Text
I
- - s cntergy operations,ine.
e 5
2%ilen Er C. Ewing, Ill f4JC a afety & Regulatory Affair 6 W3F1-98-0037 A4.05 PR June 11,1998 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of May,1998. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Should you have any questions regarding the above, please contact me at
/
(504) 739-6242 or Tim Gaudet at (504) 739-6666.
/
Very truly yours,
[
E.C. Ewing Director Nuclear Safety & Regulatory Affairs ECE/ PRS /rtk Attachment cc:
E.W. Merschoff (NRC Region IV), C.P. Patel (NRC-NRR),
J. Smith, N.S. Reynolds, B. Lewis (Utility Data Institute, Inc.),
J.T. Wheelock (INPO Records Center), NRC Resident inspectors Office 9806160472 980531
~
PDR ADOCK 05000382 R
PDR g
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 for May,1998 The unit experienced no shutdowns but had one (1) significant, though short-term, power reduction during the reporting period resulting in an average power level of 99.3%.
@h? '
Page : 1 of 6
PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 for May,1998 There were no pressurizer safety valve failures or challenges experienced during the month.
WR48 Page : 2 of 6
OPERATING DATA REPORT DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : June 8,1998 COMPLETED BY :
D. S. Freeman TELEPHONE: (504)739-6575 OPERATING STATUS l
- 1. Reporting Period May,1998 Gross Hours in Reporting Period 744
- 2. Currently Authorized Power Level (MWt) 3,390 Maximum Dependable Capacity (Net MWe) :
1,07s Design Electrical Rating (Net MWe) 1,104
- 3. Power Level to which Restricted (if any) (Net MWe)
N/A 1
- 4. Reason for Restriction (if any)
N/A l
l THIS YEAR TO MONTH DATE CUMULATIVE
- 5. Number of Hours Reactor was Crit; cal 744.0 3,623.0 94,165.7
- 6. Reactor Reserve Shutdown Hours 0.0 0.0 0.0 l
- 7. Hours Generator was On-line 744.0 3,623.0 93,108.7
- 8. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 9. Gross Thermal Energy Generated (MWH) 2,503,708 12,251,664 309,233,275
- 10. Gross Electrical Energy Generated (MWH) 852,078 4,177,054 103,397,092
- 11. Net Electrical Energy Generated (MWH) 818,015 4,010,962 98,664,299
- 12. Reactor Service Factor 100.0 100.0 84.7
- 13. Reactor Availability Factor 100.0 100.0 34.7
- 14. Unit Service Factor 100.0 100.0 83.7
- 15. Unit Availability Factor 100.0 100.0 83.7
- 18. Unit Capacity Factor (using MDC) 102.3 103.0 82.5
- 17. Unit Capacity Factor (using DER) 99.6 100.3 80.4
- 18. Unit Forced Outage Rate 0.0 0.0 3.3 FEM Page : 3 of 6
OPERATING DAT/ REPORT DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : June 8,1998 COMPLETED BY :
D. S. Freeman TELEPHONE: (504)739-6575 OPERATING STATUS (Cont.)
- 19. Shutdowns Scheduled over next 6 months (type, date and duration of each) :
NONE
- 20. If Shutdown at end of report period, estimated date of startup :
N/A
- 21. Unit is in Commercial Operation.
THIS YEAR TO MONTH DATE CUMULATIVE
- 22. Hours in Reporting Period 744 3,623 111,192
- 23. Unit Forced Outage Hours 0.0 0.0 3,218.9
- 24. Nameplate Rating (Gross MWe) 1,200 Max. Dependable Capacity (Gross MWe) 1,120
- 25. If changes occur in capacity ratings (Items 2 and 24) since the last report, f
give the reasons :
1 N/A j
M Page : 4 of 6
]
AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : June 8,1998 COMPLETED BY :
D. S. Freeman TELEPHONE: (504) 739-6575 Reporting Period :
May,1998
( NET MWe )
DAY Avg. Power Level DAY Avg. Power Level 1
1,106 16 1,110 2
1,047 17 1,110 3
1,109 18 1,110 4
1,109 19 1,110 5
1,108 20 1,110 6
1,107 21 1,109 7
1,108 22 1,108 8
1,111 23 1,108 9
1,110 24 1,107 10 1,111 25 1,106 11 1,110 26 1,106 12 1,110 27 1,106 13 1,107 28 1,105 14 1,106 29 921 15 1,106 30 1,095 31 1,099 INSTRUCTIONS :
On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
j 6%4 Page $ of 6
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : June 9,1998 COMPLETED BY :
D. S. Freeman TELEPHONE: (504)739-6575 i
REPORTING PERIOD :
May,1998 Outage Date Duration Shutdown Cause, Comments and Number (yymmdd) Type (Hours)
Reason Method Corrective Actions 98-01 980529 F
0.0 A
5 A Part-Length CEA fully inserted into the reactor due to a power supply failure.
Reactor power was reduced below 70% within one hour per Tech. Spec. requirement.
Investigation is continuing.
I Details are in corrective action document CR-98-0755.
i TYPE REASON F - Forced A - Equipment Failure (explain)
S - Scheduled B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training and METHOD License Examination 1 - Manual F - Administrative 2 - Manual Scram G - Operational Error (explain) 3 - Automatic Scram H - Other (explain) 4 - Continuation from Previous Period 5 - Power Reduction 6 - Other (explain) n,. : 6 or 6