Other: ML13212A367, ML14050A304, ML14071A620, ML14072A369, ML14092A346, ML14177A430, ML14238A691, ML15098A181, ML15106A736, RS-14-183, Updated Responses to NRC Set 14 Requests for Additional Information, Related License Renewal Application, RS-14-249, Results of Detailed Review Performed in Response to Request 1 of NRC RAI B.2.1.7-7 from Set 17, Related to License Renewal Application
|
MONTHYEARML13212A3672013-08-12012 August 2013 Plan for the Aging Management Program Regulatory Audits Regarding the Byron and Braidwood Nuclear Stations License Renewal Application Review (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: Other ML13281A5742013-11-25025 November 2013 Requests for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Aging Management, Set 3 (TAC Nos. MF1879, MF1880, MF1881, and MF1882 Project stage: RAI ML13303B4632013-11-25025 November 2013 Summary of Telephone Conference Call Held on October 22, 2013, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning RAI Set 3 for the Byron-Braidwood LRA Project stage: RAI ML13281A5692013-12-12012 December 2013 Request for Additional Information for the Review of the Byron Nuclear Station Units 1 and 2, and the Braidwood Nuclear Station Units 1 and 2, LRA - Aging Management, Set 4 Project stage: RAI ML13282A3692013-12-13013 December 2013 Requests for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Aging Management, Set 2 (TAC Nos. MF1879, MF1880, MF1881, and MF1882 Project stage: RAI RS-13-273, Responses to NRC Requests for Additional Information, Set 3, Dated November 25, 2013, Related to the License Renewal Application2013-12-17017 December 2013 Responses to NRC Requests for Additional Information, Set 3, Dated November 25, 2013, Related to the License Renewal Application Project stage: Response to RAI RS-13-274, Response to NRC Requests for Additional Information, Set 5, Dated November 22, 2013, Related to License Renewal Application2013-12-19019 December 2013 Response to NRC Requests for Additional Information, Set 5, Dated November 22, 2013, Related to License Renewal Application Project stage: Response to RAI ML13317A0752014-01-13013 January 2014 Requests for Additional Information for Review of Byron, Units 1 & 2, and Braidwood, Units 1 & 2, License Renewal Applications, Set 6 Project stage: RAI RS-14-003, Bryon, Units 1 and 2, Response to NRC Requests for Additional Information, Set 2, Dated December 13, 2013, Related to the License Renewal Application2014-01-13013 January 2014 Bryon, Units 1 and 2, Response to NRC Requests for Additional Information, Set 2, Dated December 13, 2013, Related to the License Renewal Application Project stage: Response to RAI ML14007A6582014-01-22022 January 2014 Requests for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 9 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML13309A9322014-01-23023 January 2014 Summary of Telephone Conference Call Held on October 31, 2013, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Byron Station and Braid Project stage: Draft RAI RS-14-030, Response to NRC Requests for Additional Information, Set 6, Dated January 13, 2014, Related to License Renewal Application2014-02-0404 February 2014 Response to NRC Requests for Additional Information, Set 6, Dated January 13, 2014, Related to License Renewal Application Project stage: Response to RAI ML14006A0212014-02-0606 February 2014 Requests for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application- Aging Management, Set 8 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14023A5642014-02-0707 February 2014 RAI for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 13 (TAC MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14030A5962014-02-10010 February 2014 Requests for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 12 (TAC MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14007A6032014-02-18018 February 2014 Request for Additional Information for the Review of the Byron Nuclear Station, Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, LRA - Aging Management - Set 17 Project stage: RAI ML14035A1892014-02-20020 February 2014 Summary of Telephone Conference Call Held on January 30, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Draft Request for Additional Information Pertaining to the Byron Station and Braidw Project stage: Draft RAI ML14035A5342014-02-20020 February 2014 January 22, 2014, Summary of Telephone Conference Call Held Between NRC and Exelon Generation Company, Llc., Concerning Draft Requests for Additional Information Pertaining to the Byron Station and Braidwood Station, License Renewal Applica Project stage: Draft RAI RS-14-051, Response to NRC Requests for Additional Information, Set 8, Dated February 6, 2014 Related to the License Renewal Application2014-02-27027 February 2014 Response to NRC Requests for Additional Information, Set 8, Dated February 6, 2014 Related to the License Renewal Application Project stage: Response to RAI ML14063A4952014-03-0404 March 2014 Units 1 & 2, Response to NRC Requests for Additional Information, Set 13, Dated February 7, 2014 Re License Renewal Application Project stage: Response to RAI ML14050A1672014-03-0404 March 2014 Summary of Telephone Conference Call on January 23, 2014, Between U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning RAI Set 11, for Byron-Braidwood License Renewal Application (TAC Nos. MF1879, MF1880, MF1881 Project stage: RAI ML14036A3102014-03-0404 March 2014 Summary of Telephone Conference Call Held on January 28, 2014, Between NRC and Exelon, Concerning RAI Set 10, for the Byron and Braidwood Station, LRA Project stage: RAI ML14051A4312014-03-0404 March 2014 Summary of Telephone Conferene Call Held on January 29, 2014, Between the NRC and Exelon Generating Company, Llc., Concerning RAI Set 10, for the Byron and Braidwood Station License Renewal Application (TAC Nos. MF1879, MF1880, MF1881, and Project stage: RAI ML14051A4282014-03-0606 March 2014 January 13, 2014, Summary of Telephone Conference Call Held Between the NRC and Exelon RAI Set 8, for the Byron and Braidwood Station LRA Project stage: RAI ML14050A0812014-03-0707 March 2014 Correction to Request for Additional Information B.2.1.10-1, Letter Dated February 7, 2014, for the Review of the Byron Station and Braidwood Station, Units 1 and 2, LRA Set 13 Project stage: RAI ML14058B1802014-03-11011 March 2014 Summary of Telephone Conference Call on February 18, 2014, Between U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC Concerning Draft Request for Additional Information Regarding Byron & Braidwood Stations, License Renewal Project stage: Draft RAI ML14064A4032014-03-11011 March 2014 Summary of Telephone Conference Call on February 27, 2014, Between U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC Concerning Draft Request for Additional Information Re Byron Station & Braidwood Station License Renewal Project stage: Draft RAI ML14064A3912014-03-11011 March 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 15 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14071A6202014-03-13013 March 2014 Aging Management Programs Audit Report Regarding the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 (Tac Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: Other ML14072A3692014-03-13013 March 2014 AMP Audit Enclosure (3) Project stage: Other ML14050A3042014-03-14014 March 2014 Scoping and Screening Methodology Audit Report Regarding the Byron Station, and Braidwood Station, Units 1 and 2, LRA Project stage: Other ML14058B1822014-03-18018 March 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 14 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14051A5032014-03-20020 March 2014 Request for Additional Information for the Review of the Byron Nuclear Station Units 1 and 2, and Braidwood Nuclear Station, Units 1 and 2, License Renewal Application - Set 17 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI RS-14-084, Responses to NRC Requests for Additional Information, Set 10, Dated February 26, 2014 Related to the License Renewal Application2014-03-28028 March 2014 Responses to NRC Requests for Additional Information, Set 10, Dated February 26, 2014 Related to the License Renewal Application Project stage: Response to RAI ML14084A3352014-04-0303 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 16 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14073A7052014-04-0303 April 2014 Summary of Telephone Conference Call Held on February 12, 2014, Between the NRC and Exelon, Concerning Drais Pertaining to the Byron and Braidwood Station, LRA Project stage: RAI ML14092A3462014-04-0707 April 2014 Project Manager Change for the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: Other ML14092A2612014-04-0707 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 20 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14084A4882014-04-0707 April 2014 03/04/2014 Summary of Telephone Conference Call Held Between NRC and Exelon Generation Company, LLC, Concerning Draft Request for Additional Information Pertaining to the Byron and Braidwood License Renewal Application Set 16 Project stage: Draft RAI ML14094A3662014-04-0808 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 19 Project stage: RAI ML14093B2472014-04-10010 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 18 (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14099A4852014-04-17017 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 & 2, and Braidwood Station, Units 1 & 2, License Renewal Application, Set 21, (TAC Nos. MF1879, MF1880, MF1881, and MF1882) Project stage: RAI ML14099A4932014-04-22022 April 2014 April 03, 2014 Summary of Telephone Conference Call Held Between NRC and Exelon Generation Co., LLC, Concerning Draft Request for Additional Information, Set 21, Pertaining to Byron, Units 1 & 2, Braidwood, Units 1 & 2, License Renewal Appl Project stage: Draft RAI ML14111A1182014-04-24024 April 2014 Request for Additional Information for the Review of the Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2, License Renewal Application, Set 22 Project stage: RAI ML14107A0772014-04-25025 April 2014 Summary of Telephone Conference Call Held on April 9, 2014, Between the U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC Concerning Draft Request for Additional Information, Set 23, Pertaining to the Byron Station & Braid Project stage: Draft RAI ML14107A2262014-05-14014 May 2014 Summary of Telephone Conference Call Held on March 26, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC Concerning Draft Request for Additional Information, Set 21, Pertaining to the Byron Station and Project stage: Draft RAI ML14092A4402014-05-14014 May 2014 Summary of Telephone Conference Call Held on March 19, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC Concerning Draft Request for Additional Information, Set 18, Pertaining to the Byron Station and Project stage: Draft RAI ML14112A4182014-05-14014 May 2014 Summary of Telephone Conference Call Held on April 10, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC Concerning Draft Request for Additional Information, Set 22, Pertaining to the Byron Station and Project stage: Draft RAI ML14094A4252014-05-14014 May 2014 Summary of Telephone Conference Call Held on April 1, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC Concerning Draft Request for Additional Information, Set 19, Pertaining to the Byron Station and B Project stage: Draft RAI ML14129A3392014-05-14014 May 2014 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2014-03-11
[Table View] |
July 21, 2014, Summary of Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Draft Request for Additional Information, Set 38, Pertaining to the Byron Station and BraML14205A228 |
Person / Time |
---|
Site: |
Byron, Braidwood |
---|
Issue date: |
08/11/2014 |
---|
From: |
Robinson L License Renewal Projects Branch 1 |
---|
To: |
|
---|
Robinson L, 415-4115 |
References |
---|
TAC MF1879, TAC MF1880, TAC MF1881, TAC MF1882 |
Download: ML14205A228 (7) |
|
|
---|
Category:Meeting Summary
MONTHYEARML24009A0552024-01-24024 January 2024 Summary of January 8, 2024, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Removal of the Power Distribution Monitoring System from Technical Specifications ML24018A1772024-01-19019 January 2024 Summary of August 30, 2023, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Relaxation of Inspection Requirements for the Head Penetration P-75 Flaw ML23363A0942024-01-0303 January 2024 Summary of October 4, 2023, Pre Submittal Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Revising Technical Specification 3.7.9. Ultimate Heat Sink (UHS) ML23362A0042024-01-0202 January 2024 Documentation of Cancelled September 1, 2023, Presubmittal Meeting Between the NRC and Constellation Energy Generation, LLC, Regarding 6-Month Extension of Certain Reactor Pressure Vessel Weld Inspections ML23352A3822023-12-19019 December 2023 Summary of December 11, 2023, Presubmittal Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Deletion of Technical Specification 5.6.5.b.5 ML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23164A2112023-06-14014 June 2023 Summary of the June 1, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML23129A0202023-05-30030 May 2023 Summary of March 22, 2023, Closed Meeting with Constellation Energy Generation, LLC, to Discuss a Future License Amendment Request That Allows Byron Station and Braidwood Station to Utilize a New Citicality Analysis for the Spent Fuel Pools ML23055A0352023-03-24024 March 2023 Summary of February 23, 2023, with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans to Revise Emergency Action Levels ML23033A6662023-02-0909 February 2023 Summary of Public Meeting with Constellation Energy Generation, LLC (Constellation) to Discuss Its Request for Alternatives for Certain Steam Generator Weld Inspections for Calvert Cliffs 1 & 2, Byron 1 & 2, Braidwood 1 & 2, and Ginna ML22264A1992022-11-14014 November 2022 Summary of August 22, 2022, Meeting Between the U.S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Steam Generator Welds (Epids L-2022-LRR-0074, 0076, 0079, 0091, 0092, 0093 and ML22305A5992022-11-10010 November 2022 Summary of Closed Presubmittal Meeting Between the U. S. Nuclear Regulatory Commission and Constellation Energy Generation, LLC, Regarding Transition to Framatome Fuel ML22159A2232022-06-0909 June 2022 Summary of the June 2, 2022, Public Outreach to Discuss the NRC 2021 End of Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2 ML22115A2122022-05-12012 May 2022 Summary of April 11, 2022, Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding a Future Amendment to Place One High Burnup Lead Test Assembly Into the Byron, Unit 2, Reactor ML22111A2852022-05-0909 May 2022 Summary of April 4, 2022, Meeting Between the U.S. NRC and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Pressurizer Welds (EPIDs L-2022-LLR-0035/36) ML22111A3362022-05-0909 May 2022 Summary of April 7, 2022, Meeting Between the NRC and Constellation Energy Generation, LLC, Regarding Performance Monitoring of Pressurizer Welds (Epids L-2022-LRR-0035 and 0036) ML21330A0722021-12-0303 December 2021 Summary of November 17, 2021, Meeting with Exelon Generation Company, LLC, Related to a Future License Amendment to Remove License Condition 2.C.(12)(d) for Braidwood Station, Unit 2 ML21333A1532021-11-30030 November 2021 Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval ML21237A0412021-08-30030 August 2021 Summary of the July 27, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use Case OMN-28, ML21176A0822021-07-0606 July 2021 June 15, 2021, Summary of Meeting with Exelon Generation Company, LLC Vessel Nozzle Repair Related to a Planned Request for an Alternative Related to Reactor Pressure ML21139A1852021-06-22022 June 2021 Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting ML21167A2152021-06-16016 June 2021 June 8, 2021, Summary of the Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML21147A4262021-06-0303 June 2021 Summary of May 12, 2021, Meeting with Exelon Generation Company, Llc, Related to a Planned License Amendment to Modify the Ultimate Heat Sink Technical Specifications ML21033A6582021-02-0404 February 2021 Summary of October 13, 2020, Presubmittal Meeting Between the U. S. Nuclear Regulatory Commission and Exelon Generation Company, LLC Regarding Post Shutdown Emergency Plan Staffing to Support the Planned Early Closures ML21011A2822021-01-21021 January 2021 Summary of January 6, 2021, Presubmittal Meeting Between the NRC and Exelon Generation Company, LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Unit Nos. 1 and 2 and Dresden, Units 2 and 3 ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20342A3522020-12-10010 December 2020 Summary of November 13, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alterantive to Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting (EPID-L-2020-LRM-0102) ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20280A2482020-10-0707 October 2020 Summary of September 22, 2020, Presubmittal Meeting Between the NRC and Exelon Generation Company LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Units 1 and 2 and Dresden, Units 2 and 3 ML20171A3812020-08-12012 August 2020 (COVID-19) Presubmittal Meeting Summary - Byron Unit 2 LAR - One-Time Extension of Steam Generator Tube Inspections ML20218A5302020-08-0505 August 2020 July 14, 2020, Summary of the Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of Braidwood Station, Units 1 and 2; and Byron Station, Units 1 and 2 ML20181A0002020-06-29029 June 2020 Summary of 6/24/20 Meeting with Exelon Generation Company, LLC Regarding Planned Request for Alternative to Supplemental Valve Position Indication Testing Requirements for Braidwood, Calvert Cliffs, Clinton, Limerick, Nine Mile, Peach Botto ML19326A3152019-12-0303 December 2019 Summary of November 18, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Supplemental Valve Position Indication Testing Requirements ML19326C3582019-12-0303 December 2019 Summary of November 20, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Revise the Quality Assurance Program ML19162A0272019-06-21021 June 2019 Summary of June 4, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Extend the Test Interval for Safety Relief Valves ML20108F0902019-04-20020 April 2019 April 15, 2020, Meeting Summary with Exelon Generation Company, LLC Regarding Planned Request to Defer Submittal of Owner'S Activity Report (Braidwood 2,Byron 2,Calvert Cliffs 1, LaSalle 1, Limerick 1, Nine Mile Point 2, Quad 2, R. E. Ginna ML19036A8832019-02-0707 February 2019 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use ASME Code Case N-879 ML18354B1712019-01-0202 January 2019 Summary of December 19, 2018, Meeting with Exelon Generation Company, LLC Regarding the Use of Boiling Water Reactor Vessel and Internals Project Guidelines ML18325A1712018-11-28028 November 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned Fleet License Amendment Request to Revise Technical Specifications for High Radiation Areas ML18297A1722018-10-26026 October 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned License Amendment Request to Adopt TSTF-427 ML18225A3042018-08-16016 August 2018 Summary of August 8, 2018, Meeting with Exelon Generation Company, LLC, on a Future Relief Request to Extend the Post Peening Follow-Up Inspections for Certain Reactor Pressure Vessel Head Penetrations ML18135A0222018-05-14014 May 2018 Summary of the May 10th, 2018, Public Open House Regarding Braidwood Nuclear Power Station ML18120A1772018-05-0101 May 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Draft Guidance for Emergency Response Organization Staffing ML18113A7052018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Byron Station ML18113A6592018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML18065A8362018-03-0707 March 2018 Summary of February 27, 2018, Meeting with Exelon Generation Company, LLC Planned Fleet License Amendment Request to Relocate Staff Qualification Requirements from TSs to the Quality Assurance Topical Report ML18058A5232018-03-0101 March 2018 Summary of February 26, 2018, Meeting with Exelon Generation Company, LLC Regarding Proposed Alternative to the Main Steam Isolation Valve Testing Requirements ML18018B4432018-01-25025 January 2018 Summary of December 17, 2017, Closed Meeting with Exelon Generation Company, LLC, Regarding Tvel Lead Test Assemblies to Be Placed in the Braidwood Reactor (EPID 000976/05000456/L-2017-LRM and 000976/05000457/L-2017-LRM-0047 ML17347B1022017-12-14014 December 2017 Summary of Meeting with Exelon Generation Company, LLC on Its Planned Fleet License Amendment Request to Revise the Minimum Staffing Requirements for Emergency Response 2024-01-03
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 11, 2014 LICENSEE: Exelon Generation Company, LLC FACILITY: Byron Station, Units 1 and 2 Braidwood Station, Units 1 and 2
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JULY 21, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 38, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF1879, MF1880, MF1881, MF1882)
The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on July 21, 2014, to discuss and clarify the staffs draft request for additional information (DRAI),
Set 38, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application. The telephone conference call was useful in clarifying the intent of the staffs DRAIs. provides a listing of the participants, and Enclosure 2 contains a listing of the DRAIs discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
/RA/
Lindsay Robinson, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455, 50-456, and 50-457
Enclosures:
- 1. List of Participants
- 2. List of Draft Request for Additional Information cc w/encls: Listserv
ML14205A228
- concurred via email OFFICE LA:DLR* PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME YEdmonds LRobinson YDiazSanabria LRobinson DATE 7/30/14 8/4/14 8/8/14 8/11/14
SUBJECT:
SUMMARY
OF TELEPHONE CONFERENCE CALL HELD ON JULY 21, 2014, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND EXELON GENERATION COMPANY, LLC CONCERNING DRAFT REQUEST FOR ADDITIONAL INFORMATION, SET 38, PERTAINING TO THE BYRON STATION AND BRAIDWOOD STATION, LICENSE RENEWAL APPLICATION (TAC NOS. MF1879, MF1880, MF1881, MF1882)
DISTRIBUTION EMAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsOgcMailCenter RidsNrrPMByron Resource RidsNrrPMBraidwood Resource
LRobinson DMcIntyre, OPA EDuncan, RIII JBenjamin, RIII AGarmoe, RIII JMcGhee, RIII JRobbins, RIII VMitlyng, RIII PChandrathil, RIII
TELEPHONE CONFERENCE CALL BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS July 21, 2014 PARTICIPANTS AFFILIATIONS Lindsay Robinson U.S. Nuclear Regulatory Commission (NRC)
William Holston NRC John Hufnagel Exelon Generating Company, LLC (Exelon)
Don Warfel Exelon Albert Piha Exelon Casey Muggleston Exelon Paul Cervenka Exelon Ralph Wolen Exelon Don Brindle Exelon ENCLOSURE 1
DRAFT REQUEST FOR ADDITIONAL INFORMATION BYRON STATION, UNITS 1 AND 2, AND BRAIDWOOD STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION July 21, 2014 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Exelon Generation Company, LLC (Exelon or the applicant), held a telephone conference call on July 21, 2014, to discuss and clarify the following draft request for additional information (DRAI),
Set 38, concerning the Byron Station, Units 1 and 2, and the Braidwood Station, Units 1 and 2, license renewal application (LRA).
DRAI 3.0.3-2c Applicability:
Byron Station (Byron) and Braidwood Station (Braidwood), Units 1 and 2
Background:
By letter dated June 30, 2014, the applicant responded to the staffs request for additional information (RAI) 3.0.3-2b Request (2), which revised LRA Sections B.2.1.11, B.2.1.16, and B.2.1.18 to state that:
a) the acceptance criteria for loss of coating integrity will specify that peeling, blistering, and delamination is not acceptable; b) peeling, blistering, or delamination of the coating from the base metal will be entered into the corrective action program; c) if the coating is not repaired or replaced, physical testing will be conducted to ensure that the remaining coating is tightly bonded to the base metal; d) if the coating is not repaired or replaced, the potential for further degradation of the coating will be minimized, (i.e., any loose coating is removed, the edge of the remaining coating is feathered);
e) adhesion testing using American Society for Testing and Materials (ASTM) International standards endorsed in Regulatory Guide (RG) 1.54 will be conducted at a minimum of 3 sample points adjacent to the defective area; f) a certified coatings inspector will assess indications of blisters, cracking, flaking, or rusting and document the condition and acceptance in a post-inspection report; and g) if coatings exhibiting signs of peeling, blistering, or delamination will be returned to service without repair or replacement, the applicant will conduct an evaluation of the potential impact on the system, including degraded performance of downstream components due to flow blockage and loss of material of the coated component.
Issue:
The staff has concluded that immersion coatings that have exhibited delamination or peeling should be repaired or replaced prior to returning the affected component(s) to service unless the degraded coating: (a) has been inspected, tested, evaluated, and partially corrected to minimize the potential for propagation, as described above; and (b) is inspected prior to 2 years from when the degraded condition was detected by the end of the next refueling outage and then again within 2 years by the end of the following refueling outage to ensure that the ENCLOSURE 2
delamination or peeling is not propagating, or the degraded coating is subsequently repaired or replaced.
Request:
Revise LRA Sections B.2.1.11, B.2.1.16, and B.2.1.18 to address corrective actions associated with state that coatings exhibiting peeling or delamination, which will not be repaired or replaced prior to returning the affected component(s) to service., or revise the programs to additionally include a provision to conduct followup visual inspections of the degraded coating by the end of the next refueling outage and then again by the end of the following refueling outage.
Discussion: The applicant requested clarification on the staffs request. The applicant requested the period of time in the Issue be changed to reflect a 2 year vice every outage to allow more flexibility in the management of components taken out of service since some components do not necessarily need to be inspected during outages. The staff agreed to make the change. The applicant also requested that the staff include an option to subsequently repair or replace the degraded coatings in lieu of inspection. As a result, the staff edited the Issue and Request by replacing the reference to outages with a 2 year period and to include an option to repair or replace the degraded coatings in lieu of inspections. Edits to the original DRAI discussed during the teleconference call are noted in italicize for new information and strikethrough for deleted information. This question will be sent as a formal request titled: RAI 3.0.3-2c.
DRAI B.2.1.16-1c Applicability:
Byron and Braidwood
Background:
The detection of aging effects program element of LR-ISG-2012-02 states: [i]nternal visual inspections used to detect loss of material are capable of detecting surface irregularities that could be indicative of wall loss below nominal pipe wall thickness due to corrosion and corrosion product deposition. Where such irregularities are detected, followup volumetric examinations are performed.
The response to RAI B.2.1.16-1b states:
[s]ince the nominal wall thickness is the design wall thickness of new piping, any indications of loss of material, no matter how trivial, would be an indication of wall loss below nominal.
[u]niform corrosion of steel piping in a raw water environment is expected to occur and, as such, the wall thickness of all Fire Protection System piping can be expected to be below the nominal wall thickness.
[i]nternal visual inspections are incapable of providing a quantitative assessment of the amount of wall loss of system components and instead provide only a qualitative assessment of the internal condition of the system.
[a]s such, visual inspection results will be entered into the corrective action program if unexpected levels of degradation are identified. Unexpected levels of degradation include
excessive accumulation of corrosion products and appreciable localized corrosion (e.g., pitting) beyond a normal oxide layer.
Corrective actions may [emphasis added by NRC staff] include follow-up volumetric inspections, if appropriate.
[f]ollow-up volumetric inspections will be performed as determined [emphasis added by NRC staff] by the 10 CFR Part 50 Appendix B corrective action program when visual inspections identify unexpected levels of degradation.
The staff noted that in the previous RAI response dated March 13, 2014, LRA Sections A.2.1.16 and B.2.1.16 were enhanced for Byron only to require a minimum of 30 volumetric examinations during each 3-year interval, as a result of operating experience.
The staff also noted that these sections state that existing volumetric non-destructive examinations will be credited to ensure age-related degradation is identified prior to loss of system intended function.
Issue:
The RAI response outlines the justification for an exception to conducting followup wall thickness measurements when opportunistic internal visual inspections detect loss of material that could be indicative of wall loss below nominal pipe wall thickness. The staff has concluded that the response justifies the basis for why it is impractical to base followup wall thickness measurements on internal qualitative visual inspections.
However, the response does not state what indications of unexpected degradation will result in a followup wall thickness examination.
As an alternative to opportunistic followup wall thickness measurements, the staff recognizes that periodic planned volumetric examinations could be equally effective at detecting loss of material. However, LRA Sections A.2.1.16 and B.2.1.16 do not state a minimum number of volumetric inspections that will be conducted at Braidwood, nor do they state how volumetric inspection locations will be selected at either site. In addition, although the LRA states that the volumetric examinations are being conducted at Byron as a result of operating experience, it is not clear to the staff whether the number of inspections would be reduced based on changes in operating experience.
Request:
Either provide additional details regarding the periodic volumetric examinations to be performed by the Fire Water System program (e.g., number of inspections, provisions for expanding (or reducing) inspections, inspection location selection (methology), or state what indications of unexpected degradation will result in a followup wall thickness examination for opportunistic internal visual inspections.
Discussion: The applicant requested clarification on the staffs request. The applicant noted that a previously submitted RAI response dated March 13, 2014, included an enhancement for Byron, which addressed periodic volumetric examinations. The staff agreed with the approach taken for Byron and made edits to the request to address a similar approach that could be applied to Braidwood. Edits to the original DRAI discussed during the teleconference call are noted in italicize for new information and strikethrough for deleted information. This question will be sent as a formal request titled: RAI B.2.1.16-1c.