Entergy Operttions, Inc.
Kdlona, LA 70066
=
Tel 504 739 6242 es J. Fisicaro 10 fan
- W3F1-96-0160 A4.05 PR September 13,1996 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of August,1996. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Very truly yours, 4w J.J. Fisicaro Director Nuclear Safety JJF/DFL/ssf Attachment cc:
L.J. Callan, NRC Region IV C.P. Patel, NRC-NRR
.1fy q
R.B. McGehee
- {
N.S. Reynolds F. Yost (Utility Data Institute, Inc.)
J.T. Wheelock (INPO Records Center)
NRC Resident inspectors Office 1 934 9609190014 960831 PDR ADOCK 05000302 R
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 for August,1996 A forced outage which began during the previous month, continued into the first few days of this month, accounting for the average reactor power level of 84.0%.
i Page ' I of e
PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 for August,1996 There were no pressurizer safety valve failures or challenges experienced during the month.
l
%W%
Page 2d6
1 OPERATING DATA REPORT DOCKET NUMBER :
50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
September 6,1996 COMPLETED BY :
D. S. Freeman TELEPHONE:
(504) 464-3352 OPERATING STATUS
- 1. Reporting Period August,1996 Gross Hours in Reporting Period 744
- 2. Currently Authorized Power Level (MWt) 3,390 Maximum Dependable Capacity (Net MWe) -
1,075 Design Electrical Rating (Net MWe) 1,104
- 3. Power Level to which Restricted (if any) (Net MWe)
N/A
- 4. Reason for Restriction (if any)
N/A THIS YEAR TO MONTH DATE CUMULATIVE l
1
- 5. Number of Hours Reactor was Critical 639.7 5,342.5 81,375.1
- 6. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 7. Hours Generator was On-line 631.5 5,309.3 80,395.4
- 8. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 9. Gross Thermal Energy Generated (MWH) 2,118,782 17,961,793 266,658,233
- 10. Gross Electrical Energy Generated (MWH) 706,360 6,058,900 88,917,270
- 11. Net Electrical Energy Generated (MWH) 671,953 5,795,994 84,801,809
- 12. Reactor Service Factor 86.0 91.2 84.9
- 13. Reactor Availability Factor 86.0 91.2 84.9
- 14. Unit Service Factor 84.9 90.7 83.9
- 15. Unit Availability Factor 84.9 90.7 83.9
- 16. Unit Capacity Factor (using MDC) 84.0 92.1 82.3
- 17. Unit Capacity Factor (using DER) 81.8 89.7 80.1
- 18. Unit Forced Outage Rate 15.1 9.3 3.8
%ms Pap 3 of s
OPERATING DATA REPORT DOCKET NUMBER :
50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
September 6,1996 COMPLETED BY :
D. S. Freeman TELEPHONE:
(504) 464-3352 OPERATING STATUS (Cont.)
- 19. Shutdowns Scheduled over next 6 months (type, date and duration of each) :
NONE
- 20. If Shutdown at end of report period, estimated date of startup :
N/A
- 21. Unit is in Commercial Operation.
THIS YEAR TO MONTH DATE CUMULATNE
- 22. Hours in Reporting Period 744 5,855 95,880
- 23. Unit Forced Outage Hours 112.5 545.7 3,218.9
- 24. Nameplate Rating (Gross MWe) 1,200 Max. Dependable Capacity (Gross MWe) 1,120
- 25. If changes occur in capacity ratings (Items 2 and 24) since the last report, give the reasons :
N/A e.
.a.
~
AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER :
50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
September 6,1996 i
COMPLETED BY :
D. S. Freeman TELEPHONE:
(504) 464-3352 Reporting Period.
August,1996
( NET MWe )
DAY Avg. Power Level DAY Avg. Power Level 1
1 (14) 16 1,091
~
2 (14) 17 1,091 3
(22) 18 1,090 4
(37) 19 1,090 1
5 40 20 1,090 6
998 21 1,089 7
1,088 22 1,073 8
1,092 23 1,073 9
1,093 24 1,072 10 1,077 25 1,072 11 1,091 26 1,072 12 1,080 27 1,071 13 1,090 28 1,071 14 1,090 29 1,071 15 1,090 30 1,072 31 1,068 INSTRUCTIONS :
On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
Sfv%
Page ' 5 of 6
UNIT SHUTDOWNS AND POWER REDUCTIONS
~
DOCKET NUMBER :
50-382 UNIT NAME : WATERFORD 3 DATE OF REPORT :
September 6,1996 COMPLETED BY :
D. S. Freeman TELEPHONE: (504) 464-3352 REPORTING PERIOD :
August,1996 Date Duration Shutdown Cause, Comments and Number (yymmdd) Type (Hours)
Reason Method Corrective Actions 96-02 960716 F
112.5 A
4 All 6 Baffle Bolts to the 2B RCP (Reactor Coolant Pump) broke allowing the Baffle to rub against the Heat Exchanger, and leading to abnormalities in the RCP Seal.
A controlled shutdown of the plant was performed.
Repairs included replacement of the 2B RCP Baffle Bolts, Baffle, Heat Exchanger and Seal. Refer to CR-96-1048 l
for additional details.
Continued from previous period.
TYPE REASON F - Forced A - Equipment Failure (explain)
S - Scheduled B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training and METHOD License Examination 1 - Manual F - Administrative i
2 - Manual Scram G - Operational Error (explain) 3 - Automatic Scram H - Other (explain) 4 - Continuation from Previous Period 5 - Power Reduction 6 - Other (explain)
J r.,. or.