ML20151Z621
| ML20151Z621 | |
| Person / Time | |
|---|---|
| Site: | Quad Cities |
| Issue date: | 04/28/1988 |
| From: | Hasse R, Lanksbury R, Phillips M, Vandel T NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | |
| Shared Package | |
| ML20151Z616 | List: |
| References | |
| TASK-1.C.6, TASK-TM 50-254-88-07, 50-254-88-7, 50-265-88-08, 50-265-88-8, NUDOCS 8805050326 | |
| Download: ML20151Z621 (22) | |
See also: IR 05000254/1988007
Text
.
-
. .
.
_~
-
-
. -
.,
-.
'
,
U.S. NUCLEAR REGULATORY COMMISSION
.
.
REGION III
'
Report No:
50-254/88007; 50-265/88008
Docket No: 50-254; 50-265
License No:
Licensee: Connonwealth Edison Company
Post Office Box 767
Chicago, IL 60690
Facil'. y Name: Quad Cities Nuclear Power Station, Units 1 and 2
Inspection At:
Cordova, Illinois
Inspection Conducted: March 28 through April 7, 1988
Inspectors:
R. D. Lanksbury
je
.78
Team Leader
' Date /
'
M-8
R. A. Hasse
r
,
/' /
J/-
T. E. Vandel
Date)
'
NRC Contractor:
D. A. Beckman
!
Approved By:
M. P. Phillips, Chief
ba
f/ [
Operational Programs Section
"
'
( /
f
f
Inspection Summary
Inspection on March 28 through April 17, 1988 (Report No. 50-254/88007;
i
50-265/88008).
Areas Inspected:
Special announced inspection on HPCI and RCIC operating
problems. Areas inspected included HPCI/RCIC history and management
activities, root cause detennination and corrective action, maintenance
,
activities related to HPCI and RCIC, system walkdowns, and HPCI and RCIC
,
!
surveillances.
Res ults : Of the five areas inspected no violations were identified. However,
two open items were identified to track licensee conmitted corrective actions
t
of inspector concerns.
f
8805050321, 880429
ADOCK 03000254
Q
-
!
. - . . -
- -
- . - - . - . - . -
.
. -
.-
..
,
'
',
-
.
DETAILS
1.
Persons Contacted
Commonwealth Edison Company (CECO)
- N. Kalivianakis, General Manger, BWRs
- R. L. Bax, Station Manager
- T. K. Tamlyn, Production Superintendent
- R. A. Robey, Services Superintendent
- I. M. Johnson, Nuclear Licensing Administrator
- D, A. Gibson, Regulatory Assurance Supervisor
- N. P. Smith, BWR Licensing Supervisor
- J. Kopacz, Technical Staff Supervisor
'
- M. Turczynski, Site BWR Engineering Supervisor
- D. Rajcevich, Master Instrument Mechanic
- D. W. Craddick, Master Electrician
- J. Fish, Marter Mechanic
- C. H. Norten, Quality Assurance Engineer
- G. Price, Maintenance Department
- K. Hill, Technical Staff Engineer
J. Wethington, Quality Assurance Superintendent
The inspector also contacted and interviewed other licensee and contractor
personnel.
Nuclear Regulatory Commission (NRC)
- D. M. Crutchfield, Director, Region III, IV and V Projects, NRR
- N
J. Chrissotimos, Deputy Director, DRS, RIII
- R. F. Dudler Technical Assistant, NRR
- B. Siegal,
. censing Project Manager, NRR
- R. M. Learch, Branch 1 Technical Assistant, DRP, RIII
- R. L. Higgins, Senior Resident Inspector, RIII
- R. D. Lanksbury, Reactor Inspector, RIII
- R. A. Hasse, Reactor Inspector, RIII
"T. E. Vandel, Reactor Inspector, RIII
- D. A. Beckman, Parameters, Inc.
- Denotes those attending the exit meeting on April 7,1988.
2.
HPCI/RCIC Functional Inspection
This inspection was prompted by the relatively large number of High
Pressure Coolant Injection (HPCI) and Reactor Core Isolation Cooling
(RCIC) system outages over the past several years. The purpose of the
inspection was to determine if these systems were capable of reliably
performing their design functions, were being operated and maintained in a
manner supportive of reliable operation, and to determine if adequate
corrective actions were being taken in response to identified problems.
The inspection was conducted by a review of system design, modifications,
surveillance activities, maintenance, corrective actions taken in
response to identified problems, and actions taken on the recomendations
2
.
..
.
.
.
generated by the licensee's HPCI/RCIC Task Force. This Task Force was
established by the licensee in 1986 to evaluate the problems with these
systems and recommend actions to improve their reliability.
3.
HPCI/RCIC History and Management Activities
This area of inspection was perfomed by the inspection team to evaluate
the licensee's analysis of the data gathered through various review
prosesses, actions taken to resolve concerns generated as the result of
the various reviews performed, and the status of implementation of generated
recommendations,
a.
Task Force
The HPCI/RCIC Task Force was composed of a multi-discipline team of
plant staff personnel, a member of the corporate BWR Engineering
Staff, and a General Electric representative. The responsible
technical staff systems engineer was the team leader.
The Task Force first met on July 17, 1986, to consider RCIC
reliability with the defined tasks of:
Focus on improvement of turbine performance and reliability.
Establish four modification packages to:
,
1.
Add motor operators (M0's) to turbine trip and throttle
l
valves for both the HPCI and RCIC systems.
2.
Remove low lube oil pressure RCIC turbine trip.
,
3.
Increase pipe size of RCIC turbine bearing drains.
4.
Remove unused sections of RCIC turbine lube oil piping.
,
Develop a modification to remove RCIC turbine electrical
!
'
Develop an outage surveillance on the turbine lube oil system,
f
Develop an auto-initiation surveillance on both HPCI/RCIC.
j
i
Subsequently, the task force added the following reports into
their areas of concern for resolution.
i
a.
INP0 station evaluation report, March 1987,
b.
Quality Assurance Audit Report 04-86-56, May 19, 1987,
and,
c.
Final Report of Safety System Inspections, January 15,
1988.
3
-.
-
.
,
.
,
(.
.
.
i
May
0
1
1
0
0
1
1
0-
June
0
0
0
1
0
0
0
1
July
2
1
1
1
0
1
0
0
August
1
1
1
1
1
2
0
0
September
3
0
0
0
1
1
1
0
.
!
October
0
1
2
0
0
2
1
0
i
November
2
0
2
4
0
0
2
1
December
1
0
0
2
1
1
0
3
.
~
Totals
10
10
11
14
4
8
5
9
Certain valves contributed substantially to these DVRs. These are
tabulated separately as follows:
)
HPCI Valve 2301-48 (4" M0 valve, for make-up from
condensate hot well or recycle)
9 DVRs
i
'
!
HPCI High Temperature Isolation Switch
5 DVRs
,
'
RCIC Valve 1201-48
4 DVRs
4
.
RCIC Electrical Operating Switch
6 DVRs
l
The predominant work crafts involved were mechanical and electrical,
primarily related to valve, controller and operator repair and
!
replacement.
Examples of the types of problems being experienced
!
common to both the HPCI and RCIC systems were as follows:
s
<
>
i
Stem packing leaks and bent stems
M0 valves failing to travel full stroke
!
'
'
Open shunt windings
Flow controller failures (replacement)
'
Steam exhaust check valve seat failures
!
1201/2301 - 48 valve motor mount failures (vibration)
!
1
i
l
The preventive maintenance (PM) listing in b.(1), above, were defined
l
by the licensee, as items for which work was performed before a failure
i
occurred. However, they were actually routine scheduled repair work.
!
i
The team believes that these routine maintenance items, along with the
types of valve problems listed above, could be easily corrected by a
l
,
l
well developed PM program. A PM program that utilizies trending tech-
!
niques, end of life histories, and other indicators coordinated with
.
scheduled system repair / replacement can assure system dependability.
'
This programmatic concern is further expanded later in this report.
i
c.
Audits and Other Management Information
'
,
i
Auditing activity, related to the HPCI/RCIC systems, were reviewed.
'
The items covered were as follows*
2
.
!
Audit Report #04-86-56 Safety System Modification Review Unit 2
'
)
HPCI system, May 19, 1987.
i
.
This was a comprehensive audit of the HPCI system covering
I
activities and documents, in-process work requests, surveillances,
j
<
'
j
5
i
- -
- .
- -
-
-
-
I'
'.
.
'
-
.
and completed post modification testing.
Nine findings and five
observations were generated related to Technical Specifications,
design, documentation, and testing deficiencies.
The separate functions covered by this audit included the
following:
1.
25 trodification design packages were reviewed (100% of
Uni'. 2 HPCI modifications) by auditors qualified to
independently perform the design analysis and verification.
2.
Field walk downs of accessible piping systems.
3.
In Service Inspection (ISI) documentation review.
4.
Environmental Qualification (EQ) review of all items
required to be EQ.
5.
Maintenance activities review of over 100 completed WR's.
<
6.
Operation requirements and Technical Specification matrix
requirements activities review to verify compliance.
The licensee's assessment was that the HPCI and RCIC systems were
continually capable of perfonning their committed design function even
under abnormal conditions.
The team reviewed three of the nine findings for followup and close out.
Finding #2, although current, continues open for the next refuel outage
and for the next FSAR update to complete. The resolution and changes
were being adequately resolved.
Findings #8 and #9 have been acceptably
completed and closed.
The team considered this to be a comprehensive audit performed by
qualified people and documented adequately.
However, programmatic
concerns were not covered during this audit, such as the concerns
addressed later in this report.
One additional audit (No. 4-87-19) and four surveillance reports
(4-87-07, -33. -52 and -58) regarding follow up and closed out
activity for DVR's were completed with satisfactory results.
The team inquired as to the types of information being reported to
appropriate management regarding significant deficiencies (as required
by Appendix B Criterion XVI). Following is the information provided
to the team:
1.
A QA 60-day report is routinely provided to corporate management
regarding unresolved audit report findings in excess of 60 days.
2.
A goals presentation for the Quad Cities Station was held on
November 12, 1987, in which the significant deficiencies of the
HPCI/RCIC systems were presented to top corporate management.
3.
Action Item Requests (AIR's) are developed by the plant
technical staff and issued to the BWR Engineering Division for
their control of problem items most likely to develop into
modifications. On site technical staff indicated that 5 AIR's
have been issued related to HPCI/RCIC.
6
_
.
_
_
_ -
.
._ __
.
.
-
.
i
-
4.
The plant technical staff also develops trending information in
accordance with plant administrative procedure QAP 400-14,
4
Revision 2, with a monthly trending report being issued primarily
to plant management.
<
.
e
'
No violations or deviations were identified.
,
4.
Root Cause Deter:nination and Corre?tive Action
,
The team reviewed the adequacy of the licensee's root cause determination
.
and corrective actions related to problems with the HPCI and RCIC systems.
'
The team was especially concerned with the root cause determination for
those failure types with no ' prior history along with their associated
!
corrective actions and the corrective actions for failures termed as
.
-
end-of-life failures.
!
An example of the first type involved the arcing of push button contacts at
i
the local control station for the HPCI suppression pool suction valve
1
(DVR-2-87-013).
The arcing was caused by moisture and dirt which had
i
accumulated in the switch contacts resulting in a continuous "open" signal
!
(valve is normally closed). Apparently, since there was no prior history
of this failure, corrective action involved cleaning the contacts and
,
returning to service. An example of the end-of-life failure. involved the
'
packing failure on a unit one HPCI steam supply valve (LER 86-034).
In
i
,
this case the root cause was determined to be failure due to normal weer
,
and the corrective action involved packing replacement and return to
service.
l
-
The team's concern in these cases was the failure of the licensee to
'
i
address the issue of preventing recurrence that is inherent in the concept
of corrective action.
In the case of the dirty contacts, the failure to
>
determine tne root cause (e.g., environmental conditions) precluded
i
correcting the basic problem.
The alternative for preventing recurrence.
l
periodic cleaning of the contacts (planned maintenance), was also not
addressed.
'
i
In the case of the packing failure, the end-of-life failure might be
l
'
4
considered a root cause. However, it is probably more accurate to state
i
l
the root cause as failure to anticipate the end-of-life failure and to
!
take action to replace the packing prior to in-service failure.
In either
!
case the corrective action is the same, planned maintenance (or preventive
i
maintenance in the absence of service life information).
!
The licensee indicated that both the NRC and INP0 had previously expressed
!
concerns in the area of the licensee's root cause determinations. As a
'
l
result. the licensee was in the process of preparing a program to address
!
i
this issue (error free program).
This program will require that the
person (s) evaluating the more significant events have completed the
-
Management Oversight and Risk Free (MORT) training.
Events of lesser
significance would be analyzed by person (s) having completed the in-house
training on root cause analysis (already implemented).
i
.
!
The team reviewed the lesson plan for the in-house training on root cause
!
analysis.
The training was based on the MORT concept of barrier analysis
l
I
l
.l
7
,
-
. .
- .
',
'.
and the Kepner-Tregoe change analysis process. While the materials
covered were pertinent and well prepared, the inspectors did have several
concerns.
First, the amount of material covered appeared to be too much
for the one day allotted for the training.
Secondly, it appeared that
additional empnasis could be placed on tha concepts of root cause deter-
mination and corrective action as it applies to mechanical failures (e.g.,
the dirty contact problem discussed above) vs. software failures (e.g.,
management controls).
Licensee management should consider these concerns in the development of
their corrective action program.
No violations or deviations were identified.
5.
Maintenance
A general review of the corrective and preventive maintenance programs as
they applied to the HPCI and RCIC systems was conducted.
This included a
review of the administrative procedures in place for maintenance control,
of detailed work procedures, of prior system maintenance records, and of
personnel training and qualifications. Additionally, the status of the
preventive maintenance program and its implementation, including equipment
performance and trending information, was also reviewed.
a.
The team reviewed the following maintenance administrative procedures,
using them as a basis for review of maintenance activities on the
subject systems and their auxiliaries.
QAP 500-3
Maintenance Procedures
Revision 5
QAP 500-4
Inspection of Test and Maintenance
Activities
Revision 3
QAP 500-6
Maintenance Records
Revision 1
QAP 500-9
Preventive Maintenance
Revision 2
QAP 500-15
Conduct of Maintenance
Revision 2
QAP 700-1
Training
Revision 2
Training and qualification records were reviewed for electricians
(ems) and instrument mechanics (IHs). The team found that in the last
several years the number of relatively new personnel had increased and
had reduced the previously high average experience level of the de-
partments.
This was due to staff transfers to newer CECO plants and
staffing increases at Quad Cities.
The number of fully qualified
"A"
(journeyman) level personnel is approximately equal to the number of
"B" level personnel in training in each department.
According to the
Master Electrician, EM staffing has been increased from twenty to
thirty three ems; similar increases are underway in IM staffing.
The licensee has implemented an INP0 accredited craf t and technician
training program for both initial and continuing training for these
posi ti ons .
The team found that, although many of the incumbents had
been exempted from the INPO initial training, a regular program of
continuing training was in progress with the annual training comit-
rent recently increased from 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> per year per person to 80
hours.
The "B" level personnel are participating in initial training
8
.
._-
__
__.- . - . . -
. .
- - _ . _ _ . - - .
-
.
.
..
.
,
at the Braidwood Production Training Center and the site training
center, Job specific "B" level training is also provided by a
i
structured "on the job" training program. The team reviewed the
l
licensee's methods for control of personnel assignments versus-
training level and found it to be effective.
,
!<
b.
Corrective Maintenance
Corrective maintenance was not conducted on the systems during the
inspection. Work Request packages for rea nt prior repairs were
5
reviewed along with the specific work proceddres applied:
Work Request
Description
Q55637
Repair of U2 HPCI HE Pipe Whip Restraint
Q54711
Valve 2-M0-2301-6 Dual Indication & Control Problems
Q59496
Troubleshoot U1 HPCI Emergency 011 Puep Breaker
Q61499
Valve 1-M0-1300-16 Failed to Auto Close
Q62696
U1 HPCI Gland Seal Blower Failure
Q55039
U2 RCIC Turbine Outboard Bearing Reduced Oil Flow
Q12130
Reposition U1 RCIC Turbine Thermo Well
Q56255
U2 HPCI Turbine Speed Control - No Response
Q56376
Adjust U2 HPCI Speed Control Circuits
'
Q5603
U1 HPCI Turbine Will Not Reset from Control Room
Q57381
Replace Stem & Repack Valve 1-2301-4
058731
Remove U-Bolt Support 2-1301-H11
058734
Remove Rod Hanger 1-2301-H5
058735
Remove Hod Hanger 1-2325-H66
Q62908
Unit 1 RCIC Gland Seal Condenser Pump Runs Backwards
The packages were generally found to include complete records of
repair. All work involving modification of existing systems was
authorized by an approved modification package. Although the "Tests
Required" section of the Work Request forms was frequently brief and
incomplete, the packages contained records of post maintenance testing
adequate to reestablish the functionality and operability of the
affected equipment.
The packages contained, where appropriate, mate-
rial issue and certification documentation, inspection records, and
completed procedure copies. Measurement and test equipment usage and
calibration status was documented and acceptable. The work instruc-
tions were reviewed to determine that they conformed to administrative
requirements, included sufficient detail to address the problem, and
sufficiently complemented the "skills of the craft". Use of vendor
technical information was found to be controlled in accordance with
the Vendor Technical Infomation Program (VTIP). Machinery history
data was updated, but its use was limited.
The team noted that failure causes were typically oversimplified and
could cause inaccurate application of trending data.
For example,
Work Request Q62696 (above) was listed as a normal wear failure al-
though the corrective action involved cleaning and adjustment of
auxiliary contacts, i.e. an apparent need for a routine upkeep
activity.
9
___
.
.
,
Review of the licensee's specific corrective maintenance in response
to the HPCI and RCIC betterment programs found the licer.see's o.tions
to be generally effective.
The licensee is continuing to experience
some difficulties with system auxiliaries and accessories. Examples
of this include an attempt to reset the Unit 2 RCIC cooling water
pressure regulator and it failed to respond to adjustments. Also,
during a surveillance on the same system, the team observed several
steam leaks and a governor lube oil leak requiring repair. Although
the licensee's betterment plans appeared comprehensive and proactive
as discussed elsewhere in this report, the systems appear to require
continued attention,
c.
Technical Specifications
A review of facility technical specifications was performed in order
to determine what, if any, impact they had on system reliability /
performance. The team determined that the licensee's technical
specifications were more restrictive than technical specifications
of most newer plants and the requirements contained in NUREG-0123,
Revision 3, Standard Technical Specifications for General Electric
Boiling Water Reactors (BWR/5).
The major distinction between the technical specifications is that the
facility technical soecifications require an immediate demonstration
of operability for tae backup system, whereas the NUREG-0123
requirement only requires that the backup systen be operable (i.e.,
the licensee has a current surveillance showing that the systems are
operable).
In addition, the facility technical specifications also
require daily testing which is not required by NUREG-0123.
The RICI
system technical specifications has similiar distinctions.
The team believes restrictiveness of the facility technical
specifications are basically a disincentive for the license to
perform routine corrective maintenance on the HPCI and RCIC system.
Rather than impose all the additional testing on the backup systems,
the licensee perfers to accept small steam, water, and oil leaks, and
other small problems that do not effect system operability, versus
declaring the system inoperable in order to effect repairs. This not
only leads to the systems being in a less than desirable condition
but these small deficiencies may propogate and ultimately become the
precurser to a system failure. The team recommended that the licensee
,
pursue a technical specificatian change to bring the HPCI and RCIC
!
technical specifications up to the current standards for non-operability
action.
In addition, the licensee should review their technical
l
specifications for other similiar problems.
The licensee indicated
that they would pursue this course of action.
i
1
d.
Preventive Maintenance
The licensee's current preventive maintenance (PM) program is described
l
by QAP 500-9 (above) which includes a general preventive maintenance
and surveillance pr ogram, a maintendnce history file system (the CEC 0
wide Total Job Management (TJM) System), a vibrational analysis program,
a lubrication program, and provisions for trend analysis.
The team
10
l
i
'.
'
.
found that although each of the above elements was in place to some
degree, the overall PM program was weak. The team was unable to
observe any preventive maintenance on the HPCI and RCIC systems since
none was perfomed during the inspection. The programmatic elements
and records of PM were reviewed with the following results:
(1) The program for predictive maintenance included vibration analysis,
motor operated valve testing and associated trend analysis but
did not include a program for data collatior, and trend analysis
of other maintenance related trends.
Periodic maintenance such
as scheduled lubrication, cleaning, adjustments and inspection
was found to be in-place for certain equipment such as switchgear
and instrumentation.
Planned maintenance, such as regular valve
repacking, overhauls, replacement of items with known life spans,
etc., appeared to be limited to "when needed" scheduling instead
of regular periodic performance.
Essentially no periodic or planned maintenance was provided for
the HPCI and RCIC mechanical components.
For example, only one
mechanical preventive maintenance procedure existed for the RCIC
system, QMPM 1300-1, RCIC Refuel Preventive Maintenance,
Revision 1, issued February, 1988, which provides for oil change
and lubrication.
None was provided for HPCI, Although the
licensee indicated that the pumps and turbines are opened,
inspected and overhauled periodically, ainimal preventive
maintenance of system auxiliaries was provided. As discussed
elsewhere herein, the licensee's approach to the HPCI and RCIC
bettenient activities also concentrated on corrective actions
and had minimal consideration of programmatic and preventive
actions for recurrent upkeep of the systems.
(2) Although QAP 500-9, Section C.5, required trend analysis of
general PM and surveillance results, Inservice Testing (IST)
results, vibration monitoring results, Work Request data, cali-
bration data, and Deviation Reports (DVRs) and Licensee Event
Reports (LERs), no consolidated program of trend analysis was
actually implemented as a method to determine the need for PM.
Although interviewed personnel generally had a good knowledge of
j
equipment problem history and current status, the scope of PM
l
activities appeared to be driven by either specific regulatory
initiatives (e.g. environmental qualification programs) or chronic
problems challenging plant availability.
For example, the
licensee is implementing QAP 2100-1, Conduct of Reliability
Related Activities, Revision 1, for non-safety related equipment
to improve generation reliability but had no similar program for
safety related equipment and systems, such as HPCI and RCIC.
The licensee also has a "Maintenance Rework Reporting Program"
implemented by Maintenance Department Memorandum No. 46.
This
progran only identifies repetitive repairs for individual compo-
nents, (e.g. rework of the Unit 1 HPCI turbine governor would be
identified but identical failures requiring individual repairs on
both Units 1 and 2 governors would not necessarily be identified).
The rework program, therefore, does not fulfill the intent of
11
.- ___--____ - _
..
,
.
QAP 500-9, nor meet the needs for input to PM planning and scoping.
Trend analysis was formally applied to IST and vibration monitoring
data.
Some causal factor trending was applied to LERs and DVRs.
Informal review of calibration data trends was also observed as
part of instrument maintenance and surveillance activities.
However, essentially no broad based trending of Work. Request or
other failure data was conducted for safety related systems.
Quad Cities participates in the Nuclear Plant Reliability Data
System (NPRDS), but staff interviews found that it was rarely
used and the licensee had difficulty in retrieving review data
requested by the team.
Similarly, the licensee maintains a
computerized preventtve maintenance and surveillance scheduling
system (GSRV). The inaintenance department staff had difficulty
in retrieving GSRV preventive maintenance status information for
April 1988, and the report eventually provided by the licensee
included essentially no safety related equipment information and
contained numerous "last performed /next due" data errors.
The corporate wide TJM system appears to include extensive work
and failure history information.
The system has been in place
about two years and, although some historical information is
still being entered, the system does not appear to be used for
detailed analysis of equipment performance.
For txample, the
team noted a regular history of failures for air operated valves
and their accessories (solenoids,
I/Pconverters,etc.). The
licensee was generally aware of the failure history but had not
evaluated the possible trend because the failures had not chal-
lenged plant availability rior impacted Technical Specification
operability. The team noted that, although QAP 500-9 stipulated
that the functions above be accomplished, specific responsibili-
ties for the review and analysis of the data were not specifically
assigned and no one appeared to be held accountable for the
function.
As part of the CECO corporate INP0 goals, the licensee has recently
approved Directive N00-MA.2 and "Conduct of Maintenance at Nuclear
Power Stations" for company wide application.
This 120 page
document redefines maintenance activities and responsibilities,
defines standardized plant staffing elements, and provides a
broad new program for preventive maintenance and maintenance
history use, and appears to address the team concerns and licensee
program shortcomings discussed above.
Team interviews indicated
that this program is expected to take about three years to fully
implement.
Additional licensee management attention appears warranted to
fully use the information available for development and imple-
mentation of preventive maintenance activities sensitive to
equipment performance.
No violations or deviations were identified.
12
_
_-
_ _ _ _ _ _ _ _ _ _
,
.
6.
System Walkdowns
7
a.
HPCI and RCIC Rooms - General Condition
Prior NGC inspection of these rooms had found that the general
structures and equipment appearance and state of preservation
were poor. The HPCI rooms and equipment had recently been re-
painted and preparations for painting the RCIC/ Core Spray rooms
were in progress.
During a tour of the HPCI and RCIC/Cere Spray rooms on March 29,
1988, the team observed that the Unit 2 RCIC room was being
prepared for painting.
The team found that the painting crew had
begun to install plastic sheet (drop cloth) masking and scaffold-
ing over RCIC and Core Spray pumps and equipment (scaffolding is
further discussed below). Both systems were considered to be
operable with respect to technical specifications. The floor was
strewn with loose bundles of plastic sheeting and untaped sheeting
was draped over the piping, valves and pumps.
Sheeting over the
Core Spray pump had the potential for blocking cooling air exhaust
from the pump motor and was loosely draped in the vicinity of the
pump shaft and thus providing the potential for entanglement in the
shaf t and blocking of motor air inlets. Additional sheeting was
installed over the RCIC pump and turbine, including the trip and
throttle valves, and had partially melted cn the steam supply piping.
The System Engineer accompanying the team insnediately removed sheeting
which appeared to represent the greatest risk of fouling system
components if system initiation occurred.
The licensee also dispatched
an Operating Engineer to inspect the room.
The Operating Engineer's initial inspection of the room concluded
that the conditions did not directly affect system operability
Subsequent inspection by the Production Superintendent, however,
.ndetermined that the conditions were unacceptable and resulted in
rearrangement of the plastic sheeting, removal of excess material,
u
and provision of additional instructions to the contractor painting
crews.
The licensee further confirmed, in response to an inspectors
question, that the plastic sheeting was fire retardant and did not
present a combustible hazard.
The Production Superintendent advised
the team that the Operating Engineer had been coordinating the painting
activities with the contractor crews but that the team had observed
the conditions prior to the Operating Engineer's planned final
inspection of the painting preparations.
b.
Temporary Scaffolding Installations
As part of the painting and general pre-outage preparations, contractor
crews had insti.lled scaffolding in the HPCI and RCIC rooms (and
elsewhere). L'e team found scaffolding erected above valves and
instruments and tied off to safety related equipment (air piping,
conduit,etc.).
The team expressed concern regarding the prudence
of, and procedures available for, control of non-seismic scaffolding,
susceptibility of the scaffold to installation errors and mechanical
failure, post installation inspection, and safety of transient loads
13
_
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
___
_ _ _ _
_
.
.
.
,
over and/or scaffolding secured to systems and equipment considered
,
operable with respect to TS.
The licensee reinspected the installations and modified and retied
the scaffolding to more appropriate structural members.
They advised
the team that interim guidance hac been previously provided to the
installation contractor and that a draft administrative procedure
had been developed for long term controls. This procedure was expected
to be issued during April, 1988.
The team reviewed QAP 1700-7,
Scaffold Control Requirements (DRAFT), and found that it addressed
general considerations for such installations, including "Seismic
Class !! over I" considerations but did not include several other key
fac tors .
It did not provide for a safety evaluation, addressing the
criteria of 10 CFR 50.59, of sceffold installations with respect to
review of hazards to operable safety related equipment, availability
of unaffected redundant systems, control of transient overhead loads
on the scaffold, etc.
These aspects were discussed with the Assistant
Superintendent Maintenance who said that appropriate revisions would
be made to the draft procedure prior to issuance and guidance would
be used in the interim.
This is considered an open item pending NRC
review of the final program (254/88007-01; 265/88008-01).
c.
Calibration Status - RCIC Room Reactor Vessel Level Local Indicators
local reactor water level indicating differential pressure instruments
1/2-1360-28 and 1/2-1360-29 are installed in each RCIC room. The team
noted that the calibration stickers on level indicators bore calibra-
tion dates from 1977 through 1984.
Review of Instrument Department
records determined that the actual latest calibration dates were 1984
for both Unit 1 instruments and 1983 and 1987, respectively, for the
Unit 2 instruments. The instruments are used for reactor level control
if operating the RCIC system locally in accordance with Q0P 1300-9,
RCIC Local Manual Operation Procedure,
Revision 6, which is used as
part of Abnormal Procedure Q0A 010-5, Plant Operation with the Control
Room Inaccessible, Revision 5.
The team further determined that these
instruments are not currently included in plant procedures or schedules
for periodic recalibration.
The Master Instrument Mechanic advised
the team that the instruments would be included in the periodic recal-
ibration schedule.
The frequency of calibration was under evaluation
at the end of the inspection but was expected to be on the order of
once per five years with recalibration of at least the Unit 2
instrument scheduled for the outage beginning on April 10-11, 1988.
No violations or deviations were identified.
7.
Surveillances
The team reviewed surveillance activities applicable to the HPCI and RCIC
systems including review of operations and maintenance surveillance proce-
dures and data and observation of a monthly perforTnance test of the Unit 2
RCIC system.
14
a.
>
.
.
-
.
a.
Program and Procedures
The surveillance procedures, scheduling and performance data were
compared to Technical Specifications (TS) 3 2/4.2, Protective Instru-
mentation, and 3.5/4.5, Core and Containment Cooling Systems. Current
Operations Surveillance Test Assignment Sheets QOS 005-S2, -S3, -54,
and -SS were also reviewed for conformance with TS.
In addition, a
sample of operations and maintenance procedures were reviewed using
the guidance of NUREG/CR-1368, Development of a Checklist for Evaluat-
ing Maintenance, Test, and Calibration Procedures Used in Nuclear
Power Plants, Appendix C, "Procedures Evaluation Checklist". Proce-
dures reviewed are listed below. Those annotated with a single aster-
'
isk (*) included review of performance data.
Those indicated with a
plus sign (+) included review per the NUREG/CR-1368 checklist.
Each
procedure was also reviewed using its referenced piping and instrumen-
tation diagrams and electrical schematic diagrams to verify the
technical accuracy of the test methods.
Revision
QIS 7-1*
Drywell Pressure Calibration
2
QIS 7-2*
Orywell Pressure Functional Tests
3
QIS 11-1*
Low Low Reactor Water Level Calibration
4
QIS 11-2*
Low Low Reactor Water Level Functional Test 4
QIS 15-1*+
HPCI Reactor Low Pressure Analog Trip
4
System Calibration
QIS 15-3*+
HPCI Reactor Low Pressure Transmitter
4
Calibration
QIS 16-1*+
PPCI Steam Line High Flow Analog Trip
5
System Calibration
QIS 17-1*+
RCIC Reactor Low Pressure Calibration
3
QIS 17-2*
RCIC Reactor low Pressure Functional
4
Test
QIS 18-1*
RCIC Steam Line High Flow Calibration
3
QIS 18-2*+
RCIC Steam Line High Flow Functional Test
5
QIS 27-1*+
HPCI Turbine Area High Temperature Isolation 7
Calibration
QIS 28-1*t
RCIC Turbine Area Hi Temperature Calibration 10
QMS 700-4+
HPCI Logic Functional Test
13
QMS 700-3+
RCIC Logic Functional Test
14
QOS 1300-1*+
RCIC Monthly Test (observed performance)
6
QOS 1300-3*
RCIC M0V Operability Test
3
QOS 1300-7*
RCIC Manual Initiation Test
1
00S 2300-1*
HPCI Pump Flow Rate Testing Operations
13
Q05 2300-2*
HPCI Pump Operability Test (Monthly)
10
Q05 2300-3*
HPCI Valve Operability
4
QOS 2300-4*
HPCI Power Operated Valve And Check
7
Valve Testing at Cold Shutdown
Q0S P300-6*
HPCI Power Operated Valve Test - Every
4
.
90 Days
Q0S 2300-13*
HPCI Hot Fast Initiation Test
1
i
!
15
_
_ _ _ _ _ .
_ - _
- _ _ _ .
._
-_
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
__
_ _ _ _ _ _ _
-
. _ _
_ __ ____ __
_
_ _
_ _ _ _ _
.
.
.
b.
Procedure Review Findings
The Quad Cities units were licensed in 1971-72 and most operating,
surveillance, and maintenance procedures have evolved from those origi-
nally in place at the time of licensing.
The licensee has recognized
that the plant procedures require upgrading to meet current NRC and
INP0 standards and had begun a progressive procedures improvement
program.
Mechanical and electrical maintenance and surveillance
procedures were being rewritten with substantial progress made at the
time of this inspection.
Plans for the next two to three years in-
cluded continuation of this effort.
The "new" procedures reviewed were found to be a substantial improvement
over the unrevised procedures and appeared to include both the technical
detail and human factors elements considered necessary to enhance
pc monel performance and permit strict procedure adherence.
The
unrevi ed procedures were generally found to contain minimal technical
instruction detail and relied heavily on craft knowledge and skills to
effect successful completion.
In the past, the licensee had maintained a very stable craft work
force having extensive plant specific experience.
As a result of
personnel transfers to other new CECO facilities and Quad Cities staff
growth, the experience level of the in house staff has declined, with
about half to two thirds of the Electrical and Instrument Maintenance
Departments craft personnel being in an initial training status and
having two to three years (or less) station experience. The relative-
,
ly low average experience levels, combined with the existing proce-
dures' requiring a heavy reliance on skills of the craft, emphasized
the need to expedite the procedures upgrade program.
One example of
difficulties resulting from procedure inadequacies experienced during
an instrument calibration activity is further discussed below.
Review of completed maintenance and surveillance data found that the
licensee's programs were generally effective in identifying and
correcting unacceptable results.
The licensee has, in some cases,
progressively adjusted acceptance criteria and techniques to accommo-
date observed variations in calibration and equipment performance trends.
For example, the nominal calibration of RCIC Steam Line High Flow
instruments has been adjusted to provide a comfortable margin between
the maximum observed instrument drift, the technical specification
limiting condition for operation setpoint, and the normal operating
range.
The team found no cases in which anomalous data or unsatis-
factory results were not identified and processed by the licensee's
corrective action and reporting programs.
The procedure observations b0 low each typically apply to a number of
similar procedures even though only limited examples are provided.
l
QAP 1100-3, Station Procedure Periodic Review, Revision 15, includes
checklists for review of procedures which contain some of the elements
discussed below:
NUREG/CR 1368 contains others. The procedure
upgrade and review program should be reviewed by the licensee to
ensure that it is effective in identifying and addressing these and
similar procedure weaknesses. Specific observations include:
16
-
..
.
. _ , _
-
-
_ ______ _
'.
\\
.
i
(1) QIS 15-1, HPCI Low Reactor Pressure Analog Trip System Calibration,
provides calibration of channel trip units and associated
circuits quarterly but provides for transmitter calibration only
once per operating cycle. Technical Specification Table 4.2-1,
HPCI Isolation, Low Reactor Pressure, Amendment No. 90 requires
channel calibration to be accomplished once every three months.
The existing table footnotes provide no exception for the
transmitters.
Discussions with Regulatory Assurance personne' determined that
Note 10 had been inadvertently deleted from technical specification
Table 4.2-1 during a prior amendment and had previously permitted
the transmitter calibration only once per cycle.
A proposed
technical specification Amenduent had been prepared restoring the
note, had been approved by the Onsite Review function in late 1987
(OSR No. 87-39), and had been submitted to Offsite Review (Item
No. 88-02) on February 18, 1988, for routine processing. This
finding is similar to that involvir;g incorrect technical specifi-
cation presentation of area temperature monitoring channels.
(2) The licensee's program for independent verification of prepar
return to service of safety related equipment appears weak.
NUREG 0737, Clarification of TMI Action Plan Requirements. Item
I.C.6, Guidance on Procedures for Verifying Correct Performance
of Operating Activities, requires that, for the return to service
of equipment important to safety, a second qualified operator
should verify proper system alignment unless functional testing
is used to verify that all equipment, valves, and switches are
correctly aligned. The licensee had committed to conformance
with Item I.C.6 and has included independent verification provi-
sions in the procedures reviewed.
However, the methods used for verification and documentation
provide the potential for personnel oversight.
Typically, both
'
the return to service lineup instructions and the independent
verification instructions each consist of a single, generalized
line item which covers numerous individual valve, switch, jumrar
wire, lifted lead, or relay block verification steps. Examp'es
include:
QOS 2300-1, HPCI Pump Flow Rate Test, involves extensive
-
valve and switch manipulation.
The procedure steps art not
individually signed off.
Rather, Data Sheet QOS 2300-31 is
used to document completion and single line action items
"Verify HPCI system readiness per Q0P 2300-1" and "Indepen-
dent Verification of Operability Status Following Test",
each requiring a single signature provide the only guidance
for verification the multiple return to normal steps.
Q0S 2300-3, HPCI Valve Operability Test, cycles about 15
-
valves with return to service posit'ons verified only by a
single entry check off list.
17
.
.
..
.
. ..
_
_-
- - - - . - - - - _ - - - - - - _ - - - . - - - -
-
.
,
Calibration procedures such as QIS 7-1, Drywell Pressure
-
Calibration, typically use only a single line verification
signature for independent verification of valve return to
service alignment.
In other procedures, such as QIS 28-1, RCIC Turbine Area
-
High Temperature Calibration, jumper wires are extensively
used and removal verification is provided by return of the
jumper wires to the control room.
In each case above, the methods used do not provide step by step
control of the verification process and, in some cases, require
the verifier to scan an entire procedure to determine which
components were disturbed and their respective final conditions.
In one case. QOS 2300-3, it was not clear that independent
verification was either required or performed although interviews
indicated that it had been. The above represent only selected
examples of such practices. Nearly all procedures reviewed
included some ambiguity or single step verification directions.
The team believes that the methods described above provide a high
potential for return to service realignment and independent
verification errors. The manner in which the realignments and
verifications were documented did not permit a detemination
whether the required individual equipment actions were actually
perfonned as required.
(3) Many procedures not yet revised under the upgrade program
provided precautions, limitations and actions only in the front
section of the procedure rather than preceding the action step
i
to which they applied, providing the potential for oversight.
4
For example, QOS 2300-1. HPCI Pump Flow Rate Testing, includes
eight precautions and seventeen limitations and actions which
'
warrant consideration for incorporation into the procedure action
step sequence.
(4) As indicated above, procedures typically do not require step by
step signoff. Data and required action signoffs are included in
l
separate data sheets and tables which become the documentation of
l
performance. The "linkage" between procedure action steps and
the data sheets is typically poor with data sheet step numbering
,
either absent or different from the equivalent procedure steps,
'
particularly for operating surveillances, instrument functional
tests and calibrations.
For example, the data sheets for Q05
,
2300-1 and 2300-3 include no step numbering or cross references
<
to the procedure. The data sheet numbering mismatches with the
procedure step numbering for QIS 28-1 and QIS 28-2.
The QOS
2300-2 data sheet for as left conditions includes no instructions
{
for completion or reference to the procedure action steps. As a
result the data entries were completed differently for six test
performances (both units) between December, 1987 and February,
,
1988.
18
,
?;
'
.
f
'
(5)
In nearly every case reviewed, acceptance criteria tolerances
were not expressed as ranges but rather as +/- values requiring
,
the performer to mentally calculate acceptability of results.
For example, QIS 27-1 provided an acceptance criteria for'the
1
,
HPCI area temperature isolation function of 185, +5, -10 degrees
'
i
F. rather than a range of 175 - 190 degrees F.
This practice is
contrary to fundamental human factors principals.
(6) Detailed work instructions were frequently found to be overly
!
general and relying heavily on the skills and knowledge of the
craft.
Further, .in several cases,
the instructions were suffi-
+
ciently general to permit variations or errors in performance
which could affect test outcome, particularly for less experi-
i
enced personnel.
For example, QIS 28-1 requires repetitive
,
i
installation of jumpers to test isolation logics but the instruc-
tions are provided by a single, generalized Step F.2.
Similarly,
i
QIS 17-1 includes instructions for testing the RCIC Reactor Low
'
!
Pressure Isolation when actual reactor pressure is above the
i
!
channel setpoint, requiring manipulation of switches but provid-
i
ing only generalized instructions rather than a step by step
i
method.
(7) The team observed performance of QIP 1600-3, Suppression Chamber
l,
Water Level Indication Calibration, Revision 1 on April 5,1988.
The team reviewed the above procedure and the work package for
Work Request Q65444 issued for the work and observed the first
I
half shift of initial attempts to calibrate. The "A" journeyman
Instrument Mechanic assigned to the task had previously performed
,
the calibration and appeared familiar with both the equipment
!
installation and procedure. Pre-job preparations appeared com-
1
plete with the necessary tools, material, and assisting personnel
available.
The instrument transmitter was located in the RHR P.com,
>
immediately beneath the RHR Heat Exchanger head in a 100 - 700
,
!
mrem radiation field. Additional semi-permanent test equipment
!
(calibration manometer, regulated air supply, valving, etc.) was
!
located opposite the transmitter wall mount in the torus area.
Initial difficulties were encountered in alignment of the trans-
.
I
mitter isolation valves, test manometer and air supply. The
!
equipment is located about 15 feet above floor level in the torus
area and is partially obstructed by piping.
The procedure provided
1
'
general valve lineup instructions for the test equipment which did
j
not match the actual installation. Due to the physical arrangement,
j
the technician could not see the entire test rig and had to manipu-
late the system by "feel" from a small elevated grating.
As a
result of the procedure not including valving actually installed
in the test equipment, the initial attempt to pressurize the
l
equipment for test was unsuccessful due te closed valves.
l
Procedure Step 7 instructs the performer to check the instrument
calibration and recalibrate if required.
Procedure Step 7, Note,
-
!
states "For calibration methods, see Barton Instruction Manual
l
(iiodel 368)". The connection points for the milliammeter could
i
!
19
{
. _ - - _ _ _
.
. .
'
.
not be identified in the procedure or instruction manual by the
technician. The technician initially connected the meter in a
manner he believed to be correct. This connection was incorrect
and the circuit's power supply fuse blew.
Subsequent discussion
with the Master Instrument Mechanic determined that the meter
connection points were specified in the "Limitations and Actions
Section" of the procedure instead of the "Procedure" section and
had been overlooked by the technician. Additionally, the speci-
fied points involved connection of the meter at the indicator
unit in the control room rather than at the calibration work
location.
Connection at the specified control room location
would have further compounded the difficulty of performance
requiring the technician to make local adjustments at the trans-
mitter while being directed via telephone by the person remotely
reading calibration meter. This represents an example of multiple
procedure deficiencies impacting the effectiveness of the
procedure.
Following fuse replacement, initial attempts to recalibrate the
transmitter were unsuccessful due to apparent instability in the
circuit electronics.
Additional difficulties were encountered
in maintaining a stable test air pressure due to poor response
from the semi-permanent test air regulators.
The procedure and equipment difficulties also detracted from
ALARA performance. Although the technician prudently minimized
his exposure in the higher radiation fields at the transmitter,
an extension of the normal 100 mrem daily exposure limit was
required after one half shift of work with the transmitter still
uncalibrated. The technicians exposure rate was approximately
2-4 times that of the inspector (who witnessed most of the work
from a designated ALARA waiting area within the room, about 8 - 10
feet from the transmitter).
ALARA considerations were discussed
with the Production Superintendent, Assistant Superintendent
Maintenance, and a Radiation Protection Supervisor on April 5.
The team concluded that, except for the procedure and equipment
deficiencies, the ALARA practices applied to the job were
acceptable.
The procedure deficiencies were discussed with the license
management, who indicated that the subject procedure was
generally known to require improvement but was not considered
technically inadequate. Team interview results with IM Depart-
ment personnel had indicated that this procedure was considered
difficult to perfom and that there were other similar examples
of poor instrument procedures. The licensee advised the team
that QIP 1600-3 would be revised to improve its perfonnance
prior to its next use but that the Instrument Procedures were
not scheduled for near term rewriting under the procedure upgrade
program in that they were believed to be in better overall
.
condition than the electrical and mechanical procedures which
were receiving higher priority.
20
_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ - _ __
._
_ - _ _ _ _
_ _ _ _ _ _ - _ _ _ - _
l
'L
';
-
1
'
In response to the specific team observations for this procedure
(
and the general procedure observations previously discussed, the
-
licensee committed to take the following actions to ensure that
1
any similar problematic procedures would receive priority
attention:
Instrument Department personnel would be polled to identify
-
similar problem procedures.
These procedures will be
revised prior to their next use.
Partial polling had been
completed by the end of the inspection with the remainder
of the staff to be contacted within.the following several
t
days. At the close of the inspection, one additional
'
procedure was reported to require immediate revision by
,
licensee management.
j
l
A procedure user's feedback / comment sheet will be implemented.
-
These sheets will be attached to all instrument procedures
,
.
and will require direct feedback from performance of each
procedure.
The licensee expected to implement this process
'
by April 15, 1988.
g
i
t
All instrument procedures will be subjected to the comment
i
-
sheet process and resulting coments will be incorporated
into the procedures by the end of CY 1988,
t
4
.'
This is considered an open item pending NRC review of the
implementation of the above program (254/88007-02; 265/88008-02).
'
>
c.
Surveillance Observation
!
>
On April 4, 1988, the team observed performance of 005 1300-1, RCIC
Monthly Test, from the control room and locally at the RCIC room. The
l
'
test was completed satisfactorily, however minor difficulties were
encountered.
l
The procedure, Step F.6 requires that the RCIC test bypass (to contam-
[
j
inated condensate storage tank) be opened a "pre-determined number of
!
turns" to establish a pump discharge pressure of 1150 to 1350 psig.
!
i
]
However, the procedure does not provide or refer the operator to the
required valve position. As a result, the operators encountered
,
difficulty in setting the valve position resulting in a slight delay
1
in completing the test.
e
During the test, maintenance personnel attempted to reset the cooling
i
water flow pressure regulator (part of the RCIC action plan), and were
.
!
unable to obtain valve response. Also, a minor lube oil leak was
,
!
found on the turbine governor, the system engineer was notified, and
l
a work request was requested.
~;
i
No violations or deviations were identified.
,
,
I
l
l
.
h
21
{
i
,
,
' , '
.
,
8.
Open Items
Open items are matters which have been discussed with the licensee which
will be reviewed further by the inspector, and which involve some action
on the part of the NRC or licensee or both. Open Items disclosed during
the inspection are discussed in Paragraphs 6.b and 7.b.(7).
9.
Exit Interview
The team met with licensee representatives (denoted in Paragraph 1) at the
conclusion of the inspection on April 7,1988, and sunmarized the scope
and findings of the inspection activities. The team also discussed the
likely infonnational content of the inspection report with regard to
documents or processes reviewed by the team during the inspection.
None
of the areas expected to be contained in the report were identified by
the licensee as propriety.
The licensee acknowledged the findings of the
inspection.
i
22