ML20138K584

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Jan 1997 for Waterford 3 Ses
ML20138K584
Person / Time
Site: Waterford Entergy icon.png
Issue date: 01/31/1997
From: Freeman D, Gaudet T
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
W3F1-97-0027, W3F1-97-27, NUDOCS 9702190052
Download: ML20138K584 (7)


Text

I Entergy l"M?a""""' '"*-

' Operations rgygg W3F1-97-0027 A4.05 PR February 13,1997 U.S. Nuclear Regulatory Commission A1TN: Document Control Desk Washington, D.C. 20555

Subject:

Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:

Attached is the subject monthly report which covers the operating statistics for the month of January,1997. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.

Should you have any questions regarding the above, please contact me at (504) 739-6666 or David Litolff at (504) 739-6693.

Very truly yours, T.J. Gaudet Acting - Director i Nuclear Safety & Regulatory Affairs TJG/DFL/ssf jY l Attachment cc: L.J. Callan (NRC Region IV), C.P. Patel (NRC-NRR),

R.B. McGehee, N.S. Reynolds, F. Yost (Utility Data Institute, Inc.),

J.T. Wheelock (INPO Records Center), NRC Resident inspectors

~

Offira i 9702190052 970131 I DR ADOCK0500g2 j

l

. NRC MONTHLY OPERATING REPORT l

i

SUMMARY

OF OPERATIONS l WATERFORD 3 for January,1997 l The unit operated at an average reactor power level of 99.9% and experienced no shutdowns

! or significant power reductions during the period.

t l

[

2SM1 Page . I of 6

4 . PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES 1

WATERFORD 3 for January,1997 4

There were no pressurinr safety valve failures or challenges experienced during the month.

"4 k

i i

i i

6

)

l j

1  ;

i.

I f

i e

1 4

9 2/197 Page: 2 of 6

.&s ,4 J +. A A4 ._, ,., tap s 2=-__.5 m. +A4a mJ, _ . a:m - m.m. ma mmei. _maAa.a OPERATING DATA REPORT

.i 1

DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : February 5,1997 COMPLETED BY : D. S. Freeman

, TELEPHONE: (504) 464 3352

OPERATING STATUS j 1. Reporting Period  : January,1997 Gross Hours in Reporting Period  : 744 1

4

2. Currently Authorized Power Level (MWt)  : 3,390 Maximum Dependable Capacity (Net MWe) : 1,075 Design Electrical Rating (Net MWe)  : 1,104
3. Power Level to which Restricted (if any) (Net MWe)  : N/A
- 4. Reason for Restriction (if any) N/A  ;

i

! THIS YEAR TO f MONTH DATE CUMULATIVE l 5. Number of Hours Reactor was Critical 744.0 744.0 85,048.1 2 6. Reactor Reserve Shutdown Hours o.o 0.0 0.0

. 7. Hours Generator was On-line 744.0 744.0 84,0s8.4

8. Unit Reserve Shutdown Hours o.0 0.0 0.0

] 9. Gross Thermal Energy Generated (MWH) 2,520,469 2,520,469 27s,777,s34

10. Gross Electrical Energy Generated (MWH) 859,s30 859,s30 93,04s,910

, 11. Net Electrical Energy Generated (MWH) 824,90s 824,90s 88,757,566

12. Reactor Service Factor 100.0 100.0 85.4 I 13. Reactor Availability Factor 100.0 100.0 85.4 i 14. Unit Service Factor 100.0 100.0 84.4 j 15. Unit Availability Factor 100.0 100.0 84.4 I 16. Unit Capacity Factor (using MDC) 103.1 103.1 82.9
17. Unit Capacity Factor (using DER) 100.4 100.4 so.s l 18. Unit Forced Outage Rate 0.0 0.0 3.7 i

, 2/5M7 Page 3of6

1

i OPERATING DATA REPORT 4

DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : February 5,1997 l

COMPLETED BY : D. S. Freeman TELEPHONE: (504) 464-3352

, OPERATING STATUS (Cont.)

+

19. Shutdowns Scheduled over next 6 months (type, date and duration of each)

I REFUEL - April 11,1997 - 34 days

1
20. If Shutdown at end of report period, estimated date of startup .: N/A I
21. Unit is in Commercial Operation.

THIS YEAR TO MONTH DATE CUMULATIVE

22. Hours in Reporting Period 744 744 99,553 I
23. Unit Forced Outage Hours 0.0 0.0 3,218.9 l 1

, 24. Nameplate Rating (Gross MWe)  : 1,200 i

j Max. Dependable Capacity (Gross MWe)  : 1,120 i

25. If changes occur in capacity ratings (Items 2 and 24) since the last report, give the reasons :

N/A l

J k

4 k

l i

gw Page : 4 of 6 4

- - - - _ y

1 .

l e

AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER : 50-382 i UNIT NAME : WATERFORD 3 l DATE OF REPORT : February 5,1997  :

COMPLETED BY : D. S. Freeman  ;

TELEPHONE: (504) 464-3352  ;

I Reporting Period . January,1997 ( NET MWe )

? .

DAY Avg. Power Level DAY Avg. Power Level j 1 1,111 16 1,109 ,

2 1,110 17 1,108 3 1,110 18 1,109 l 4 1,110 19 1,110 5 1,109 20 1,111 6 1,106 21 1,110 7 1,108 22 1,110 8 1,108 23 1,109 9 1,109 24 1,108 10 1,109 25 1,108 11 1,110 26 1,108 12 1,110 27 1,106 13 1,109 28 1,105 ,

14 1,110 29 1,106 I 15 1,110 30 1,107 l 31 1,108 INSTRUCTIONS :

On this form, list the average daily unit power level in MWe-Net for each ]

day in the reporting month. Compute to the nearest whole megawatt.  !

1%7 Page S of 6

I .

r .

i UNIT SHUTDOWNS AND POWER REDUCTIONS I

DOCKET NUMBER : 50-382 ,

UNIT NAME : WATERFORD 3 j DATE OF REPORT : February 5,1997 i COMPLETED BY : D. S. Freeman TELEPHONE: (504) 464-3352 1

REPORTING PERIOD : January,1997 Date Duration Shutdown Cause, Comments and Number (yymmdd) Type (Hours) Reason Method Corrective Actions NONE l

)

I i l

)

1 TYPE REASON F - Forced A - Equipment Failure (explain)

S - Scheduled B - Maintenance or Test  !

C - Refueling I D - Regulatory Restriction  !

E - Operator Training and METHOD License Examination 1 - Manual F - Administrative 2 - Manual Scram G - Operational Error (explain) 3 - Automatic Scram H - Other (explain) l 4 - Continuation from Previous Period

'i - Power Reduction 6 - Other (explain)

Pape , 6 of 6