Forwards Staff Requirements Memo Response,Dtd 990525,which Provides Actions NRC Plans for Continued Oversight of safety-conscious Work Environ & Employee Concerns Program
ML20212A750
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 09/10/1999
From: John Nakoski
NRC (Affiliation Not Assigned)
To: Concannon T, Woollacott E
CONNECTICUT, STATE OF
Shared Package
ML20212A755 List:
References
SECY-99-010-C, NUDOCS 9909170123
Download: ML20212A750 (3)


Text

D; September 10, 1999 Ms. Terry Concannon Mr. Evan W. Woollacott Co-Chair Co-Chair Nuclear Energy Advisory Council Nuclear Energy Advisory Council 415 Buckboard Lane 128 Terry's Plain Road Marlborro, CT 06447 Simsbury, CT 06070

Dear Ms. Concannon and Mr. Woollacott:

On July 15,1999, the Connecticut Nuclear Energy Advisory Council (NEAC) and U.S. Nuclear Regulatory Commission (NRC) held a meeting in Waterford, Connecticut. As requested during that meeting, the enclosed Staff Requirement Memorandum (SRM) response, dated May 25,1999, provides the actions the NRC staff plans for continued oversight of the safety-conscious work environment (SCWE) and employee concerns program (ECP) at the Millstone Nuclear Power Station (Millstone). The plan includes criteria to determine if increased regulatory actions are warranted. The plan also provides for periodic assessments until ongoing organizational changes and further improvements to the ECP/SCWE at Millstone are achieved.

In addition, much of the publicly available NRC information is located on the NRC's Webpage located at www.nrc. gov under the " News & Information" link. Two valuable sources in that link are the " Selected Reports" in the " Documents" category and the " Staff Papers" in the

" Commission" category. Under " Selected Reports", you will find a link to Millstone specific information, while in the " Staff Papers" link, you will find indexes of staff papers to the Commission, SRMs, Commission voting records, and other related documents. While the staff will continue to work closely with members of the NEAC to ensure your informational needs are met, these links should provide valuable information that you can readily access.

Should you require additional information, or have further questions or comments, please contact me at 301-415-1278.

Sincerely, ORIGINAL SIGNED BY:

John A. Nakoski, Sr. Project Manager, Section 2 Project Directorate i Division of Licensing Project Management Office of Nuclear Reactor Regulation

Enclosure:

As stated DISTRIBUTION Docket Files (50-336,50-423) PD l-2 Rdg PUBLIC EAdensam JClifford JZwolinski/SBlack JLinville, RI REaton JNakoski DLew, RI DOCUMENT NAME: G:\PDI-2\millston e3\N EACSCW E.wpd To receive a copy of this docuenent, indicate in the bos "C' copy w/o attach /enci"E" copy w/ attach /enci"N" no copy OFFICE PDI-2/PM , N PDI-2/LA W PDI-2/SC PDI:D , 6 NAME JNakoskiM TClark E JC$fford EAden Y I DATE 9 / ~7- /99 9 /'l /99 9 /i /99 9 / /0 /99 OFFICIAL RECORD COPY f

9909170123 990910 PDR ADOCK 05000336 , 1./g P PDR l'P024

. . 1 S::ptember 10, 1999 a Ms. Terry Concannon Mr. Evan W. Woollacott Co-Chair Co-Chair Nuclear Energy Advisory Council Nuclear Energy Advisory Council 415 Buckboard Lane 128 Terry's Plain Road Marlborro, CT 06447 Simsbury, CT 06070

Dear Ms. Concannon and Mr. Woollacott:

On July 15,1999, the Connecticut Nuclear Energy Advisory Council (NEAC) and U.S. Nuclear Regulatory Commission (NRC) held a meeting in Waterford, Connecticut. As requested during that meeting, the enclosed Staff Requirement Memorandum (SRM) response, dated May 25,1999, provides the actions the NRC staff plans for continued oversight of the safety-conscious work environment (SCWE) and employee concerns program (ECP) at the Millstone Nuclear Power Station (Millstone). The plan includes criteria to determine if increased regulatory actions are warranted. The plan also provides for periodic assessments until ongoing organizational changes and further improvements to the ECP/SCWE at Millstone are achieved. -

In addition, much of the publicly available NRC information is located on the NRC's Webpage located at www.nrc. gov under the " News & Information" link. Two valuable sources in that link are the " Selected Reports" in the " Documents" category and the " Staff Papers" in the

" Commission" categorf. Under " Selected Reports", you wi!! find a link to Millstone specific information, while in the " Staff Papers" link, you will find indexes of staff papers to the Commission, SRMs, Commission voting records, and other related documents. While the staff will continue to work closely with members of the NEAC to ensure your informational needs are met, these links should provide valuable information that you can readily access.

Should you require additional information, oc have further questions or comments, please contact me at 301-415-1278.

Sincerely, ORIGINAL SIGNED BY:

John A. Nakoski, Sr. Project Manager, Section 2 Project Directorate i Division of Licensing Project Management i Office of Nuclear Reactor Regulation l

Enclosure:

As stated DISTRIBUTION Docket Files (50-336,50-423) PD l-2 Rdg PUBLIC EAdensam JClifford JZwolinski/SBlack JLinville, RI REaton JNakoski DLew, RI DOCUMENT NAME: G:\PDI-2\ millstone 3\NEACSCWE.wpd ,

To receive a copu of this document, indicate in the box 'C' copy w/0 8ttach/enct 'E' copy w/ attach /enct *N' no copy '

OFFICE PDI 2/PM , N PDI-2/LA N PDI-2/SC PDI:D , E NAME JNakoski/M TClark JCMord EAden Y DATE 9 / ~+ /99 / /99 8l /i /99 9 / /0 /99 l OFFICIAL RECORD COPY L

p p ua l* [ 4 UNITED STATUS j j

't NUCLEAR REGULATORY COMMISSION o WASHINGTON. D.C. 2055MX)01

%, # September 10, 1999 l Ms. Terry Concannon Mr. Evan W. Woollacott p Co-Chair Co-Chair Nuclear Energy Advisory Council Nuclear Energy Advisory Council 415 Buckboard Lane 128 Terry's Plain Road Marlborro, CT 06447 Simsbury, CT 06070

Dear Ms. Concannon and Mr. Woollacott:

On July 15,1999, the Connecticut Nuclear Energy Advisory Council (NEAC) and U.S. Nuclear Regulatory Commission (NRC) held a meeting in Waterford, Connecticut. As requested during that meeting, the enclosed Staff Requirement Memorandum (SRM) response, dated May 25,1999, provides the actions the NRC staff plans for continued oversight of the safety-conscious work environment (SCWE) and employee concerns program (ECP) at the Millstone Nuclear Power Station (Millstone). The plan includes criteria to determine if increased regulatory actions are warranted. The plan also provides for periodic assessments until ongoing organizational changes and further improvements to the ECP/SCWE at Millstone are achieved.

In addition, much of the publicly available NRC information is located on the NRC's Webpage located at www.nrc. gov under the " News & Information" link. Two valuable sources in that link are the " Selected Reports" in the " Documents" category and the " Staff Papers" in the

" Commission" category. Under " Selected Reports", you will find a link to Millstone specific .

information, while in the " Staff Papers" link, you will find indexes of staff papers to the  !

Commission, SRMs, Commission voting records, and other related documents. While the staff will continue to work closely with members of the NEAC to ensure your informational needs are met, these links should provide valuable information that you can readily access.

l Should you require additional information, or have further questions or comments, please contact me at 301-415-1278. 1 l

Sincerely,

] /

t (-

(J n A. Nakoski, Sr. Project Manager, Section -- 2 oject Directorate I -

Division of Licensing Project Management Office of Nuclear Reactor Regulation

Enclosure:

As stated ,

1