Text
y.
Ente gy Operrtlins.Inc.
Killona. LA 70066 Tel 504 739 6242 ames J. Fisicaro
%T:*2T W3F1-96-0197 A4.05 PR November 14,1996 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of October,1996. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Very truly yours, J.J. Fisicaro Director Nuclear Safety JJF/DFL/ssf Attachment cc:
L.J. Callan, NRC Region IV I
hql C.P. Patel, NRC-NRR R.B. McGehee N.S. Reynolds F. Yost (Utility Data Institute, Inc.)
J.T. Wheelock (INPO Records Center) 30049 NRC Resident inspectors Office 9611190178 961031 PDR ADOCK 05000382 R
l NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS l
WATERFORD 3 for October,1996 1
The unit operated at an average reactor power level of 99.6% and experienced no shutdowns or significant power reductions during the period.
i i
I l
4 i
l l
l 4
4 I
(3w Patie. I of 6
(
4 PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 for October,1996 i
i There were no pressurizer safety valve failures or challenges experienced curing the month.
4
)
I a
k i
a i
!i i
a 1
J i
J 4
e f
i i.
4 IIN Page 2 of 6 e
OPERATING DATA REPORT f
DOCKET NUMBER : 50-382 j
UNIT NAME : WATERFORD 3 DATE OF REPORT : November 5,1996 COMPLETED BY :
D. S. Freeman TELEPHONE : (504) 464-3352 OPERATING STATUS
- 1. Reporting Period October,1996 Gross Hours in Reporting Period 745
- 2. Currently Authorized Power Level (MWt) 3,390 Maximum Dependable Capacity (Net MWe) :
1,075 Design Electrical Rating (Net MWe) 1,104 -
- 3. Power Level to which Restricted (if any) (Net MWe)
N/A
- 4. Reason for Restriction (if any)
N/A l
THIS YEAR TO MONTH DATE CUMULATIVE
- 5. Number of Hours Reactor was Critical 745.0 6,807.5 82,840.1
- 6. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 7. Hours Generator was On-line 745.0 6,774.3 81,860.4
- 8. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 9. Gross Thermal Energy Generated (MWH) 2,514,187 22,913,788 271,610,228
- 10. Gross Electrical Energy Generated (MWH) 641,590 7,709,890 90,568,260
- 11. Net Electrical Energy Generated (MWH) 806,938 7,376,219 86,382,034
- 12. Reactor Service Factor 100.0 93.0 85.1
- 13. Reactor Availability Factor 100.0 93.0 85.1
- 14. Unit Service Factor 100.0 92.5 84.1
- 15. Unit Availability Factor 100.0 92.5 84.1
- 16. Unit Capacity Factor (using MDC) 100.8 93.7 82.5
- 17. Unit Capacity Factor (using DER) 98.1 91.3 80.4
- 18. Unit Forced Outage Rate 0.0 7.5 3.8 Page 3 of 6
[
OPERATING DATA REPORT l
DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
November 5,1996 COMPLETED BY :
D. S. Freeman TELEPHONE: (504) 464-3352 OPERATING STATUS (Cont.)
4
- 19. Shutdowns Scheduled over next 6 months (type, date and duration of each) :
1 NONE-l
- 20. If Shutdown at end of report period, estimated date of startup :
N/A
~ 21. Unit is in Commercial Operation.
THIS YEAR TO MONTH DATE.
CUMULATIVE i
- 22. Hours in Reporting Period 745 7,320 97,345
- 23. Unit Forced Outage Hours 0.0 545.7 3,218.9 l
- 24. Nameplate Rating (Gross MWe) 1,200 l
Max. Dependable Capacity (Gross MWe) 1,120
- 25. If changes occur in capacity ratings (Items 2 and 24) since the last report, give the reasons :
N/A i
i a
j t idN Page : 4 of 6
i*
l l
AVERAGE DAILY UNIT POWER LEVEL j
DOCKET NUMBER :
50-382 UNIT NAME : WATERFORD 3 s
DATE OF REPORT : November 5,1996 2
j COMPLETED BY :
D. S. Freeman i
TELEPHONE:
(504) 464-3352 l
b l
.i i
I Reporting Period :
October,1996
( NET MWe )
l 4
DAY Avg. Power Level DAY Avg. Power Level 1
1,080 16 1,089 l
2 1,081 17 1,088 j
3 1,081 18 1,088 l
4 1,082 19 1,088
{
5 1,084 20 1,089 6
1,085 21 1,090 l
7 1,085 22 1,088 l
8 1,086 23 1,090 l
9 1,088 24 1,091 10 1,088 25 1,081 11 1,089 26 975 j
12 1,090 27 1,080 13 1,089 28 1,087
.h 14 1,089 29 1,088 15 1,089 30 1,089 31 1,089 INSTRUCTIONS :
On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
Page $ of 6
1 UNIT SHUTDOWNS AND POWER REDUCTIONS i
DOCKET NUMBER : 50-382
}
UNIT NAME : WATERFORD 3 i
DATE OF REPORT : November 5,1996 COMPLETED BY :
D. S. Freeman TELEPHONE: (504) 464-3352 REPORTING PERIOD :
October,1996 Date Duration Shutdown Cause, Comments and Number (yymmdd) Type (Hours) Reason Method Corrective Actions NONE 4
e se TYPE REASON F - Forced A - Equipment Failure (explain)
S - Scheduled B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training and METHOD License Examination 1 - Manual F - Administrative 2 - Manual Scram G - Operational Error (explain) 3 - Automatic Scram H - Other (explain) 4 - Continuation from Previous Period 5 - Power Reduction 6 - Other (explain) 1t%
Page 6 of 6