Forwards Safety Evaluation Accepting Util 831107 & 850709 Responses to Items 3.1.1,3.1.2,4.1 & 4.5.1 of Generic Ltr 83-28 Re post-maint Testing Verification & Reactor Trip Sys Reliability
ML20138P064
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/30/1985
From: Stolz J
Office of Nuclear Reactor Regulation
To: Williams J
TOLEDO EDISON CO.
Shared Package
ML20138P066 List:
References
GL-83-28, TAC-52912, TAC-53067, TAC-54058, NUDOCS 8511060353
Download: ML20138P064 (2)


Text

' "

October 30, 1985 Docket No. 50-346 DISTRIBUTION GEdison Docket File ACRS-10 NRC PDR Ringram L POR G0ick Mr. Joe Williams, Jr. ORB #4 Rdg ADeAgazio Vice President, Nuclear HThompson TTaylor(RITI)

Toledo Edison Company OELD Gray File Edison Plaza - Stop 712 EJorden EBrach 300 Madison Avenue BGrimes 40rnstein Toledo, Ohio 43652 JPartlow WPaulson

Dear Mr. Williams:

SUBJECT:

RESPONSE TO GENERIC LETTER 83-28, ITEMS 3.1.1, 3.1.2, 4.1, 4.5.1 -

DAVIS BESSE NUCLEAR POWER STATION The staff has reviewed the following portions of Toledo Edison's November 7, 1983 (Serial No.1000) and July 9,1985 (Serial No.1164) responses to Generic Letter 83-28:

Post-Maintenance Testing Verification (Reactor Trip System Components) item 3.1.1 and 3.1.2.

Reactor Trip System Reliability (Vendor Related Modifications) Item 4.1.

Reactor Trip System Reliability (System Functional Testing) Item 4.5.1.

Our review also referenced a portion of Section II.B.3 - Maintenance improvement Program, from your report " Course of Action Report." which was submitted Septenber 10, 1985 (Serial No. 1182).

Based on the review of the documents cited above, we have determined that the responses for the four items identified are acceptable. A copy of our Safety Evaluation is enclosed.

Sincerely.

  • w un ;:s Lt Jv.a.J..i h t*

John F. Stolz, Chief Operating Reactors Branch #4 Division of Licensing

Enclosure:

Safety Evaluation cc w/ enclosure:

See next page q

851106035305g]PDR PDR AM p{

pl h4:0L ORQ l0L

/ Tibick;cr JSt b 10/3/85 10/ /E.

I' l Mr. J. Williams Davis-Besse Nuclear Power Station Toledo Edison Company Unit No. 1 l

Cc:

Donald H. Hauser, Esq. Ohio Department of Health The Cleveland Electric ATTN: Radiological Health Illuminating Company Program Director P. O. Box 5000 P. O. Box 118 Cleveland, Ohio 44101 Columbus, Ohio 43216 Mr. Robert F. Peters Attorney General .

Manager, Nuclear Licensing Department of Attorney Toledo Edison Company General Edison Plaza 30 East Broad Street 300 Madison Avenue Columbus, Ohio 43215 Toledo, Ohio 43652 Mr. James W. Harris, Director Gerald Charnoff Esq. Division of Power Generation Shaw, Pittman, Potts Ohio Department of Industrial Relations and Trowbridge 2323 West 5th Avenue 1800 M Street, N.W. P. O. Box 825 Washington, D.C. 20036 Columbus, Ohio 43216 Paul M. Smart, Esq. Mr. Harold Kohn, Staff Scientist Fuller & Henry Power Siting Comission 300 Madison Avenue 361 East Broad Street P. O. Box 2088 Columbus, Ohio 43216 Toledo, Ohio 43603 Pr. Robert B. Borsum President, Board of Babcock & Wilcox Ottawa County Nuclear Power Generation Port Clinton, Ohio 43452 Division Suite 200, 7910 Woodmont Avenue Bethesda, Maryland 20814 Resident Inspector U.S. Nuclear Regulatory Comission 5503 N. State Route 2 Oak Harbor, Ohio 43449 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

-