y Ent gy peritlins, Inc.
Of Killona, LA 70066 Tel 504 739 6242 a.
I C Ewing. lll ar Safety & Regulatory Affairs W3F1-98-0188 A4.05 PR November 16,1998 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of October,1998. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
4 Should you have any questions regarding the above, please contact me at (504) 739-6242 or E.P. Perkins at (504) 739-6379.
Very truly yours, E.C. Ewing Director Nuclear Safety & Regulatory Affairs ECE/ALL/ssf Attachment l
cc:
E.W. Merschoff (NRC Region IV), C.P. Patel (NRC-NRR),
J. Smith, N.S. Reynolds, B. Lewis (Utility Data institute, Inc.),
J.T. Wheelock (INPO Records Center),
NRC Resident inspectors Office 9811190005 981031 PDR ADOCK 05000382 R
PDR [
l J
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 1
for October,1998 A forced outage which began during the previous month and was extended due to Hurricane Georges, continued into the beginning of October, accounting for the average reactor power level of 97.3%.
1 we.
e,as
PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 for October,1998 There were no pressurizer safety valve failures or challenges experienced during the month.
l I
I I
l I
I n,,.
r2a+
l
N OPERATING DATA REPORT DOCKET NUMBER :
50-382 i
UNIT NAME : WATERFORD 3 i
DATE OF REPORT :
November 5,1998 COMPLETED BY :
D. S. Freeman TELEPHONE:
(504)739-6575 l
OPERATING STATUS
- 1. Reporting Period October,1998 Gross Hours in Reporting Period 745
- 2. Currerttly Authorized Power Level (MWt) 3,390 Maximum Dependable Capacity (Net MWe) :
1,07s Design Electrical Rating (Net MWe) 1,104
- 3. Power Level to which Restricted (if any) (Net MWe)
N/A
- 4. Reason for_ Restriction (if any)
N/A THIS YEAR TO MONTH DATE CUMULATIVE
- 5. Number of Hours Reactor was Critical 740.s 6,937.5 97,480.2
- 6. Reactor Reserve Shutdown Hours o.o 0.0 0.o
- 7. Hours Generator was On-line 733.s 6,870.2 96,356.0
- 8. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 9. Gross Thermal Energy Generated (MWH) 2,456,6s2 22,983,018 319,964,629
- 10. Gross Electrical Energy Generated (MWH) 834,706 7,775,938 106,995,976
.11 Net Electrical Energy Generated (MWH) 799,378 7,435,964 102,089,301
- 12. Reactor Service Factor 99.4 95.1 84.9
-13. Reactor Availability Factor 99.4 95.1 84.9
- 14. Unit Service Factor 98.5 94.2 83.9
.15. Unit Availability Factor 98.5 94.2 83.9 16.- Unit Capacity Factor (using MDC) 99.8 94.8 82.7
- 17. Unit Capacity Factor (using DER) 97.2 92.3 80.5
- 18. Unit Forced Outage Rate 1.5 5.2 3.6 IIM6M Page. 3 or 6 n.,-
j OPERATING DATA REPORT i
DOCKET NUMBER :
50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
November 5,1998 1 -
COMPLETED BY :
D. S. Freeman TELEPHONE:
(504)739-6575 a
i OPERATING STATUS (Cont.)
- 19. Shutdowns Scheduled over next 6 months (type, date and duration of each) :
1 REFUEL OUTAGE #9 - commencing on February 5,1999 - 40 day outage I
- 20. If Shutdown at end of report period, estimated date of startup :
N/A 1
- 21. Unit is in Commercial Operation.
1 THIS YEAR TO MONTH DATE CUMULATIVE
- 22. Hours in Reporting Period 74s 7,29s 114,865 j
- 23. Unit Forced Outage Hours 11.s 378.2 3,597.2 4
j
- 24. Nameplate Rating (Gross MWe) 1,200 j-Max. Dependable Capani'" (Gross MWe) 1,120
- 25. If changes occur in capacity ratings (ltems 2 and 24) since the last report, i
give the reasons :
i N/A i
j 1
i i
g gfgg.
Page 4 of 6
AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
November 5,1998 COMPLETED BY :
D. S. Freeman TELEPHONE: (504) 739-6575 Reporting Period :
October,1998
( NET MWe )
j DAY Avg. Power level DAY Avg. Power level i
1 1
139 16 1,111 3
2 1,028 17 1,112
]
3 1,099 18 1,112 3
4 1,100 19 1,106
{
5 1,101 20 1,107 6
1,103 21 1,107 7
1,097 22 1,108
~
i 8
1,100 23 1,108 I
9 1,106 24 1,109 j
10 1,107 25 1,109 11 1,107 26 1,109 12 1,108 27 1,108 13 1,108 28 1,108 14 1,108 29 1,109 j
15 1,110 30 1,108 31 1,109 l
lNSTRUCTIONS :
On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
II/16@t Page 5 of 6
o UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
November 5,1998 COMPLETED BY :
D. S. Freeman TELEPHONE:
(504) 739-6575 REPORTING PERIOD :
October,1998 l
Outage Date Duration Shutdown Cause, Comments and Number (yymmdd) Tyoe (Hours)
Reason Method Corrective Actions 98-05 980917 F
11.5 A
4 Outage continued from the previous month. Involved the replacement of Pressurizer Code Safety Valves, recon-necting Main Transformer B after being swapped with a i
spare, and delays in the return to power due to the threat of Hurricane Georges.
se 1
TYPE REASON F - Forced A - Equipment Failure (explain) l S - Scheduled B - Maintenance or Test C - Refueling D - Regulatory Restriction l
E - Operator Training and l-METHOD License Examination l
1 - Manual F - Administrative 2 - Manual Scram G - Operational Error (explain) 3 - Automatic Scram H - Other (explain) 4 - Continuation from Previous Period 5 - Power Reduction 6 - Other (explain) num n,.
a s