Informs That Proposed Changes to Tech Spec Will Be Provided Approx 60 Days Prior to Return to Power from Current Outage, in Response to 820920 Generic Ltr 82-16 & NUREG-0737
ML13317A469
Person / Time
Site: San Onofre 
Issue date: 12/09/1982
From: Krieger R
SOUTHERN CALIFORNIA EDISON CO.
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 GL-82-16, TAC-44128, NUDOCS 8212200063
Download: ML13317A469 (2)


Text

Southern California Edison Company P.O. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 December 9, 1982 Director, Office of Nuclear keactor Regulation Attention: 0. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Gentlemen:

Subject:

Docket No. 50-206 NUREG-0737 Technical Specifications San Onofre Nuclear Generating Station Unit 1

References:

1. Letter, 0. G. Eisenhut, NRC, to All Pressurized Power Reactor Licensees, NUREG-0737 Technical Specificatons (Generic Letter No. 82-16), September 20, 1982
2. Letter, K. P. Baskin, SCE, to D. M. Crutchfield, NRC, Clarification of TMI Action Plan Requirements, December 8, 1981 Reference 1 provided us with model technical specifications for the post-TMI requirements of NUREG-0737. It also requested a response within 90 days of receipt of the letter, which would require our response by December 29, 1982 based upon our receipt date of September 30, 1982.

The purpose of this correspondence is to inform you that we will provide a proposed change to the San Onofre Unit 1 Technical Specifications responsive to Reference 1 approximately sixty days prior to return to power from the current outage. This schedule is in accordance with our prior commitment in Reference 2, which indicated that the TMI Action Plan Requirements described therein would be completed prior to return to power from this outage.

The model technical specifications enclosed with Reference 1 do not cover all of the post-TMI requirements currently being implemented at San Onofre Unit 1. Notwithstanding this need for model technical specifications, we are attempting to draft technical specifications for all of the modfications being completed during the current outage. If model technical 81220006P 821209 PDR ADOcK 05000206 PDR

Mr. D.

December 9, 1982 specifications for the remainder of the post-TMI requirements,' identified in Reference 2 to be completed during the current outage, were issued in time to support our schedule, they would be incorporated into the above discussed proposed change.

If you have any questions regarding the above discussed schedule, please let me know.

Very truly yours, R. W. Krieger Supervising Engineer San Onofre Unit 1 Licensing