Notifies That Written & Oral Exams for Operator & Senior Operators Scheduled for Wk of 860505.Approved Ref Matl Listed in Encl 1 Required by 860317
ML20210B895
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 02/04/1986
From: Reyes L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Dewitt R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
References
NUDOCS 8602100129
Download: ML20210B895 (5)


Text

- .

.c FEB 0 4 1966 y.

' Docket No.'50-155-Consumers Power Company.

ATTN: M.. R. B, DeWitt Vice President

Nuclear. Operations-212 West Michigan Avenue Jackson, MI 49201

~

Dear Mr. DeWitt:

SUBJECT:

OPERATOR AND SENIOR OPERATOR LICENSING EXAMINATIONS In.a telephone conversation between Mr. R. Buckner, Training Supervisor, and Mr.:J. McMillen, Section Chief, arrangements were made for the administration of examinations at.the Big Rock Point Plant.

.The written ~and oral examinations are scheduled for the week of May. 5,1986.

In order-for us to meet this schedule, it will be necessary for the facility to furnish the approved reference material listed in Enclosure 1 " Reference-Material. Requirements for Operator / Senior Operator Licensing Examinations" by March 17,1986.. Any delay in. receiving this material will result in a delay

.in administering the-examinations. Our examinations are~ scheduled far in

. advance with considerable planning to best utilize our limited examiner -

4 manpower and to' meet' the examination dates requested by the various facilities.

Therefore, missing the March '17,1986 deadline, even by a few days, wi_ll 1ikely result in a long delay since it may not be possible to reschedule examinations at other facilities. Mr. Buckner has been advised of our reference material

{ requirements, the number of reference material sets that are required, and the examiners' names and addresses where each set is-to be mailed.'

~

' The facility management is responsible for providing adequate space and facilities in' order to properly conduct the written examinations.

Enclosure 2, " Administration of Operator / Senior Operator Licensing Written Examinations," describes our requirements. for conducting tisse examinations.

Mr. Buckner has also been infomed of these requirements.

' All' operator and senior license applications should noimally be submitted ~at least.60 days prior;to the first examination dates so that we will be able to review.the training and experience of the candidates, process the medical certifications, and prepare final examiner assignments after candidate eligibility has been determined. -If the applications are not received at

'least 30 days prior to the examination dates it is likely that a postponement will be necessary.

'%2$0h [

v .

Consumers Power Company 2 This request for information was approved by the Office of Management and Budget under Clearance Number 3150-0101, which expires June 30, 1986.

Comments on burden and duplication may be directed to the Office of Management' and Budget, Reports Management Room 3208, New Executive Office Building, Washington, D.C.- 20503.

Thank you for your consideration in this matter. If you have any questions regarding the examination procedures and requirements, please contact

J..I. McMillen at (312) 790-5559.

Sincerely, ORIGINAL SIGNED BY LUIS A. REYES Luis A. Reyes, Chief Operations Branch

Enclosures:

1. Reference Material Requirements for Operator / Senior Operator Licensing-Examination
2. Administration of Operator Licensing Written Examinations cc w/ enclosures:

Mr. D. J. VandeWalle, Director Nuclear Licensing D. P. Hoffman, Plant Superintendent R.~Buckner, Plant Training Manager DCS/RSB (RIDS)

. Licensing Fee Management Branch Resident Inspector, RIII Ronald Callen, Michigan-

. Public Service Comission Nuclear Facilities and Environmental. Monitoring Section cc w/o enclosures:

T. S. Rotella, Project Manager, NRR B.'Boger, Branch Chief, OLB RIII RII d

flen/mab R e 12/0k/86 ff

ENCLOSURE I Reference Material Requirements for Operator / Senior Operator Licensing Examinations Nete: Required Material is indicateo by an "X" opposite the item.

_X_ 1. Procedure Index (alphabetical by subject)

X 2. All administrative Procedures (as applicable to reactor operation or safety X 3. All Integrated Plant Procedures (Nomal or General Operating Procedures)

X 4. Emergency Procedures (Emergency Instructions, Abnormal or Special Procedures)

X 5. Standing Orders (Important orders which are safety related and may supersede the regular procedures)

X 6. Fuel Handling.and Core Loading Procedures, (Initial Core Loading Procedure, when appropriate)

_X_ 7. Annunciator Procedures (alarm procedures, including set points)

X 8. Radiation Protectio'n Manual (Radiation Control Manual or Procedures)

_X_ 9. Emergency Plan Implementing Procedures

_X_ 10. Technical Specifications X 11. Lesson Plans (Training Manuals, Plant Orientation Manual, System Descriptions, Reactor Theory, Thermodynamics, etc.)

_X_ 12. System Operating Procedures X 13. Piping and Instrumentation Diagrams, electrical single line diagrams, or flow diagrams X 14. Technical Data Book, and/or plant curve infomation as used by operators X 15. Ques'tions and Answers that Licensee has prepared (Voluntary by Licensee)

16. Malfunction and Initial Condition Material for Simulator (if applicable)

2 All of the above reference material should be approved, final issues, and should be so marked. Uncontrolled, preliminary, or other such issues will not bc acceptable except for cold license examinations. All procedures and reference material should be bound or in the form as'used by the control room operators, with appropriate indexes or tables of contents so that they can be used efficiently.

If a cold-license plant has not finalized some of the material, the chief examiner is responsible for ensuring that the most complete, up-to-date material is available and that agreement has been reached with the licensee for limiting changes before the administration of the examination.

ENCLOSURE 2 Administration of Reactor / Senior Reactor Operator Licensing Written Examinations Operator Licensing Branch requirements are:

1. A single room shall be provided for completing the written examination.

The location of this room and supporting restroom facilities shall be such as to prevent contact with all other facility and/or contractor personnel during the duration of the written examination. If necessary, the facility should make arrangements for the use of a suitable room at a local school, motel, or other building. Obtaining this room is the responsibility of the licensee.

2. Minimum spacing is required to ensure exam integrity as detennined by the chief examiner. Minimum spacing should be one candidate per table, with 3 foot spacing between tables. No wall charts, models, and/or other training materials shall be present in the examination room.
3. Suitaoie arrangements are to be made by the facility if the candidates are to have lunch, coffee, etc. These arrangements shall comply with Item 1 above. These arrangements will be reviewed by the examiner and/or proctor.

4

4. A copy of the written examination and answer key shall be given to the utility training department after the last candidate has turned in his completed examination. The utility will then have until the end of the exam week to provide comments and supporting documentation to suggest changes or corrections to the examination and answer key. The utility may provide these comments in writing to the Chief Examiner before he leaves the site or forward them to the Operator Licensing SectNn Chief in the appropriate regional office.

! 5. The licensee will provide pads of 8-1/2 x 11" lined paper in unopened

! packages for each candidate's use in completing the examination. The l

examiner will distribute these pads to the candidates. All reference material needed to complete the examination will be furnished by the exeriner. Candidates can bring pens, pencils, calculators or slide rules into the examination room and no other equipment or reference material is allowed.

6. Only black ink or dark pencils should be used for writing answers to questions.

l l