Special Rept:On 930610,Containment 650 Elevation High Range Train a Area Radiation Detector 2-VRA-2310 Declared Inoperable Due to Inability to Perform Channel Checks.Repair Work Completed on 930729 & Detector Declared Operable
ML17331A963
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 08/26/1993
From: BLIND A A
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9309100036
Download: ML17331A963 (3)


Text

ACCELERATE DOCUMENT DISTRIBUTION SYSTEMREGULAT~INFORMATION DISTRIBUTIO~YSTEM (RIDS)ACCESSION NBR 9309100036 DOC.DATE: 93/08/26 NOTARIZED:

NO DOCKET t FACIL:50-315 Donald C.Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 nt Unit 2 Indiana M 05000316 50 316 Donald C.Cook Nuclear Power Pla AUTH.NAME AUTHOR AFFILIATION BLIND,A.A.

Indiana Michigan Power Co.(formerly Indiana&Michigan Ele RECIP.NAME RECIPIENT AFFILIATION R Document Control Branch (Document Control Desk)

SUBJECT:

Special rept:on 930610,Containment 650 Elevation High Range Train A Area Radiation Detector 2-VRA-2310 declared inoperable due to inability to perform channel checks.Repair work completed on 930729&detector declared operable.-DISTRIBUTION CODE: IE22D COPIES RECEIVED:LTR L ENCL O SIZE: TITLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt, etc.NOTES: D A, RECIPIENT ID CODE/NAME PD3-1 LA DEANiW INTERNAL: ACNW AEOD/DSP/TPAB NRR/DE/EELB NRR/DORS/OEAB NRR/DRCH/HICB NRR/DRIL/RPEB

/J)SSA/SPLB RES~F LE 02 GN9 FILE 01 EXTERNAL'G&G BRYCE t J H NRC PDR NSIC POOREiW.COPIES LTTR ENCL RECIPIENT ID CODE/NAME PD3-1 PD AEOD/DOA AEOD/ROAB/DSP NRR/DE/EMEB

.NRR/DRCH/HHFB NRR/DRCH/HOLB NRR/DRSS/PRPB NRR/DSSA/SRXB RES/DSIR/EIB L ST LOBBY WARD NSIC MURPHY,G.A NUDOCS FULL TXT COPIES LTTR ENCL D NOTE T'0 ALL""RIDS"'RECIPIENTS.

PLEASE HELP US TO REDUCE WASTE!CONTACT THE DOCUMEN'I'ON'I'ROL DI:SV~ROOM Pl-37 (EXT.504-2065)TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 30 ENCL D Indiana Michigan Power Company Cook Nuclear Plant~One Cook Place Bridgman, tell 49I06 616 465 5901 INDIANA NICHIGAN POMfM Donald C.Cook Nuclear Plant Unit Nos.1 and 2 Docket Nos.50-315 and 50-316 License Nos.DPR-58 and DPR-74 Special Report Technical Specification 3.3.3.1 United States Nuclear Regulatory Commission Attn: Document Control Desk 11555 Rockville Pike Rockville, Maryland 20852 August 26, 1993 Gentlemen:

This Special Report is being submitted in accordance with Technical Specification (TS)3.3.3.1, Action Statement 22A, to inform the NRC that the Containment 650'levation High Range Train.'A'rea Radiation Detector, 2-VRA-2310, was inoperable longer than allowed by the Action Statement.

On July 10, 1993 at 1330 hours0.0154 days <br />0.369 hours <br />0.0022 weeks <br />5.06065e-4 months <br />, the detector was declared inoperable due to the inability to perform the channel checks required by the surveillance requirements.

Although the detector was still functional, it was considered and declared inoperable.

The redundant instrumentation was confirmed to be operable.However, the Special Report required by TS 3.3.3.1 was not submitted to the NRC when the detector remained inoperable in excess of the 7 day Action Statement requirement.

The failure to comply with the Special Report requirement was discovered on July 30, 1993, and is rectified by transmittal of this letter.This event resulted from the repair action not being prioritized in accordance with the applicable LCO restoration requirement, coincident with the failure to identify the need for a Special Report.This is attributed to: 1)ineffective communication of the TS Action Statement requirement via the Work Request,.which,led.to a,,priority code assignment that was not consistent.

with the time limit or special reporting requirements imposed by the TS, and 2)subsequent reviews did not detect the oversight.

9309100036 930826 PDR ADOCK 05000315 8 FDR Special Report August 26, 1993 Page 2 of 2 The 2-VRA-2310 repair work was completed on July 29, 1993.A hard reboot was performed, the parameter files were inserted, and the channels were reinitialized.

The Surveillance 2 IHP, 4030 STP.195 was performed satisfactorily and the detector was declared operable on July 29, 1993 at 1430 hours0.0166 days <br />0.397 hours <br />0.00236 weeks <br />5.44115e-4 months <br />.To prevent this problem from recurring, actions are being taken by the Plant to improve the Action Request initiation and review process.Respectful y, 8 94 A.A.Blind Plant Manager c: E.E.Fitzpatrick J.B.Martin, Region III T.E.Murley, NRC NRC Resident Inspector G.Charnoff, Esq.D.Sherman, ANI Library INPO NFEM Section Chief, State of Michigan