UNITED STATES OF AMERICA ATOMIC ENERGY COMMISSION In the Matter of
)
)
THE CINCINNATI GAS & ELECTRIC COMPANY
)
COLUMBUS AND SOUTHERN OHIO ELECTRIC COMPANY )
Docket No. 50-358 THE DAYTON POWER AND LIGHT COMPANY
)
)
Wm. H. Zimmer Nuclear Power Station
)
l DETERMINATION TO CONTINUE CERTAIN ACTIVITIES AT THE WM. H. ZIMMER NUCLEAR POWER STATION 1
Pursuant to the provisions of Section 50.10 of 10 CFR Part 50 of the Atomic Energy Commission's (Commission) regulations, the Commission has determined that The Cincinnati Gas & Electric Company, the Columbus and Southern Ohio Electric Company, and The Dayton Power and Light Company (the applicants) may continue certain site preparation activities involving the Wm. H. Zimmer Nuclear Power Station prior to a decision regarding the issuance of a construction permit.
In an application dated April 6, 1970, The Cincinnati Gas & Electric Companf, the Columbus and Southern Ohio Electric Company, and The Dayton Power and Light company applied for a permit to construct a boiling water nuclear power reactor, designated as the Wm. H. Zimmer Nuclear Power Station, located on the Ohio River in Clermont County, Ohio. On March 21, 1972, the Commission adopted revised regulations concerning site prepara-tion, and, by letters dated March 31, 1972, and April 19, 1972, the applicants submitted in accordance with Section 50.10 of 10 CFR Part 50, as revised, reasons why site preparation activities already commenced at the Zimmer site should be permitted to continue.
The site preparation 8709240155 870921 PDR FOIA MENZB7-111 PDR
~
, involves grading, road construction, site drainage, excavation and recompaction in the circulating water piping, reactor, and turbine generator areas, preparation and erection of temporary buildings for construction, and construction of a river terminal and related facilities.
(This latter activity does not incluJe disturbing the river bed.)
On the basis of the applicants' environmental report and the Commission's Draft Environmental Statement Related to the Proposed 1
Construction of the Wm. H. Zimmer Nuclear" Power Station and the supple-mental information submitted by the applicant on March 31, 1972, and on April 19, 1972, and after consideration and balancing of the environmental factors specified in 10 CFR 8 50.10(d)(2) of the Commission's regulations, it has been determined that the continuation of the above-mentioned site preparation activities is authorized pending a decision concerning the issuance of a construction permit to the applicants for the Wm. H. Zimmer Nuclear Power Station.
This determination shall have no bearing upon the subsequent granting or denial of a construction permit for the proposed,Wm. H. Zimmer Nuclear Power Station and any site preparation work shall be performed entirely at the risk of the applicants.
The basis for making this determination is set forth in a document entitled " Discussion and Findings by the Directorate of Licensing, U.S.
Atomic Energy Commission, Relating to a Request to Continue Certain Site Activities at the Wm. H. Zimmer Nuclear Power Station Prior to the Completion of the NEPA Environmental Review, AEC Docket No. 50-358".
- ~
7, 3'-
The applicants' letters dated March 31, 1972, and April 19, 1972, the regulatory staff's Safety Evaluation, dated February 18, 1972, the-applicants' Environmental Report, dated June 22, 1971, with supplements and amendments thereto, the Commission's " Draft Environmental Statement Related to the Proposed Construction of the Wm. H. Zimmer Nuclear Pever Station", dated March, 1972, and the Discussion and Findings referred to above are available for public inspection at the Commission's Public Document Room, 1717 H Street, N.W., Washington, D.C., and the Clermont
' County Court House, Batavia, Ohio. Copics of the Discussion and Findings document. may be obtained upon request addressed to the United States Atomic Energy Commission, Washington, D.C.
20545, Attention:
Deputy Director for Reactor Projects, Directorate of Licensing.
DatedatBethesda, Maryland,thisSh/dayof3hh,1972.
FOR THE ATOMIC ENERGY COMMISSION Y
/
p A.
ambusso, Deputy Director for Reactor Projects
]
Directorate of Licensing 8
l-O