Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Pole Shafts for All Four Breakers Replaced During Recently Completed Refueling Outage
ML20247N728
Person / Time
Site: Millstone Dominion icon.png
Issue date: 07/24/1989
From: Mroczka E
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To: Russell W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
A07039, A7039, IEB-88-001, IEB-88-1, TAC-65955, TAC-65956, NUDOCS 8908030133
Download: ML20247N728 (2)


Text

'

i NORTHEAST UTILITIES o n.,,i ome.. . somen si,,,,, B.,un, conn.c,ico, THE CffMNEC1fC# L4HT eMD.OWf t COe#W Z "[*Z'lU'j

, '"" P.O. BOX 270 HARTFORD, CONNECTICUT 06141-0270 g '

i d .mma tures uw.es==ce.

co.,,

oatmass .wcma (203) 665-5000 l

July 24, 1989 Docket No. 50-423 A07039 Re: NRC Bulletin 88-01 TACS 65955/65956 Mr. William T. Russell, Regional Administrator Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

References:

(1) NRC Bulletin No. 88-01: Defects in Westinghouse Circuit Breakers, dated February 5, 1988.

(2) E. J. Mroczka letter to V. T. Russell, " Response to NRC Bulletin No. 88-01", dated March 25, 1988.

Gentlemen:

Millstone Nuclear Power Station, Unit No. 3 NRC Bulletin No. 88-01 Defects in Westinghouse Circuit Breakers Roterence (1) requires licensees using certain Westinghouse circuit breakers to perform inspections of those breakers. Reference (2) provided Northeast Nuclear Energy Company's (NNECO) initial response to Reference (1). As described in Reference (2), the two reactor trip breakers and two bypass breakers did not meet all of the Reference (1) short term inspection acceptance criteria. Therefore, the pole shafts for all four breakers were replaced during the recently completed refueling outage. All actions required by this Bulletin are now complete.

If there are any questions, please do not hesitate to contact my staff.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY

/ NM A)

E. K fr6dzka~ f/

Senid Vice Prefident 8908030133 890724 PDR g ADOCK 05000423 PDC

^

[8k

USNRC

'*A07039/P:ga 2 July 24, 1989 STATE OF CONNECTICUT )

) ss. Berlin COUNTY OF HARTFORD )

Then personally appeared before me, E. J. Mroczka, who being duly sworn, did state that he is Senior Vice President of Northeast Nuclear Energy Company, Licensee herein, that he is authorized to execute and file the foregoing information in the name and on behalf of the Licensee herein, and that the statements contained in said information are true and correct to the best of his knowledge and belief.

11&L 1F Notary Pub MyCommission Expires March 31,1993 cc: U. S. Nuclear Regulatory Commission Document Control Desk Vashington, DC 20555 D. H. Jaffe, NRC Project Manager, Millstone Unit No. 3 V. J. Raymond, Senior Resident Inspector, Millstone Unit Nos. 1, 2, and 3 l