|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20205B9601999-03-24024 March 1999 Seventh Partial Response to FOIA Request for Documents. Records in App N Already Available in Pdr.App O Records Being Released in Entirety & App P Records Being Withheld in Part (Ref FOIA Exemptions 7C,2 & 5) ML20205A2771999-03-19019 March 1999 Advises of NRC Planned Insp Effort Resulting from Vogtle PPR on 990208.PPR for Plant Involved Participation of All Technical Divs in Evaluating Insp Results & Safety Performance Info for Period of Dec 1997 - Jan 1999 ML20207L8281999-03-0808 March 1999 Forwards Partially Withheld Insp Repts 50-424/99-01 & 50-425/99-01 & Notice of Violation ML20207J0431999-03-0303 March 1999 Forwards Insp Repts 50-424/98-10 & 50-425/98-10 on 981227- 990213.No Violations Noted.Licensee Conduct of Activities at Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices ML20203G5691999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Ltr Indicating No Candidates or Ltr Listing Names of Candidates for Exam ML20202H9691999-01-29029 January 1999 Forwards Safety Evaluation Authorizing Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant, Unit 1 ML20199J7931999-01-20020 January 1999 Forwards Insp Repts 50-424/98-09 & 50-425/98-09 on 981115-1226 at Vogtle Units 1 & 2.No Violations Were Identified.Conduct of Activities at Vogtle Was Generally Characterized by safety-conscious Operations ML20199K1381999-01-12012 January 1999 Informs That on 990117,Region II Implemented Staff Reorganization as Part of agency-wide Streamlining Effort, Due to Staffing Reductions in FY99 Budget.Organization Charts Encl ML20198S1601998-12-31031 December 1998 Forwards SER of Licensee Second 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief for Vogtle Electric Generating Plant Submitted on 970529. INEEL/EXT-98-01007 Rept Also Encl ML20199E4741998-12-23023 December 1998 Provides Summary of 981105 Training Managers Conference Held in Atlanta,Georgia.Conference Agenda,List of Conference Attendees,Presentation Slides & Preliminary Schedule for FY99 & FY00 Encl ML20199J9781998-12-22022 December 1998 Responds to 981209 Meeting Re Installation of Seismic Clips on Cutler Hammer Electrical Circuit Breakers.Forwards List of Attendees & Handouts ML20198F6711998-12-11011 December 1998 Forwards Insp Repts 50-424/98-08 & 425/98-08 on 980927-1114. No Violations Identified ML20198N9431998-12-10010 December 1998 Ack Receipt of Response, to NOV Issued on 980112 Re Surveillance Testing of Reactor Trip Sys P-4 Interlock Feature at Licensee Facility.Nrc Agrees That Surveillance Testing Not Required ML20196J2181998-12-0101 December 1998 Advises of Planned Insp Effort Resulting from 981102 Insp Planning Meeting.Historical Listing of Plant Issues Called Plant Issues Matrix & Insp Plan,Including Specific Insps Such as in Security & Radiological Protection Areas Encl ML20196J2581998-12-0101 December 1998 Confirms Arrangements Made Between J Bailey & B Holbrook, Re Info Meeting Scheduled for 990210 to Discuss Licensee Performance,New Initiatives & Other Regulatory Issues Pertaining to Listed Facilities ML20196B1231998-11-23023 November 1998 Confirms Telephone Conversation Between J Bailey & P Skinner on 981120 Re Info Meeting Which Has Been Scheduled for 981209 in Atlanta,Ga,To Discuss Issues Re Seismic Retainer Clips ML20196D4981998-11-13013 November 1998 Informs That on 981007,NRC Administered Gfes of Written Operator Licensing Examination.Copy of Answer Key & Master Bw/Pwr GFE Encl,Even Though Facility Did Not Participate in Exam.Without Encl ML20195B3391998-11-0909 November 1998 Forwards Partially Withheld Insp Repts 50-424/98-12 & 50-425/98-12 on 981005-09 (Ref 10CFR73.21).No Violations Noted.Conduct of Activities Generally Characterized by safety-conscious Operations & Sound Engineering ML20155H2501998-10-21021 October 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-424/98-05 & 50-425/98-05 Issued on 980723.Concluded for Reasons Stated That Example 2 Violation Occurred as Stated in NOV ML20155A7491998-10-15015 October 1998 Forwards Insp Repts 50-424/98-07 & 50-425/98-07 on 980816-0926 & Nov.Insp Generally Characterized by Safety Conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML20155B7771998-10-0909 October 1998 Extends Invitation to Attend Training Manager Conference on 981105 in Atlanta,Georgia.Conference Designed to Inform Regional Training & Operations Mgt of Issues & Policies That Effect Licensing of Reactor Plant Operators ML20155B4621998-09-25025 September 1998 Discusses OI Investigation Which Completed on 980728. Investigation Reviewed Circumstances Surrounding Apparent Disabling of Fire Computer Trouble Alarm by Unit Shift Supervisor.Concludes Enforcement Discretion Warranted ML20153B0401998-09-17017 September 1998 Responds to 980904 e-mail Message Making Certain Observations Re Apparent Increase in Reactor Trips at Plant, Units 1 & 2.NRC Concluded That Licensee post-trip Reviews Adequately Conducted & That No Adverse Trends,Apparent ML20153B9311998-09-16016 September 1998 Forwards RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations, Responses for Plant,Units 1 & 2 ML20153F7081998-09-11011 September 1998 Provides Summary of 980909 Meeting Held to Discuss TS & Other Regulatory Issues Re Vogtle Electric Generating Plant. List of Meeting Attendees & Copy of Presentation Slides Encl ML20154C4871998-09-10010 September 1998 Forwards Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815 & Nov.One Violation Involved Failure to Implement Adequate C/As for Repeated Failures to Enter Applicable TS Limiting Conditions for Operation ML20151U7901998-09-0909 September 1998 Discusses 980615 Request for Exemption from Requirement of 10CFR73.55(e)(1) & (f)(1) to Provide Continuous Staffing of Plant CAS During Contingency Events.Request Denied ML20151S7291998-09-0202 September 1998 Discusses Evaluation of Util Response to GL 97-05 for Plant, Units 1 & 2.NRC Did Not Identify Any Concerns W/Sg Tube Insp Techniques Employed at Plant ML20239A4251998-08-27027 August 1998 Informs of Change Being Implemented by Region II Re Administrative Processing of Licensee Responses to Nov.Nov Responses Will Be Formally Ack as Part of Periodically Issued Integrated Insp Repts 1999-09-01
[Table view] |
Text
- . - - - .- - - - - - - - - . - - . - - - - . _ - - .- -
, . September 17, 1998
- l Mr. Michael J. Mulligan 5420 Maltdie Court Sugar Hill, GA 30518
Dear Mr. Mulligan:
The purpose of this letter is to respond to your e-mail message, dated September 4,1998 (Enclosure 1), in which you made certain observations regarding an apparent increase in reactor trips at the Vogtie Electric Generating Plant (VEGP), Units 1 and 2.
The NRC staff and licensees are interested in reactor trips at all nuclear power facilitics in that trips subject a facility to transient conditions that could have adverse impacts on plant i equipment. The !!censee for VEGP, like other licensees, conducts post-trip reviews to ,
determine the cause of any reactor trip in order to eliminate these causes and detect adverse l
trends in reactor operations (e.g., an excessive number of operator errors that could be l significant contributors). In addition, the NRC staff routinely reviews the licensee's post-trip ;
review e' forts to assure the effectiveness of these reviews. Finally, the NRC staff indeper ::ently reviews industry experience and trends data to ascertain if any nuclear power facility is experiencing an excessive number of reactor trips. These and other evaluation
_ programs are described in Enclosure 2, " Evaluating Reactor Licensees."
Thus far, the NRC staff has concluded that the VEGP licensee's post-trip reviews are adequately conducted and that no adverse trends, regarding reactor trips, are apparent for VEGP.
With regard to the other concerns you voiced in your September 4,1998, e-mail message, such I as the effect of the VEGP licensee's budgetary constraints, grid stability, and labor issues, these sorts of concerns are routinely evaluated when they appear to be contributing to adverse operating trends at nuclear power facilities. No such trends are currently evident at VEGP.
Sincerely, ORIGINAL SIGNED BY:
David H. Jaffe, Senior Project Manager Project Directorate 11-2 '
Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket Nos. 50-424 and 50-425
Enclosures:
- 1. E-mail dated September 4,1998 ;
- 2. Evaluating Reactor Licensees Distribution. 4 ., , ,
~ gr See next page a:.C b b e - ' " a E To receive a copy of this document, indicate in the box: "C" = Copy without attachment / enclosure "E" = Cop f with attachment / enclosure, "N" = No copy /
OFFICE P M :P DfT M _,l LA:PDil4 31Y D:PDi$u l (A)D$PE l l l 1 NAME DJaffeb )/ LBerry' \N \ ' HBerk$v' JZwdllhliiki 4/ R98 DATE 3/F7987// 6/4(/98 () /lL/98 / /98 / /97
. DOCUMC.NT NAME: G:\VOGTLE\MILLIGAN.92 OFFICIAL RECORD COPY 9809220289 980917 FDR ADOCK 05000424 H PDR
g J ,
Distribution for Yellow Ticket #0(380186 dated September 17, 1998
- Docket File (w/ origina! incoming) -
PUBLIC (w/ incoming)
PD 11-2 Rdg. (w/ incoming)' ,
' SCollins/FMiraglia BBoger BSheron JRoe '
RZimmerman
- JZwolinski
' HBerkow DJaffe (w/ incoming)
RLaskin (e-mail RSL), DRPE ' j LBerry l NRR Mailroom (YT #0980186 w/ incoming) (0-5-E-7) )
NOlson l PSkinner, Rll l' LPlisco, Ril l
l i
i l
li
/ .
.l 1 /
/
l Df
. . c. m o
, c I-
l l
.f*%%
p UNITED STATES NUCLEAR REGULATORY COMMISSION f WASHINGTON, D.c. 20566 4001
%,. . . . . ,o September 17, 1998 Mr. Michael J. Mulligan 5420 Maltdie Court Sugar Hill, GA 30518 l
Dear Mr. Mulligan:
The purpose of this letter is to respond to your e-mail message, dated September 4,1998 (Enclosure 1), in which you made certain observations regarding an apparent increase in .
reactor trips at the Vogtle Electric Generating Plant (VEGP), Units 1 and 2.
l The NRC staff and licensees are interested in reactor trips at all nuclear power facilities in that trips subject a facility to transient conditions that could have adverse impacts on plant l l equipment. The licensee for VEGP, like other licensees, conducts post-trip reviews to !
determine the cause of any reactor trip in order to eliminate these causes and detect adverse '
trends in reactor operations (e.g., an excessive number of operator errors that could be ;
significant contributors). In addition, the NRC staff routinely reviews the licensee's post-trip ;
review efforts to assure the effectiveness of these reviews. Finally, the NRC staff l independently reviews industry experience and trends data to ascertain if any nuclear power facility is experiencing an excessive number of reactor trips. These and other evaluation programs are described in Enclosure 2, " Evaluating Reactor Licensees."
Thus far, the NRC staff has concluded that the VEGP licensee's post-trip reviews are adequately conducted and that no adverse trends, regarding reactor trips, are apparent for l
VEGP.
I With regard to the other concerns you voiced in your September 4,1998, e-mail message, such l as the effect of the VEGP licensee's budgetary constraints, grid stability, and labor issues, these sorts of concerns are routinely evaluated when they appear to be contributing to adverse operating trends at nuclear pewer facilities. No such trends are currently evident at VEGP.
Sincerely, i
\
_- C David N fie, enior Project Manager
, Project Directorate ll-2 l Division of Reactor Projects - 1/11 l Office of Nuclear Reactor Regulation l j Docket Nos. 50-424 and 50-425 l 1
Enclosures:
- 1. E-mail dated September 4,1998
- 2. Evaluating Reactor Licensees 4
I 4 i
m . . _. - . . . . _ . - . _ _ .._ . _ _ _ _ . _ _ _ . . _ _ _ _ _ . _ . . _ . _ _ . . _ -
i Fress: _ ' Michael Mulligan * <m.mulligangworkinet.att. net >
To: . ' Mike D* <necapasover. net >. " Victor Dncks' <VLDen... l Date: 9/4/9310:5 sam :j Sutdeet: Vo6tle Plant Trending l' Mr. Dricks Am I picking up an increasing trend of plant trips at Vogtle 1 and 2 in the .j last year? Didn't they have some employee and Union troubles. like ahnost a i
strike recendy? Noticed that Ga PUC is talking about a general rate reduction and Ga power is talking "about reducing Vogtles long term debt in these goood times. Isn't GA grid system
. (capacity) pretty tight this year? Are we seeing the initial stage of an improper maintenance and operating budget squeeze that has effected plant capacity factor and reliability. Might this be an indicator of a trend with the rest of the Southern's system. And how far is this from a safety 1 concern? mike mulligan 1
l 4
i i
4
(
f f
i l
- - 1 I
k^
ENCLOSURE 1
... . . .. * ::.:..: =~~.:
ReactorLicensees httpJAmw. arc.stv/OPA/gmship/ process.hte i j Evaluating Reactor Licensees i As part ofits mission to protect public health and safety and the environment, the Nuclear Commission (NRC) monitors and evaluates the safety performance oflicensees who operate mor 100 commercial nuclear plants in the United States. This rigorous oversight includes eva concems, assessing operational events and experience, and reviewin evaluations and actions are based on publicly available information.g enforcem:nt actions. All The process used to determine the level ofplant safety is comprehensive to ensure NRC has an acc and objective understanding. It involves a number of NRC programs that continually examine p operations, operational events and plant management. Two proi; rams-insoections and analysis of operational data-provide primary mformation that is used in ot ser evaluations by the NRC's staff. About i once every six months, NRC senior managen meet with the Commission to discuss the yrformanc i nuclear Rockvil aower plants based on the staff's evaluations. These meetings are held at NRC's acadqu e, Maryland, and are open to the public.
1 INSPECTION PROGRAM i NRC resident inspecton assigned to specific plant sites, augmented by specialists from headquarter regional offices, conduct year round inspections oflicensee activities. Inspections are planned a performed both routinely and in response to events, enforcement allegations or emergmg issues.
Mspection findings and conclusions are documented in repons, w,hich are reviewed and approved b inspectors' managers. These repons and associated findings are available for review and analysis NRC offices and by the public.
ANALYSIS OF OPERATIONAL DATA PROGRAM In addition to the day-to-day and special inspections, mechanical, electrical and other plant problems carefully analyzed by the NRC. Reviews are conducted by the Office of Nuclear Reactor Regulation (NRR), which has primary responsibility for ovenight of the inspection progmm for nuclear plants, and the Office for Analysis and Evaluation of Operational Data (AEOD).
The NRR reviews reports from licensees, NRC inspectors and industry groups to assess their safety im ponance, generic unplications and the need for any immediate corrective action. AEOD screens ind i ividual plant events or incidents to identify forerunners to potential severe accidents. In addition, i AEOD conducts an analysis of plant operating experience as reflected in eight performance indicators (PI). These indicators include data on unplanned automatic reactor shutdowns, equipment and safety system failures and worker radiation ex highlights trends in safety performance posures.
both good and poor. AEOD's findings are published m a repon Stemming from these two arograms are other evaluative processes, desenbed below, that NRC uses to assess plant performance. %ese vary in scope, frequency, level ofreview and duration.
Plant Performance Reviews At least semi-annually, NRC staffin each of four regional offices bring together the findings of NRC inspectors, AEOD analyses and enforcement actions (i.s.,
regulations) to give NRC senior managers a look at how b, penalties for hcensee violation eensees have performed over the previous six months. These assessments, called plant performance reviews (PPRs), help managers decide which plants require additional close attention for the next six months. These penodic reviews also are a arimary source ofinformation in assessing plant Meetings. The results of PPRs are made public. performance for the semi annual Senio Integrated Performance Assessment Process (IPAP)
Independent of day-to-day oversight of nuclear plants by the resid:nt inspectors, teams of senior NRC ft m a w n s
. . _ . . - . - ~ . . --.. ..- .
bap1/www. arc. gov /OPA/gmWrip/ process.b
.E I e, inspectors conduct integrated 1
- rformance assessments at selected plants each year. The purpose is to venfy that a licensee's actual rformance matches the performance reflected in written records for the 7tevious two years. Findings from the IPAP de directinput to the stematic Assessment of
'. L icensee Performance (SA. P program that s described below. An IP j report with final conclusions include recommendations for plant inspections and is made available to the public.
i 1 SALPs i
j The SALP evaluations employed by the NRC are conducted every 12 to 24 months to assess lon performance of each nuclearpower plant. The staff review includes the use of boards comprised of managers from a regional office and a manager from NRR. The board members review inspection
! results, enforcement actions that may have been taken against a licensee, and results of the lates IPAPs, performance indicators, licensee self assessments, third- assessments and in-depth i
discussions with licensees. Typically, the board also visits the j for a first-hand assessment. The result of the SALP review is a report that assigns one of three ratings to a plant: I for superior ormance,2 for good performance and 3 for acceptable cNnal areas: (1) plant operations, (2) maintenance, 3) performance. The ratings focus j managers use the SALP findings to identify those ant that areas (at a p require )mercased mspectio Generally, a plant receives a SALP review every 12-18 months. Plants whose performance is rated superior may have the period extended to 24 months before another SALP is perfonned. All SALP
) reports are made available to the public.
1 i Senior Management Meetings
- About two months before the semiannual Senior Management Meeting (SMM), the four regional l
administrators and the Director of NRR discuss at a screening meeting the nu nerous staffassessments and inspection results for each plant nationwide. Results of PPRs, performance indicators, inspection j
findings and SALPs are considered at these meetings. If a plant's performance ap s to be declining j
significantly, or if there are significant concerns about its performance, it will be laced on the agenda for discussion at the SMM.
}
The SMMs are chaired by the NRC's Executive Director for Operations and include all regional j administrators, office directors and senior managers. To arrive at an objective evah:ation of a
- omerational safety performance, the managers use a standard set ofquestions in five ar j
eTectiveness oflicensee self-assessment,2) operational performance (frequency of abnormal eve ;
human performance,4) material condition (safety system reliability / availability) and 5) engineering and design. With this template of questions guiding discussions, the mana performance is of most concem and warrant increased NRC These attention.gers identify those plants w plants are placed on NRC's
" Watch List." Plants already on the Watch List that have demonstrated improved performance over an extended period may be taken off the list. Plants that have demonstrated superior performance are also identified.
The Watch List has three categories:
- 1) Plants removed from the list;
- 2) Plants authorized to operate that NRC will monitor most closely; and
- 3) Shutdown plants requiring NRC authorization to resume operations and which NRC will monitor closely.
After the Senior Management Meeting, the safety performance ofplants that are placed on or taken off the Watch List are discussed at the semi annual public meetings with the Commission, generally durirg summer and winter timeframes. Also discussed are those plants whose performance is trending downward.
The NRC notifies the chief executive officers of the utilities operating those plants of concem to the
-m.... ._
L bap://www. arc.sov0PA/gmoripW b
t;
- agency and indicates the need to coneet weaknesses. Those having plants removed from the lis those which have demonstrated superior perf;nnance are also notified.
i' July 1996 Send Comments or Questions to ocaSnre rov i
1 l
l l
i i
l l
l
' k;
'C c-
p,
- 4 v ._ ;
_ : . y. - +--
FROM: , ORIGINAL DUE DT: / / TICKET NO: 0980186 '
DOC DT:'09/04/98 NRR RCVD-DATE:' 09/04/98
- TO: i Victor Dricks l FOR SIGNATURE OF : ** YEL DESC: ROUTING:
'Voct1e Plant' Trending Collins /Miraglia :
Boger
.Sheron Roe Zimmerman y
NRR Mailroom ;
i ASSIGNED TO: CONTACT:
DRPE Zwolinski
- SPECIAL INSTRUCTIONS OR REMARKS: I For appropriate action.
l
., 1 l
j:
I i
l l
4
'j
- j:' ' s
. . ~. = . -. - . . . - ... ..
.,. w*
From: . " Michael Mulligan" <m. mulligan @weldnet.att. net >
To: " Mike D" < necnp@sover. net > , " Victor Dricks" <VLD@n... <
Date: . 9/4/9810:58am
Subject:
Vogtle Plant Trending '
l Mr. Dricks !
Am I picking up an increasing trend of plant trips at Vogtle 1 and 2 in the last year? Didn't they have some employee and Union troubles, like almost a strike recently? Noticed that Ga PUC 1 is talking about a gene al rate reduction and Ga power is talking about reducing Vogtles long term debt in these goood times. _ !sn't GA grid system l (capacity) pretty tight this year? Are we seeing the initial stage of an '
improper maintenance and operating budget squeeze that has effected plant 'j capacity factor and reliability. Might this be an indicator of a trend with ;
the rest of the Southern's system. And how far is this from a safety J concern? mike mulligan l I
l i
I I
J l
1 i
l l
l 1
l I
l I