Letter Sequence Other |
|---|
|
Results
Other: 0CAN048804, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Informs That No Instances of Circuit Breakers Being Installed in safety-related Applications Identified at Plant, 3F0288-18, Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Plant Does Not Use Westinghouse Circuit Breaker Models DS-206,DSL-206,DS-416,DSL-416 & DS-420, A07039, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Pole Shafts for All Four Breakers Replaced During Recently Completed Refueling Outage, BECO-88-050, Notifies That Westinghouse Circuit Breakers Not in Use or Planned to Be Used in safety-related Applications at Util, in Response to NRC Bulletin 88-001, GO2-88-084, Submits Info as Requested by NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, GO2-88-153, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Results of Reinsp of Nine Breakers After Removal of Spring Provided, ML17251B046, ML17284A611, ML18152A818, ML20147F998, ML20147G854, ML20148A890, ML20148B666, ML20148K225, ML20148Q724, ML20149M198, ML20150A899, ML20150B182, ML20150B526, ML20150C407, ML20150C743, ML20150D397, ML20151A945, ML20151B202, ML20151E018, ML20151E419, ML20151E868, ML20151G115, ML20151G791, ML20151H779, ML20151H965, ML20151Q920, ML20154D233, ML20154E154, ML20155A456, ML20155E392, ML20196H353, ML20205P688, ML20235J165, ML20235J168, ML20236A614, ML20236A849, ML20236D105, ML20236F547, ML20236S018, ML20247K075, NRC-88-0072, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Does Not Utilize Subj Circuit Breakers, RBG-27645, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Does Not Utilize Any Circuit Breakers Subj to Bulletin in Class 1E Svc at Plant, W3P88-0051, Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Util Does Not Use Westinghouse Series Ds Circuit Breakers & Not Subj to Insps Requested in Bulletin
|
MONTHYEARML20235S2971987-10-0202 October 1987 Summary of 870923 Meeting W/Westinghouse Re Technical Basis for Westinghouse Recommended Actions,Criteria & Conclusions in to Utils That Use Models DS-416,DSL-416, DS-420,DS-206 & DSL-206 Switchgear in Class 1E Svc Project stage: Meeting ML20236A6141987-10-16016 October 1987 Advises That Util Insp of Reactor Trip Breakers Revealed Catawba Pole Shaft Which Had Welds W/Indications of Cracking.Forwards Informal Technical Communication from Franklin Research Ctr Re Initial Observation Project stage: Other ML20236A8491987-10-16016 October 1987 Forwards I.6177-5-1, Interim Rept on McGuire Reactor Trip Breaker 2B Failure Evaluation & Rcommended Corrective Actions from Westingtonhouse. Rept Explains Mechanical Binding Which Kept Breaker from Opening on 870702 Project stage: Other ML20236D1051987-10-21021 October 1987 Provides Record of 871020 Telcon Between D Hood,D Sellers & V Hodge of NRC & J Mcvicker & Cowne of Bg&E Re Unit 1 480 Volt Circuit Breaker W/Broken Weldment Connecting Ctr Pole Lever to Pole Shaft.Util Exam Results in 860918 Memo Project stage: Other ML20236F5471987-10-23023 October 1987 Documents 871020 Telcon W/Util Re Unit 2 Circuit Breaker Pole Shaft Weld Failure Project stage: Other ML20236F9651987-10-27027 October 1987 Notification of 871103 Meeting W/Util & Westinghouse in Philadelphia,Pa to Discuss Results of Franklin Research Ctr Exam of Cracks in Pole Shaft Welds of Reactor Trip Breaker Project stage: Meeting ML20236S0181987-11-18018 November 1987 Summarizes 871020 Telcon Between NRC & Util Re Two Broken Fillet Welds on Pole Shaft Assembly of Circuit Breaker That Energizes Emergency Fire Protection Pumps for Facility. Photographs Attached to 870710 Memo to NRC Encl Project stage: Other ML20149M1981988-02-16016 February 1988 Advises That Since Util No Longer Operating Reactor Licensee Due to 870430 Shutdown & 870804 Amend,Modifying License DPR-45 to Possess But Not Operate Status,Generic Ltr 88-01 Determined Inapplicable to Facility Project stage: Other 3F0288-18, Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Plant Does Not Use Westinghouse Circuit Breaker Models DS-206,DSL-206,DS-416,DSL-416 & DS-4201988-02-23023 February 1988 Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Plant Does Not Use Westinghouse Circuit Breaker Models DS-206,DSL-206,DS-416,DSL-416 & DS-420 Project stage: Other ML20196H3531988-02-25025 February 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. No Westinghouse Ds Series Circuit Breakers Installed at Facility Project stage: Other ML20147G8541988-03-0101 March 1988 Responds to NRC Bulletin 88-001 Re Westinghouse Ds Series Circuit Breakers Used in safety-related Applications.Plant Does Not Have Any Westinghouse Ds Series Circuit Breakers Project stage: Other ML20147F9981988-03-0404 March 1988 Submits Response to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Author Does Not Utilize Any Westinghouse Circuit Breakers,As Identified in Subj Bulletin,In Class 1E Applications at Facility Project stage: Other ML20150B1821988-03-0707 March 1988 Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Plant Does Not Use Westinghouse Circuit Breakers in Class 1E Applications So Bulletin 88-001 Does Not Apply to Plant Project stage: Other ML20148A8901988-03-0707 March 1988 Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Unit 1 Has No Westinghouse Ds Circuit Breakers Used in Class 1E Application.Unit 2 Reactor Trip & Bypass Breakers Insp Initiated Per Info Notice 87-035 Project stage: Other ML20150A8991988-03-0909 March 1988 Provides Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Determined That Westinghouse Series Ds Circuit Breakers Not Employed at Plant.Insp Required by Bulletin Not Applicable to Plant Project stage: Other ML20150C4071988-03-11011 March 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Determined That Westinghouse Type Ds Circuit Breakers Not Used at Plant Project stage: Other BECO-88-050, Notifies That Westinghouse Circuit Breakers Not in Use or Planned to Be Used in safety-related Applications at Util, in Response to NRC Bulletin 88-0011988-03-15015 March 1988 Notifies That Westinghouse Circuit Breakers Not in Use or Planned to Be Used in safety-related Applications at Util, in Response to NRC Bulletin 88-001 Project stage: Other ML20148B6661988-03-16016 March 1988 Responds to 880205 NRC Compliance Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Westinghouse Ds Series Circuit Breakers Not Used in Class IE Svc at Plant Project stage: Other NRC-88-0072, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Does Not Utilize Subj Circuit Breakers1988-03-24024 March 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Does Not Utilize Subj Circuit Breakers Project stage: Other ML20148K2251988-03-25025 March 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Two Reactor Trip Breakers & Two Reactor Trip Bypass Breakers Subj to Bulletin Used at Millstone Unit 3.Main Pole Shaft Weld Insps Completed by 880225 Project stage: Other ML20151G7911988-03-28028 March 1988 Confirms That Westinghouse Ds Breakers Not Used at Facility, Per IE Bulletin 88-001, Defects in Westinghouse Circuit Breakers Project stage: Other W3P88-0051, Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Util Does Not Use Westinghouse Series Ds Circuit Breakers & Not Subj to Insps Requested in Bulletin1988-03-29029 March 1988 Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Util Does Not Use Westinghouse Series Ds Circuit Breakers & Not Subj to Insps Requested in Bulletin Project stage: Other ML20151A9451988-03-30030 March 1988 Responds to IE Bulletin 88-001 Re Westinghouse Ds/Dsl Circuit Breakers.Ref Components Not Utilized at Facility Project stage: Other 0CAN048804, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Informs That No Instances of Circuit Breakers Being Installed in safety-related Applications Identified at Plant1988-04-0101 April 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Informs That No Instances of Circuit Breakers Being Installed in safety-related Applications Identified at Plant Project stage: Other RBG-27645, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Does Not Utilize Any Circuit Breakers Subj to Bulletin in Class 1E Svc at Plant1988-04-0404 April 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Util Does Not Utilize Any Circuit Breakers Subj to Bulletin in Class 1E Svc at Plant Project stage: Other ML20151B2021988-04-0404 April 1988 Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Insp of All Westinghouse DS-415 Reactor Trip & Bypass Breakers Completed on 880308 & Results Encl Project stage: Other ML18152A8181988-04-0505 April 1988 Responds to IE Bulletin 88-001, Defects in Westinghouse Circuit Breakers. No Westinghouse Type Ds Breakers Used at Plant Project stage: Other ML17251B0461988-04-0707 April 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Plant Does Not Have Westinghouse Circuit Breakers Subj to Bulletin Project stage: Other ML20151H7791988-04-0707 April 1988 Informs That Westinghouse Ds Circuit Breakers Not Utilized in Any 1E Application at Plant But Used in non-1E Applications & Will Be Included in Util Preventive Maint Program Project stage: Other ML20148Q7241988-04-0707 April 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. No Westinghouse Models DS-206,DSL-206, DS-416,DSL-416 or DS-420 Breakers in Class 1E Circuits at Hatch Project stage: Other ML20151E4191988-04-0808 April 1988 Responds to 880205 NRC Bulletin 88-01 Re Defects in Westinghouse Circuit Breakers for Facilities.Westinghouse Ds Series Circuit Breakers Not Used at Plants.Other Provisions of Bulletin Do Not Apply to Plants Project stage: Other ML20151E8681988-04-11011 April 1988 Forwards Response to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers in Class 1E Svc.All Required long-term & short-term Insps Completed Project stage: Other GO2-88-084, Submits Info as Requested by NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers1988-04-11011 April 1988 Submits Info as Requested by NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers Project stage: Other ML20151G1151988-04-13013 April 1988 Ack Receipt of in Response to NRC Bulletin 88-001 Re Westinghouse Circuit Breakers.Plant Does Not Use or Plan Use of Circuit Breakers,Therefore Matter Closed Project stage: Other ML20151H9651988-04-13013 April 1988 Responds to NRC Bulletin 88-001, Deficiencies in Westinghouse Circuit Breakers. Bulletin Addresses Deficiencies Exclusive to Westinghouse Ds/Dsl Type Circuit Breakers & Outlines Specific Insps to Be Performed Project stage: Other ML20205P6881988-04-20020 April 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. No Circuit Breakers Subj to Bulletin Installed in Plant Project stage: Other ML20155E3921988-06-0909 June 1988 Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit breakers.Sixty-six of sixty-seven Breakers Required New Pole Shafts Due to Failure of Welds to Meet Bulletin Requirements Resulting from Insp Project stage: Other ML20150C7431988-06-28028 June 1988 Forwards Arvin/Calspan Investigation of Trip Breaker Failure..., Explaining Mechanical Binding Which Caused Failure on 870702 Project stage: Other ML20150B5261988-06-30030 June 1988 Informs That All Class 1E DS-416 Breakers Now in Use Comply W/Nrc Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers Project stage: Other ML20150D3971988-07-0505 July 1988 Advises That Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Satisfactory Project stage: Other GO2-88-153, Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Results of Reinsp of Nine Breakers After Removal of Spring Provided1988-07-13013 July 1988 Responds to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Results of Reinsp of Nine Breakers After Removal of Spring Provided Project stage: Other ML20151E0181988-07-14014 July 1988 Advises That Util 880407 Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Satisfactory Project stage: Other ML20151Q9201988-08-0202 August 1988 Informs That Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Satisfactory Project stage: Other ML20154E1541988-09-0909 September 1988 Advises That 880408 Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Satisfactory Project stage: Other ML20154D2331988-09-0909 September 1988 Informs That Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers, Satisfactory & No Further Reply Necessary Project stage: Other ML20155A4561988-09-29029 September 1988 Requests Addl Info Re Util 880908 Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers. Response Requested within 70 Days of Ltr Date Project stage: Other ML17284A6111988-11-18018 November 1988 Advises That Util 880411 & 0713 Responses to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers Satisfactory Project stage: Other ML20235J1651989-02-17017 February 1989 Provides Final Response to NRC Bulletin 88-001, Defects in Westinhouse Circuit Breakers. Alignment Check Specified in 871201 Submittal Satisfactorily Performed During Installation of Replacement Pole Shaft in Breakers Project stage: Other ML20235J1681989-02-17017 February 1989 Advises That 880314 Response to NRC Bulletin 88-001, Defects in Westinghouse Circuit Breakers Satisfactory. Westinghouse Ds Series Circuit Breakers Not Used in safety-related Applications at Plant Project stage: Other ML20247C7191989-05-15015 May 1989 Forwards Supplemental Response to NRC Bulletin 88-001 Re Westinghouse Series Ds Circuit Breakers.Insp Info Corrected Project stage: Supplement 1988-03-07
[Table View] |
Text
-
d
~
h L
'A@
g T.iepnone <412) 393-sooo WYE". PA 1507M004 shippingpod March 7, 1988 U. S. Nuclear Regulatory Commission Attn:
Document Control Desk Washington, DC 20555
Reference:
Beaver Valley Power Station, Unit No. 1 and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50- 412, License No. NPF-73 NPC Bulletin No. 88-01; Defects in Westinghouse Circuit Breakers (TACS 65955/65956)
Gentlemen:
NRC Bulletin 88-01 requested that we perform and document inspection of the welds on the pole shafts and inspection of the alignment of the breaker closing mechanism for any Westinghouse series DS circuit breakers that are used in Class 1E service.
Beaver Valley Unit No. 1 has no DS circuit breakers that are used in Class lE application.
The reactor trip and reactor trip bypass breakers for Unit 1 are Westinghouse DB-50 breakers.
Beaver Valley Unit No.
2 reactor trip and reactor trip bypass breakers, however, are Westinghouse DS-416 breakers.
No other Westinghouse DS series breakers are used in Class lE application at Unit 2.
An inspection was performed on the Unit 2 reactor trip and bypass breakers in September, 1987.
This inspection was initiated after receiving NRC Information Notice 87-35, "Reactor Trip
- Breaker, Westinghouse Model DS-416, Failed to Open on Manual Initiation from the Control Room".
All pole shaft welds (with the exception of the auxiliary switch lever weld) were inspected.
While this inspection was not done to the full criteria of Bulletin 88-01 (proper weld
- size, length, fusion, absence of cracks and porosity), the pole shaft welds were inspected for proper weld size and langth.
This inspection was performed by a
qualified welding inspector.
The l
results of this inspection noted that all four breakers pole shafts did not meet the 3/16 inch fillet weld size criteria.
However, all four breakers did meet the 1/8 inch fillet weld size criteria for 120*
continuous around the shaft.
While not part of the inspection criteria at the
- time, the inspection report also noted some discontinuities including lack of fusion, crator cracks and porosity on a
few welds.
Breaker alignment
- checks, as described in the Westinghouse Technical Bulletin NSID TB 87-11, were also performed during this inspection and found to be acceptable.
8803210225 880307 PDR ADOCK 05000334 O
DCD
/i
NRC Bulletin No. 88-01; Defects in Westinghouse Circuit Breakers (TACS 65955/65956)
Page 2 When NRC Bulletin 88-01 was received the Train "B" reactor trip bypass breaker was removed for re-inspection to determine the extent of these discontinuities noted in the earlier inspection and to inspect the welds to the full criteria provided by Bulletin 88-01.
As a
result of this inspection, it was determined that the welds on this breaker's pole shaft satisfied the criteria of Sections 6.1.2 and 7.1 of the Westinghouse Technical Bulletin (as modified by NRC Bulletin 88-01) for 1/8 inch fillet welds.
The pole shaft welds for this breaker were also observed by members of your staff (Mr.
D.
S.
Hood and Mr.
C.
D.
Sellers) on 2/17/88.
The Train "A" reactor trip bypass breaker pole shaft was subsequently re-inspected.
The pole i
shaft welds on this breaker also satisfied the Westinghouse Bulletin section 6.1.2 criteria (as modified).
These bypass breaker weld inspections were performed by a qualified welding inspector.
The Unit 2
reactor trip breakers have not been re-inspected to date to ensure full compliance with the short-term criteria of NRC Bulletin 88-01.
Tne bulletin requested this inspection be completed within 30 days after receipt of the bulletin.
Per this response we request that this inspection be delayed until the next available maintenance outage on Unit 2
following receipt of acceptable pole shaft replacements from Westinghouse.
This delay is requested for the following reasons:
1)
The reactor trip breaker pole shaft welds were inspected in September 1987.
While this inspection was not performed to the full criteria of NRC Bulletin 88-01, the inspection documented that the shaft welds meet the required size and length requirements of the Westinghouse
- Bulletin, Section 6.1.2.
No other indications were noted on the welds fcr these breakers (lack of fusion, cracks or porosit'f) with the exception that some porosity was observed on one of the welds on tne Train "A"
reactor trip breaker.
However, this porosity was not quantified since no criteria was available at the time.
We believe the weld will meet the less than 1/16 inch cumulative diameter per one inch of weld criteria for porosity when re-inspected.
2)
Ereaker disassembly is required to allow access to the pole
' shafts.
The required breaker disassembly, weld inspection and creaker reassembly will take greater than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to complete.
The Unit 2
Technical Specifications allows a maximum of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> operation on the bypass breakers for surveillance testing.
Breaker manipulations, between the reactor trip and bypass
- breakers, could be attempted to place the bypass breakers in the reactor trip breakers position to allow time for this inspection,
- however, this evolution would significantly increase the potential for an inadvertent reactor trip.
3)
An order for replacement pole shafts has been placed with Westinghouse.
- However, no acceptable replacement shafts are available at present.
NRC Bulletin No. 88-01; Defects in Westinghouse Circuit
~ Breakers (TACS 65955/65956)
,~
Page 3 4)
There are a
minimal number of cycles on the Unit 2 reactor trip and. bypass breakers.
This should minimize the potential for degradation of any weld due to cycle fatique.
The Train "B"
bypass breaker has approximately 780 cycles which is the maximum number of cycles of the four breakers.
In
- summary, proper alignment of the Unit No. 2 reactor trip and bypass breakers has been verified as described in the Westinghouse Bulletin.
The reactor trip bypass breakers pole shaft welds have been inspected and satisfy the acceptance criteria of sections 6.1.2 and 7.1 of the Westinghouse Bulletin as modified by NRC Bulletin 88-01.
The two main reactor trip breakers have been inspected,
- however, complete compliance with the acceptance criteria of Sections 6.1.1 or 6.1.2 of the Bulletin has not been demonstrated.
This inspection will be completed at the next available maintenance outage after receiving acceptable replacement pole shafts.
Details of this inspection will be provided on a
follow-up response following completion of this inspection.
Both the reactor trip and bypass breaker pole shaft welds will be re-inspected every 200 cycles of operation (not to exceed 4000 cycles of operation) until the breaker pole shafts have been replaced with pole shafts meeting the requirements of Section 6.1.1 of the j
Bulletin.
The following information is provided concerning the cost of complying with this bulletin.
(1) staff time to perform requested inspections, corrective actions and associated operability testing - 70 manhours to date.
(2) staff time to prepare requested documentation - 30 manhours.
(3) additional cost incurred as a result of the inspection findings (e.g.,
cost of corrective
- actions, cost of down time) - it is i
estimated that four replacement pole shafts and materials will cost approximately $6,500 with 32 manhours per breaker to install 4
the shafts and do required testing.
l Should you have any questions with this response, please contact my office.
2 Very truly yours, As D. Sicoor
, Vice President, Nuclear cc:
Mr. J. Beall, Sr. Resident Inspector Mr. W. T. Russell, NRC Region I Administrator Mr.
P. Tam, Project Manager Director, Safety Evaluation & Control (VEPCO)
9 COMMONWEALTH OF PENNSYLVANIA)
)
SS:
COUNTY OF BEAVER
)
on this
/Id day of
//2/#O
- 1988, M /t / v ///. I d e A u,
a Notary Public in and fer said before me, Commonwealth' and County, personally appeared J. D. Sieber, who being duly
- sworn, deposed, and said that (1) he is Vice President of Duquesne
- Light, (2) he is duly authorized to execute and file the foregoing Submittal on behalf of said Company, and (3) the statements set forth in the Submittal are true and correct to the best of his knowledge, information and belief.
kOM Y/L (XYJro'
~-
un._,-
smPPtsarest 8000, sEAIER CNETT sf Ceesessist DPtets eCT,23.1988 ei.r. %, w s..
w w e m w Submittal:
Duquesne Light Company Response to NRC Bulletin 88-01, dated March 7, 1988.
?