August 2, 1988 Docket Nos. 50-313 and 50-368 Mr. T. Gene Campbell

-Vice President, Nuclear Operations Arkansas Power.& Light Company Post Office Box 551 Little Rock, Arkansas 72203

Dear Mr. Campbell:

SUBJECT:

NRC BULLETIN 88-01, "DEFECTS IN WESTINGHOUSE CIRCUIT BREAKERS" (TACS65955/65956)

On February 5, 1988, NRC Bulletin 88-01 was issued and requested holders of operating licenses or construction pemits to provide letters of confirmation to the NRC of the completion of specified inspections on Westinghouse DS series circuit breakers. Addressees who do not have DS series circuit breakers in Class IE service were requested to provide a letter to the NRC stating this fact.

Your response dated April 1, 1988 confirmed that Westinghouse DS series circuit breakers are not used in safety-related applications at Arkansas Nuclear One. Thus, your response to Bulletin 88-01 is satisfactory and no further reply is necessary.

Sincerely,

/s/

C. Craig Harbuck, Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc: See next page DISTRIBUTION

. Docket File:' j NRC PDR Local PDR PD4 Reading i

L. RuhEnstein J. Calvo P. Noonan C. Harbuck C. Abbate OGC-Rockville E. Jordan B. Grimes ACRS(10)

PD4 Plant File DHood

  • See previous concurrence:

PDIV:PE PDIV:PM g PDIV:D p M 0(\\

L(\\

CAbbate/kb CHarbuck JCalvo 08/02/88 08/ f-/88 08/1/88 8808110330 880802 PDR ADOCK 05000313 O

PDC

Docket Nos. 50-313/368 Mr. Dan R. Howard, Manager Licensing Arkansas Power & Light Company Post Office Box 551 Little Rock, Arkansas 72203

Dear Mr. Howard:

SUBJECT:

NRC BULLETIN 88-01, "DEFECTS IN WESTINGHOUSE CIRCUIT BREAKERS (TACS65955/65956)

On February 5, 1988, NRC Bulletin 88-01 was issued and requested holders of operating licenses or construction pemits to provide letters of confirmation to the NRC of the completion of specified inspections on Westinghouse DS series circuit breakers. Addressees who do not have DS series circuit breakers in Class IE service were requested to provide a letter to the NRC stating this fact.

Your response dated April 1, 1988 confirmed that Westinghouse DS series circuit breakers are not used in safety-related applications at the Arkansas Nuclear One plant. Thus, your response to Bulletin 88-01 is satisfactory and no further reply is necessary.

Sincerely, C. Craig Harbuck, Project Manager Project Directorate - IV Division of Reactor Projects - III.

IV, Y and Special Projects Office of Nuclear Reactor Regulation cc: See next page DISTRIBUTION Docket File NRC PDR Local PDR PD4 Reading L. Rubenstein J. Calvo P. Noonan C. Harbuck C. Abbate OGC-Rockville E. Jordan B. Grimes ACRS (10)

PD4 Plant File DHood PDIV: b POIV:PM PDIV:D CAbbate/tb CHarbuck JCalvo 08/9/88 08/ /88 08/ /88

August 2,1988 Docket Nos. 50-313 and 50-368 Mr. T. Gene Campbell Vice President, Nuclear Operations Arkansas Power & Light Company Post Office Box 551 Little Rock, Arkansas 722C3

Dear Mr. Campbell:

SUBJECT:

NRC BULLET!H 88-01, "DEFECTS IN WESTINGHOUSE CIRCUlT BREAKERS" (TACS65955/65956)

On February S, 1988, NRC Bulletin 88-01 was issued and requested holders of operating licenses or constructior, permits to provide let;ers of confirmation to the NRC of the completion of specified inspections on Westinghouse DS series circuit breakers. Addressees who do not have DS series circuit breakers in Class 1E service were requested to provide a letter to the NRC stating this fact.

Your response dated April 1,1988 confimed that Vestinghouse DS series circuit breakers are not used in safety-related acplications at Arkansas Nuclear One. Thus, your response to Bulletin 88-01 is satisfactory and no further reply is necessary.

Sincerely,

/s/

C. Craig Harbuck, Project b ager Project Directorate - IV Division of Reactor Projects - III,

!Y, V and Special Projects Office of Nuclear Reactor Regulation cc: See next page DISTRIBUTION Docket File NRC PDR Local PDR PD4 Reading L. Rubenstein J. Calvo P. Hoonan C. Harbuck C. Abbate OGC-Rockville E. Jordan B. Grimes ACRS(10)

PD4 Plant File DHood "See previous concurrence:

JCalvo /1X PDIV:0 PDIV:PE PDIV;PM g CAbbatelkb CHarbuck 08/02/88 08/2-/88 08/1-/88

w.

b Micoq'o, s

4 UNITED STATES v

NUCLEAR REGULATORY COMMISSION

~~,

g

,j y

j WASHING TON, D. C. 20555
  • g * * *. * /

August 2,1988 Docket Nos. 50-313 and 50-368 Mr. T. Gene Campbell Vice President, Nuclear Operations Arkansas Pcwer & Light Company Post Office Box 551 Little Rcck, Arkansas 72203

Dear Mr. Carrpbell:

SUBJECT:

NRC BULLETIN 88-01, "DEFECTS IN WESTINGHOUSE CIRCUIT BREAKERS" (TACS 65955/C5956)

On February 5,1988, NRC Bulletin CE-01 was issued and requested holders of cperating licenses or construction pertMts to provide letters of confirmation to the NRC of the completion cf specified inspections on Westinghouse DS series circuit breakers. Addressecs wno do not have DS series circuit breakers in Class IE service were requested to provide a letter to the NRC stating this fact.

Your respense dated April 1,1988 confirmed that Westingbouse DS series circuit breakers are not used in safety-related applications at Arkansas Nuclear One. Thus, your response to Bulletin 88-01 is satisfactory and no further reply is necessary.

Sincee'ely, 46 C. Craig Harbuck, Project fianager Project Directorate - IV Division of Reactor Frojects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation cc: See next page

~

Mr. T. Gene Campbell Arkansas Nuclear One Arkansas Power & Light Company Unit Nos. I and 2 cc:

Mr. Dan R. Howard, Manager Mr. Charles B. Brinkman, Manager Licensing Washington Nuclear Operations Arkansas Nuclear One C-E Power Systems P. O. Box 608 7910 Woodmont Avenue Russellville, Arkansas 72801 Suite 1310 Bethesda, Maryland 20814 Mr. James 4. Levine, Executive Director Site Nuclear Operations Mr. Frank Wilson, Director Arkansas Nuclear One Division of Environmental Health P. O. Box 608 Protection Russellville, Arkansas 72801 Department of Health

, Arkansas Department of Health Nicholas S. Reynolds, Esq.

4815 West Markham Street Bishop, Liberman, Cook, Little Rock, Arkansas 72201 Purcell & Reynolds 1200 Seventeenth Street, N.W.

Honorable William Abernathy Suite 700 County Judge of Pope County Washington, D.C.

20036 Pope County Courthouse Russelville, Arkansas 72801 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Office cf Executive Director for Operations 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Senior Resident Inspector U.S. Nuclear Regulatory Comission 1 Nuclear Plant Sad Russellville, A.ansas 72801 Ms. Greta Dicus, Director Division of Environment Health Protection Arkansas Department of Health 4815 West Markam Street little Rock, Arkansas 72201 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division Suite 220 1700 Rockville Pike, Suite 525 Rockville, Maryland 20852