Monthly Operating Repts for Oct 1998 for Turkey Point,Units 3 & 4.With 981112 Ltr
ML17354B190
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 10/31/1998
From: Hovey R, Mowrey C
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-97-02, GL-97-2, L-98-281, NUDOCS 9811200095
Download: ML17354B190 (13)


Text

REGULAT~ INFORMATION DISTRIBUTIO YSTEM (RIDS)

ACCESSION NBR:9811200095 DOC.DATE: 98/10/31 NOTARIZED: NO DOCKET I FACIL:50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 05000250 50-"51 Turkey Point Plant, Unit 4, Florida Power and Light' 05000251 AUTH.NAME AUTHOR AFFILIATION MOWREY,C.L. Florida Power & Light Co.

HOVEY,R.J. Florida Power &. Light Co.

RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating repts for Oct 1998 for Turkey Point, Units 3 &. 4.With 981112 ltr.

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

E NOTES:

RECIPIENT COPIES RECIPIENT COPIES XD CODE/NAME LTTR' ENCL ID CODE/NAME LTTR ENCL PD2-3 PD 1 JABBOUR,K 1 1 INTERNAL: AEOD/SPD/RRAB 1 1 1 1 OC/DBA/PAD 1 1 RGN2 1 1 EXTERNAL: LITCO BRYCE,J H 1 1 NOAC 1 1 NRC PDR 1 1 D

0 NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD) ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 9 ENCL 9

NOV 18 1998 PtPK.

L-98-281 10 CFR $ 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthl 0 eratin Re ort In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the October 1998 Operating Data Report and Summary of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours, R. J. Hovey Vice'President Turkey Point Plant CLM Attachments cc: Regional Administrator, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Plant 98ii200095 '781031 PDR ADQCK 05000250 POor g R PDR an FPL Group company

'1 1~

AVERAGE DAILYUNIT POWER LEVEL DOCKET NO. 50-250 UNIT: k I EP DATE: November 5 1998 COMPLETED BY. C.L. M E E ONB'.

REPORT MONTH October 1998 DAY AVERAGE DAILYPOWER LEVEL (Mwe-Net) 10/1/98 0 10/2/98 0 10/3/98 0 10/4/98 0 10/5/98 0 10/6/98 0 10/7/98 0 10/8/98 0 10/9/98 0 10/1 0/98 0 10/11/98 0 10/12/98 0 10/1 3/98 0 10/14/98 0 10/1 5/98 0 10/16/98 0 10/1 7/98 0 10/1 8/98 0 10/1 9/98 0 10/20/98 0 10/21/98 0 10/22/98 0 10/23/98 0 10/24/98 0 10/25/98 0 10/26/98 0

'0/27/98 0 10/28/98 0 10/29/98 118 10/30/98 250 10/31/98 298

OPERATING DATA REPORT DOCKET NO. 50-250 UNIT NAME TURKEY POINT UNIT 3 DATE November 5 1998 COMPLETED BY ~C. L. Mowre TELEPHONE REPORTING PERIOD October 1998 (Month/Year)

1. Design Electrical Rating (MWe-Net) 720
2. Maximum Dependable Capacity (MWe-Net) 693 e

MONTH -YTD- CUMULATIVE

3. Number of Hours Reactor Was Critical 97.7 6328.2 159446.0
4. Number of Hours Generator Was On Line 72.9 6294.7 157253.6
5. Unit Reserve Shutdown Hours 0.0 0.0 121.8
6. Net Electrical Energy (MWH) 12866.0 4360947.0 100773503.0

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-250 UNIT NARK: k k k DATE: November 5 1998 COMPLETED BY C. L. Mowre TELEPHONE: 305 246-6204 REPORT MONTH October 1998 No. Date Duration Reason'ethod of r Corrective Action (Hours)

Reactor'ause Shutting Down Co~ents 19980001 9/21/98 601. 0 lg3 Shut down for refueling, tripped automatically at 8%

power due to Intermediate Range N35 misad)ustment (NOTE:

this entry was included in last month's report. The refueling outage extended into this month, so the duration has been changed to reflect the outage hours incurred in October.)

19980004 10/26/98 70. 0 Outage extension due to Hurricane Georges.

19980003 10/29/98 Turbine overspeed test following refueling outage.

F Forced Reason Method 1 - Manual S - Scheduled A Equipment Failure 2 - Manual Scram B - Maintenance or Test 3 - Automatic Scram C - Refueling 4 - Continued D Regulatory restriction 5 Load Reduction E - Operator Training & 9 - Other (Explain)

License Examination F - Administrative G - Operational Error (Explain)

H - Other (Explain)

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO. 50-250 CN . N DATE: November 5 1998 COMP P. 'C.

O'NLNPNONB:

off REPORT MONTH October 1998 Unit 3 was shut down for a refueling outage for most of October. The unit's return to power operations was delayed by about 70 hours8.101852e-4 days <br />0.0194 hours <br />1.157407e-4 weeks <br />2.6635e-5 months <br /> by Hurricane Georges (see LER 250/98-005). The unit was restarted on October 27, and placed on line on October 28. Early on October 29, the unit was taken back lin to perform a turbine overspeed test, and placed back on line later that day.

Power was slowly increased, and finished the month at approximately 49% reactor power.

DATE:

k AVERAGE DAILYUNIT POWER LEVEL DOCKET NO.

LBE:

CDHP EP DBP:

PELEPHDHE:

50-251 November C.

PP 5 1998 REPORT MONTH October 1998 DAY AVERAGE DAILYPOWER LEVEL (MWe-Net) 10/1/98 705 10/2/98 703 10/3/98 701 10/4/98 700 10/5/98 700 10/6/98 702 10/7/98 704 10/8/98 702 10/9/98 698 10/1 0/98 701 10/11/98 701 10/12/98 700 10/1 3/98 701 10/14/98 705 10/1 5/98 711 10/16/98 712 10/1 7/98 715 10/1 8/98 716 10/1 9/98 715 10/20/98 709 10/21/98 705 10/22/98 703 10/23/98 714 10/24/98 725 10/25/98 726 10/26/98 723 10/27/98 723 10/28/98 720 10/29/98 720 10/30/98 719 10/31/98 716

OPERATING DATA REPORT DOCKET NO. 50-251 UNIT NAME TURKEY POINT UNIT 4 DATE November 5 1998 COMPLETED BY ~C. L. Mowre TELEPHONE REPORTING PERIOD October 1998 (Month/Year)

1. Design Electrical Rating (MWe-Net) 720
2. Maximum Dependable Capacity (MWe-Net) 693 MONTH -YTD- CUMULATIVE
3. Number of Hours Reactor Was Critical 745.0 7296.0 156603.5
4. Number of Hours Generator Was On Line 745.0 7296.0 152272.5
5. Unit Reserve Shutdown Hours 0.0 0.0 577.2
6. Net Electrical Energy (MWH) 528565.0 5131628.0 98623265.0

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.

UNIT NAME:

DATE:

~ki 50-251 kk November 5 1998 COMPLETED BY C. L. Mowre TELEPHONE: 305 246-6204 REPORT MONTH October 1998 Date Type'uration Reason* Method of r Corrective Action to (Hours)

Reactor'ause Shutting Dcxca prevent Recurrence N/A N/A N/A N/A N/A P forced Reason Method S - Scheduled A - Equipment Failure 1 - Manual B - Maintenance or Test 2 Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory restriction 4 Continued E - Operator Training r 5 - Load Reduction License Examination 9 - Other (Explain)

F - Administrative 6 - Operational Error (Explain)

H - Other (Explain)

~

C

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO. 50-251 UNIT: k i N4 DATE: November 5 1998 COMPLETE BY: C. L. Mowre TELEPHONE:

REPORT MONTH October 1998 Unit 4 operated at essentially 100% for the entire month of October, 1998.