Forwards Safety Insp Rept 50-440/87-03 on 870117-0303 & Notice of Violation.Written Response Required Re Item 2
ML20206A133
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 04/01/1987
From: Warnick R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
Shared Package
ML20206A137 List:
References
NUDOCS 8704070426
Download: ML20206A133 (2)


See also: IR 05000440/1987003

Text

L {} mD

.

O

e

APR '11987

Docket No. 50-440

The Cleveland Electric Illuminating

Company

ATTN: Mr. Murray R. Edelman

Vice President

Nuclear Group

Post Office Box 5000

Cleveland, OH 44101

Gentlemen:

This refers to the routine safety inspection conducted by Messrs.

K. A. Connaughton, G. F. O'Dwyer and P. R. Wohld, of this office on

January 17 through March 3,1987, of activities at Perry Nuclear Power

Plant, Unit 1, authorized by NRC Facility Operating License No. NPF-58

and to the discussion of our findings with Messrs. M. D. Lyster,

C. M. Shuster, and E. Riley at the conclusion of the inspection.

The enclosed copy of our inspection report identifies areas examined

during the inspection. Within these areas, the inspection consisted

of a selective examination of procedures and representative records,

observations, and interviews with personnel.

During this inspection, certain of your activities appeared to be in

violation of NRC requirements, as described in the enclosed Notice.

With respect to item 1, the inspection showed that action had been

taken to correct the identified violation and to prevent recurrence.

Our understanding of your corrective action is described in Paragraph

4c of the enclosed inspection report. Consequently, no reply to the

violation is required and we have no further questions regarding this

matter at this time.

Regarding the remaining item 2, a written response is required.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy

of this letter, the enclosures, and your response to this letter will

be placed in the NRC Public Document Room.

The responses directed by this letter and the accompanying Notice are

not subject to the clearance procedures of the Office of Management and

Budget as required by the Paperwork Reduction Act of 1980, PL 96-511.

DON 0$8jj44g

PDR \

\

.- . _ - . - - _ . . ._ .,

i.

.

, The Cleveland Electric Illuminating 2 APR '11987

Company

'

We will gladly discuss any questions you have concerning this inspection.

Sincerely,

fl eff'

R. F. Warnick, Chief

Reactor Projects Branch 1

Enclosures:

1. Notice of Violation

2. Inspection Report

50-440/87003(DRP)

cc w/ enclosures:

J F. R. Stead, Manager, Perry

l Plant Technical Department

j M. D. Lyster, Manager, Perry Plant

Operations Department

Ms. E. M. Buzzelli, General Supervising

Engineer, Nuclear Licensing and

Compliance Section

DCS/RSB (RIDS)

Licensing Fee Management Branch

Resident Inspector, RIII

Harold W. Kohn, Ohio EPA

Terry J. Lodge, Esq.

James W. Harris, State of Ohio

Robert M. Quillin, Ohio

Department of Health

State of Ohio, Public

Utilities Commission

RIII 17 RIII

Knop /jp P ps Warnick

,