i Entergy Operaations,inc.
s
', y Kswa L A 7mk$
/.
Te 504 739 6774 i
R. F. Burski Due s N n:n Severy Mhnhnd 3 W3F1-95-0145 A4.05 PR September 12, 1995 L
U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject monthly report which covers the operating statistics for the month of August, 1995. This report is submitted per l
Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Very truly yours, suudk:
R.F. Burski Director Nuclear Safety 4
RFB/DFL/ssf Attachment cc:
L.J. Callan, NRC Region IV C.P. Patel, NRC-NRR R.B. McGehee N.S. Reynolds F. Yost (Utility Data Institute, Inc.)
J.T. Wheelock (INP0 Records Center)
NRC Resident Inspectors Office 9509140004 950831 F i gDR ADOCK 05000382 I
pog _.__
l
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 for August, 1995 The unit operated at an average reactor power level of 99.96% and experienced no shutdowns or significant power reductions during the period, b
e I
h
- 195 r.,: i a e i
i PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 for August, 1995 There were no pressurizer safety valve failures or challenges experienced during the month.
i i
)
Page: 2 of e
I OPERATING DATA REPORT I
DOCKET NUMBER :
50-382 UNIT NAME :
WATERFORD 3 DATE OF REPORT :
September 1, 1995 COMPLETED BY :
D. S. Freeman TELEPHONE :
(504) 464-3352 OPERATING STATUS
- 1. Reporting Period August, 1995 Gross Hours in Reporting Period 744 2
Currently Author.ed Power Level (MWt) :
3,390 i
Maximum Dependable Capacity (Net MWe) :
1,075 l
Design Electrical Rating (Net MWe) :
1,104 3.
Power Level to which Restricted (if any) (Net MWe) :
N/A
- 4. Reason for Restriction (if any)
N/A THIS YEAR TO MONTH DATE CUMULATIVE
- 5. Number 6 Hours Reactor was Critical 744.0 5,387.9 74,110.7
- 6. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
- 7. Hours Generator was On-line 744.0 5,368.0 73,212.3
- 8. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 9. Gross Thermal Energy Generated (MWH) 2,521,249 18,144,899 242,474,508
- 10. Gross Electrical Energy Generated (MWH) 830,400 6,043.720 80,778,180
- 11. Net Electrical energy Generated (MWH) 792,427 5,779,733 77,022.099
- 12. Reactor Service Factor 100.0 92.4 85.1
- 13. Reactor Availability Factor 100.0 92.4 85.1
- 14. Unit Service Factor 100.0 92.1 84.1
- 15. Unit Availability Factor 100.0 92.1 84.1
- 16. Unit Capacity Factor (using MDC) 99.1 92.2 82.2
- 17. Unit Capacity Factor (Using DER) 96.5 89.8 80.1
- 18. Unit Forced Outage Rate 0.0 7.9 3.5 W195 Page. 3 of 6
l OPERATING DATA REPORT DOCKET NUMBER :
50-382 UNIT NAME :
WATERFORD 3 DATE OF REPORT :
September 1, 1995 COMPLETED BY :
D. S. Freeman TELEPHONE :
(504) 464-3352 OPERATING STATUS (Cont.)
- 19. Shutdowns Scheduled over next 6 months (type, date and duration of each) :
REFUEL - September 22, 1995 60 Days
- 20. If Shutdown at end of report period, estimated date of startup:
N/A
- 21. Unit is in Commercial Operation.
THIS
' YEAR TO MONTH DATE CUMULATIVE
- 22. Hours in Reporting Period 744 5.831 87.096
- 23. Unit Forcij Outage Hours 0.0 463.0 2.673..2
- 24. Nameplate Rating (Gross MWe) :
1.200 Max. Dependable Capacity (Gross MWe) :
1.120
- 25. If changes occur in capacity ratings (Items 2 and 24) since the last report, give the reasons :
N/A t
J j
i l
AVERAGE DAILY UNIT POWER LEVEL l
1 DOCKET NUMBER :
50-382 UNIT NAME :
WATERFORD 3 DATE OF REPORT :
September 1, 1995 COMPLETED BY :
D. S. Freeman
]
TELEPHONE :
(504) 464-3352 i
Reporting Period :
August, 1995
( NET MWe )
DAY Avg. Power Level DAY Avg. Power Level t
1 1,069 16 1,067 2
1,069 17 1,066 j-3 1,070 18 1,065 4
1,069 19 1,064 l
5 1,069 20 1,064 6
1,069 21 1,065 I
7 1,069 22 1,065 1
8 1,067 23 1,064 9
1,066 24 1,063 10 1,067 25 1,062 l
11 1,068 26 1,061 12 1,067 27 1,060 13 1,067 28 1,060 i
14 1,065 29 1,060 l
15 1,066 30 1,060 l
31 1,061 INSTRUCTIONS :
i On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
1 3
i.
1 4
MMS Page : 5 of 6
i UNIT SHUTDOWNS AND POWER REDUCTIONS l
DOCKET NUMBER :
50-382 UNIT NAME :
WATERFORD 3 DATE OF REPORT :
September 1, 1995 COMPLETED BY :
D. S. Freeman TELEPHONE :
(504) 464-3352 i
REPORTING PERIOD :
August, 1995 Date
- Duration
- Shutdown Cause, Comments and Number (yymmdd)
Type (Hours)
Reason Method Corrective Actions NONE IYEE REASON F - Forced A - Equipment Failure (explain)
S - Scheduled B -Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training and METHOD License Examination 1 - Manual F - Administrative 2 - Manual Scram G -Operational Error (explain) 3 - Automatic Scram H -Other (explain) 4 - Continuation from Previous Period 5 - Power Reduction 6 - Other (explain) 4 telm Page 6 of 6