
l l
!
!
l l
,
)
- 11 -
l
'
,b d
. . , - - . - . ~. .
g _ -- _ _ . - - _
- _ _ _ _ - - - - - - ,
- e
< .
, - .
,
,
[
- .
q
..
.
TABLE 1 1
.
*
INDICATIONS OF FUMP FAILURE PARAMETER LOOP A B PITMP SPEED (RPM) 685 685 (60%)
DRIVE FLOW:(GPM) 26 x 103 32 x 103 PUMP MOTOR CURRENT (AMP) 240 280
, ;a PUMP AP (PSI)' 65 50 TOTAL JET PUMP FLOW (LBS/HR) 36 x 106 34 x 106 JET PUMP AVG PLOW (LBS/HR) 3.5 x 106 3.1 x 106 REACTOR WATER LEVEL (IN) 30 35 JET PUMP 17 FLOW (LBS/HR) --
4.6 x 106 i
'
J
, ___ _ _ _ _ _ _ _ _ - _ _ _
- - - - - - - - - - - - - -
_
-.
^
,
.
-
JET PitMP APRA/IGepsw
\
. \
/
l
'
O b LOOP 5')
l % O .
_
99 2 h r O l
, sto
, 1 ,
.
is o
" J@
-
C. ORE Cf n@* %toas.~ d-4>hd p -p .
o8 )
$% ,
l
;
p _
y 2
_
, ,
RP9
~
l j
'
. &
;
loof'13
,
I fiyare . 1
$
b
~~
L -_ - . - - _--
e
* e' .
;
,
m
-
..
*
.
. -
-
-
[3 D c-
. -
-
a m \.'u 4 (-f &*! .Nsbahl7 sam' BkN
-- , , - -
tumifE E Nang,*[/gM [[fCC
}. ! . L,
;
.
, ,
.
/ m-
.
. ;
/
.
/
}.
~
O
"
i
*
..
-
,I
.
.- . 4 h k l .
'
.
'
.
' lf .
Ratirainer Aswb/ Cale [f"
*
.
.
I -
f i
\
l ?'s 1
.
y _U J .. .
w
'
7; m,
'
-
. ,
.
, .
-
o f .
( 1
.
*
'R, drainer Gate
. Pla view
.
'fET PthHPMsEMBL .
'
.
fijrre . !
w'. '
.
-
,
.
'
*~
'
'
BEAM- BOLT /] s SEMBL/
.
-
s.u r -
.
, Fiess W " V 02 g 1 h
.
es t=~
S a--
;
: t o%--d?"l xR l/
L b
/ p
- t_ L? 1
/
,
e
- -
-
.
-
. ve. - 1_ _ . .
,r - -' ; .__;. , .
/
'
rZh -
'
-
;/
Re7m"on m =; 'g
'
E
,
,,,,,,
' '
,,
,
.
\
j,
- i
-
1 Em: i j J %a c.,e k g : i 7 .. I f
.
; . (*"""$). f .
l
'
" '
-
,
-
,
i
=-
[
(
.
_ /m . . . . ..
/ ^ . ..
. .
e *
%
*
,
.
.
\ .,
.;
x
*
l ,
-
. .
'o
,
: :
,
I?E5TRatND? C,NTE BodrMsO4BLY :
I .
, .6 e6?T
.
.
p l k 1 i
.
/
/
/
'
_ i (
__ FIELD J,
,
I'1~
-
N wn0 2.-
es z_ _k ,t
.- !
c b=- ei u ,
' [ e.n, cz.m.mh
_
c.- - - a
) N .. '\.,._ \ '\ '. ,
/N h h h h \'f
.
..
Ii ii l lees-mn,ye J
#w / M) ' i i r_.._f i
gf bra (Nor Re-ewacto)
.
.
D7'are 4
:
,
i
. Il
. . . _ _ _
e
* s
" ' + . . *
s
.g
'
. -
t
,
_. __ _ _ & .L. u, _ _ _ . _ ... _I : ,;7 r ,
!
)
,
" * .g *"
.- ! N y,34
,
,
s i
. a
'
W /ff w& _
= 2.5" = + 4 - .198 "
Jef Pu- p Hetaine, t!< chet
,
e*
/ , ~
l
:
-- - - y . _ _
'l:
4 .
2.,25 4 4'R
_1 c
, O////[/ ~# F Beam B o Thrasi Dix.
t I
L i
h9urc 5 .$.k'ebtk
-
o f-_Urtrecettetd . G uYk y
- ..
$ ,4
}}