Summarizes 850325 Mgt Meeting in Region II Re Briefing on Readiness Review Module Entitled, Reinforced Concrete Structures. In-depth Presentation Will Better Enable NRC to Conduct Evaluation of Module
ML20129H104
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 04/24/1985
From: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Kelly R
GEORGIA POWER CO.
References
NUDOCS 8507180508
Download: ML20129H104 (4)


Text

r u

! $ Odt APR 2 41985 Georgia Power Company ATTN: Mr. R. J. Kelly Executive Vice President P. O. Box 4545 Atlanta, GA 30302 Gentlemen:

SUBJECT:

MEETING

SUMMARY

- V0GTLE FACILITY, DOCKET NOS. 50-424 AND 50-425 This refers to the management meeting conducted at your request in the NRC Region II Office on March 25, 1985. This meeting was held to brief the NRC on the first Vogtle Readiness Review Module entitled " Reinforced Concrete Structures." -

It is our opinion that this meeting was beneficial and has provided a compre-hensive overview of the Vogtle Readiness Review Program and, specifically, the Reinforced Concrete Structures Module. This in-depth presentation will better enable the NRC to conduct its evaluation of this module.

In accordance with Section 2.790 of NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC Public Document Room.

Should you have any questions concerning these matters, we will be pleased to discuss them.

Sincerely, S Y.

J. Nelson Grace Regional Administrator

Enclosure:

Attendance List cc w/ encl:

R. E. Conway, Senior Vice Presidentx Nuclear Power D. O. Foster, Vice President and General Manager Vogtle Project H. H. Gregory, III, General Manager, Vogtle Nuclear Construction G. Bockhold, Jr. , Vogtle Plant Manager  ;

L. T. Gucwa, Chief Nuclear Engineer cc w/ encl: (See page 2)  !

B507100508 850424 i\

PDR ADOCK 05000424 A

PDR 1E l l

APR 2 41985 Georgia Power Company 2 cc w/ enc 1:

Ruble A. Thomas, Vice President-Licensing Vogtle Project Ed Groover, Quality Assurance Site Manager C. W. Hayes, QA Manager J. T. Beckham, Vice President

& General Manager - Operations J. A. Bailey, Project Licensing Manager George F. Trowbridge, Esq.

Shaw, Pittman, Potts and Trowbridge Bruce W. Churchill, Esq.

Shaw, Pittman, Potts and Trowbridge Ernest L. Blake, Jr. , Esq.

Shaw, Pittman, Potts and Trowbridge James E. Joiner, Troutman, Sanders, Lockerman and Ashmore James G. Ledbetter, Commissioner Department of Human Resources Charles H. Badger, Office of Planning and Budget, Management Review Division Deppish Kirkland, III, Counsel Office of the Consumer's Utility Council Douglas C. Teper, Georgians Against Nuclear Energy Laurie Fowler, Legal Environmental Assistance Foundation Tim Johnson, Executive Director Educational Campaign for a Prosperous Georgia Morton B. Margulies, Esq., Chairman Administrative Judge, Atomic Safety and Licensing Board Panel Dr. Oscar H. Paris, Administrative Judge Atomic Safety and Licensing Board Panel Gustave A. Linenberger, Jr., Administrative Judge, Atomic Safety and Licensing Board Panel bec w/ encl:

E. Reise, ELO M. Sinkule, RII NRC Resident Inspector Document Control Desk State of Georgia RII RII RII RII RII h

WRankin MSfnkdle h VBrownlee rwa ker J01shinsfi 4/g/85 4/94/85 4 p /85 4/Q/85 4/2f85*

i

APR 2 41985 ENCLOSURE LIST OF PRINCIPAL PARTICIPANTS V0GTLE READINESS REVIEW MEETING MARCH 25, 1985 Georgia Power Company R. E. Conway, Senior Vice President - Nuclear Power D. O. Foster, Vice President and Project General Manager / Vogtle Project P. D. Rice, Vice President and General Manager Quality Assurance H. P. Walker, Manager Unit Operations, Nuclear Operations R. W. McManus, Assistant Project Construction Manager Southern Company Services W. M. Wright, Readiness Review Design Discipline Manager, Southern Company Services W. C. Ramsey, Vogtle Electric Generating Plant, Southern Company Services J. A. Bailey,' Project Licensing Manager Stone and Webster J. A. Curtin, Readiness Review - Industrial Design Review S. L. Stamm, Readiness Review, Industrial Design Review Teledyne R. D. Ciatto, Principal Engineer Troutman, Sanders, Lockerman and Ashmore C. W. Whitney, Project Legal Counsel NRC-NRR E. G. Adensam, Chief, Licensing Branch, 4 G. E. Lear, Chief Structural Geotechnical Engineering Branch N. I. Chokshi, Structural Engineer Geotechnical Branch K. C. Leu, Structural Engineer Geotechnical Branch E. J. Sullivan, Technical Assistant, Division of Engineering M. A. Miller, Project Manager NRC-IE B. K. Grimes, Director, Division of Quality Assurance Vendor and Technical Training Center Programs G. T. Ankrum, Chief, Quality Assurance Branch J. L. Milhoan, Chief, Licensing Section, Quality Assurance Branch G. J. Overbeck, Mechanical Engineer (Westec)

.}

gog 9. A 1985 Enclosure 2 NRC-EDO E. W. Brach, Coordinator for Regional Operations, EDO NRC-Region II J. N. Grace, Regional Administrator J. A. Olshinski, Deputy Regional Administrator R. D. Walker, Director, Division of Reactor Projects (DRP)

P. R. Bemis, Director, Division of Reactor Safety (DRS)

V. L. Brownlee, Chief, Reactor Projects Branch 2, DRP A. R. Herdt, Chief, Engineering Branch, DRS M. V. Sinkule, Chief, Reactor Projt. cts Section 20, DRP T. E. Conlon, Chief, Plant System Section, DRS -

W. F. Sanders, Senior Resident Inspector, Vogtle W. M. Hill, Technical Assistant, DRS J. R. Harris, Reactor Engineer, DRS W. H. Rankin, Acting Project Engineer, DRP Intervenor D. C. Teper, Georgians Against Nuclear Energy