Forwards Special Power Ascension Team Insp Rept 50-443/90-81 on 900316-0502.Power Ascension Test Program Acceptable
ML20055F539
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 07/02/1990
From: Hodges M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Ellen Brown
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
Shared Package
ML20055F540 List:
References
NUDOCS 9007180002
Download: ML20055F539 (2)


See also: IR 05000443/1990081

Text

._ -

_

._77

,

,-

- . .

4 .-

. , ;,

.;

JUL 0 2 tem

Docket No. 50-443-

Public Service Company of New Hampshire

ATTN: Mr. Edward A. Brown

President and Chief Executive Officer

Post Office Box 300

Seabrook, New Hampshire

03874

Gentlemen:

Subject: NRC Region 1 Inspection 50-443/90-81

This refers to the Special Power Ascension Team inspection conducted between

March 16.and May 2, 1990, at Seabrook Station, Unit 1. Seabrook, New Hampshire.

The results of the inspection, as detailed in the enclosed inspection report,

were discussed with D. Moody and other members of your staff each week by our

inspectors.

As you know, several problems identified during the Power Ascension Test

Program, many in non-safety related systems, caused significant delays in your

power ascension test program. Consequently the program was at about-the

sixteenth day of your original schedule, with the reactor at about 8 percent

power prior to the shutdown on April 28, 1990 for a significant modification

of_the low pressure section of the turbine.

By the conclusion of this inspec-

tion period, we had witnessed the power ascension tests for the five percent

test plateau and the turbine testing.

Based on the tests witnessed, our insoectors concluded that the power ascension

tests, thus far, were performed in a safe and controlled manner by a knowledgeable

operations and startup staff. Also the inspection team concluded that the Power

t

Ascension Test Program at Seabrook Station was being conducted in accordance

with procedures and administrative requirements.

.

5 .esponse to this letter is required, Thank you for your cooperation.

Sincerely,

Ori,ind Cigned Dy:

le.tvin W. Hodges

Marvin W, Hodges, Director

Division of Reactor Safety

Enclosure: NRC Region I Inspection Report No. 50-443/90-81

r ' j g'

0FFICIAL RECORD COPY

SB 90-81 - 0001.0.0

1

9007180002 900702

- gon noccuosooga

n .g

~'

o;

.

.;.

'

JUL 0 21990

-

Public Service Corepany of

2

New Hampshire

cc w/tnc1:

L. E. Meglathlin, Jr., President and Chief Executive Officer, PSNH

T. C. Feigenbaum, Senior Vice Prtsident and Chief Operating Officer, ilHY

J. M. Peschel, Regulatory Compliance, liHY

R. M. Kacich, l'anager of Generation Facilities Licensing, HUSCO

J. F. Opeka, Executive Vice President, NU

G. Garfield, Esquire

D. E. Moody, Station 1.'anager, l(HY

1. Harpster, Director of Licensing Services

R. Hallisey, Director Dept. of Public Health. Commonwealth of 14ssachusetts

S. Woodhouse, Legislative Assistent

Public Document Room (PDR)

local Public Docur,ent Room (LPDR)

Nuclear Safety Information Center (llSIC)

NRC Resident Inspector

State of liew Hampshire, SLO

Cornmonwealth of liassachusetts, SLO Designee

Seabrook Hearing Service List

bec w/ enc 1:

Region I Docket Room (with concurrences)

lianagement Assistant DRMA (w/o enc 1)

R. De11any: DRSS

E. McCabe, DR'<

J. Johnson, f.RP

N. Dudley, S AI - Seabrook (w/ concurrences)

K. Abreham, PA0 (20) SALP Report and (2) All Inspection Reports

J. Caldwell, E00

V. Nerses -(RR

.

Q

Q-

RI:DRS

RI@RS

RI:DRS

Trapp/rw

Eapen

Durr

e

6/f/90

6/ /90

6/#//90

0FFICIAL RECORD COPY

SB 90-81 - 0001.1.0

05/30/90

_ .

. . .

.

... . . ...

. . .

...

. . . .

.

. . . .

. .

. . . . . . .

. . . . . . .