ML20148A890

From kanterella
Jump to navigation Jump to search

Responds to NRC Bulletin 88-001 Re Defects in Westinghouse Circuit Breakers.Unit 1 Has No Westinghouse Ds Circuit Breakers Used in Class 1E Application.Unit 2 Reactor Trip & Bypass Breakers Insp Initiated Per Info Notice 87-035
ML20148A890
Person / Time
Site: Beaver Valley
Issue date: 03/07/1988
From: Sieber J
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
IEB-88-001, IEB-88-1, IEIN-87-035, IEIN-87-35, TAC-65955, TAC-65956, NUDOCS 8803210225
Download: ML20148A890 (4)


Text

-

d

~

h L

'A@

g T.iepnone <412) 393-sooo WYE". PA 1507M004 shippingpod March 7, 1988 U. S. Nuclear Regulatory Commission Attn:

Document Control Desk Washington, DC 20555

Reference:

Beaver Valley Power Station, Unit No. 1 and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50- 412, License No. NPF-73 NPC Bulletin No. 88-01; Defects in Westinghouse Circuit Breakers (TACS 65955/65956)

Gentlemen:

NRC Bulletin 88-01 requested that we perform and document inspection of the welds on the pole shafts and inspection of the alignment of the breaker closing mechanism for any Westinghouse series DS circuit breakers that are used in Class 1E service.

Beaver Valley Unit No. 1 has no DS circuit breakers that are used in Class lE application.

The reactor trip and reactor trip bypass breakers for Unit 1 are Westinghouse DB-50 breakers.

Beaver Valley Unit No.

2 reactor trip and reactor trip bypass breakers, however, are Westinghouse DS-416 breakers.

No other Westinghouse DS series breakers are used in Class lE application at Unit 2.

An inspection was performed on the Unit 2 reactor trip and bypass breakers in September, 1987.

This inspection was initiated after receiving NRC Information Notice 87-35, "Reactor Trip

Breaker, Westinghouse Model DS-416, Failed to Open on Manual Initiation from the Control Room".

All pole shaft welds (with the exception of the auxiliary switch lever weld) were inspected.

While this inspection was not done to the full criteria of Bulletin 88-01 (proper weld

size, length, fusion, absence of cracks and porosity), the pole shaft welds were inspected for proper weld size and langth.

This inspection was performed by a

qualified welding inspector.

The l

results of this inspection noted that all four breakers pole shafts did not meet the 3/16 inch fillet weld size criteria.

However, all four breakers did meet the 1/8 inch fillet weld size criteria for 120*

continuous around the shaft.

While not part of the inspection criteria at the

time, the inspection report also noted some discontinuities including lack of fusion, crator cracks and porosity on a

few welds.

Breaker alignment

checks, as described in the Westinghouse Technical Bulletin NSID TB 87-11, were also performed during this inspection and found to be acceptable.

8803210225 880307 PDR ADOCK 05000334 O

DCD

/i

NRC Bulletin No. 88-01; Defects in Westinghouse Circuit Breakers (TACS 65955/65956)

Page 2 When NRC Bulletin 88-01 was received the Train "B" reactor trip bypass breaker was removed for re-inspection to determine the extent of these discontinuities noted in the earlier inspection and to inspect the welds to the full criteria provided by Bulletin 88-01.

As a

result of this inspection, it was determined that the welds on this breaker's pole shaft satisfied the criteria of Sections 6.1.2 and 7.1 of the Westinghouse Technical Bulletin (as modified by NRC Bulletin 88-01) for 1/8 inch fillet welds.

The pole shaft welds for this breaker were also observed by members of your staff (Mr.

D.

S.

Hood and Mr.

C.

D.

Sellers) on 2/17/88.

The Train "A" reactor trip bypass breaker pole shaft was subsequently re-inspected.

The pole i

shaft welds on this breaker also satisfied the Westinghouse Bulletin section 6.1.2 criteria (as modified).

These bypass breaker weld inspections were performed by a qualified welding inspector.

The Unit 2

reactor trip breakers have not been re-inspected to date to ensure full compliance with the short-term criteria of NRC Bulletin 88-01.

Tne bulletin requested this inspection be completed within 30 days after receipt of the bulletin.

Per this response we request that this inspection be delayed until the next available maintenance outage on Unit 2

following receipt of acceptable pole shaft replacements from Westinghouse.

This delay is requested for the following reasons:

1)

The reactor trip breaker pole shaft welds were inspected in September 1987.

While this inspection was not performed to the full criteria of NRC Bulletin 88-01, the inspection documented that the shaft welds meet the required size and length requirements of the Westinghouse

Bulletin, Section 6.1.2.

No other indications were noted on the welds fcr these breakers (lack of fusion, cracks or porosit'f) with the exception that some porosity was observed on one of the welds on tne Train "A"

reactor trip breaker.

However, this porosity was not quantified since no criteria was available at the time.

We believe the weld will meet the less than 1/16 inch cumulative diameter per one inch of weld criteria for porosity when re-inspected.

2)

Ereaker disassembly is required to allow access to the pole

' shafts.

The required breaker disassembly, weld inspection and creaker reassembly will take greater than 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to complete.

The Unit 2

Technical Specifications allows a maximum of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> operation on the bypass breakers for surveillance testing.

Breaker manipulations, between the reactor trip and bypass

breakers, could be attempted to place the bypass breakers in the reactor trip breakers position to allow time for this inspection,
however, this evolution would significantly increase the potential for an inadvertent reactor trip.

3)

An order for replacement pole shafts has been placed with Westinghouse.

However, no acceptable replacement shafts are available at present.

NRC Bulletin No. 88-01; Defects in Westinghouse Circuit

~ Breakers (TACS 65955/65956)

,~

Page 3 4)

There are a

minimal number of cycles on the Unit 2 reactor trip and. bypass breakers.

This should minimize the potential for degradation of any weld due to cycle fatique.

The Train "B"

bypass breaker has approximately 780 cycles which is the maximum number of cycles of the four breakers.

In

summary, proper alignment of the Unit No. 2 reactor trip and bypass breakers has been verified as described in the Westinghouse Bulletin.

The reactor trip bypass breakers pole shaft welds have been inspected and satisfy the acceptance criteria of sections 6.1.2 and 7.1 of the Westinghouse Bulletin as modified by NRC Bulletin 88-01.

The two main reactor trip breakers have been inspected,

however, complete compliance with the acceptance criteria of Sections 6.1.1 or 6.1.2 of the Bulletin has not been demonstrated.

This inspection will be completed at the next available maintenance outage after receiving acceptable replacement pole shafts.

Details of this inspection will be provided on a

follow-up response following completion of this inspection.

Both the reactor trip and bypass breaker pole shaft welds will be re-inspected every 200 cycles of operation (not to exceed 4000 cycles of operation) until the breaker pole shafts have been replaced with pole shafts meeting the requirements of Section 6.1.1 of the j

Bulletin.

The following information is provided concerning the cost of complying with this bulletin.

(1) staff time to perform requested inspections, corrective actions and associated operability testing - 70 manhours to date.

(2) staff time to prepare requested documentation - 30 manhours.

(3) additional cost incurred as a result of the inspection findings (e.g.,

cost of corrective

actions, cost of down time) - it is i

estimated that four replacement pole shafts and materials will cost approximately $6,500 with 32 manhours per breaker to install 4

the shafts and do required testing.

l Should you have any questions with this response, please contact my office.

2 Very truly yours, As D. Sicoor

, Vice President, Nuclear cc:

Mr. J. Beall, Sr. Resident Inspector Mr. W. T. Russell, NRC Region I Administrator Mr.

P. Tam, Project Manager Director, Safety Evaluation & Control (VEPCO)

9 COMMONWEALTH OF PENNSYLVANIA)

)

SS:

COUNTY OF BEAVER

)

on this

/Id day of

//2/#O

1988, M /t / v ///. I d e A u,

a Notary Public in and fer said before me, Commonwealth' and County, personally appeared J. D. Sieber, who being duly

sworn, deposed, and said that (1) he is Vice President of Duquesne
Light, (2) he is duly authorized to execute and file the foregoing Submittal on behalf of said Company, and (3) the statements set forth in the Submittal are true and correct to the best of his knowledge, information and belief.

kOM Y/L (XYJro'

~-

un._,-

smPPtsarest 8000, sEAIER CNETT sf Ceesessist DPtets eCT,23.1988 ei.r. %, w s..

w w e m w Submittal:

Duquesne Light Company Response to NRC Bulletin 88-01, dated March 7, 1988.

?