Forwards Summary of Action Plan to Resolve Fuel Bldg Overstress Conditions
ML20248E239
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 09/29/1989
From: Cockfield D
PORTLAND GENERAL ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8910050115
Download: ML20248E239 (2)


Text

.

go. '"*>

- asums PbrticvriGerieralElectricCoiiipray p -E David W. Cockfield Vice President, Nuclear September 29, 1989 Trojan Nuclear Plant Docket 50-344 License NPF-1

.U.S. Nuclear Re6ulatory Commission ATTN: Document Control. Desk Washington DC 20555

Dear Sirs:

Design Verification Prograr? - Fuel Building Action Plan By letter dated August 31, 1989, " Trojan Nuclear Plant Long-Term Pipe Support Design Verification Program",-Portland Ceneral Electric Company (PGE) reported to the Nuclear Regulatory Commission (NRC) that under the Design Verification Program the evaluation of the Fuel Building had confirmed and quantified code overstresses existing under seismic and tornado loading conditions. PG2 informed the NRC that we were developing a formal action plan to resolve the overstress conditions and that we would submit details of.the plan by September 29, 1989. The attachment provides a summary of the action plan.

A Justification for Continued Operation (JCO) is being issued to support Plant operation until modifications are completed to restore structural steel members and connections to allowable streps levels and performance limits specified in the Final Safety Analysis Report. The modifications will be completed by December 1, 1990.

Sincerely. -

Attachment c: Mr. John B. Martin Regional Administrator. Region V U.S. Nuclear Regulatory Commission Mr. David Stewart-Smith State of Oregon Department of Energy Mr. R. C. Barr NRC Resident Inspector Trojan Nuclear Plant 8910050115 890929 t FDR ADOCK 05000344 P PDC ld()d 121 S W Saknon Street. Portland. Oregon 97204 j ,

Lm___l..__.1.___. _ _ . _ _ .

l

~ +1.

~.~

..a_Nif;,' .Trojcn Cuclear Planti Documsnt Control Dask-14 e W

. Docket' 50-344. September 29,J1989:

f 4 License NPF Attachment-K Page 1 of l'

SUMMARY

OF ACTION PLAN TO-RESOLVE FUEL' BUILDING OVERSTRESS CONDITIONS The following is a. listing of the actions being undertaken by Portland General. Electric Company (PGE) to resolve the overstress conditions which L have been confirmed and quantified for the. Fuel' Building. The act. ions are subject to chango as resolution of the problemiprogresses; however,

( the modifications to restore the Fuel Building structural framing L

allowable stress levels will be completed by December 1,l1990.

1<

j. Task Description Due Date -Status Itamize all conditionsiof overstress in 09/21/89 . Complete the Fuel Building' structural steel fram-ing under Safe Shutdown Earthquake (SSE)

'and tornado loadings.

Issue's Justification for Continued Oper- 10/06/89 Open

- ation documenting:that the Fuel Building structural steel framing will retain .

functional requirements-(structural inte-grity) during,the' SSE and 200 mph tornado loadings.

' Establish' Fuel' Building structural steel 10/15/89 Open modification' design criteria and document reconciliation with the Trojan Final Safe-ty Analysis. Report (FSAR).

Issue detailed construction packages (DCPs) 07/15/90 Open for modification of the Fuel Building

. structural steel framing.

Issue pre-1990 refueling outage and 07/30/90 Open post-1990 refueling outage Fuel Building structural steel framing modification

_ work plans.

Perform pre-1990 refueling outage 03/21/90 Open Fuel Building structural steel framing modifications.

Perform post-1990 refueling outage 12/01/90 Open Fuel Building structural steel framing modifications.

Document Fuel Building structural steel 06/30/91 Open framing modifications in the Trojan FSAR.

- LCD/bsh/3624W.0989

'