Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement
Results
Other: 05000206/LER-1981-013, Forwards LER 81-013/99X-0.Detailed Event Analysis Submitted, 05000206/LER-1981-013-99, /99X-0:on 810618,power Operated Relief Valve Controller Opened Twice During Normal Pressure Transient Following Reactor Trip.Caused by Setting Time Constant to Off to Satisfy NUREG-0737,Item II.K.3.9, L-81-029, Forwards Proposed Licensing Exam Schedule for 1981-82 for Reactor & Senior Operator Candidates,Per 810807 Request, L-82-002, Informs That Necessary Procedures Per NUREG-0737,Item I.A.1.3 Re Use of Overtime Required by Generic Ltr 82-12 Will Be Implemented by 821001.Tech Spec Will Not Be Submitted for Review Pending Receipt of Model Tech Specs, ML13308A671, ML13308B064, ML13308B821, ML13308B925, ML13310A775, ML13310A777, ML13310A778, ML13310A826, ML13310A828, ML13310A923, ML13310A926, ML13310B078, ML13310B081, ML13310B120, ML13310B280, ML13310B546, ML13310B619, ML13311B030, ML13316B714, ML13317A133, ML13317A134, ML13317A166, ML13317A190, ML13317A263, ML13317A267, ML13317A289, ML13317A367, ML13317A369, ML13317A377, ML13317A391, ML13317A427, ML13317A450, ML13317A454, ML13317A468, ML13317A478, ML13317A479, ML13317A484, ML13317A488, ML13317A490, ML13317A507, ML13317A512, ML13317A519, ML13317A553, ML13317A567, ML13317A581, ML13317A616... further results
|
MONTHYEARML13333A4221979-10-22022 October 1979 Forwards Responses to NRC post-TMI Requirements Re Design & Analysis,Operations,Rcs High Point Vents,Emergency Preparedness & Instrumentation to Monitor Containment Conditions Project stage: Other ML13303A7381979-10-30030 October 1979 Summary of 790927 Meeting W/Utils in San Clemente,Ca Re Emergency Plan Review Project stage: Request ML13322A6191979-11-15015 November 1979 Summary of 791108 Telcon W/Util Re Unacceptable Schedule for Implementing Lessons Learned Task Force Items Project stage: Other ML13333A4571979-12-14014 December 1979 Forwards Revisions to Util 790913 Commitments Re Compliance w/short-term TMI Lessons Learned Task Force Requirements Per NUREG-0578 Project stage: Other IR 05000206/19790161980-01-0404 January 1980 IE Insp Rept 50-206/79-16 on 791101-02 & 26.No Noncompliance Noted.Major Areas Inspected:Scope & Methods of Field Insp for IE Bulletin 79-14,repair of Shorted Electrical Buswork & Licensee Design Change Proposal Project stage: Request ML13311B0301980-01-21021 January 1980 Discusses Response to NRC 800102 Order to Show Cause Re Implementation of NUREG-0578 Category a Requirements.Will Continue Operation Until 800315.Shutdown on 800131 Would Severely Impact Power Reliability in Pacific Northwest Project stage: Other ML13333A4781980-01-23023 January 1980 Advises That Responses to NRC Requesting Info Re Small Break LOCA Guidelines Will Be Submitted by 800228. Bulletin Response Will Be Sent by 800228 Project stage: Other ML13333A4811980-01-24024 January 1980 Forwards Corrected Page 3 of App 10 to Enclosure a of Re Power Reliability Info.Omitted Info Sent to R Weiner of DOE on 800118 Project stage: Other ML13333A4831980-01-29029 January 1980 Confirms 800124 & 25 Telcons Re Facility 800126 Shutdown for Implementation of Lessons Learned Task Force Category a short-term Requirements Re Reopening of Containment Isolation Valves Project stage: Other ML13308B0641980-01-30030 January 1980 Concludes That Inadequate Justification Exists to Extend Util 800131 Deadline to 800315 for Response to 800102 Order to Show Cause Why All Category a Lessons Learned Requirements Should Not Be Implemented Project stage: Other ML19290E8091980-02-0101 February 1980 Denies Request for Shutdown Extension Until 800315 to Complete Category a Requirements W/Available Equipment. Reopening of Containment Isolation Valves Until Further Mods Completed Acceptable Project stage: Other ML13333A4981980-02-0808 February 1980 Submits Addl Info Re Commitment Schedule for short-term Lessons Learned Task Force Requirements.Circuitry to Close Auxiliary Feedwater Motor Operated Discharge Valve Will Be Installed During Apr 1980 Refueling Outage Project stage: Other ML13333A5031980-02-13013 February 1980 Forwards Justification for RCS Subcooling Setpoint,In Response to NRC 791227 Request.Addl Info Will Be Forwarded in Response to IE Bulletin 79-27 by 800228 Project stage: Other ML13316B7141980-03-0707 March 1980 Advises NRC of Delay in Responding to Item 4 of as Part of Response to IE Bulletin 79-27.Submittal Rescheduled from 800228 to 800701 Project stage: Other ML13330A0251980-03-25025 March 1980 Forwards Addl Info for Implementation of TMI short-term Lessons Learned Task Force Requirements.Describes Mods to Backup Nitrogen Pneumatic Supply & Valve Position Indication.Drawing Available in Central Files Only Project stage: Other ML13330A0271980-03-28028 March 1980 Responds to NRC 800117 Request for Review of Draft Evaluation of SEP Topic XV-20, Radiological Consequences of Fuel Damaging Accidents,(Inside & Outside Containment). Review Confirms Facts as Correct Project stage: Request ML13330A0321980-04-11011 April 1980 Confirms 800410 Telcons W/Regulatory Personnel Re Implementation of Several Category a TMI Lessons Learned Task Force Requirements Described in Project stage: Other IR 05000206/19800041980-04-11011 April 1980 IE Insp Rept 50-206/80-04 on 800128-0229.Noncompliance Noted:Failure to Rept Reactor Protection Sys Setpoints Less Conservative than Those Established by Tech Specs & Use of Nonstandard Fitting Project stage: Request ML13331B3711980-05-0707 May 1980 Ro:On 800506,during Refueling Operations,After Lowering of Reactor Internal Instrumentation Package,Incore Instrumentation Package for Thimble Location D-7 Found Bent Outward.Caused by No Provision for Thimble Passage to Core Project stage: Request ML13330A0521980-05-22022 May 1980 Discusses Open Items Re Implementation of Category a Lessons Learned Task Force Requirements Per NRC 800502 Request.Open Items Involve Instrumentation for Inadequate Core Cooling, post-accident Sampling & Reactor Cooling Sys Venting Project stage: Other ML13330A0621980-06-13013 June 1980 Discusses Completed Review of NRC Forwarding Five Addl Items Resulting from post-TMI Reviews.Forwards Commitments to Meet Implementation Requirements for Items 1-5 Project stage: Other ML13319A2131980-07-0909 July 1980 Forwards Post-Accident Sampling Sys,Capabilities & Description, & Drawings,In Response to Open Item Identified in NRC Re Implementation of TMI Lessons Learned Requirements.Drawings Available in Central Files Only Project stage: Other IR 05000206/19800201980-07-0909 July 1980 IE Insp Rept 50-206/80-20 on 800616-19.No Noncompliance Noted.Major Areas Inspected:Major Maint,Major Surveillance, IE Bulletin & Circular Followup & Independent Insp Effort Project stage: Request ML13322A7711980-07-0909 July 1980 Post-Accident Sampling Sys,Capabilities & Description Project stage: Other ML13302A4691980-09-12012 September 1980 Forwards Amend 20 to Fsar.Amend Contains Responses to NUREG- 0660 & NUREG-0694, TMI-Related Requirements for New Ols Project stage: Request ML13322A9461980-09-12012 September 1980 Notifies That Actions Required in NRC Re License Amend Application Concerning Implementation of TMI Lessons Learned Requirements Cannot Be Accomplished by 800912. License Amend Application Will Be Submitted by 810116 Project stage: Other ML13330A1321980-10-0909 October 1980 Notifies That Date for Submittal of Info Re Design Details for Reactor Coolant Vents & Addl Info for Main Steam Line Piping Integrity Evaluation Will Be Submitted 801101 & 1201,respectively Project stage: Other ML13330A1351980-10-15015 October 1980 Provides Plans,Schedules & Commitments to Meet Interim Criteria for Shift Staffing & Administrative Controls,In Response to NRC 800731 Request.Full Compliance W/Criteria Will Be Achieved No Later than 820701 Project stage: Other ML13316A5161980-10-31031 October 1980 Environ Qualification of Electrical Equipment Project stage: Request ML13330A1581980-12-23023 December 1980 Advises That Response to NRC Requesting Confirmation for Implementation Dates of TMI-related Items Will Be Submitted by 810105 Project stage: Other ML13308B8211980-12-30030 December 1980 Submits Addl Info Re Description of Shift Technical Advisor Training Program & Plans for Requalification Training Per 791031 Request Project stage: Other ML13330A1661981-01-0707 January 1981 Notifies That License Amend Application to Incorporate Applicable Tech Specs for Implementing TMI-2 Lessons Learned Category a Items Will Be Submitted by 810401 Project stage: Request ML13308A6711981-01-13013 January 1981 Advises That Licensee Inadvertently Omitted Info from Re Plans for Implementation of Action Item II.K.3.25 in NUREG-0737 Re Effect of Loss of Ac Power on Pump Seals. Evaluation Will Be Submitted by 820101 Project stage: Other ML13330A1911981-01-14014 January 1981 Informs That Radiochemical & Chemical Analysis Mods Promised in Util No Longer Necessary.Due to Other TMI Recommendations,Samples Can Be Analyzed Outside Lab.Cart Mounted Iodine Sampler W/Single Channel Analyzer to Be Used Project stage: Other ML14135A0051981-01-23023 January 1981 High Radiation Sampling Station General Piping Arrangement Plan Project stage: Other ML13330A1931981-02-0202 February 1981 Forwards Application for Amend 96 of License DPR-13 Project stage: Request IR 05000206/19810041981-02-25025 February 1981 IE Insp Rept 50-206/81-04 on 801229-810130.No Noncompliance Noted.Major Areas Inspected:Followup on Systematic Appraisal of Licensee Performance & Allegation by Contractor Employee Project stage: Request ML13330A2411981-03-0606 March 1981 Responds to IE Bulletin 80-04, Analysis of PWR Main Steam Line Break W/Continued Feedwater Addition. Auxiliary Feedwater Sys Automatic Initiation Will Occur on Low Steam Generator Level W/Setpoint at 5% of Narrow Range Instrument Project stage: Other ML13330A2661981-03-17017 March 1981 Forwards Listing Containing Brief Description of Design Changes Completed During 1980 Per 10CFR50.59b & Rept on Challenges to Relief & Safety Valves Per NUREG-0578 Project stage: Other ML13330A2671981-03-18018 March 1981 Advises That post-accident Sampling Sys,Described in Licensee ,Will Not Include Capability to Perform Chloride Analysis,Per NUREG-0737 & NUREG-0578.Chloride Analyses Using Dilute Samples Are Inaccurate Project stage: Other ML13330A2911981-04-13013 April 1981 Responds to NRC 801031 Request for Clarification of NUREG-0737 Requirements & Confirmation of Implementation Date.Rept by NUS Corp, Control Room Habitability Evaluation San Onofre Generating Station,Unit 1 Encl Project stage: Request ML13302B0341981-04-13013 April 1981 Summary of 810310 Meeting W/Utils in Bethesda,Md Re Explosion Hazards.Attendance List & Applicant Handouts Encl Project stage: Request ML13331A0741981-04-17017 April 1981 Requests That NRC Finish Review of Util Compliance W/Ie Bulletin 79-06C, Nuclear Incident at TMI - Suppl. Review Completion Needed for Util to Complete Design Change to Assure Automatic Tripping of Reactor Coolant Pumps Project stage: Other ML13330A2991981-04-20020 April 1981 Forwards Response to NUREG-0737,Item II.K.3.17 Re ECCS Equipment Outages.Also Forwards Analysis of Probability of Toxic Gas Hazard for San Onofre Nuclear Generating Station as Result of Truck Accidents Near Plant Project stage: Other ML13317A6101981-05-0707 May 1981 Forwards Addl Info Re SEP Topic XV-16, Radiological Consequences of Failure of Small Lines Carrying Primary Coolant Outside Containment, Per 801215 & 810319 Requests Project stage: Request ML13317A6161981-05-12012 May 1981 Advises That TMI Action Plan Item II.K.3.9 Was Not Completed by 810101.Facility Has Been Shut Down Since Apr 1980.Item Will Be Completed Prior to Restart.Also Lists Completion Schedules for Items II.D.3,II.E.4.2.,II.G.1 & III.D.3.3 Project stage: Other ML13317A6271981-06-0808 June 1981 Submits Results of Evaluation of Containment post-accident Pressure Reanalysis on Operational Limits,In Response to TMI Action Plan Item II.E.4.2(5).Peak post-accident Pressure & Temp in 770119 Analysis Is Still Applicable Project stage: Other ML20196A6141981-06-15015 June 1981 IE Review & Evaluation of Licensee Implementation of TMI Action Plan Requirement 1.C.5, `Procedures for Feedback of Operating Experience to Plant Staff Project stage: Other ML20196A6061981-06-15015 June 1981 IE Review & Evaluation of Licensee Conformance W/Tmi Action Plan Requirements 1.A.1.3, `Shift Manning Part 1,Limit Overtime Project stage: Other ML13317A6371981-06-17017 June 1981 Advises That Effluent Monitoring Sys,Per NUREG-0737,Item II.F.1 Will Not Be Completed Prior to Startup,As Remote Readout Gm Detector Has Been Removed.Interim Requirements of NUREG-0578 Will Be Met Per Project stage: Other 1980-04-11
[Table View] |
Text
Docket No. 50-206 NO79
.5 41L 9
LICENSEE: Southern California Edison Company FACILITY: San Onofre Nuclear Generating Station Unit 1
SUBJECT:
SUMMARY
OF NOVEMBER 8, 1979 PHONE CONVERSATION REGARDING LESSONS LEARNED IMPLEMENTATION During a phone conversation on November 8, 1979, the NRC Lessons Learned Implementation Team discussed with the licensee its October 17, 1979 response to our September 13, 1979 letter.
The team informed the licensee of those lessons learned items for which the licensee's proposed schedule for implementation is unacceptable. These items, along with the proposed and required completion dates, are listed in Enclosure
- 1.
The team also informed the licensee of those items for which further clarification of the licensee's commitment is necessary to' demonstrate compliance with the lessons learned requirements. These items and the associated team questions are listedin Enclosure 2.
By letter dated October 30, 1979, we provided additional clarification of the lessons learned reqU.rements to all licensees. We also requested that within 15 days licensees justify proposed actions not in complete agreement with the staff's requirements and improve the implementation schedule where it differed from the staff's requirements. During this phone conversation we informed the licensee that those items listed in Enclosure 1 should be addressed in their response. In addition, the licensee agreed to provide the information requested in Enclosure 2 in its response to our October 30, 1979 letter or as soon thereafter as possible.
Alfred Burger, Project Manager Operating Reactors Branch #2
-Division of Operating Reactors Enclosures (2):
J As stated 7911300 OFFICe.
DOR:0RB #
OR:0R #2
.L..
SURNAME.A eD m
I 4b.;:*
..A nri 1 11//979 11/
/79 1 /t/79 DATE1..6)
RIN..1..
N=C FORM 318 (9.76) 1WRCM 024 U.S. GOVERNENT PmRTIN ow-FIE: '197
- zo0 - 7es
-2 cc w/enclosures:
Charles R. Kocher, Assistant General Counsel Southern California Edison Company Post Office Box 800 Rosemead, California 91770 David R. Pigott Samuel B. Casey Chickering & Gregory Three Embarcadero Center Twenty-Third Floor San Francisco, California 94111 Jack E. Thomas Harry B. Stoehr San Diego Gas & Electric Company P. 0. Box 1831 San Diego, California 92112 U. S. Nuclear Regulatory Commission ATTN:
Robert J. Pate P. 0. Box 4167 San Clemente, California 92672 Mission Viejo Branch Library 24851 Chrisanta Drive Mission Viejo, California 92676 Mr., James H. Drake Vice President Southern California Edison Company 2244 Walnut Grove Avenue Post Office Box 800 Rosemead, California 91770
ENCLOSURE 1 SAN ONOFRE 1 ITEMS THAT DO NOT MEET LESSONS LEARNED IMPLEMENTATION SCHEDULE
- 1. Section 2.1.3.a -
Direct Indication of PORV and Safety Valve Position The installation of the direct position indication is currently scheduled for the March-April 1980 refueling outage. The installation of the direct position indication should be complete on or before the NRC-required date of January 1, 1980.
- 2. Section 2.1.4 - Containment Isolation Provisions Modifications of the containment isolation signal (CIS) to provide diversity in the parameters sensed for initiation are scheduled for completion during the refueling outage currently scheduled for March-April 1980. The CIS modifications should be completed on or before the NRC-required date of January 1, 1980.
- 3. Section 2.1.4 - Containment Isolation Provisions Modifications of the CIS to prevent re-opening of the containment isolation valves are scheduled to be completed during the refueling outage currently scheduled for March-April 1980. These modifications should be completed on or before the NRC-required date of January 1, 1980.
- 4. Section 2.1.3.b. -
Instrumentation for Detection of Inadequate Core Cooling Our position is that the decision as to whether or not additional instrumentation needs are incorporated into the SEP Program will be delayed until additional instrumentation is identified.
- 5. Section 2.2.2.b -
Onsite Technical Support Center Completion of the Onsite Technical Support Center is scheduled for the September-October 1981 refueling outage. This center should be completed on or before the NRC-required date of January 1, 1981.
- 6. Containment Pressure Indication, Containment Water Level Indication, and Containment Hydrogen Indication These items are presently scheduled to be completed during the September-October 1981 refueling outage. These modifications should be completed on or before the NRC-required date of January 1, 1981.
ENCLOSURE 1
-2
- 7. Reactor Coolant System Vents Our position is that the decision as to whether or not the reactor coolant system vents are incorporated into the SEP Program will be delayed until the description of the reactor coolant system vents is provided.
- 8. Section 2.1.6.a -
Systems Integrity Measurements of leakage rates should be scheduled to comply with the lessons learned implementation date of January 1, 1980.
Additionally, a summary report of the leakage reduction program should be provided by January 1,. 1980 as noted in the October 30, 1979 Harold R. Denton's letter to All Operating Nuclear Power Plants. Your response should include a commitment to perform necessary plant modifications by January 1, 1980.
- 9. Section 2.1.6.b - Shielding Review Our position is that the decision as to whether or not shielding modifications are incorporated into the SEP Program will be delayed until the design review is completed on or before January 1, 1980.
- 10.
Section 2.1.8.a -
Post-Accident Sampling Your schedule should be revised to coincide with the lessons learned implementation schedule. Our position is that the decision as to whether or not plant modifications required by this section are incorporated into the SEP Program will be delayed until the sampling review is completed on or before January 1, 1980.
- 11.
Section 2.1.8.b - High Range Radiation Monitor Your commitment should be revised to include installation of the noble gas effluent monitor, capability for sample analysis under accident conditions, and installation of high range radiation monitors inside containment by January 1, 1981.
ENCLOSURE 2 SAN ONOFRE 1 CLARIFICATION OF PROPOSED ACTIONS ARE NEEDED IN ORDER TO VERIFY CONFORMANCE TO LESSONS LEARNED REQUIREMENTS
- 1. Section 2.1.1 -
Emergency Power Supply Requirements Clarification of the existing station instrument air supply for the PORV block valves is required:
- a. State whether the instrument air supply for the PORV block valves satisfy the single failure criterion.
- b. State how many cycles of-the PORV block valves are accommodated by the instrument air system accumulators.
- 2. Section 2.1.4 - Containment Isolation Provisions In the San Onofre submittal dated June 25, 1979, systems determined to be essential were identified. Further clarification is needed before the NRC-required date of January 1, 1980. Specifically, all "lines associated with engineered safety features" and all "lines which are normally closed during operating modes requiring containment integrity and remain closed following an accident" should be identified. Further, the bases for identifying these lines as essential should be provided.
- 3. Section 2.1.5.a - Dedicated Containment Penetrations With regards to the existing San Onofre Unit 1 purge system to meet the requirements of Section 2.1.5.a, a complete description of the planned system should be provided on or before the required January 1, 1980 implementation date.
- 4. Section 2.1.3.b -
Instrumentation for Detection of Inadequate Core Cooling The additional information for the subcooling meter as detailed in the Harold R. Denton letter of October 30, 1979, should be submitted.
- 5. Section 2.2.1.b -
Shift Technical Advisor Your proposal to select one of the alternatives to the shift technical advisor as listed in the September 13, 1979 letter to operating reactors is noted. It should be recognized, however, that the listed alternatives were those previously reviewed by the staff and were found to be unacceptable for the reasons indicated in the September 13, 1979 letter.
A clarification is therefore requested of the method by which you intend to implement the staff's requirement on the shift technical advisor.
ENCLOSURE 2
-2
- 6. Section 2.2.2.b - Onsite Technical Support Center Additional clarification is requested which addresses communication links (how many), access of engineering records (distance, time),
and the visual display of station technical data.
The current proposal of a data "pass-through" window does not address the type of data that can be transmitted in this fashion, the timelines of the data, nor the possible distraction to and burden on the control room watchstanders from such a system.
- 7. Section 2.1.8.a -
Post-Accident Sampling Your commitment should include the commitment to provide the capability to conduct sample analysis of dissolved gases (H2,02) in -the reactor coolant and hydrogen in the containment atmosphere.
DISTRIBUTION NRC PlYR Local PDR ORB #2 Reading NRR Reading H. Denton E. Case D. Eisenhut R. Vollmer W. Russell B. Grimes T. J. Carter A. Schwencer D. Ziemann T. Ippolito W. Gammill L. Shao J. Miller R. Reid V. Noonan P. Check G. Lainas G. Knighton A. Burger OELD I&E (3)
R. Fraley, ACRS (16)
H. Smith Program Support Branch TERA NSIC J. Olshinski (2)
J. Burdoin J. Kerrigan N. Anderson C. Willis oI InsL
.URNAME g................................
I..........
NRC FORM 318 (9.76) NRQ( 0240 U.S. GOVERNMENT PRINTING opICes: 1978 - 20e - 769
Docket No. 50-206 N
g3 9 Licensee: Southern California Edison Company Facility: San Onofre Nuclear Generating Station, Unit 1
Subject:
Summary of November 8, 1979 Phone Conversation Regarding 480V Switchgear Fault in 4 KV Switchgear Room A conference telephone call was held on November 8, 1979, between J. Curran, San Onofre Unit 1 Plant Manager, R. Krieger, Senior Engineer of Southern California Edison Company (SCEC, the licensee), A. Burger, J. Burdoin, L. Derderian of the DOR staff and G. Klingler, B. Faulkenberry of I&E, to obtain more detailed information on the subject event. The switchgear failure required shutdown of the plant. The licensee had promptly reported the event to the NRC. SCEC provided the following details.
On November 7, 1979, at 12:37 Pacific Time the operators in the control iroom heard a loud noise followed by several annunciator alarms which indicated loss of 480 bus voltage and fire (set off by smoke detectors) in the 4 KV switchgear room located below the control room. The operator immediately tripped the reactor, all control rods dropped into the core, boration was started and a normal shutdown proceeded. The Unit 1 fire brigade assembled and arrived inside the 4 KV.switchgear room Yvthiin 4 minutes from the receipt of the control room alarms.
The Camp Pendleton fire brigade which had been promptly notified arrived on-the-scene within eleven minutes from receipt of the control room alarms. The fire brigade established that an electrical fault had occurred in the No. 1 480V switchgear. There.was no fire but only a great deal of smoke from the electrical fault. There were no injuries to personnel.
When the -back of the switchgear was removed, it was found that the center "B" phase-of the bus tap (the bus bars between the main bus and the circuit breakers) for a containment sump recirculating pump had faulted to ground (phase to ground fault).
This pump was not operable at the time and the circuit breaker was open. (Another redundant sump recirculating pump which is powered from a separate 480V bus located in the 480V switchgear room was operable). The circuit breaker which energizes the 480V bus in the 4 KV switchgear room operated on instantaneous overcurrent to clear the fault.
The damage was limited to the "B" phase bus bar and control wiring. The 6 /
debris was removed and the switchgear unit #1 was returned to service before noon on November 8, 1979.
SURNAM9)2 RCOR31(97)NRCM 0240us.
GOVERNMuNT PmATmN oPPIce: 1970 - Zes - re