ML20012B411
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/02/1990
From: Mroczka E
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20012B412 List:
References
B13469, NUDOCS 9003140354
Download: ML20012B411 (3)


Text

C4

~

y, n<:,

  • 7 - N _IfTILITIES o.n.,.i onic... seio.n sir i. 8.riin. conn.ciicui 3

P.O. BOX 270 1

HARTFORD, CONNECTICUT 06141-0270

^

k U

N$ NE.7.,,%",

(203) 665-5000

)

s i

March 2, 1990-1-

Docket No. 50-423 B13469 Re:

10CFR50.90 1

U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

Reference:

(1)

E. J.

Mroczka' letter to the U.S.

Nuclear Regulatory Commission, " Millstone Nuclear Power Station, Unit No. 3, Proposed Revision to Technical Specifications, Accumu-lators," dated December 11, 1989.

Gentlemen:

Millstone Nuclear Power Station, Unit No. 3 Proposed Revision to Technical Specifications. Accumulators By "B13110, Application for Amend to License NPF-49,extending Interval That Accumulator Can Be Inoperable,Due to [[Atomic Element" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Concentration Outside Required Limit or for Reason Other than Closed Isolation Valve from 1 H to 72 H|letter dated December 11,1989]] (Reference (1)), Northeast Nuclear Energy

-Company (NNECO). submitted a proposed ' revision to the Technical Specifications for Millstone Unit No. 3.

In a subsequent discussion with the NRC Staff,

additional information was requested to clarify the changes proposed to the Action Statements. for an inoperable accumulator.

The purpose of this submit-tal is-to provide the Staff with the requested information.

The proposed changes, transmitted in Reference (1), would allow 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to restore the inoperable accumulator (proposed ACTION statement 'a'), except as a result of a closed isolation valve or boron concentration, or 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

-(proposed: ACTION statement

'c') if the inoperability is due to the boron concentration not being within the limits.

These proposed changes are being combined into a single ACTION statement.

Specifically, the revised proposed

' ACTION statement 'a' will allow 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> to restore the inoperable accumulator, except as a result of a' closed isolation valve.

It should-be noted that the significant hazards consideration discussion previously included in the "B13110, Application for Amend to License NPF-49,extending Interval That Accumulator Can Be Inoperable,Due to [[Atomic Element" contains a listed "[" character as part of the property label and has therefore been classified as invalid. Concentration Outside Required Limit or for Reason Other than Closed Isolation Valve from 1 H to 72 H|December 11, 1989, letter]] is still applicable for the above revised change. The revised Technical Specification page is provid-ed inLAttachment 1.

[pk 9003140354 9003 DR ADOCK 050 Q

P U.

pp\\

, OS342J AEV. 4 i

o U.S. Nuclear Regulatory Commission t

B13469/Page 2 March 2, 1990 We trust the Staff finds this additional information helpful.

Should you have any additional questions, please contact our licensing representative direct-ly.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY l'& W E. J. MrK zka

/

Senior Vice President cc:

W. T. Russell, Region I Administrator D. H. Jaffe, NRC Project Manager, Millstone Unit No. 3 l

W. J. Raymond,-Senior Resident Inspector, Millstone Unit Nos. 1, 2, and 3 Mr. Kevin McCarthy, Director Radiation Control Unit Department of Environmental Protection Hartford, Ct C5116 STATE OF CONNECTICUT)

) ss. Berlin COUNTY OF HARTFORD )

Then personally appeared before me, E. J. Mroczka, who being duly sworn, did state that he is Senior Vice President of Northeast Nuclear Energy Company, a l

Licensee herein, that he is authorized to execute and file the foregoing information -in the name and on behalf of the Licensee herein, and that the statements contained in said information are true and correct to the best of l

his knowledge and belief.

Iwrm On Sheltc(%

l Notary Public l

l I

l l

l 1

r;

'A 7

i Docket No. 50-423 i

B13469 l

.r.

i l

')

Millstone Nuclear Power Station, Unit No. 3-Proposed Revision to Technical Specifications Accumulators

-i i

(..

l

.i 1.

p l

1.

i l

1 March 1990 i

-.