Monthly Operating Rept for Apr 1995 for Turkey Point Units 3 & 4.W/950512 Ltr
ML17352B168
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 04/30/1995
From: Knorr J, Plunkett J
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
L-95-145, NUDOCS 9505190385
Download: ML17352B168 (12)


Text

P RI C) RIP'Y (ACCELERATLD RIDS PROCESSIi~

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

DOCKET FACIL:50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 05000250 50-251 Turkey Point Plant, Unit 4, Florida Power and Light C 05000251 AUTH. NAME AUTHOR AFFILIATION KNORR,Z.E. Florida Power & Light Co. P PLUNKETT,J.F. Florida Power & Light Co.

RECIP.NAME RECIPIENT AFFILIATION .R

SUBJECT:

Monthl rept for Apr 1995 for Turkey Point Units 3 & 4. /950512 l DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-1 PD 1 1 CROTEAU,R 1 1 INTERNAL: AEOD/SPD/RRAB 1 1 ~AXLE CENTRE 01 1 1 NRR/DIS P/PI PB 1 1 NRR/DOPS/OECB 1 1 RGN2 1 1 EXTERNAL: LITCO BRYCE,J H 1 1 NOAC 1 1 NRC PDR 1 1 U

ELDER N

YOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE iVKSTE! COYTACT'I'HE 'DOCL'WfEN'I'ONTROL DESK, ROOb,f PI -37 (EAT. 504- 083 ) TO DISTRI 8 UTIOY LIS'I'S I'OR DOC!.'ifEN'I'S YOI 'ON" I'l I NATE YOL'R NAifL P ROif I," D!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 10 ENCL 10

MAY 12 1995 L-95-145 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:

Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of NUREG-0020, attached are the April 1995 Operating Status and Summary of Operating Experience Reports for Turkey Point Units 3 and 4.

Very truly yours, T. F. Plunkett Vice President Turkey Point Plant JEK Attachments cc: S. D. Ebneter, Regional Administrator, Region II, USNRC T. P. Johnson, Senior Resident Inspector, USNRC, Turkey Point

.'Plant i SQO>=

9505i F0385 moe30--

PDR ADOCK 05000250 R PDR an FPL Group co'mpany

I UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

REPORT MONTH No. Date Duration (Hours)

Reason Method of Reactor'icensee Shutting Event Reportt System Code Code'ause Component 4 Corrective Action to Prevent Recurrence Down 02 950407 40.0 95-004 CRDRVE Replace contzol rod drive mechanism power supply F Forced Reason

- Equipment Failure Method Exhibit G - Instructions Exhibit - Source 1 - Manual 1 Same S Scheduled A for Preparation of Data B Maintenance or Test 2 - Manual Scram Entry Sheets Licensee C - Refueling 3 - Automatic Scram Event Roport (LER) File D Regulatory zestriction 4 - Continued (NVREG-0161)

E Operator Training 4 5 - Load Reduction License Examination 9 - Other (Explain)

F G - Administrative Operational Error (Explain)

H - Other (Explain)

DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE MONTH AVERAGE DAILY POWER LEVEL (MWe-Net) 4/01/95 675 4/02/95 653 4/03/95 690 4/04/95 697 4/05/95 682 4/06/95 689 4/07/95 596 4/08/95 0 4/09/95 99 4/10/95 671 4/11/95 672 4/12/95 684 4/13/95 684 4/14/95 684 4/15/95 680 4/16/95 682 4/17/95 681 4/18/95 678 4/19/95 671 4/20/95 684 4/21/95 687 4/22/95 679 4/23/95 678 4/24/95 680 4/25/95 673 4/26/95 677 4/27/95 649 4/28/95 649 4/29/9S 680 4/30/95 678

OPERATING DATA REPORT DOCKET NO 50 - 250 DATE 5/ 8/95 CONTACT J. E. KNORR TELEPHONE 305/246/6757 OPERATING STATUS

1. UNIT NAME: TURKEY POINT UNIT 3
2. REPORTING PERIOD: APRIL 1995
3. LICENSED THERMAL POWER (MWT): 2200
4. NAMEPLATE RATING (GROSS MWE): 760
6. MAXZMUM DEPENDABLE CAPACITY (GROSS MHL~ 699
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 666
8. ZF CHANGES OCCUR IN CAPACITY RATINGS (ITEH~MBER 3 THROUGH 7)

SINCE LAST REPORT, GIVE REASONS:

9. I
10. REASONS FOR RESTRICTIONS, IF ANY:

MONTHLY -YTD- CUMULATIVE ll.

12.

HOURS IN REPORT PERIOD:

NUMBER OF HOURS REACTOR 719 683.7 2879 2843.7 196376.6 131822.1

13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 844.4
14. HOURS GENERATOR ON-LINE 679.0 2839.0 129887.7
15. UNIT RESERVE SHUTDOWN HO 0.0 0.0 121.8 T4 74256 ETF6016 Y7U331950
17. GROSS ELECTRICAL ENERGY GENERATED (MWHj 478297 2024742 86786206
18. NET ELECTRICAL ENERGY GENERATED (MWH) 455084 1930785 82125212
19. UNIT SERVICE FACTOR 94.4 98.6 66.1
20. UNIT AVAILABILITYFA 94.4 98.6 66.2
21. CAPACITY FACTOR (USING MD 95.0 100.7 63.8
22. CAPACITY FACTOR (USING DER NET) 91.3 96.8 60.3
23. UNIT FORCED OUTAGE RATE 5.6 1.4 11.1
24. SHUTDOWNS SCHEDULED OVER REFUELING SCHEDULED SEPTEMBER 1995
25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

DOCKET NO.

UNIT DATE:

COMPLETED BY:

TELEPHONE:

REPORT MONTH Unit 3 operated at essentially 100% reactor power until April 7.

On April 7 the unit was manually shut down to replace a control rod drive power supply. The unit was manually tripped from the intermediate range when the power supply failed. The unit was returned to power on March 9, and remained at essentially 100%

power for the remainder of the month.

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.

UNIT DATE COMPLETED BY TELEPHONE MONTH AVERAGE DAILY POWER LEVEL (MWe-Net) 4/01/95 679 4/02/95 657 4/03/95 693 4/04/95 696 4/05/95 694 4/06/95 688 4/07/95 686 4/08/95 686 4/09/95 683 4/10/95 677 4/11/95 685 4/12/95 '85 4/13/95 684 4/14/95 683 4/15/95 682 4/16/95 683 4/17/95 681 4/18/95 679 4/19/95 679 4/20/95 679 4/21/95 680 4/22/95 679 4/23/95 677 4/24/95 683 4/25/95 672 4/26/95 678 4/27/95 695 4/28/95 682 4/29/95 683 4/30/95 685

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NQ.

UNIT NAME:

DATE:

COMPLETED BY:

TELEPHONE:

REPORT MONTH No. Date Type Duration (Hours)

Reason Method of Shutting Licensee Event Roportf System Code code'ause Component & Corzectivo Action to Pzovont Recurrence Dawn Reactor N/A P Porced Reason Method Exhibit G - Xnstructions Exhibit 1 - same Source S Scheduled A - Equipmont Eailuro 1 - Manual for Preparation of Data B - Maintenance or Test 2 - Manual Scram Entry Sheets Licensee C - Refueling 3 - Automatic Scram Event Report (LER) Pile D - Regulatory restriction 4 Continued (NUREG-0161)

E - Operator Training & 5 Load Reduction License Examination 9 - Other (Explain)

F - Administrative G - Operational Error (Explain)

H - othoz (Explain)

OPERATING DATA REPORT DOCKET NO 50 - 251 DATE 5/ 8/95 CONTACT J. E. KNORR TELEPHONE 305/246/6757 OPERATING STATUS

1. UNIT NAME: TURKEY POINT UNIT 4
2. REPORTING PERIOD: APRIL 1995
3. LICENSED THERMAL POWER (MWT): 2200
4. NAMEPLATE RATING (GROSS MWE): 760
    • RW:
6. MAXIMUM DEPENDABLE CAPACITY (GROSS MRE): 699
7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 666
8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEH~MBER 3 THROUGH 7)

SINCE LAST REPORT, GIVE REASONS:

9. /
0. REASONS FOR RESTRICTIONS, IF ANY:

MONTHLY -YTD- CUMULATIVE

1. HOURS IN REPORT PERIOD: 719 2879 190108.0
2. NUMBER OF HOURS REACTOR 719.0 2757.1 127604.8
3. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 166.6
4. HOURS GENERATOR ON-LINE 719.0 2748.6 123512.2
5. UNIT RESERVE SHUTDOWN HO 0.0 0.0 577.2

~TE933 53%7069 2EUE84778 83408741

7. GROSS ELECTRICAL ENERGY GENERATED (MWHj 514839 1960091
8. NET ELECTRICAL ENERGY GENERATED (MWH) 491394 1868438 78948024
9. UNIT SERVICE FACTOR 100.0 95.5 65.0
0. UNIT AVAILABILITYFA 100.0 95.5 65.3
1. CAPACITY FACTOR (USING MD 102.6 97.4 63.3

,2. CAPACITY FACTOR (USING DER NET) 98.6 93.6 59.9

.3. UN1T FORCED OUTAGE RATE 0.0 4.5 10.8

.4. SHUTDOWNS SCHEDULED OVER NONE

5. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

DOCKET NO.

UNIT'ATE'OMPLETE BY:

TELEPHONE:

REPORT MONTH Unit 4 operated at essentially 100% reactor power for the entire month.