Requests Submittal of Current Emergency Operating Procedures Generation Package within 60 Days of Ltr Date,In Response to Util 851023 Response to NRC Concerns
ML20154P679
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 05/26/1988
From: Mcneil S
Office of Nuclear Reactor Regulation
To: Tiernan J
BALTIMORE GAS & ELECTRIC CO.
References
GL-82-33, TAC-44289, TAC-44290, NUDOCS 8806060035
Download: ML20154P679 (2)


Text

~ ~

l(. .

3 May 26, 1988-b Docket Nos. 50-317 DISTRIBUTION and 50-318 4eeteenme- s LTripp NRCPDR OGC-WF Local PDR EJordan' i PDI-1 Rdg. JPartlow '

I Mr. J. A. Tiernan SVarga.- ACRS(IO)

Vice President-Nuclear Energy -BBoger Baltimore Gas and Electric Company CVogan P.O. Box 1475 SMcNeil  ;

Baltimore, Maryland 21203 JPersensky ,

Dear Mr. Tiernan:

SUBJECT:

' REQUEST FOR ADDITIONAL INFORMATION - TMI-ACTION ITEM I.C.1.3.a. EMERGENCY OPERATING PROCE0CRES GENERATION PACKAGE (TACS 44289 AND 44290)

Your submittal of March 14, 1984, provided the Calvert Cliffs Units l'and 2 Emergency Operating Procedures Generation Packaga (PGP) for NRC staff review.

The PGP, in accordance with Generic Letter 82-33, consi',ted of the 1) Emergency Operating Procedures (EOP) Writers Guide, 2) E0P Verification / Validation Plan, and 3) E0P Training Plan. Subsequently, on October 23, 1985, you provided-

  • additional information and performed PGP revisions in response to NRC concerns  !

raised after an initial NRC staff review of the PGP. {

To assist the NRC staff in completing our review of the Calvert Cliffs 1 and 2 I PGP, it is requested that you provide a copy of the current PGP (the ECP Writers Guide, the E0P Verification / Validation Plan, and the E0P Training Plan) within 60 days of the date of issuance of this letter.

This request for information affects fewer than 10 respondents; therefore, OMB clearance is not required under Public Law 95-511.

Sincerely.

OrQb! Wsd W Scott Alexander McNeil, Project Manager Project Directorate I-1 Division of Reactor Projects, I/II cc: See next page pu PDI-1 9'd PDI-1 8(M) PDI-1 CVogan SMcNeil: dig RCapra 5/p/83 5/.4/88 5//6/88 8806060035 080526 PDR ADOCK 05000317 F PDR

p 9

Mr. J. A. Tiernan Baltimore Gas & Electric Company Calvert Cliffs Nuclear Power Plant cc:

Mr. John M. Gott, Presideht Regional Administrator, Region I l Calvert County Roard of U.S. Nuclear Regulatory Comission >

Comissioners 475 Allendale Road Prince Frederick, Maryland 20768 King of Prussia, Pennsylvania 19406 D. A. Brune. Esq.

General Counsel Baltimore Gas and Electric Company P. O. Box 1475 Baltimore, Maryland 21203 Mr. Jay E. Silberg, Esq.

Shaw, Pittman, Potts and Trowbridge 1800 M Street, NW Washington, DC 20036 Mr. M. E. Bowman, General Supervisor Technical Services Engineering Calvert Cliffs Nuclear Power Plant MD Rts 2 & 4 P. O. Box 1535 Lusby, Maryland 20657-0073 Resident Inspector c/o U.S. Nuclear Regulatory Comission  ;

P. O. Box 437  !

Lusby, Maryland 20657-0073 I Bechtel Power Corporation ATTN: Mr. D. E. Stewtet Calvert Cliffs Project Engineer 15740 Shady Grove Road Gaithersburg, Maryland 20760 Combustion Engineering, Inc. l ATTN: Mr. W. R. Horlacher, III  !

Project Manager i P. O. Box 500 l 1000 Prospect Hill Road Windsor, Connecticut 06095-0500  :

Department of Natural Resources l Energy Administration, Power Plant l Siting Program i ATTN: Mr. T. Magette l Tawes State Office Building '

Annapolis, Maryland 21204