Requests That Submittal of Plant Protective Sys Setpoint Info Be Deferred Until 870831,in Response to NRC . Delay Due to Recent Efforts Focusing on Plant Restart Issues
ML20210B061
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 04/27/1987
From: Brey H
PUBLIC SERVICE CO. OF COLORADO
To: Calvo J
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM), Office of Nuclear Reactor Regulation
References
P-87155, TAC-47416, NUDOCS 8705050222
Download: ML20210B061 (2)


Text

-

G rubiic service ~ - ee '-

2420 W. 26th Avenue, Suite 100D, Denver, Colorado 80211 April 27, 1987 Fort St. Vrain Unit No. 1 P-87155 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555 Attention: Mr. Jose Calvo, Director Project Directorate IV Docket No. 50-267

SUBJECT:

Revision of Commitment Dates

REFERENCES:

1)NRCletter,Heitnerto Williams, dated November 26,1986(G-86624) 2)NRCletter,Heitnerto Williams, dated October 16, 1986 (G-86545)

3) PSC letter, Walker to Berkow, dated May 15, 1986 (P-86279)

Dear Mr. Calvo:

In Reference 1 the NRC recommended that PSC resubmit their proposed Technical Specification for the Plant Protective System (PPS)

Setpoints allowable valves based on annual or refueling surveillance frequencies by the end of January, 1987. Due to recent efforts focusing on plant restart issues, PSC has not been able to respond to this request. For the same reason, PSC has not yet respor.ded to a request for additional PPS setpoint and surveillance requirements information(Reference 2). The infont.ation needed by the NRC will require significant coordination with plant operations personnel recently heavily involved in plant restart activities. PSC requests that submittal of the PPS setpoint information be deferred until August 31, 1987.

\

en g7o4y,

?DR OgCK05000267 P

fi PDR

~

P-87155

.i Pag 2 2-April 27, 1987 In Reference 3 PSC indicated that-the results of analyses and trip setpoint justification for the PPS parameter, Programmed Feedwater

. Flow-Low would be submitted to the NRC in 1986. As discussed above, involvement of plant personnel in EQ and startup related activities has postponed this effort. A new action plan is being developed to address the entire scope of the PPS setpoint program. Upon approval of this action plan PSC will advise the NRC of the schedule for resolving this issue.

Should 'you have any questions concerning this matter, please contact Mr. M. H. Holmes at (303) 480-6960.

Very truly yours, N

H. L. Brey, Manager i Huclear Licensing and Fuels Division HLC/DCG:jmt 4