Forwards Insp Repts 50-317/85-09 & 50-318/85-09 on 850401-0506 & Notice of Violation.Potential Negative Trend in Performance of Control Room Operators May Result from Weaknesses in Control Room Operator Training
ML20127E391
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 06/18/1985
From: Wenzinger E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML20127E393 List:
References
NUDOCS 8506240536
Download: ML20127E391 (2)


See also: IR 05000317/1985009

Text

i h

UUN 181985

DOCKET / LICENSE: 50-317/DPR-53

50-318/DPR-69

Baltimore Gas and Electric Company

ATTN: Mr. A. E. Lundvall, Jr.

Vice President, Supply

P. O. Box 1475

Baltimore, Maryland 21203

Gentlemen:

Subject: Inspection Report Nos. 50-317/85-09, 50-318/85-09

This transmits the April 1 - May 6, 1985, resident inspection findings by Messrs.

T. Foley and D. Trimble at the Calvert Cliffs Nuclear Power Plant, Lusby, Maryland.

Those findings were based on observation of activities, interviews, independent

measurements, and document reviews, and have been discussed with Mr. Russell of

your staff.

An apparent violation of NRC requirements is cited in Appendix A and categorized

under the revised NRC Enforcement Policy, 10 CFR 2 Appendix C (47 FR 9987, March

8, 1984). This violation and the licensee identified violations discussed herein,

together with the responses by newly qualified Control Room Operators to inspector

questioning identified in paragraph 4.a appear to be indications of a potential

negative trend in the performance of Control Room Operators. This potential trend

may be the result of weaknesses in control room operator training. Attention to

this area may be warranted.

This notice is sent to you pursuant to the provisions of Section 2.201 of NRC's

" Rules of Practice", Part 2, Title 10, Code of Federal Regulations. Although Sec-

tion 2.201 requires you to submit to this office, within 30 days of your receipt

of this notice, a written statement of explanation, we note that this violation

was corrected prior to the completion of our inspection, and therefore, no response

with respect to this matter is required.

Your cooperation with us is appreciated.

Sincerely, Original Signed By:

,

'

$

Edward C. Wenzinger, Chief

Projects Branch No. 3

Division of Reactor Projects

Enclosures:

1. Appendix A, Notice of V olation

2. NRC:RI Report 50-317/85-09, 50-318/85-09

8506240536

PDR 850618ADOCK

PDR 05000317

G

YW1 l

r

-

,.

',

Baltimore Gas and Electric Company 2

cc w/encls:

-R. M. Douglass, Manager, Quality Assurance

L. B. Russell, Plant Superintendent

Thomas Magette, Administrator, Nuclear Evaluations

R. C. L. Olson, Principal Engineer

J. A. Tiernan, Manager, Nuclear Power

R. E. Denton, General Supervisor, Training and Technical Services

Public Document Room (PDR)

Local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of Maryland (2)

bec w/encls:

Region I Docket Room-(with concurrences)

Senior Operations Officer (w/o enclosure)

Director, DRS

Director, DRSS

DRP Section Chief

R. Keller, DRP

!

,

RI:DRP RI: RI:DRP

jf V (cf Qk

Foley/Trimble/ss E er Wenzinger

6/11/85 h/,

/' 0FFICIAL RECORD COPY

.

_ . . _ , . . _. , _ _ . _ . . . , _ . _ , _ _ , _ . _ . , _ . . - , . , . , _ , -