Advises That 860925 Rev 6 to Emergency Plan Consistent W/ Provisions of 10CFR50.54(q) & Acceptable.Further Changes to Emergency Plan &/Or Implementing Procedures Should Be Submitted to NRC for Approval
ML20212B134
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 12/18/1986
From: Shafer W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
References
NUDOCS 8612290177
Download: ML20212B134 (2)


Text

f,'

QEC 1 81986 Docket No. 50-440 Docket No. 50-441 The Cleveland Electric Illuminating Company ATTN: Mr. Murray R. Edelman Vice President Nuclear Group Post Office Box 5000 Cleveland, OH 44101 Gentlemen:

This is to acknowledge receipt of Revision 6 to the Perry Nuclear Power Plant Emergency Plan submitted to us by letter dated September 25, 1986.

We have reviewed the changes to the Perry Nuclear Power Plant Emergency Plan and determined that they are consistent with the requirements of 10 CFR 50.54(q) and do not decrease the effectiveness of the emergency plan. These changes are, therefore, acceptable.

Please be reminded that 10 CFR 50.54(q) requires NRC approval of any changes to your emergency plan which may decrease its effectiveness. However, if your safety review assures no decrease in emergency preparedness effectiveness, then such changes may be made without prior NRC approval. In all cases, you must furnish copies of each proposed change to the NRC in accordance with 10 CFR 50.54(q). Also, any changes to the Emergency Plan Implementing Procedures should be made in accordance with the requirements of 10 CFR Part 50, Appendix E, Section V.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter will be placed in the NRC's Public Document Room.

Should you have any questions regarding this letter, please contact Mr. James E. Foster of my staff at (312) 790-5655.

Sincerely,

" Original ciered by U.D. Shsfer" 8612290177 861218 PDR W. D. Shafer, Chief F ADOCK 05000440 PDR Emergency Preparedness and Radiological Protection Branch See Attached Distribution RIII RIII RIII unS h (JCd Snell

/Cc4 RII

/

Foster /ib Knogp'

<2fi c/n n

82/ d' t s' Sh ly U[

The Cleveland Electric Illuminating 2 DJEC 181986 Company Distribution cc: 'F. R. Stead, Manager, Perry Plant Technical Department M. D. Lyster, Manager, Perry Plant Operations Department Ms. E. M. Buzzelli, General Supervising Engineer, Nuclear Licensing and Compliance Section DCS/RSB (RIDS)

Licensing Fee Management Branch Resident Inspector, RIII Harold W. Kohn, Ohio EPA Terry J. Lodge, Esq.

James W. Harris, State of Ohio Robert H. Quillin, Ohio Department of Health State of Ohio, Public Utilities Commission D. Matthews, EPB, 0IE W. Weaver, FEMA Region V

,