Requests Extension for Submittal of Required Documents for Relicensing of Univ of Fl Teaching Reactor.Entire Package Will Be Delivered for Printing by 810115 W/Expected 10-day Turnaround & Mailing by or Prior to 810131
ML19343B796
Person / Time
Site: 05000083
Issue date: 12/19/1980
From: Diaz N
FLORIDA, UNIV. OF, GAINESVILLE, FL
To: John Miller
Office of Nuclear Reactor Regulation
References
NUDOCS 8012300506
Download: ML19343B796 (2)


Text

!

\

.

N\ J CcLLEcz NUCLEAR FACILITIES DIVISION UNIVERSITY OF FLORIDA

- Y- OF DEPARTMENT OF NUCLEAR ENGINEERING SCIENCES 3 102 NUCLEAR REACTOR BUILDING

/ ENGINEERING GAINESVILLE, FLORIDA 32611 AREA CODE 904 PHONE 392-1429 December 19, 1980 Mr. James R. Miller Standardization and Special Projects Branch Division of Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555 RE: UFTR Relicensing Facility License R Docket 50-83

Dear Mr. Miller:

We are respectfully requesting a short extension on the submittal of the required documents for the relicensing of the UFTR, We are firmly committed to a January 31, 1981 submittal; earlier submittal is possible depending on University of Florida approval.

In support of our request, the following information is submitted:

1. The Physical Protection and Safeguards Plan was submitted on August 4,1980, in compliance with 10 CFR 73.

l 2. The Financial Qualifications Statement was submitted on December 8,1980.

3. The Operator Requalification Plan is completed, has been approve'd by Oper-ator Licensing and our Safety Committee, and will be made part of the January '81 submittal.
4. The SAR is completed and approved by the Safety Review Subcommittee with the following exceptions:

a) Accident Analysis Chapter which is in final type and will be dis-l tributed for review by December 31, 1980.

b) Technical Specifications, which are in final revision and will be dis-tributed for review on January 5,1981.

,

5. The Emergency Plan has been completed and distributed but it needs revision I to assure complaince with Reg. Guide 2.6 and staff recommendations.

We have made arrangements to have the entire package delivered for printing 0 by January 15, 1981 with an expected 10 day turnaround and mailing by or prior to January 31, 1981. 0 4 0

-

ou m oo soc -

1 NILS J. DIAZ, DIRECTOR (904)392-1406 l

,

EGL 4 EMPLOYMENT OPPORTUNITYf AFFIRMATNE ACTION EMPLOYER l

, .

'

i

" 'tils J. Diaz to J. Miller

, page two Decem:er 19, 1980 We hope this schedule meets with your approval. We are expediting every aspect of the submittal process but do not wish to compromise the quality or the completeness of the documentation.

Sincerely yours,

-Q \2

, , ., i ig i Ub/L ,

-Nils"J. Diaz

.. )

Professor and Director of Nuclear' Facilities j c.c. A.M. Jacobs M.J. Chanian

/