UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 April 23, 2018 LICENSEE:
Exelon Generating Company, LLC FACILITY:
Byron Station, Units 1 and 2
SUBJECT:
SUMMARY
OF THE APRIL 18, 2018, OPEN HOUSE TO DISCUSS THE 2017 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF BYRON STATION On April 18, 2018, from 6:00 p.m. to 7:00 p.m. (CDT), the NRC held an open house to discuss the 2017 End-of-Cycle plant performance assessment of Byron Station. The open house was held at the Jarrett Prairie Center near Byron, Illinois. The enclosure is a list of attendees for the meeting.
During the open house, the NRC discussed their assessment of Byron Stations performance that was documented in the March 2, 2018, End-of-Cycle Assessment Letter (reference ADAMS Accession Number ML18058A979). Throughout the open house, members of the public were afforded the opportunity to ask questions of the NRC representatives in attendance.
Representatives of the NRC made copies of the above letter and other brochures and fact sheets that are available on the NRC public web site available to the members of the public that were present.
_/RA/______________________
Eric Duncan, Branch Chief Branch 3 Division of Reactor Projects Docket Nos. 50-454; 50-455 License Nos. DPR-37; DPR-66
Enclosure:
Pubic Meeting Attendees cc: Distribution via LISTSERV
SUBJECT:
SUMMARY
OF THE APRIL 18, 2018, OPEN HOUSE TO DISCUSS THE 2017 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF THE BYRON STATION DISTRIBUTION:
Jeremy Bowen RidsNrrDorlLpl3 RidsNrrPMByron Resource RidsNrrDirsIrib Resource Steven West Darrell Roberts Richard Skokowski Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML18113A705 OFFICE RIII NAME EDuncan:lg DATE 4/23/2018 OFFICIAL RECORD COPY