Line 3: |
Line 3: |
| | issue date = 11/30/1991 | | | issue date = 11/30/1991 |
| | title = Monthly Operating Repts for Nov 1991 for Turkey Point Units 3 & 4.W/911213 Ltr | | | title = Monthly Operating Repts for Nov 1991 for Turkey Point Units 3 & 4.W/911213 Ltr |
| | author name = PLUNKETT T F, TIERNEY R A | | | author name = Plunkett T, Tierney R |
| | author affiliation = FLORIDA POWER & LIGHT CO. | | | author affiliation = FLORIDA POWER & LIGHT CO. |
| | addressee name = | | | addressee name = |
|
---|
Category:MONTHLY OPERATING ANALYSIS REPORT
MONTHYEARML17355A4471999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Turkey Point,Units 3 & 4.With 991008 Ltr ML17355A4121999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Turkey Point,Units 3 & 4.With 990909 Ltr ML17355A3981999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Turkey Point,Units 3 & 4.With 990809 Ltr ML17355A3841999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Turkey Point,Units 3 & 4.With 990713 Ltr ML17355A3511999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Turkey Point,Units 3 & 4.With 990609 Ltr ML17355A3331999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Turkey Point,Units 3 & 4.With 990511 Ltr ML17355A2911999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Turkey Point,Units 3 & 4.With 990414 Ltr ML17355A2551999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Turkey Point Nuclear Power Plant,Units 3 & 4.With 990315 Ltr ML17355A2261999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Turkey Point,Units 3 & 4.With 990211 Ltr ML17355A1911998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Turkey Point,Units 3 & 4.With 990112 Ltr ML18008A0461998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Turkey Point,Units 3 & 4.With 981209 Ltr ML17354B1901998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Turkey Point,Units 3 & 4.With 981112 Ltr ML17354B1311998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Turkey Point Unit 3 & 4.With 981012 Ltr ML17354B0981998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Turkey Points,Units 3 & 4.With 980915 Ltr ML17354B0771998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Turkey Point,Units 3 & 4.W/980810 Ltr ML17354B0241998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Turkey Point,Units 3 & 4.W/980709 Ltr ML17354A9711998-05-31031 May 1998 Monthly Operating Repts for Turkey Point,Units 3 & 4. W/980611 Ltr ML17354A9231998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Turkey Point,Units 3 & 4.W/980511 Ltr ML17354A8821998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Turkey Point,Units 3 & 4.W/980409 Ltr ML17354A8311998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Turkey Point,Units 3 & 4.W/980311 Ltr ML17354A7871998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Turkey Point,Units 3 & 4.W/980209 Ltr ML17354A7581997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Turkey Point,Unit 3 & 4.W/980112 Ltr ML17354A7381997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Turkey Point,Units 3 & 4.W/971215 Ltr ML17354A7211997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Turkey Point,Units 3 & 4.W/971114 Ltr ML17354A6811997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Turkey Point,Units 3 & 4.W/971009 Ltr ML17354A6221997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Turkey Point. W/970909 Ltr ML17354A6051997-07-31031 July 1997 Monthly Operating Repts for July 1997 for TPS.W/970806 Ltr ML17354A5731997-06-30030 June 1997 Monthly Operating Repts for June 1997 for Turkey Point,Units 1 & 2.W/970710 Ltr ML17354A5261997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Turkey Point Units 3 & 4.W/970612 Ltr ML17354A5071997-04-30030 April 1997 Monthly Operating Repts for April 1997 for TPS.W/970512 Ltr ML17354A4631997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Turkey Point Units 3 & 4.W/970408 Ltr ML17354A4351997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Turkey Point,Units 3 & 4.W/970311 Ltr ML17354A4131997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Turkey Point,Units 3 & 4.W/970213 Ltr ML17354A3851996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Turkey Points Units 3 & 4.W/970110 Ltr ML17354A3631996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Turkey Point Units 3 & 4.W/961211 Ltr ML17354A3461996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Turkey Point,Units 1 & 2.W/961113 Ltr ML17354A2981996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Turkey Point Units 3 & 4.W/961014 Ltr ML17353A8831996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Turkey Point Units 3 & 4.W/960912 Ltr ML17353A8571996-07-31031 July 1996 Monthly Operating Repts for July 1996 for Turkey Point Plant Units 3 & 4.W/960813 Ltr ML17353A7731996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Turkey Point Units 3 & 4.W/960710 Ltr ML17353A7301996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Turkey Point Units 3 & 4.W/960612 Ltr ML17353A6971996-04-30030 April 1996 Monthly Operating Repts for Apr 1996 for Turkey Point Units 3 & 4.W/960513 Ltr ML17353A6391996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Turkey Point Units 1 & 2.W/960415 Ltr ML17353A5971996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Turkey Point Units 3 & 4.W/960313 Ltr ML17353A5601996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Turkey Points 3 & 4.W/960213 Ltr ML17353A5361995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Turkey Point Units 3 & 4.W/960112 Ltr ML17353A4831995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Turkey Point Units 3 & 4.W/undated Ltr ML17353A4441995-10-31031 October 1995 Monthly Operating Repts for Oct 1995 for Turkey Point Units 3 & 4.W/951115 Ltr ML17353A4111995-09-30030 September 1995 Monthly Operating Repts for Sept 1995 for Turkey Point Units 3 & 4.W/951012 Ltr ML17353A3541995-08-31031 August 1995 Monthly Operating Repts for Aug 1995 for Turkey Point Units 3 & 4.W/950912 Ltr 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217L9371999-10-20020 October 1999 Safety Evaluation Supporting Licensee Proposed Alternative from Certain Requirements of ASME Code,Section XI for First 10-Yr Interval Request for Relief for Containment Inservice Insp Program ML17355A4471999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Turkey Point,Units 3 & 4.With 991008 Ltr ML17355A4121999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Turkey Point,Units 3 & 4.With 990909 Ltr ML17355A3981999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Turkey Point,Units 3 & 4.With 990809 Ltr ML17355A3891999-07-20020 July 1999 LER 99-001-00:on 990623,manual Rt from 100% Power Following Multiple Control Rod Drops Was Noted.Caused by Manual Action Taken by Reactor Control Operator.Inspected & Repaired Stationary Gripper Regulating Cards.With 990720 Ltr ML17355A3841999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Turkey Point,Units 3 & 4.With 990713 Ltr ML17355A3681999-06-30030 June 1999 Revised Update to Topical QA Rept, Dtd June 1999 ML17355A3611999-06-30030 June 1999 Refueling Outage ISI Rept. ML17355A3511999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Turkey Point,Units 3 & 4.With 990609 Ltr ML17355A3331999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Turkey Point,Units 3 & 4.With 990511 Ltr ML20217B9871999-04-0808 April 1999 Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 971014-990408 ML17355A2881999-04-0505 April 1999 COLR for Turkey Point Unit 4 Cycle 18. ML17355A2911999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Turkey Point,Units 3 & 4.With 990414 Ltr ML17355A2551999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Turkey Point Nuclear Power Plant,Units 3 & 4.With 990315 Ltr ML17355A2261999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Turkey Point,Units 3 & 4.With 990211 Ltr ML17355A2201999-01-20020 January 1999 Refueling Outage ISI Rept. ML17355A1911998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Turkey Point,Units 3 & 4.With 990112 Ltr ML18008A0461998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Turkey Point,Units 3 & 4.With 981209 Ltr ML17354B1921998-11-18018 November 1998 LER 98-007-00:on 981020,containment Purge Supply,Valve Opened Wider than TS Limit.Caused by Improper Setting of Mechanical Stops.Incorporated Improved Standard Method of Measuring Angular Valve Position Into Sp.With 981118 Ltr ML17354B1891998-11-0909 November 1998 Simulatory Certification Update 2. ML17354B1901998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Turkey Point,Units 3 & 4.With 981112 Ltr ML17354B1591998-10-23023 October 1998 COLR for Turkey Point Unit 3 Cycle 17. ML17354B1361998-10-16016 October 1998 LER 98-004-00:on 980921,automatic Reactor Trip Occurred. Caused by Inadequate re-correlation of Intermediate Range Neutron Flux Instrumentation Reactor Trip Bistable. Enhanced Applicable Plant Procedures.With 981016 Ltr ML17354B1311998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Turkey Point Unit 3 & 4.With 981012 Ltr ML17354B0971998-09-0909 September 1998 Part 21 Rept Re Possible Machining Defect in Certain One Inch Stainless Steel Swagelok Front Ferrules,Part Number SS-1613-1.Caused by Tubing Slipping Out of Fitting at Three Times Working Pressure of Tubing.Notified Affected Utils ML17354B0981998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Turkey Points,Units 3 & 4.With 980915 Ltr ML17354B0771998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Turkey Point,Units 3 & 4.W/980810 Ltr ML17354B0341998-07-15015 July 1998 LER 98-003-00:on 980619,discovered That Auxiliary Feedwater Sys Was Inoperable Due to Inadequate Inservice Testing of Valves.Caused by Misunderstanding of Testing Criteria.Util Revised Procedures & Verified Operability of Valves ML17354B0241998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Turkey Point,Units 3 & 4.W/980709 Ltr ML17354B0171998-06-29029 June 1998 Rev 1 to PTN-FPER-97-013, Evaluation of Turbine Lube Oil Fire. ML17354A9841998-06-18018 June 1998 LER 97-007-01:on 970730,automatic Reactor Trip Occurred Due to Closure of B Msiv.Caused by Failed BFD22S Relay.Six Relays on 3A,3B & 3C MSIVs Were Replaced & Implemented Plant Change to Disable Electronic Trip Function on 3 AFW Pumps ML17354A9741998-06-0909 June 1998 LER 98-002-00:on 980513,discovered Potential LOCA-initiated Electrical Fault Which Places ECCS Outside Design Basis. Caused by Inadequate Review of Effect on non-safety Circuit failures.Re-powered PC-*-600A Relays ML20248F7441998-05-31031 May 1998 Reactor Vessel Working Group,Response to RAI Regarding Reactor Pressure Vessel Integrity ML17354A9711998-05-31031 May 1998 Monthly Operating Repts for Turkey Point,Units 3 & 4. W/980611 Ltr ML17354A9231998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Turkey Point,Units 3 & 4.W/980511 Ltr ML17354A8821998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Turkey Point,Units 3 & 4.W/980409 Ltr ML17354A8511998-03-24024 March 1998 LER 97-009-01:on 971114,discovered That CR Console Switch for 3B Sgfp Was Not in Start Position.Caused by Inadequate Procedural Guidance.Revised Procedures 3/4-OP-074,informed Personnel of Event & Performed Walkdown of CR ML17354B0001998-03-18018 March 1998 Florida Power & Light Topical Quality Asurance Rept, Dtd June 1998 ML17354A8441998-03-18018 March 1998 LER 98-001-00:on 980216,manual Reactor Trip Occurred Due to Loss of Turbine Control Oil Pressure W/Steam Leak in Auxiliary Feedwater Steam Supply Piping.Auxiliary Governor Maint Instructions Will Be revised.W/980318 Ltr ML17354A8311998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Turkey Point,Units 3 & 4.W/980311 Ltr ML17354A7871998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Turkey Point,Units 3 & 4.W/980209 Ltr ML17354A7581997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Turkey Point,Unit 3 & 4.W/980112 Ltr ML17354A7361997-12-12012 December 1997 LER 97-009-01:on 971114,identified That CR Console Switch for 3B SG Feedwater Pump Was Not in Start Position.Caused by Inadequate Procedural Guidance.Procedures 3/4-OP-074,SGFP Were revised.W/971212 Ltr ML17354A7381997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Turkey Point,Units 3 & 4.W/971215 Ltr ML17354A7211997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Turkey Point,Units 3 & 4.W/971114 Ltr ML17354A7491997-10-13013 October 1997 SG Insp Rept. ML17354A8851997-10-13013 October 1997 FPL Units 3 & 4 Changes,Tests & Experiments Made as Allowed by 10CFR50.59 for Period Covering 960408-971013. ML17354A6801997-10-0808 October 1997 LER 97-008-00:on 970909,containment Sump Debris Screens Outside Design Basis Due to Stress Damage Was Discovered. Caused by Inadequate Procedural Guidance & Personnel Error. Discrepancies Found on Screens corrected.W/971008 Ltr ML17354A6791997-10-0606 October 1997 COLR Unit 4 Cycle 17, for Turkey Point ML17354A6811997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Turkey Point,Units 3 & 4.W/971009 Ltr 1999-09-30
[Table view] |
Text
ACCELERATED DISTRIBUTION DEMONS~TION SYSTEM 1~REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)DOCKET FACIL:50-250 Turkey Point Plant, Unit 3, Florida Power and Light C 05000250 50-251 Turkey Point Plant, Unit 4, Florida Power and Light C 05000251 AUTH.NAME AUTHOR AFFILIATION TIERNEY,R.A.
Florida Power&Light Co.PLUNKETT,T.F.
Florida Power&Light Co.R RECIP.NAME RECIPIENT AFFILIATION
SUBJECT:
Monthl repts for Nov 1991 for Turkey Point Units 3&4 911213 tr.DISTRIBUTION CODE: IE24D COPIES RECEIVED ILTR i ENCL Q SIZE: TITLE: Monthly Operating Report (per Tech Specs)NOTES D RECIPIENT ID CODE/NAME PD2-2'A AULUCK,R INTERNAL: AEOD/DOA PEB10 R FILE 01 EXTERNAL: EG&G BRYCE,J.H NSIC COPIES LTTR ENCL 3 3 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME PD2-2 PD AEOD/DSP/TPAB NRR/DOEA/OEAB RGN2 NRC PDR COPIES LTTR ENCL 1 1 D D D NOTE TO ALL"RIDS" RECIPIENIS:
D D PLEASE HELP US TO REDUCE WASFE!CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT.20079)TO ELIMINATE YOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!TOTAL NUMBER OF COPIES REQUIRED: LTTR 14 ENCL 14 ii'I P.O.Box 029100, Miami, FI33102-9100 DEC 1$'IS[L-91-333 10 CFR 50.36 U.S.Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.20555 Gentlemen:
RE: Turkey Point Units 3 and 4 Docket Nos.50-250 and 50-251 Monthl 0 eratin Re ort In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of NUREG 0020, attached are the November 1991 Operating Status and Summary of Operating Experience.
Reports for'Turkey Point Units 3 and 4.Very truly yours, T.F.Plunkett Vice President Turkey Point Nuclear TFP/DRP/RAT attachments cc: Stewart D.Ebneter, Reg'i:onal Administrator, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Plant 9112240319 911130 PDR ADOCK 05000250:R PDR~wu-~an FPL Group company 7p t'
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.50-250 UNIT Turke Point 3 DATE December 11 1991 COMPLETED BY R.A.Tierne TELEPHONE 305'46-6970 MONTH November 1991 AVERAGE DAILY POWER LEVEL (MWe-Net)11/01/91 11/02/91 11/03/91 11/04/91 11/05/91 11/06/91 11/07/91 11/08/91 11/09/91 11/10/91 11/11/91 11/12/91 11/13/91 11/14/91 11/15/91 11/16/91 11/17/91 11/18/91 11/19/91 11/20/91 11/21/91 11/22/91 11/23/91 11/24/91 11/25/91 11/26/91 11/27/91 11/28/91 11/29/91 11/30/91 682 678 674 673 682 688 684 680 687 703 704 703 487 401 692 568 463 646 614 646 648 619 342 609 693 702 703 686 695 693 444k l y'I P'll OPERATING STATUS OPERATING DATA RFPORT DOCKET NO 50-250 DATE 12/1 1/91 COMP!.ETED BY R.A.TIERNEY TELEPHONE 305/246/6970 1.UNIT NAME: TURKEY POINT UNIT 3 2.ttEPOR!ING PERIOD: NOVEMBER 199 1 3.'CENSED THERMAL POWER (MliilT)E 2200 4.NAMEPLATE RATING (GROEL MWE)I 760 E.OEEIGN ELECTRICAL RATING (NET MWE): ,'393 6, MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 699 7.MAXIMUM DEPENDABLE CAPACITY (NEt MWE): 666 8.:f Ct(ANGES OCCUR IN CAPACITY RAIIN(5 (ITEMS tEUMBER 3 THROUGH 7)StNCE LAST REPORT, GlVE REASONSE 9 POWFR LEVEL TO WHICH RESTRICTED'P ANY (~ET MWE)!0.Rf.ASUNS FOR RESTRICTIONS, IF ANY: hIONTHLY YTO-CUMULATIVE 11~I!OURS IN REPORT PERIOD: 3 2, NUMBLtt OF t!OURS REACTOR WAS CRITICAL:3.Rf A<Tt)R RESFRVE SHUTDOWN HOURS,'4."Ot)R'ENERATOR ON-LINE 15."I'OBSERVE SHUTDOWN HOURS 1 6'E~>'PS THERMAL ENERGY GFNERATED (MWtt)7.LRE)5:3 t(LEI TR ICAI.EN RGY GENERATED (MWH)3 8-'El>f t ECTRI CAL Et!ERGY GENERATED (MWH)!9 v 1 SERVICE FACTOR 2G UN)t AVAILABILITY FACTOR 2'.APACE)'Y FACTOR" USING MDC NE1)2.E.Af'AC'.TY 1-AC10R (USING DER NET)23 Et I 1 3 OltCED OUTAGRE RATE 74.SEE"'1)OWNS SCHEDtt'D OVER NEX-6 MONTHS 720 720.0 0.0 720.0 g~0.0 t=a3685 482405 459450 160 0 100.0 95.8 92.!0.0 8016 1508.1 0.0 1411.8 0.0 2699222 862070 798932 17.6 17.6 15.0 14.4 1.8 166449.6 10598 1.3 844.4 104467 5 121.8 216930864 69478061 65677450 62,8 62.8 60.4 56.9 12.3 25.IF St'13 I DOWN A1 END OF REV')8 I 1'I:R lOU.Eb 1 I MAT ED DATE OF STARTUP t
UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH November, 1991 DOCKET NO.50 250 UNIT NAME Turkey Point II 3 pATE December ll, 1993.COMPLETED BY-A Tierney TELEPHONE (305)246-6970 No.Date Type'uration (Hours)Reason~Method of Shutting Down Reactor" Ucensee Event Report¹System Code4 Component odes Cause&Corrective Actionto Prevent Recurrence 03 9111133 F 27:25 N/A RB CONROD Unit 3 reduced power due to control rods partially inserting into the core.04 9111166 12r89 N/A CC VALVEX Unit 3 reduced power due to a reheat intercept valve failing to re-open within 5 mine.05 911122 36:40 N/A HC PUMPXX Unit 3 reduced power to.repair the 3B Heater Drain Pump.F Forced S Scheduled Reason A-Equipment Failure(Explain)
B-Maintenance or Test C-Refueling 0-Regulatory Restriction E-Operator Training&Ucense Examination F-Administrative G-Operational Error (Explain)H-Other (Explain)3 Method 1-Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Load Reduction 9-Other (Exphin)Exhibit G-instructions for Preparation of Data Entry Scheets Ucensee Event Report(LER)
File (NUAEG4161) 5 Exhibit1-Same Source II
SUMMARY
OF OPERATING EXPERIENCE'OCKET NO.50-250 UNIT Turke Point 3 DATE December 12 1991 COMPLETED BY R.A.Tierne TELEPHONE 305 246-6970 REPORT MONTH November 1991 While performing equipment repairs on the (manual/auto) station PCV-3-455C the Pressurizer Operating Reli.'ef Valve (PORV)was opened.Unit 3 reduced power on November 13', 1991 due to four (4)control rods in Rod Bank C partially inserting into the core.This occurred during maintenance of a"Signal" card in the Rod Control Cabinet.Unit 3 returned to full power on November 14, 1991.Unit 3 reduced power on November 16, 1991 when the Southeast Reheat Intercept Valve failed to re-open within 5,minutes.
The Reheat Intercept Valve was repaired and Unit 3 was returned to full power on November 17, 1991..Unit 3 again reduced power on November 22, 1991 to repair the 3B Heater Drain Pump.Unit 3 was returned to full power on November 24, 1991.
II 0 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.50-251 UNIT Turke Point 4 DATE December 11 1991 COMPLETED BY R.A.Tierne TELEPHONE 305 246-6970 MONTH November 1991 AVERAGE DAILY POWER (MÃe-Net)LEVEL 11/01/91 11/02/91 11/03/91 11/04/91 11/05/91 11/06/91 11/07/91 11/08/91 11/09/91 11/10/91 11/11/91'11/12/91 11/13/91 11/14/91 11/15/91 11/16/91 11/17/91 11/18/91 11/19/91 11/20/91 11/21/91 11/22/91 11/23/91 11/24/91 11/25/91 11/26/91 11/27/91 11/28/91 11/29/91 11/30/91 281 287 485 668 675 654 681 679 685 692 692 690 690 688 684 681 678 676 679 678 677 677 674 673 544 217 295 510 681 681 "1 Q(t 4 i)t 0 0>ERAT ING STATUS OPERATING DATA REPORT DOCKE1'O 50-251 DATE 12/11/91 COMPLETED BY R.A.TIFRNEY TELEPHONE 305/246/6970 UNIT NAME: TURKEY POINT UNIT 4 2.REPORtING PERIOD: NOVEMBER l99l l 1CENSEO THERMAL POWER (MW>)6 2200 4 NAMEPLATE RATING (GROSS MWE): 760 6'I'SIGN ELECTRICAI.
RATIIIG (NET MITE)I 693 6.MAXIMUM OEPENOABLE CAPACITY (GROSS MNE): 699 7.MAXIMUM DEPENDABLE CAPACITY (NET MWE): 666 B.1F CEIANGES OCCUR IN CAPACITY RA1 INIAS (I IEMS NUMBER 3 THROUGH 7)SINCE AST REPORTS GIVE REASONS: 9.1'OWER LEVEL TO WHICH RESTRICTED, IF ANY (NE>MWE)10 REASONS FOR RESTRICTIONS, IF ANY: MONTHLY-YTD-CUMULATIVE 11.T(OURS IN RElrURT PERIOD: 1~PlUMBER OF HOURS REACTOR WAS CRITICAL;3.Pra(tOR RESERVE SHUTDOWN HOURS 14.TOU()S GENERATOR ON-LINE 15.l>NI1 RCSERVE SHUTDOWN HOURS (r((Umb ELLCTR I CAL ENERGY GENERATED (MWH)18.Nl.'-f 1 Ei.,RICAL FNf 4GY GENERATED (MWH)19.trW1,'ERVICE FACTOR 20.UN I.'vP ILABILI't'Y FACTOR:-'1.CAP</I"~FACTOR (U ING MDC FIET)~22.LaPaLl 1 Y iALfOR'.AJSING DER NET)23 Nl1 Fi)(lCED OU-n.0 RATE 24=SSl(ETDOWAIS SCHFOl.0/ER NEX (MONTHS 720 7'20.0 0.0 720.0 0.0 1445968 460775 438067 100.0 100.0 91.4 87.8 0.0 8016 864.6 0.0 782.7 0.0 1501489 475130 434851 9.8 9.8 8.1 7.8 0.0 160181.0 102050.9 166.6 98349.8 32.}207131549 66088010 62488479 61.4 61.4 59.7 56.3 11.8.25~<<F SHUf-DOWN AT END OF REPOR'1 PFRIOU.ESIIMAIED DATE OF STARTUP:
UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH November, 1991 DOCKET NO.ff UNjT NAME Turke Foint P4" DATE December 11 1991 COMPLETED BY R.A.Tierney TELEPHONE 305 246-6970 Date Type'uration (Hours)Reason2 Method of Shutting Down Reactor Ucensee Event Report¹System Code4 Component Codes Cause S Corrective Actionto Prevent Recurrence 911031 54 44 B IC INST RU Unit 4 reduced power for current adjust-ments on the Nuclear Instrumentation System (NIS).911125 68:30 N/A SG COND Unit 4 reduced power to perform repairs on a condenser tube leak.F Forced S Scheduled 2 Reason A-Equipment Failure(Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training 8 License Examination F-Administrative G-Operational Error(Exphin)
H-Other(Exphin)
Method 1-Manual 2-Manual Scram 3-Automatic Scram 4-Continued 5-Load Reduction 9-Other(Exphin)
Exhibit G-Instructions for Preparation of Data Entry Scheets Ucensee Event Report (LER)File (NUREG4161)
Exhibit1-Same Source
'~l
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.50-251 UNIT Turke Point 4 DATE December'll 1991 COMPLETED BY R.A.Tierne TELEPHONE 305 246-6970 REPORT MONTH November 1991 Unit 4 reduced power on October 31, 1991 to perform current adjustments on the Nuclear Instrumentation System (NIS).Unit 4 was returned to full power on November 3, 1991.Unit 4 reduced power on November 25, 1991 to perform repairs on a Condenser Tube leak.The unit was returned to full power.on November 28, 1991.
0 0 1 1 8,~