Monthly Operating Rept for Feb 1998 for Waterford 3
ML20248L362
Person / Time
Site: Waterford Entergy icon.png
Issue date: 02/28/1998
From: Ewing E, Freeman D
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
W3F1-98-0042, W3F1-98-42, NUDOCS 9803200003
Download: ML20248L362 (7)


Text

.

O Ente gy perations Inc.

Killona. LA 70066 Tel 504 739 6242

. r C. Ewing, til iu ety & Regulatory Affairs W3F1-98-0042 A4.05 PR March 16,1998 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk  ;

Washington, D.C. 20555 '

Subject:

Waterford 3 SES i Docket No. 50-382 License No. NPF-38 l Monthly Operating Report i Gentlemen:

Attached is the subject monthly report which covers the operating statistics for the month of February,1998. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38. I Should you have any questions regarding the above, please contact me at (504) 739-6242 or Tim Gaudet at (504) 739-6666.

Very truly yours, E.C. Ewing 0 >

Director Nuclear Safety & Regulatory Affairs ECE/ PRS /ssf l!$l$f5fl$fflf

    • hllll Attachment cc: E.W. Merschoff (NRC Region IV), C.P. Patel (NRC-NRR),

J. Smith, N.S. Reynolds, B. Lewis (Utility Data institute, Inc.),

l J.T. Wheelock (INPO Records Center), NRC Resident inspectors j OMce

. ,n44o 9803200003 980228 PDR ADOCK 050003921 R PDR ..

j i

NRC MONTHLY OPERATING REPORT l .

SUMMARY

OF OPERATIONS WATERFORD 3 for February,1998 The unit operated at an average reactor power level of 99.9% and experienced no shutdowns or significant power reductions during the period.

l 1

i l

l I l k'IW Page : 1 of 6 C __ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _

~

1 l

l PRESSURIZER SAFETY VALVE l

l FAILURES AND CHALLENGES WATERFORD 3 for February,1998 i

There were no pressurizer safety valve failures or challenges experienced during the month.

I I I

i I

AM94 Page . 2 of 4 l

OPERATING DATA REPORT DOCKET NUMBER : 50-382  !

UNIT NAME : WATERFORD 3 DATE OF REPORT : March 3,1998 COMPLETED BY : D. S. Freeman TELEPHONE: (504)739-6575 i

OPERATING STATUS l 1. Reporting Period  : February,1998 ,

Gross Hours in Reporting Period  : 672 f

i

2. Currently Authorized Power Level (MWt)
  • 3,390

]

Maximum Dependable Capacity (Net MWe)
1,075 l Design Electrical Rating (Net MWe)  : 1,104  ;
3. Power Level to which Restricted (if any) (Net MWe)  : N/A

'4. Reason for Restriction (if any)  : N/A l THIS YEAR TO MONTH DATE CUMULATIVE

5. Number of Hours Reactor was Critical 672.0 1,416.0 91,958.7
6. Reactor Reserve Shutdown Hours o.o 0.0 0.0
7. Hours Generator was On-line 672.0 1,416.0 90,901.7 l _8. Unit Reserve Shutdown Hours 0.0 0.0 0.0 l 9. Gross Thermal Energy Geneiated (MWH) 2,276,816 4,790,581 301,772,192
10. Gross Electrical Energy Generated (MWH) 778,057 1,635,855 100,855,893
11. Net Electrical Energy Generated (MWH) 747,309 1,571,088 96,224,425
12. Reactor Service Factor 100.0 100.0 84.4
13. Reactor Availability Factor 100.0 100.0 84.4
14. Unit Service Factor 100.0 100.0 83.4
15. Unit Availability Factor 100.0 100.o 83.4
16. Unit Capacity Factor (using MDC) 103.4 103.2 82.1
17. Unit Capacity Factor (using DER) 100.7 100.5 80.0
18. Unit Forced Outage Rate o.0 0.0 3.4 1/16NS Page : 1 of 6 l
f. -

9 L

OPERAT!NG DATA REPORT DOCKET NUMBER : 50 382 UNIT NAME : WATERFORD 3 DATE OF REPORT : March 3,1998 COMPLETED BY : D. S. Freeman TELEPHONE: (504) 739-6575 OPERATING STATUS (Cont.)

19. Shutdowns Scheduled over next 6 months (type, date and duration of each) :

l NONE

20. lf Shutdown at end of report period, estimated date of startup :

N/A

21. Unit is in Commercial Operation.

THIS YEAR TO MONTH DATE CUMULATIVE

22. Hours in Reporting Period 672 1,416 10s,sas
23. Unit Forced Outage Hours o.o 0.0 3,21s.9 l 24. Nameplate Rating (Gross MWe)  : 1,200 Max. Dependable Capacity (Gross MWe) -

1,120

25. If changes occur in capacity ratings (Items 2 and 24) since the last report, give the reasons :

N/A l

e

_ r a as j

L I

AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER : 50-382 ,

UNIT NAME : WATERFORD 3 DATE OF REPORT : March 3,1998 COMPLETED BY : D. S. Freeman TELEPHONE : (504)739 4 575 s

l Reporting Period : February,1998 ( NET MWe )

DAY Avg. Power Level DAY Avg. Power Level 1 1,113 16 1,112 2 1,113 17 1,111 3 1,112 18 1,112 4 1,112 19 1,112 5 1,111 20 1,112 6 1,112 21 1,113 7 1,112 22 1,113

~

8 1,111 23 1,113 ,

9 1,111 24 1,113 ]

10 1,111 25 1,113 11 1,112 26 1,112 12 1,112 27 1,113 13 1,112 28 1,113 14 1,111 15 1,112 INSTRUCTIONS :

On this form, list the average daily unit power level in MWe-Net for each i day in the reporting month. Compute to the nearest whole megawatt.

l

%WUS Page : 5 of 6

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER : 50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT : March 3,1998 COMPLETED BY : D. S. Freeman TELEPHONE: (504) 739-6575 REPORTING PERIOD : February,1998 Date Duration Shutdown Cause, Comments and Number (yymmdd) Type (Hours) Reason Method Corrective Actions NONE

~

_ TYPE REASON F - Forced A - Equipment Failure (explain)

S - Scheduled B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training and METHOD License Examination 1 - Manual F - Administrative 2 - Manual Scram G - Operational Error (explain) i 3 - Automatic Scram H - Other (explain) 4 - Continuation from Previous Period 5 - Power Reduction 6 - Other (explain) i m .,.

j 1 . _ _ _ - _ _ _ _ _ _ _ __ a