ML20059K704
| ML20059K704 | |
| Person / Time | |
|---|---|
| Site: | Calvert Cliffs |
| Issue date: | 09/07/1990 |
| From: | Hodges M NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Creel G BALTIMORE GAS & ELECTRIC CO. |
| References | |
| NUDOCS 9009240189 | |
| Download: ML20059K704 (3) | |
See also: IR 05000317/1990001
Text
!
.
.
.
.
,
[
a
4
,
s
.
,
.
,-
-
,
SEP 0 71990
j
t
Docket Hos. 50-317
.
50-318
,
Baltimore Gas and Electric Company
ATTN: Mr. George C. Creel
Vice President
Nuclear Energy
>
.
Calvert Cliffs Nuclear Power Plant
!
MD Rts 2 & 4, P.O. Box 1535
Lusby, Maryland 20657
Gentle:nen:
i
Subject:
Inspection Nos. 50-317/90-01 and 50-318/90-01
This refers to your letter dated May 15, 1990, in response to our letter, dated
-
April.9, 1990, and to the telephone conversations on August 15 and 22, 1990.
We have reviewed your responses to the violations and note the corrective
,
L
actions taken to restore compliance. Your actions will be reviewed in future.
'
NRC inspections.
-
In the subject response, you did not accept Violation A, Part 1, as stated in
,
that your procedures permit the use of corrective action systems other than
]
the nonconformance reporting system for controlling deficient welds'provided
- that tracking and followup through closure are commensurate.
Further, in your
response, you' stated that the system actually used to track and followup the
deficient welds required improvement to provide documentation of repair defi-
ciencies'after the final NDE process, assessment of preventive actions, and
.
trending. As we discussed in the reference telephone conversations, we agree
that the thrust of the Notice of Violation was not accurate but that the actual
'
violatior e the failure to comply with 10 CFR 50, Appendix B, Criterion XVI
i
as descr,M a above.
Therefore, the violation, as previously transmitted, is
i
1
l
hereby c u nged to invoke 10CFR 50, Appendix B, Criterion XVI.
l
Your response also denied Violation B of-that same Notice regarding the length
,
of experience required to qualify visual inspectors.
Your procedure implies
that an inspector can achieve VT-1,2,3 and 4 certification with only 3 months
of total experience collectively.
Subsequent discussions with your staff on
,
this' matter concluded that the codes and associated standards are not clear
'
regarding the intent of the requirements and that a code interpretation is
appropriate. We, therefore, will hold our decision in abeyance on the disposi-
,
tion of this violation pending your receipt of the code interpretation and
-review by the NRC.
Your response to' Violation C of the same notice regarding the numbering and
location system for weldt in the erosion corrosion program was found
acceptable.
<
OFFICIAL RECORD COPY
WINTERS 6/12/90 - 0001.0.0
90092401e9 900907
09/04/90
'
ADOCK 05000317
d:O I (
,
Q
__
.
.
SEP 071990
E
-
,
Baltimore Gas and Electric Co.
2
'
Based on this and other related inspections, we note that the nondestructive
examiw. tion inspection program at Calvert Cliffs is composed of two distinct
elements, the onsite and the corporate inspection groups.
It appears that the
source of our concerns exist predominately with the corporate inspection group
that performs inspections for the fossil as well as the nuclear facilities.
Recognizing that the quality requirements for the fossil facilities are not as
stringent,.we believe that your attention is warranted to ensure that the
practices and procedures for nuclear work by this group are equivalent to
those employed by the onsite NDE group.
Your cooperation with us is appreciated.
Sincerely,
Originct Stnr) Cy:
Marvin W. Ilodscs
Marvin W. Hodges, Director
Division of Reactor Safety
cc w/er.ci:
R. McLeat Administrator, Nuclear Evaluations
J. Walter, Engineering Division, Public Service Commission of Marylana
G. Adams, Licensing (CCNPP)
K. Burger, Esquire, Maryland People's Counsel
P. Birnie, Maryland Safe Energy Coalition
Public Document Room (PDR)
local Public Document Room (LPDR)
Nuclear Safety Information Center (NSIC)
NRC Resident Inspector
State of Maryland (2)
beu w/ enc 1:
Region I Docket Room (with concurrences)
R. Bellamy, DRSS
J. Linville. DRP
C. Cowgill, DRP
C, Lyon, DRP
D. Vito, DRP
B. Summers, DRP
M. Callahan, OCA
D. Mcdonald, NRR
R. Capra, NRR
J. Caldwell, EDO
OFFICIAL RECORD COPY
WINTERS 6/12/90 - 0002.0.0
09/04/90
T p aq w
W E m T
<
-
M-
ci)
-. _ u
1
c
,
4
,
p
,
,
,,
cd. w .
.
m
.
.4
,
,
. ,,
,
,
.,
,
4c.ys, wm
w m -
m
a ..
-
7
.a . t
._t._
. ,
,
'
s
HH19 3.A, ' -yCl
+,xhr '
- -
,
,
s e. w.. j[
' *;
i.sF,P:0 7 20..
'.y
NW " ; l.
~
m_
%
'
-
'
-
'
'
'
'
.
,
,
_
,
,
,
,
h, m.
_
.
, ,
r: . , + ,
..-
c.
. . - .
,
,
c
s.,_
~
<
yw4.yu. J,n,.3 . geh' imore Gas' and Electric' Co.1
3?
,_4
.
s._,
,
o
s
. i,
u
w
f'
- -
'
,
3)sfirA4,q ttt.., _
,
c]
m
' >
i
W; Mpal%r-
<
i
&
.L
,
.,
s : . g.m
W-
+
,
. w. > , i. i i - +
t
y& .wl';
i
Q
M
s
em f MU hiO
- I
wp <3. ~ , .4/ _
z.s
y
j
, j. ~
$l,
s+
t
. . . ..
7:fd.f M,
.
'.
,
>
--e t. ..y
$l<' '
=
,
.
-Qs _ ; ;.
.
>
'jf:y
ta
,
\\
\\
g. r. 4,,p .p , 2 = - ~
,
- s
a
w
.
q.
-i
m 9; %m
'
-
i
,,
0,' _ki ,ib I . e.
- Nj
w%,e
o.
-
,
1,
si
<
,
.
,
m. ,_ m.
.
.~ c<
t
n
-
ae
. , ,
_- ( c .
I
.
a
,y
fg
4
'
G,- @s
x . a,yr
.:.
~-
.
jW
r
-
'
g-
r
a'WW
s
o
J
1
-e..,.
4
p
.,
,m<
.:
'
-
m
- 3
' ,
% 1[
'
' ( ..
i
in
i
' ;'.
a wc
o,
,
.~[re ;f
'
.
q
i
~
w
- a
,
,
,.y
m
g,s;m ;
,
,
u
s
'
f
bh,; N'[ y;:
<
_'
n
cu
e. hi , ..3 v. c
-
i
,.
. 6
9
,
a
!
t l5,.
h.(,f'b-f , ' ,[ .
_
i.
,
').
1-
-I'6
'
.
,
--
v
.,
~
, .
.,
Oslo
\\ +t j
r
w
,
-,
s
. >
>
,
- .
t
,
-w
3yi
.
j. )
'
a
s.-.
x
.
.
,
,
n
-..,-;
.
,
,
,
.
,3
a-
g
.
- ,
~
.
i
i
-
-
,
.
p;
r
.
,
a
s
.
<
..
.
n
'
,'
,.h
., # 8,.
-- j '-
i-
-
p ;l' +
.,'4
- .- ,
..
f
...t
.,
ye
,
1
, ~o.
,
u.
a<
4m' ([r
Y. '
' -
,-, '
,s
--f
i
. . J.h '.,p-
<,
7
a1
e;
N
EJA
iPj
&+
' '
,
,<
,
..
+
-
'.p Q ;
~
<
';
e
A -< - . r
g ., 4
-M 'g
.iv<,
y
8
.a ;'
.'
.y-
.. i z
u
i ','i--
,
a
' \\ b
~b'8
e
,8:\\:
-
o1
m,
ay
_l
i
- l
'
h1 $rJf)
.RI;DRS
RI,
RI;DRS -
1
Wir+.ers/rw
Kerp
Durr
-I
0
'
6/i>/90
6/ W 0
ff/90
I
,
.
k
u,
4
'
I
J
l
2
!
E
OFFICIAL RECORD COPY
WINTERS 6/12/90 - 0003.0.0
L
06/12/90
s
h
-,
'I t i
.
(--
yi'_
-
,
%'
'
,,
>
r
.
.
.i
E.2.Z_Y__-Z_I __ 'ON , &
vi u
.
,-*r=rr=-e-4+.w--*weriv=='
-www<we*=s-w' s- v
- 5**
' r **W e m b
'w'****'"*"*""h"****'-*N"******'
- "-*'T #8
'-
"N
' ' - ' ' * "
'
!
,
.a.
'-
BALTIMORE
,
GAS AND
ELECTRIC
CHARLES CENTER * P.O. BOY 1975 * BALTIMORE. MARYLAND 21203 1475
i
'
?
Otomoe C. CattL
'-
'
ViCt P6t $sctet
Nuckt an (hteet
uo.>,.......
'
1
'
May 15,1990
i
4
U. S. Nuclear Regulatory Commission
I
Washington, DC 20555
ATTENTION:
Document Col. trol Desk
i
SUBJECT:
Calvert Cliffs Nuclear Power Plant-
!
Unit Nos.1 & 2; Docket Nos. 50-317E& $0-318
Combined insnection Renort Nos. 50-317/o0-Oli 50-318/90-01
.
1
REFERENCES:
(a) Letter from Mr. M. W. Hodges (NRC) to Mr. G. C. Creel (BG&E),
!
dated April 9,1990, same subject'
,
Gentlemen:
- ,
!
'
Reference (a) forwarded Nuclear Regulatory Commission (NRC) Region I Combined
l
Inspection Report 50-317/90-01; 50-318/90-01. Appendix A to Reference (a)'is a Notice
of
Violation - regarding- deficiencies
related
to
non-destructive
examination
and
inservice
inspection
activities
at
Calvert
Cliffs.
Enclosure
(1)
provides ' our-
'
response to the Notice of Violation.
Should you have any further questions regarding this matter, we will be pleased to
discuss them with you.
Very truly yours,
i
'
I
GCC/MDM/bjd
!
Enclosure
, Oh
.
-
'
.
,
6
.
.
.
.
__
_
_
.
>
I
1
i
l
>
>
'Doccment C6atrol Desk
.
May 15,1990
i
.
Page 2
i
1
I
cc:
D. A. Brune, Esquire
J. E.
Silberg, Esquire
R. A.Capra,NRC
1
D. G. Mcdonald, Jr., NRC
J
1. T. Martin, NRC
i
L. E. Nicholson, NRC
R. McLean, DNR
I
J
l
l
,
i
!
.
p
- .
- -
--
>
-
..
a
ENCL (EUR.E (1)
,.
'
'
REPLY TO A NOTICE OF VIOLATION
INSPECTION REPORT 50-317/90-01: 50-318/90-01
VIOLATION A
Part 1:
,
I.
DESCRIPTION AND CAUSE OF THE EVENT
The first item contained in Violation A, of Nuclear Regulatory Commission (NRC)
Inspection Report 50-317/90-01; 50-318/90-01, indicates that welds determined to
be unacceptable by radiography, were not documented in a Non-Conformance Report
=
(NCR)as required by Calvert Cliffs Quality Assurance Procedure (QAP) 26.
Examples included welds performed on the Auxiliary Feedwater System in the Fall
of 1982.
Baltimore Gas and Electric (BG&E) does not accept this violation. As stated in
the Inspection Report, Calvert Cliffs Quality Assurance Procedure (QAP) 26
Revision 41, Attachment B, lista deficient welding, under the category of
Deficient Workmanship, as a Condition Adverse to Quality. An NCR can be issued
for a Condition Adverse to Quality, however, Section 7.1 of QAP 26 states,
"An NCR is not required if the condition is reported through the
mechanism of another Corrective Action System that provides tracking
and follow-up through closure;
i.e.,
MR, LER, audits, etc."
The inspection Report states we were in non-compliance with QAP 26 because the
Non Destructive Examination (NDE) Program did not document welding defects
through an NCR. Instead, an NDE report was generated, as part of the welding
Maintenance Request (MR)/ Maintenance Order (MO) Package, to document and track
corrective actions. We believe this was consistent with the allowed methods of
documenting Conditions Adverse to Quality, in QAP 26.
In reviewing the process for documenting NDE corrective actions, it was noted
that although the NDE procedures ensured tracking and closcout of deficient welds
before closing out an MR, other aspects such as documentation of repair
deficiencies not corrected after the final NDE process, assessment of preventive
actions, and trending required improvement. Revisions to the NDE procedures to
correct these deficiencies will be completed by July 27, 1990.
QAP 26 is also being revised to clarify the interface between NCRs and other
corrective action proens.
Part 1
1.
DESCRIPTION AND CAUSE OF THE EVENT
The second item contained in Violation A Appendix A, of the Inspection Report
describes two examples of poor radiographic work practices as a result of failing
to follow procedures. Specifically, thirteen weld radiographs were accepted with
density readings outside the allowable range and read points were not marked on
welds that were not part of the Inservice Inspection Program. These practices,
,
affecting the quality of work, resulted in violations of code requirements.
-1
..
. - _ -
- _ - _ - - _ _ - _ _ - - _ _ _ _ _
..
o
ENCLOSURE (1)
..
'
REPLY TD A NOTICE OF VIOLATION
INSPECTION REPORT 50-317/90-01: 50-318/90-01
II.
CORRECITVE STEPS TAKEN AND RESUL'IS ACHIEVED
The review of radiographic film requires the use of numerous Codes and Standards
to establish the acceptance or rejection of a radiograph. To ensure complete and
accurate reviews, new directions regarding film interpretations were issued to
all certified radiographers at Calvert Cliffs, via a controlled memo on April 13,
1990. As of April 13, 1990, a second review of all Calvert Cliffs radiographs
has been required to ensure applicable Codes and Standards are used.
The individual performiw the second party review must be a Baltimore Gas and
Electric (BG&S) . ' M i * vel 11 or !!! radiographer, if no discrepancies in
the initial interv E
m 0 .snd, and no problems with the film quality are
enecentered, th'
v
mh reviewer will initial the data sheet, indicating
his neceptance. 4
.m,
4
be resolved by the NDE Unit Supervisor.
<
III.
CORRECITVE STLH .jQZ y .LL BE TAKEN TO AVOID FURTHER
VIOLATIONS
in addition to the second party review, more detailed and specific directions for
radiography will be incorporated into the radiography procedures within our NDE
program. These changes will be made by August 31, 1990.
IV.
DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED
Full compliance will be achieved by August 31, 1990, after the radiography
procedures are changed.
VIOLATION B
1.
DESCRIPTION AND CAUSE OF THE EVENT
Violation B, Appendix A, of the inspection Report indicates that BG&E's NDE
Control Procedure 5.020 does not conform to the requirements of ANSI N45.2.6.
The ANSI standard is invoked by Subarticle IWA-2300 of ASME Section XI,1983
Edition through Summer 1983 Addenda. Specifically, these sections of the Code
recommended the necessary qualifications for non-destructive examination
personnel that are certified to perform visual inspections (Type VT2, VT3, and
VT4). The standard recommends a Level 11 Inspector acquire 3 years of experience
before being certified whereas BG&E only requires 3 months.
Section 3.5 of ANSI N45.2.6, the standard referenced by the ASME code for
qualificetion of inspection, exarr.ination and testing personnel for nuclear power
plants, is titled * Education and Experience-Recommendations".
1
-2-
,.
.
-
.
.
-_
-
_
.
o
o
ENCLCEURE (1)
-
,,
'
REPLY TO A NOTICE OF VIOLATION
INSPECTION REPORT 50-117/90-0l! 56-31g/90-01
The stardard ecommends a Level II inspector acquire 3 years of experience before
being certified. The standard also recognizes equivalent methods for
demonstrating competency may be substituted for experience. Sectioa 3.5 of the
standard states,
"These education and experience recommendations should be treated to
recognize that other factors may provide reasonable assurance that a
person can competently perform a particular task. Other factors which
may demonstrate capability in a given job are previous performance or
satisfactory completion
of capability testing."
Interpretation of this section has been provided in two ASME Boiler and Pressure
Vessel Code Cases. N-448 and N-449. These Code Cases have been determined by the
NRC to be suitable for use and are listed in NRC Regulatory Guide 1.147. Both
Cases provide alternatives to IWA-2300 % paragraph (c). Sub-paragmph (c) is
'
where the ASME Code states personnel shN J be qualified in accordanct with ANSI
N45.2.6Property "ANSI code" (as page type) with input value "ANSI</br></br>N45.2.6" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process.. The alternatives to Sub-paragraph (c) are the provisions prc.vided in
,
'
Sub-paragraphs (a) and (b) of IWA-2300.
j
Sections (a) and (b) of IWA-2300 reference guidelines set forth in The American
Society for Nondestructive Testing's (ASNT) procedure SNT-TC-1 A.1980 Edition.
!
According to Code Cases N t48, and -449, providing a training program that is
consistent with the guidelines of SNT-TC-I A to qualify examinetion personnel, is
!
,
I
an acceptable alternative to ANSI N45.2.6.
.
CONCLUSION
We believe the NDE Program at BG&E complies with the wording and intent of the ASME
'
code.
Our training program, which includes general and specific written examinations. -
as well as practical examinations, is consistent wi6 the guidelines in SNT-TC-l A. We
therefore believe we are in compliance with Title .1, Paragraph 50.55a of the Code of
Federal Regulations.
i
VIOL ATION C
!
l.
QESCRIPTION AND CAUSE OF THE EVENT
Violation C Appendix A, of the laspection Report states that BG&E practices for
the identification of weld center lines does not conform with the ASME Section
XI,1983 Edition through Summer 1983 Addenda, requirements of IWA-2600 and
Appendix 111, Supplement 2. Specifically, welds were identified during the
inspection that did not have center line reference maikings.
ASME Section XI states, in IWA-2610, that "A reference system shall be
established for all welds subject to surface or volumetric examination. Each
such weld and area shall be located and identified
b'> a system of referena
points. The system shall permit identification of e; .1
weld, location of each
weld center line, and designation of regular intervals along the length or the
weld."
!
-3-
--
- .
. - - .
--
--
- . - .
.
.. .
.
..
>
!
..
..o
ENCIA5URE II)
!
,,
REPLY TO A NCyl' ICE OF YlOLATION
INSPECTION REPORT 50-317MS-41: 50-318/90-01
The ultrasonic examination procedures at Calvert Cliffs und a Jystem which
permits the identification of weld center lines through the use of weld profiles
and indication mapping. The pro.:edures did not require the permanent marking of
centerlines.
II.
CORRECTIVE STEPS TAKEh AND.RESULTE ACHIEVED
Our Inservice Inspection (ISI) Program will be improved by the use of permanent
markins. On April 24, 1990, a memo was issued to all NDE examiners to require
pennanent weld zero and center line identification prior to any ASME XI surface
or volumetric exp.mination of piping welds.
III.
CORRECTIVE STEPS WHICH WILL BE TAKEN TO AVOfD FURTHER
VIOLATIONS
A procedure fo. identifying weld center lines will bis issued which will address
permanently marking tne zero reference and the weld 2 enter line. This procedure
will be in place by July 27, 1990.
IV.
DATE WHEN FULL COMPLIANCE Wrt.t. BE ACHIEVED
.
Full compliance was achieved on April 24,199(
- 'nemo requiring permanent
markings was issued to all examiner *. Additionai .. enw will be provided in
the procedure to be issued by July 27, 1990.
EXTENSION
The original due date for this response was May 9,1990. A one-week extens.on was
granted by Region 1 on May 8,1990. The extension was requested to allow sufficient
time to resolve comments received on the first internal draft.
l
l
4