PY-CEI-NRR-2405, Informs NRC That Pnpp Staff Has Implemented Formal Industry Position on Severe Accident Mgt

From kanterella
Jump to navigation Jump to search
Informs NRC That Pnpp Staff Has Implemented Formal Industry Position on Severe Accident Mgt
ML20195H903
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 06/14/1999
From: Myers L
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
PY-CEI-NRR-2405, NUDOCS 9906180030
Download: ML20195H903 (1)


Text

p

  • f%rry Nuclear Pdwer Plant 10 Center Road l

~

Petry Ohio 44081 m

Lew W Myers 440-280-5915 Vce President Fat 440-280-8029 June 14,1999 PY-CE!/NRR-2405L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant l J

Docket No. 50-440 Implementation of the Severe Accident Management Guidelines Ladies and Gentlemen:

By letter dated March 22,1995 (Letter Number PY-CEI/NRR-1910L), the Perry Nuclear Power Plant (PNPP) stafTstated that it would implement the formal industry position on severe accident management as approved by the Nuclear Energy Institute's (NEI) Nuclear Strategic Issues Advisory Committee on November 14,1994. That position is based upon use of NEI 91-04,

" Severe > ' dent Issue Closure Guidelines", Revision 1. This letter is to inform the Nuclear Regulatory Commission that the PNPP staff has implemented the aforementioned industry position.

If you have questions or require additional information, please contact Mr. Henry L. Hegrat, Manager-Regulatory Affairs, at (440) 280-5606.

Very truly yours, l

)

t f j cc: NRC RegionIII Administrator g NRC Resident Inspector NRR Project Manager 0

9 9906180030 990614 PDR ADOCK 05000440 p PDR _ _ _ ,