ML20204E802

From kanterella
Revision as of 22:06, 30 December 2020 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Forwards Safety Insp Repts 50-440/86-19 & 50-441/86-04 on 860707-11.No Violation Noted
ML20204E802
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 07/25/1986
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
Shared Package
ML20204E808 List:
References
NUDOCS 8608010261
Download: ML20204E802 (3)


See also: IR 05000440/1986019

Text

.

.

JUL 251986

,

Docket No. 50-440

Docket No. 50-441

The Cleveland Electric Illuminating

Company

ATTN: Mr. Murray R. Edelman

Vice President

Nuclear Group

Post Office Box 5000

Cleveland, OH 44101

Gentlemen:

This refers to the routine safety inspection conducted by J. Foster and other

representatives of this office on July 7-11, 1986, of activities at Perry

Nuclear Power Plant, Units 1 and 2, authorized by NRC Facility Operating

License No. NPF-45 and Construction Permit No. CPPR-149, and to the discussion

of our findings with Mr. E. Riley and others of your staff at the conclusion

of the inspection.

The enclosed copy of our inspection report identifies areas examined during

the inspection. Within these areas, the inspection consisted of a selective

examination of procedures and representative records, observations, and

interviews with personnel.

No violations of NRC requirements were identified during the course of this

inspection.

During the exit interview, we received commitments to revise your Emergency

Plan to include provisions for periodic shift augmentation drills, and to

perform a detailed review of your Emergency Action Levels (EALs). Actions

taken to fulfill these commitments will be reviewed in a subsequent inspection.

Open Items that were identified during this inspection are summarized in

Enclosure A to this letter.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of

this letter, and the enclosures, will be placed in the NRC Public Document Room.

8608010261 860725

PDR ADOCK 05000440

f

G PDR hh 3

s

.

Th C veland Electric Illuminating 2

JUL 251986

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

woriginal sfeed W T D F"

W. D. Shafer, Chief

Emergency Preparedness and

Radiological Protection Branch

Enclosures:

1. Enclosure A

Open Items

2. Inspection Reports

No. 50-440/86019(DRSS);

No.50-441/86004(DRSS)

cc w/ enclosures:

F. R. Stead, Manager, Perry

Plant Technical Department

M. D. Lyster, Manager, Perry Plant

Operations Department

E. M. Buzzelli, General Supervising

Engineer, Nuclear Licensing and

Fuel Management Section

DCS/RSB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

l Harold W. Kohn, Ohio EPA

Terry J. Lodge, Esq.

James W. Harris, State of Ohio

Robert H. Quillin, Ohio

Department of Health

l

l

l RIII RIII RIII RIII RII: !

i WGS e WGSh wt,Sf R e O

l Fosted/mj Smith Snel K p Shr

l

l

r/a/* w/s'

yo

$5'

yo Y"

j'g

yes

L

. ___ ._ _

.

ENCLOSURE A

Open Items

1. The conditions listed in the Perry Nuclear Power Plant Emergency Plan

(PNPPEP) corresponds to the guidance contained in NUREG-0654, Appendix 1.

'

However, some of the distinctly observable events that guide the user to

the emergency condition level are suspect or ambiguous. Several examples

are listed in the appendix to this report. The licensee has committed to

perform a detailed review of the EALs. This will be tracked as Open Item

(No. 440/86019-01; No. 441/86004-01).

2. The licensee was encouraged to incorporate semiannual activation of

emergency call-out procedures into their emergency preparedness plan

and drill program. A commitment to this effect was received at the

exit interview. This will be tracked as Open Item No. (440/86019-02;

No.441/86004-02).

.

!

!

.