Monthly Operating Rept for Jan 1994 for Waterford 3.W/940211 Ltr
ML20063H363
Person / Time
Site: Waterford Entergy icon.png
Issue date: 01/31/1994
From: Burski R, Wiegert E
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
W3F1-94-0015, W3F1-94-15, NUDOCS 9402170329
Download: ML20063H363 (7)


Text

_,

I

'l

' Entsrgy Opsrations,Inc. ,I

< = ~ ENTERGY eo cox 8 i Kiliora LA 70066

. Tei 504 739 6774 R. F. Burski Dectip  !

Ntahir Safety I W#ert.itd 3 l W3F1-94-0015 'I A4.05 l PR i

February 11, 1994 j U.S. Nuclear Regulatory Commission ,

ATTN: Document Control Desk Washington, D.C. 20555

Subject:

Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:

Attached is the subject monthly report which~ covers lthe operating  !

statistics for the month of January,1994. This report is, submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.

Very truly yours, l 4

i

. . . - rski

g. D'- ctor Nuclear Safety RFB/TSB/ssf Attachment i cc: '.L.J. Callan, (NRC Region IV)', R.B. McGehee, N.S. Reynolds, F. Yost (Utility' Data Institute, Inc.),- .,

J.T. Wheelock (INP0 Records Center),.NRC' Resident j Inspectors Office l il l

]

9402170329 940131 P :y l PDR R

'.ADOCK 05000382-PDR, f

g. - ' gli 1 l

. \\ .

f l

NRC MONTHLY OPERATING REPORT

SUMMARY

OF OPERAT!ONS WATERFORD 3 I l

l JANUARY 1994 l

l l

The unit operated at an average reactor. power of 99.8% and experienced no shutdowns or significant -

power reductions during the period.

i l

1 1

l i

1

PRESSURIZER SAFETY VALVE .

FAILURES AND CHALLENGES WATERFORD 3 i

During the month of January 1994, there were no pressurizer safety valve failures or challenges.

0 t

.'h t

t 0

l i

i t l

l I

t

OPERATING DATA REPORT <

DOCKET NUMBER: 50-382 UNIT NAME: :- WATERFORD 3 '

DATE OF REPORT: .. FEBRUARY,1994 COMPLETED BY:- E.G.WlEGERT' TELEPHONE: '504-7394446 OPERATING STATUS'

1. Reporting Period: January,1994 -

Gross Hours in Reporting Period: 744

2. Currently Authorized Power Level (MWt): 3390 Maximum Dependable Capacity (Net MWe): 1075 Design Electrical Rating (Net MWe): 1104.
3. Power Level to which Restricted (if any) (Net MWe): N/A
4. Reasons for Restriction (if any): N/A i

THIS MONTH ' .YR TO DATE - ' CUMULATIVE .

5. Number of Hours Reactor was Critical 744.0 744.0; 61,844.0-
6. Reactor Reserve Shutdown Hours 0 ^
7. Hours Generator was On-une . 744.0 ~ ' 744,0 -' ' 61,032.2-
8. Unit Reserve Shutdown Hours -0 ' 9. Gross Thermal Energy Generated (MWH) 2,517,230- 2,517,230 . 201,545,707'
10. Gross Electrical Energy Generated (MWH) 824,170 824,170 67,244.950
11. Net Electrical Energy Generated (MWH) 789,732 789,732 64,100,177
12. Reactor Service Factor 100.0 100.0 84.4

. 13. Reactor Availability Factor 100.0 100.0 = 84.4 1

14. Unit Service Factor 100.0 100.0 83.3
15. Unit Availability Factor 100.0 100.0 83.3
16. Unit Capacity Factor (using MDC) 98.7 98.7 81.4
17. Unit Capacity Factor (Using DER) 96.1 '96.1 79.3
i. 18. Unit Forced Outage Rate 3.4

e OPERATING DATA REPORT DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 DATE OF REPORT: FEBRUARY,1994 '

COMPLETED BY: E.G;WlEGERT TELEPHONE: 504-739-6448 q OPERATING DATA REPORT (Con't)

19. Shutdowns Scheduled over next 6 Months (type, date and duration of each): ,

Refueling - March 4,1994. Planned duration - 52 days, I

20. If Shutdown at end of report period, estimated date of startup: N/A '
21. Unit in Commercial Operation 4 THIS MONTH YR TO DATE CUMULATIVE
22. Hours in Reporting Period 744.0 744.0 73,249.0
23. Unit Forced Outage Hours 0.0 ' O.0- ' 2,178.7
24. Nameplate Rating (Gross MWe): 1200
25. If Changes Occur in Capacity Ratings (Items Number 2 and 24) Since Last Report, Give Reasons: N/A

~

i l

I L

\ .

1 AVERAGE DAILY. UNIT POWER LEVEll DOCKET, NUMBER: 382 _ ,

UNIT NAME: , WATERFORD 3;.

DATE OF. REPORT:: ; FEBRUARYi1994., _ i i . COMPLETED BY: - E.G. WlEGERT :

. TELEPHONE: 504-739-6446?

MONTH JANUARY.1993 DAY AVERAGE DALLY POWER LEVEL . DAY ' i AVERAGE DAILY POWER LEVEL:, ,

. (MWe-NET) ' (MWe-NET) -- ,

1 1064 17 <- - 1064:

l- 2 1063 18- 1060-l s 3 1063 119 1061-4 1062 -f20 1061 5 1062 21 1064 L. ,

6 1037 22 1061:

7 1062 23: 1062 ,

8 1062 24- 11063- . ,

9 1063 25' 1'061 10 1063 i

-26 1062-

. 7. .

11 1063 27- 1062-i 'j 12 1063 28 1062' 1

13 1063 29 1062~

14 1063 30 -1062 15 1062 31 '1062 16 1063 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the. reporting month.

Compute to the nearest whole megawatt, N

5 r- r-

  • e-==
  • w ( w* *
  • 6
  • t' e

8 UNIT SHUTDOWNS AND POWER REDUCTIONS ,

DOCKET NUMBER: 50-382 UNIT NAME: WATERFORD 3 .

DATE OF REPORT: FEBRUARY,1994 -

COMPLETED BY: E.G. WlEGERT TELEPHONE: 504-739-6446 REPORT FOR JANUARY.1994 Type Method of Shutting F = Forced Duration Down the Reactor or Cause, Comments and Number Dale S = Scheduled (Hours) Reason (1) Reducina Power (2) Corrective Actions NONE (1) REASON (2) METHOD A =' Equipment Failure (explain) . 1= Manual-B= Maintenance orTest ~ 2=: Manual Scram C=- Refueling .3 = : Automatic Scram D= . Regulatory Restriction 4= Continuation from Previous Period

'E=

Operator Training and ' 5= Power Reduction License Examination 6= Other(explain)

F= Administrative

' G = - Operational Error (explain) -

H =- Other(explain) .

w -

-