Forwards NRC Form 536, Operator Licensing Exam Data, in Response to Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams
ML20212E652
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 09/21/1999
From: Jeffery Wood
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
AL-99-03, PY-CEI-NRR-2432, NUDOCS 9909270099
Download: ML20212E652 (2)


Text

f5 J>-

E Peny Nudear Power Plant

  • * *
  • P . 44

&KM

  • 440-280-5224 Vee President, NGdear py:440.gm September 21,1999 PY-CEl/NRR-2432L United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Perry Nuclear Power Plant Docket No. 50-440 l

Voluntary Response to Administrative Letter 99-03 Ladies and Gentlemen:

The enclosed Nuclear Regulatory Commission (NRC) Form 536, " Operator Licensing l Examination Data," is being submitted in response to NRC Administrative Letter 99-03,

" Preparation and Scheduling of Operator Licensing Examinations.

There are no regulatory commitments contained in this letter or its attachment. If you have questions or require additional information, please contact Mr. Gregory A. Dunn, Manager - Regulatory Affairs, at (440) 280-6305.

Very truly yours,

/

Attachment cc: NRC Project Manager NRC Resident inspector NRC Region ill I l Yb  ;

l i

9909270099 990921440 l f PDR ADOCK 0 g l

AttiChment

. M* PY-CEl/NRR-2432L Pzge 1 of 1 NRC FORM 536 U.S NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO 3150-0131 EXPIRES 07/31/2002 (7 1999)

Es#metod burden per response k comply w6th this voluntary informebon

- consecon request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection !s used to plan OPERATOR LICENSING - budoets and resourc= for operator =aminecons. Send mmments

- EXAMINATION DATA ""'*"' *""*""*"** * #m Roc rde L W Bench W E6)

U S Nucieer Regulatory Commission, Washington, DC 20555-0001 or by intemet omsH to bjs19nrc. gov, and to the Desk Officer, Offlee of informabon and Regulatory Affaire. NEOB-10202, (3150-0131), Othee of Management and Budget Washington, DC 20503. If a means used to impose en informabon collecton does rW display a currency valid OMB control number, the NRC may not conduct or sponsor, and a person le noi roo.*ed e rapand e, the information concebon FACluTY NRC REGION Perry Nuclear Power Plant A. PROPOSED EXAMINATION PREPARATION SCHEDULE l

PROPOSED NUMBER - CY 2QQQ CY 2QQ1 CY 2QQ2 CY 2QO3 l 1 1 ESTIMATED NUMBER OF LICENSEE-PREPARED j EXAMINATIONS B. INITIAL OPERATOR LICENSING EXAMINATIONS PROPOSED NUMBER CY 2QQ0Q CY 2QQ1 CY 20Q2 CY 2003 1

NUMBER OF REACTOR OPERATORS 4 6 '

NUMBER OF SENIOR REACTOR OPERATORS-INSTANT 6 4 NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE 2 2 NUMBER OF SENIOR REACTOR OPERATORS-LIMITED 0 0 PROPOSED DATES 4 l

PRIMARY DATE 1/08/01 12/11/02 ALTERNATE DATE 1/15/01 12/04/02 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2000 CY 2QQ1 PROPOSED NUMBER FIRST SECOND FIRST SECOND ESTIMATED NUMBER OF CANDIDATES 12 12 NRC FORM 536 (7.190s) PRINTED ON RECYCLED PAPER THIS FORM WAS DESIGNED USING INFORMS