Informs of Independent Verification Insp of Const Activities & Matls Using NDE Van on 850715-26.Requests That Documentation Packages Be Prepared on Welds Selected by NRC by 850701.Van Info & Insp Specifics Encl
ML20127B429
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 05/28/1985
From: Ebneter S
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Harrison R
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
References
NUDOCS 8506210468
Download: ML20127B429 (6)


Text

,

s. -a, MAY 2 81985 Docket No. 50-443 Public Service Company of New Hampshire ATTN: Mr. Robert J. Harrison President and Chief Executive Officer P. O. Box 330 Manchester, New Hampshire 03105 Gentlemer.:

Subject:

NRC Independent Measurements The NRC will perform an independent verification inspection at Seabrook Nuclear Power Station, Unit 1 using the NRC Nondestructive Examination (NDE)

Van and contractor technicians under NRC direction. Construction activities and materials will be sampled through nondestructive examinations as a supple-ment to our existing inspection efforts. Similar nondestructive examinations by the NRC have been performed on a routine basis at other licensee construction sites.

The inspection onsite will begin on July 15, 1985, and will conclude on July 26, 1985. Welds will be selected by the NRC resident inspector for exami-nation by the NDE van team. We request that documentation packages be prepared by your staff for the selected welds. Additional information on the requested document packages is provided in Attachment A. It is requested that all docu-ment packages be in the NRC Region I office by July 1,1985. The data packages will be reviewed by the Regional office for completeness and technical content.

We will update our NDE procedures to be consistent and with your committed codes and standards. All documentation supplied by your staff will be returned, upon request, at the conclusion of the inspection.

- Members of your staff will be kept informed of our inspection progress and sig-nificant findings. An exit meeting with you or members of your staff will be conducted on July 26, 1985, in accordance with our normal procedures. The evaluation of examination results and preparation of an inspection report will be completed and the results of the inspection will be transmitted to you through the standard NRC inspection report. Additional information relating to the NDE van activities at your facility are discussed in Attachments B and C.

8506210468 850528 PDR ADOCK 05000443 G PDR'

/E0/

OFFICIAL RECORD COPY KERCH410B - 0001.0.0 i 05/17/85 l t

a

m Public Service Company of 2 New Hampshire If you should have any further questions regarding this planned inspection, please contact the assigned Senior Resident Inspector, or Mr. Jacque P. Durr at (215) 337-5282 of the NRC Region I Office. Your cooperation in this matter is appreciated.

Sincerely, AV

- Stewart D. Ebneter, Direct Division of Reactor Safety Attachments:

As Stated cc:

John DeVincentis, Director, Engineering and Licensing William B. Derrickson, Senior Vice President Warren Hall, Operational Services Supervisor Donald E. Moody, Station Manager - Seabrook Station Gerald F. Mcdonald, Construction QA Manager Public Document Room (POR) local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector State of New Hampshire bec:

Region I Docket Room (with concurrences)

Section Chief, DRP RI:DRS RI:DRS RI:DRS Kerch Durr Ebneter 4/v, 4,y 0FFICIAL RECORD COPY KERCH410B - 0002.0.0 05/17/85

DATA PACKAGES - ATTACHMENT A After the welds have been selected for NDE inspection, we request that you prepare a package containing the following on each weld:

Inspection Report Weld History (QC History)

' Material. Certifications for base materials Weld Wire Certifications Piping drawings, isometric of weld locations NDE Reports on all NDE performed NDE Procedures for RT, PT, MT and VT Bolt Torquing Procedures (Structural and Pipe Hangers)

Piping and Installation Procedure (only section that specifies code and addenda)

The assembled packages should be forwarded to:

US Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, Pennsylvania 19406 ATTN: Mr. Harry Kerch

SUPPLEMENTAL NDE VAN INFORMATION ATTACHMENT B

1. NDE Van Support Requirements We request that the NRC-NDE Van be positioned as near as practicable to the containment area entrance to facilitate the performance of inspec-tions.
a. The van requires the following connections while sited at your facility:

Site water with a garden hose connection - this water is-for film rinse. ,

Requirement for film rinse water drain (continual). No chemical disposal will occur from the van without prior concurrence from appropriate licensee personnel. At the end of the independent inspection, the NRC needs to dispose of the film developing chemicals prior to moving the van from the site.

Two 30 amp, 110 volt circuits are required for operation of the van,

b. The van will contain PT and MT approve materials. The team will need two rolls of your chemically approved tape and two approved markers for identifying welds and marking weld areas.
c. It will be necessary for you to remove the paint, rust or other mate-rial that could interfere with PT or MT on the selected welds. Also, we will need scaffolding erected and insulation removed for access.
2. Administrative Information
a. The radiation source will be a nominal 100 curie IR-192 source. This source is licensed by NRC, but owned by the NRC contractor.
b. The names of the NRC and contractor NDE personnel will be supplied to you by Region I. Clearance for these personnel is necessary.

2

Attachment B (Continued)

c. We request that you hold a mini-radiation safety training course for the NRC NDE personnel. This course should familiarize the personnel with your facility and procedures and should not exceed 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> in length.
d. A camera site pass will be needed for a Canon AE-1, 35 mm, camera, Serial No. 1969401,
e. The NDE personnel will be using 5 watt Motorola radios on the site; the frequency used by the NRC is 165.6625 MHz.

.,.-._._,__._,,_,_,_.___r . ._, _-____ ~ . _ - . , __,-y._._ , . . _ ___ _._,._ _ _ . ___..__.___--.- - -y -

SCOPE OF INSPECTION ATTACHMENT C The NDE van team will perform the following examinations and inspections as appropriate:

Radiography:

Pipe butt and socket welds and other appropriate pressure boundary components.

Ultrasonics:

Flaw detection and material thickness measurements, as appropriate, of piping, welds, structural components, vessels, heat exchangers, bo'lts and other equip-ment.

Liquid Penetrant:

Piping system components and structural elements.

Magnetic Particle Piping system components and structural elements.

Hardness Testing:

All of the previously listed components.

Windsor Probe:

Safety related concrete.

Delta Ferrite Indications (Severn Gage):

Stainless steel welds.

Alloy Analysis:

Selected metallic components will have confirmatory chemical analysis performed.

Visual Examinations:

Weld quality and configuration verification of piping and structural systems.

Quality Records Review:

Welding documentation, materials and. personnel certification, NDE records to include radiographs.

.