MONTHYEARML19347C0651980-10-0101 October 1980 Forwards Application for Amend of License DPR-34,changing Tech Specs 2.0 & Tables 3.3.1 & 4.4-1 Through 4.4-4 to Revise Instrument Setpoints Project stage: Request ML19347C0701980-10-0101 October 1980 Application for Amend of License DPR-34,changing Tech Specs 2.0 & Tables 3.3.1 & 4.4-1 Through 4.4.4 to Revise Instrument Setpoints Project stage: Request ML19347C0731980-10-0101 October 1980 Proposed Changes to Tech Specs 2.0 & Tables 3.3.1 & 4.4-1 Through 4.4-4,revising Instrument Setpoints.Supporting Documentation Encl Project stage: Request ML20028E3271983-01-14014 January 1983 Requests Technical Assistance W/Proposed Tech Spec Setpoint Revs Requested by Util.Region Will Provide Assistance,Act as Contact Between NRR & Util & Process & Issue Change.Nrr Will Review Request & Issue Ser.W/O Encl Project stage: Other ML20072P1341983-07-11011 July 1983 Proposed Tech Spec Changes Assuring Operability of Plant Protective Sys Limiting Conditions for Operation Defining Trip Setpoint Operability Project stage: Other ML20087E6151984-02-17017 February 1984 Rev a to Work Spec WS-93-0004, Reevaluation of Plant Protection Sys Setpoints Project stage: Other ML20087E5941984-03-0909 March 1984 Forwards Rev a to Work Spec WS-93-0004, Reevaluation of Plant Protection Sys Setpoints, as Result of 831027 Agreement to Revise Previous Application for Amend to Tech Specs Project stage: Request ML20112J0981985-03-18018 March 1985 Advises That Setpoint Reevaluation Program & Tech Spec Update Program Adopted.Proposed Amend to License DPR-34 for Plant Protective Sys Setpoints Will Be Submitted on or Before 850501 Project stage: Other ML20127P1071985-06-21021 June 1985 Advises That Util 850607 Submittal Re Draft Tech Specs for Control Rod Operability Acceptable Provided That Listed Changes Made.Confirmatory Submittal by Licensee of Revised Draft Tech Specs Should Be Provided Prior to Restart Project stage: Request ML20209F4231985-06-21021 June 1985 Forwards Application for Amend to License DPR-34,revising Tech Specs Re Limiting Conditions for Operation of Protective Sys Instrument Setpoints & Allowable Values Project stage: Request ML20209F4401985-06-21021 June 1985 Application for Amend to License DPR-34,revising Tech Specs Re Limiting Conditions for Operation of Protective Sys Instrument Setpoints & Allowable Values.Fee Paid Project stage: Request ML20209F4461985-06-21021 June 1985 Proposed Tech Specs Re Limiting Conditions for Operation of Protective Sys Instrument Setpoints & Allowable Values Project stage: Other ML20136F6651985-12-31031 December 1985 Informs of Continuation of Reviews Re Allowable Value & Trip Setpoint.Tech Spec Changes Submitted in .After Acceptable Margin Established Analyses Will Be Performed. Tech Spec Change Request Will Be Submitted by 860401 Project stage: Other ML20137P8021986-01-24024 January 1986 Forwards Draft Safety Evaluation Re 850621 Request to Change Tech Specs on Plant Protection Sys Instrumentation Setpoints.Resubmittal of Proposed Tech Specs to Reflect Acceptable Setpoints Requested within 45 Days Project stage: Draft Approval ML20140F8271986-03-25025 March 1986 Ack Receipt of NRC Re Proposed Tech Spec Change Request for Plant Protective Sys Trip Setpoints.Reevaluation of Basis & Analyses for Setpoint Justification for Fixed Feedwater Flow Low Parameter in Progress Project stage: Request ML20155E8421986-04-14014 April 1986 Advises That Addl Time Required to Fully Integrate Tech Spec Changes Re Plant Protection Sys Setpoints Into Existing Format.Tech Spec Amend Request Will Be Submitted by 860516 Project stage: Other ML20210S3261986-05-15015 May 1986 Forwards Application for Amend to License DPR-34,changing Plant Protective Sys Trip Setpoints & Surveillance Requirements.Summary of Proposed Changes & Comments on Draft SER Also Encl.Fee Paid Project stage: Draft Request ML20210S3291986-05-15015 May 1986 Application for Amend to License DPR-34,changing Plant Protective Sys Trip Setpoints & Surveillance Requirements Project stage: Request ML20210S4191986-05-15015 May 1986 Proposed Tech Specs,Changing Plant Protective Sys Trip Setpoints & Surveillance Requirements Project stage: Other ML20211P8291986-07-18018 July 1986 Ack Receipt of Re Plant Protective Sys Setpoints. Item Under Review w/860930 Target Completion Date Project stage: Other ML20211E0111986-10-16016 October 1986 Forwards Request for Addl Info Re NRC Review of Util Info on Plant Protective Sys Trip Setpoints & Surveillance Requirements Against Draft Safety Evaluation Forwarded on 860124 Project stage: Draft Approval ML20214P5751986-11-26026 November 1986 Recommends That Util Propose Tech Specs Based on Annual Allowable Values Re Plant Protective Sys Trip Setpoints. Response Requested within 60 Days of Ltr Date Project stage: Other ML20210B0611987-04-27027 April 1987 Requests That Submittal of Plant Protective Sys Setpoint Info Be Deferred Until 870831,in Response to NRC . Delay Due to Recent Efforts Focusing on Plant Restart Issues Project stage: Other ML20235A9971987-08-28028 August 1987 Forwards Response to NRC 861016 Request for Addl Info on Util 850621 & 860515 Requests for Amend to Tech Specs Re Trip Setpoints & Operating Requirements.Proposed Tech Specs Also Encl Project stage: Request ML20235B0091987-08-28028 August 1987 Proposed Tech Specs Re Trip Setpoints & Operating Requirements Project stage: Other ML20235R4161987-10-31031 October 1987 Draft Eg&G Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station Project stage: Draft Other ML20235V8871987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept Project stage: Draft Other ML20236V3191987-10-31031 October 1987 Draft Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept Project stage: Draft Other ML20236V2941987-11-25025 November 1987 Forwards Draft EGG-NTA-7289, Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Technical Evaluation Rept.Discussion of Encl Draft W/Nrc at 871202 Meeting Proposed ML20237D6921987-12-15015 December 1987 Summary of 871203 Meeting W/Util & Inel Re Protective Sys Setpoints in Tech Specs.List of Meeting Attendees Encl Project stage: Meeting ML20149M2731988-02-0808 February 1988 Forwards Application for Amend to License DPR-34,revising Tech Specs on Plant Protective Sys Trip Setpoints & Operating Requirements Project stage: Request ML20149M2851988-02-0808 February 1988 Application for Amend to License DPR-34,revising Tech Specs Re Plant Protective Sys Trip Setpoints & Operating Requirements Project stage: Request ML20149M2901988-02-0808 February 1988 Proposed Tech Spec Re Plant Protective Sys Trip Setpoint & Operating Requirements Project stage: Other ML20151B0031988-03-31031 March 1988 Technical Evaluation Rept for Plant Protective Sys Trip Setpoints for Fort St Vrain Nuclear Generating Station, Informal Rept Project stage: Other ML20154B8061988-04-28028 April 1988 Forwards Notice of Consideration of Issuance of Amend to License DPR-34 & Opportunity for Hearing Re 880208 Application Concerning Setpoints for Plant Protective Sys Project stage: Other ML20154B8131988-04-28028 April 1988 Notice of Consideration of Issuance of Amend to License DPR-34 & Opportunity for Hearing.Amend Modifies Setpoints Used in Plant Protective Sys Project stage: Other ML20195B4981988-06-0303 June 1988 Forwards Notice of Environ Assessment & Finding of No Significant Impact Re Util 880208 Application Concerning Setpoints for Plant Protective Sys Project stage: Other ML20195B5481988-06-0303 June 1988 Notice of Environ Assessment & Finding of No Significant Impact Re Util 880208 Proposed Revised Setpoints for Plant Protective Sys to Allow for Administrative Errors.Commission Has Decided Not to Prepare EIS Project stage: Other ML20151A9881988-06-20020 June 1988 Forwards Amend 60 to License DPR-34,safety Evaluation & Technical Evaluation Rept EGG-NTA-7289.Amend Revises Setpoints for Plant Protective Sys to Allow for Instrumentation Error Project stage: Approval 1986-04-14
[Table View] |
Text
A o
O PublicService o..
Companyof Colorado P.O. Box 840 201 - 0840 2420 W. 26th Avenue, Suite 1000, Denver, Colorado 80211 Dy*y,c March 25, 1986 Fort St. Vrain Unit No. 1 P-86170 Director of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC 20555 Attn: Mr. H.N. Berkow, Director Standardization and Special Projects Directorate Docket No. 50-267
SUBJECT:
Fort St. Vrain - Plant Protective System Trip Setpoints
REFERENCES:
(1) NRC Letter dated January 24, 1986, Berkow to Walker (G-86053)
(2) PSC Letter dated June 21,1985, Lee to Johnson (P-85214)
(3) PSC Letter dated December 23, 1985, Brey to Berkow (P-85491)
Dear Mr. Berkow:
Public Service Company of Colorado (PSC) is in receipt of your letter dated January 24, 1986 (Reference 1) regarding our proposed Technical Specification Change Request for the Plant Protective System (PPS)
Trip Setpoints (Reference 2).
PSC has been in contact with Mr. Xen Heitner of the NRC staff obtaining clarification on the contents of the interim Technical Specification submittal.
PSC is now progressing to revise the existing Technical Specifications using the guidance provided in of Reference 1.
PSC plans to submit the Technical Specification Amendment request by April 14, 1986.
g6\\
8604010187 860325 PDR ADOCK 05000267 P
PDR
~
PSC will resolve the NRC's coments on the Technical Gpecification format, footnotes, action statements and other related aspects and incorporate these resolutions into the current overall schedule for the Technical Specification Upgra:fe Program' (Reference 3).
For the Fixed Feedwater Flow Low Parameter setpoint which the staff found unacceptable, PSC is in the process of re-evaluating the basis and analyses for the setpoint justification.
PSC will submit, under separate cover, our schedule for providing any additional information I
on this setpoint as soon as our re-evaluation is complete.
In the interim we will continue to use our current setpoint value of ~ 20%
which the staff recommends.
Should you have any questiens concerning this matter, please contact Mr. M.H. Holmes at (303) 480-6960.
l Very truly yours, Jq1Luwe x_.,
H.L. Brey, Manager l
Nuclear Licensing and Fuels Division HLB /JS:pa l