Submits Response to NRC AL 99-02,requesting That Licensees Provide Numerical Estimates of Licensing Actions to Be Expected to Be Submitted in Fy 2000 & 2001
ML20210D457
Person / Time
Site: Millstone  Dominion icon.png
Issue date: 07/20/1999
From: Olivier L
NORTHEAST NUCLEAR ENERGY CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
AL-99-02, B17811, NUDOCS 9907270246
Download: ML20210D457 (4)


Text

_*

Rope Ferry Rd. (Route 156), Teterford, CT 06385 Nht -

Nuclear Energy mi.tooe N aear e , statio.

Northeast Nuclear Eoergy Company P.O. Box 128 Waterford, CT 06385-0128 (860) 447-1791 Fax (860) 444-4277 The Northeast Utilities System JLL 2 01999 Docket Nos. 50-245 50-336 50-423 B17811 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Millstone Nuclear Power Station, Unit Nos.1,2, and 3 Administrative Letter 99-02. "Operatina Reactor Licensina Action Estimates" The purpose of this letter is to respond to Administrative Letter (AL) 99-02, " Operating Reactor Licensing Action Estimates." AL 99-02 requests licensees to provide numerical estimates of the licensing actions expected to be submitted in Fiscal Years (FY) 2000 and 2001. For submittals expected to generate complex reviews, the letter requests licensees to provide short titles, as well.

Northeast Nuclear Energy Company expects to submit licensing actions as summarized in Attachment 1 to this letter.  ;

There are no regulatory commitments contained within this letter.

1 If you have any questions conceming this submittal, please contact Mr. Paul R. Willoughby at (860) 447-1791, Ext. 3655.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY i

b l teon J. p)Ivier " " I 270035 Senior Wce President and l Chief Nuclear Officer  ;

cc: See page 2 I i

9907270246 990720 PDR ADOCK 05000245 P PDR

[

U.S. Nuclear RGguttory Commission B17811\Page 2 Attachment 1) Licensing Action Estimates cc: H. J. Miller, Region i Administrator L. L. Wheeler, NRC Project Manager, Millstone Unit No.1 D. P. Beaulieu, Senior Resident inspector, Millstone Unit No. 2 R. B. Eaton, NRC Senior Project Manager, Millstone Unit No. 2 A. C. Cerne, Senior Resident inspector, Millstone Unit No. 3 J. A. Nakoski, NRC Project Manager, Millstone Unit No. 3 4

r-o .

l Docket No. 50-245 l 50-336 50-423 E17811 l

)

Attachment 1 Mills'one Nuclear Power Station, Unit Nos.1,2 and 3 Licensina Action Estimates l

I l

l i

i l

1 July 1999 l

4 U.S. Nucl=r Regul: tory Commission B17811%ttachment 1\Page 1 Millstone Unit Nos.1. 2. & 3 Licensina Action Estimates (Estimates of requests for new license amendments, exemptions and reliefs)

FY 2000 (10/1/99 - 9/30/00) FY 2001 (10/1/00 - 9/30/01) i Millstone Unit No.1 1 1*

Millstone Unit No. 2 8 6** ]

Millstone Unit No. 3 12 6" J

  • Submittal of application for Independent Spent Fuel Storage Installation for Millstone Unit No.1.

" Includes the conversion to improved Technical Specifications for Millstone j Unit Nos. 2 & 3.  !