Provides Guidelines for Review of Emergency Exercise Objectives & Scenario Packages Prior to Plant Partial Participation Emergency Exercise Scheduled for Wk of 890925, Including Schedule
ML20247L941
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 05/05/1989
From: Lazarus W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Ellen Brown
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
Shared Package
ML20247L917 List:
References
FOIA-89-326, FOIA-89-A-27 NUDOCS 8909250093
Download: ML20247L941 (2)


Text

-

g w mw - - - - - - - - - - - - - - - - - -

,s . .

, n .

g'

. /,a***:g-h, UNif(D STATES

. *y e NUCLEAR MOOLATORY COMMISSION j REGION I 478 ALLENoALE ROAD

(.*...* xiuo oF PpusStA, PENNSYLVANIA 19408 MAY 05 1S33 C O -!

Docket No.: 50-443 gril 101989 Public Service Company of New Hampshire ATTN: Mr. Edward A. Brown, President NUCbNE bS If -'

and Chief Executive Officer New Hampshire Tanter (TiVf tiWn - .

Post Office Box 300 Seabrook, New Hampshire 03874 Gen t*emen:

subject: Emergency Exercise Objective and Scenario Guidelines In order for the Region to fully support the Seabrook Station partial partici-pation einergency exercise scheduled for the week of September 25, 1989 an adequate review of the exercise objectives and scenario is essential. The guidelines identified beim will be used for the submittal and review of the objectives and scenario packages prior to the exercise. You will note that the schedule has been revised to reflect milestones established in FEMA's guidance memorandum EX-3 dated February 26, 1988. Region I has found that Ifeensees generally comply with these guidelines, bewever, we recognize the need to stress the importance of both completeness and timeliness.

The following schedule should be used for all exercises:

Days _in Advance _

Information to be Submitted _

90 Description and scope of exercise, and the objec-tives to be fulfilled should be received in the Region I office. The objectives should include specific objectives to demonstrate, where appro-priate, the effectiveness of corrective actions teken in regard to problem areas which have been previously identified during NRC inspection, emergency, exerc,iset and drilli,arHL.yonc .intacM1.

evaluation process.

75 NRC will provide comments, in writf ag, based on our review of your submittal.

60 Complete exercise scenario package with modified

- objectives, schedules, exercise rules, all controlla contingency and simulation information, all data, including plant data, radiation level and release rate date, and samptles..of the. data .tet be,-presented should be received in the Region I office, i

l 30 NRC will provide coments, in writing, based on our l

(and our contractor's) review of your submittab.J-1 8909250093 890920 PDR FOIA BROCK 89-A-27 PDR

i.

Public Service Company N 0 5 7;pg

, of New Hampshire In order to protect the scenario from disclosure to participants, in lieu of normal distribution, please provide copies only as follows: two copies to the Chief, Onergency Preparedness Section at the letterhead address, marked "EMER-GENCY EXERCISE SCENARIO /0SJECTIVES"; one copy directly to Battelle Pacific Borthwest Laboratory, Attn: Mr. James Jamison, Emergency Preparedness Group, Health Physics Department, 2955 George Washington Way, Richland, Washington 99352;. and oe cooy-.-tm t& M Res44entxInspetton. If'yw-a:itidpate th'at the established schedule will not be met, please notify us at the earliest possible date.

The NRC emergency preparedness specialist responsible for evaluation of your exercise is Mr. Edwin F. Fox. Please identify the name, address and phone number of the individual on your staff with whom we should interface.

Tour continued cooperation in this matter is greatly appreciated. If you have any concerns or questions, please contact Mr. Fox at 215-337-5044 Sincerely,

( .

Wil fam J #s C fef-Emergene pa i ess Section Facilities Radiological Safety and Safeguards Branch Division of Radiation Safety and Safeguards cc: J. C. Duffett, President and Chief Executive Officer, PSNH

7. C. Feigenbaum, Vice President, Engineering, Licensing and Ouality Program NKY J. M. Peschel, Reculatory Services Manager, NHY D.E. Moody,StationManager,NHY P. W., Apes, Jr., Assistant Secretary of Public Safety.

Commonwealth of Massachusetts Pubite Docamene Roon-(PUR)"

LocalPthlicDocumentRoom(LPOR)(NSIC)

Nuclear Safety Information Center NRC Resident Inspector State of New Hampshire Commonwealth of Massachusetts Seabrook Hearing Service List

_ _ - _ _ _ _ _ _ _ -