| title = Wolf Creek Generating Station - NRC Integrated Inspection Report 05000482/2018002 and Assessment Follow-Up Letter
| title = NRC Integrated Inspection Report 05000482/2018002 and Assessment Follow-Up Letter
| author name = Taylor N H
| author name = Taylor N
| author affiliation = NRC/RGN-IV
| author affiliation = NRC/RGN-IV
| addressee name = Heflin A C
| addressee name = Heflin A
| addressee affiliation = Wolf Creek Nuclear Operating Corp
| addressee affiliation = Wolf Creek Nuclear Operating Corp
| docket = 05000482
| docket = 05000482
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:ust 12, 2018
[[Issue date::August 12, 2018]]


Mr. Adam C. Heflin, President and Chief Executive Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839
==SUBJECT:==
WOLF CREEK GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000482/2018002 AND ASSESSMENT FOLLOW-UP LETTER


SUBJECT: WOLF CREEK GENERATING STATION
==Dear Mr. Heflin:==
- NRC INTEGRATED INSPECTION REPORT 05000482/2018 00 2 AND ASSESSMENT FOLLOW
On June 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Wolf Creek Generating Station. On July 17, 2018, the NRC inspectors discussed the results of this inspection with Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.
-UP LETTER


==Dear Mr. Heflin:==
NRC inspectors documented two findings of very low safety significance (Green) in this report.
On June 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Wolf Creek Generating Station. On July 17, 2018, the NRC inspectors discussed the results of this inspection with Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President , and other members of your staff. The results of this inspection are documented in the enclosed report. NRC inspectors documented two findings of very low safety significance (Green) in this report. Both of these findings involved violations of NRC requirements. Additionally, NRC inspectors documented one Severity Level IV violation with no associated finding. The NRC is treating these violation s as non-cited violation s (NCV) consistent with Section 2.3.2 of the Enforcement Policy. If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S.
 
Both of these findings involved violations of NRC requirements. Additionally, NRC inspectors documented one Severity Level IV violation with no associated finding. The NRC is treating these violations as non-cited violations (NCV) consistent with Section 2.3.2 of the Enforcement Policy.


Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555
If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at the Wolf Creek Generating Station.
-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at the Wolf Creek Generating Station
. If you disagree with a cross
-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S.


Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Wolf Creek Generating Station.
-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Wolf Creek Generating Station
. In the 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006, Agencywide Documents Access and Management System (ADAMS) ML18052A345), the NRC identified a cross
-cutting theme in the safety conscious work environment (SCWE) area.


On August 8, 2018, the NRC documented an assessment of the licensee's progress in addressing the SCWE theme in NRC Inspection Report 05000482/201800 7 (ADAMS ML18218A265). The inspectors determined that while the licensee had taken some corrective actions to address the work environment challenges on site, these actions had not yet been effective to improve the SCWE in the maintenance support group. Based on this conclusion and the previously documented finding with a cross
In the 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006, Agencywide Documents Access and Management System (ADAMS) ML18052A345), the NRC identified a cross-cutting theme in the safety conscious work environment (SCWE) area. On August 8, 2018, the NRC documented an assessment of the licensees progress in addressing the SCWE theme in NRC Inspection Report 05000482/2018007 (ADAMS ML18218A265). The inspectors determined that while the licensee had taken some corrective actions to address the work environment challenges on site, these actions had not yet been effective to improve the SCWE in the maintenance support group.
-cutting aspect related to the inconsistent implementation of SCWE policy (S.1)
, as discussed in NRC Inspection Report 05000482/2017004 (ADAMS ML18043A114), the NRC determined that a theme in the SCWE area continues to exist. The NRC will continue to monitor your staff's progress in implementing corrective actions for this theme.


This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading
Based on this conclusion and the previously documented finding with a cross-cutting aspect related to the inconsistent implementation of SCWE policy (S.1), as discussed in NRC Inspection Report 05000482/2017004 (ADAMS ML18043A114), the NRC determined that a theme in the SCWE area continues to exist. The NRC will continue to monitor your staffs progress in implementing corrective actions for this theme.
-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding.


"
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.


Sincerely,/RA/ Nicholas H. Taylor, Chief Project Branch B Division of Reactor Projects Docket No. 50
Sincerely,
-482 License No. NPF-42  
/RA/
Nicholas H. Taylor, Chief Project Branch B Division of Reactor Projects Docket No. 50-482 License No. NPF-42


===Enclosure:===
===Enclosure:===
Inspection Report 05000482/2018002 w/Attachment s: 1. Documents Reviewed 2 Request for Information Inservice Inspection 3. Request for Information Occupational Radiation Safety Inspection 4. Request for Information Quarterly Baseline Inspection
Inspection Report 05000482/2018002 w/Attachments:
1. Documents Reviewed 2 Request for Information Inservice Inspection 3. Request for Information O


1 Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number:
==Inspection Report==
05000482 License Number:
Docket Number: 05000482 License Number: NPF-42 Report Number: 05000482/2018002 Enterprise Identifier: I-2018-002-0012 Licensee: Wolf Creek Nuclear Operating Corporation Facility: Wolf Creek Generating Station Location: Burlington, Kansas Inspection Dates: April 1, 2018 to June 30, 2018 Inspectors: D. Dodson, Senior Resident Inspector F. Thomas, Resident Inspector C. Alldredge, Health Physicist I. Anchondo, Reactor Inspector J. Melfi, Project Engineer J. ODonnell, CHP, Health Physicist Approved By: N. Taylor Chief, Project Branch B Division of Reactor Projects 1 Enclosure
NPF-42 Report Number:
05000482/2018002 Enterprise Identifier:
I-2018-002-0012 Licensee: Wolf Creek Nuclear Operating Corporation Facility: Wolf Creek Generating Station Location: Burlington, Kansas Inspection Dates:
April 1, 2018 to June 30, 2018 Inspectors:
D. Dodson, Senior Resident Inspector F. Thomas, Resident Inspector C. Alldredge, Health Physicist I. Anchondo, Reactor Inspecto r J. Melfi, Project Engineer J. O'Donnell, CHP, Health Physicist Approved By:
N. Taylor Chief, Project Branch B Division of Reactor Projects 2


=SUMMARY=
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensee's performance by conducting an Integrated Inspection at Wolf Creek Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an Integrated Inspection at Wolf Creek Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC-identified and self-revealed findings, violations, and additional items are summarized in the table below.
 
List of Findings and Violations Announcement of an NRC Inspectors Presence by Station Personnel Cornerstone      Significance                                        Cross-cutting  Report Aspect          Section Not              Severity Level IV                                  Not            71111.20 -
Applicable        NCV                                                Applicable      Refueling 05000482/2018002-01                                                and Other Closed                                                              Outage Activities The inspectors identified a Severity Level IV non-cited violation (NCV) of 10 CFR 50.70(b)(4),
Inspections, associated with the licensees failure to ensure the arrival and presence of NRC Inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility without a specific request by the NRC inspector.


NRC-identified and self-revealed findings, violations, and additional items are summarized in the table below.
Specifically, a contract radiation protection technician entered the spent fuel pool building where the resident inspector was present and observing core offload activities, and the technician informed members of a work crew of the whereabouts of an NRC radiation protection inspection team without being requested to do so; this impacts the NRCs ability to regulate and perform unannounced inspections.


List of Findings and Violations Announcement of an NRC Inspector's Presence by Station Personnel Cornerstone Significance Cross-cutting Aspect Report Section Not Applicable Severity Level IV NCV 05000482/2018002
Failure to Maintain Adequate Pressurization of the Control Room Envelope Cornerstone       Significance                                       Cross-cutting Report Aspect         Section Mitigating        Green                                              [H.3] -        71152 -
-0 1 Closed   Not Applicable 71111.20 - Refueling and Other Outage Activities The inspectors identified a Severity Level IV non-cited violation (NCV) of 10 CFR 50.70(b)(4), "Inspections," associated with the licensee's failure to ensure the arrival and presence of NRC Inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility without a specific request by the NRC inspector.
Systems          NCV 05000482/2018002-02                            Human          Problem Closed                                             Performance, Identification Change          and Management      Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion III, Design Control, was identified when the licensee failed to adequately recognize that the cable spreading room floor was a control building ventilation isolation boundary. Specifically, the licensee cut openings in the floor/ceiling between the 2,032 foot and 2,016 foot elevations of the control building and the impact on the control room envelopes ability to pressurize was not recognized. This was a primary contributor to the train B control room emergency ventilation system being unable to maintain the appropriate pressure in the control room envelope.


Specifically, a contract radiation protection technician entered the spent fuel pool buildin g where the resident inspector was present and observing core offload activities
Failure to Adequately Implement Instrumentation and Controls Surveillance Procedures Cornerstone     Significance                                 Cross-cutting       Report Aspect             Section Initiating      Green                                         [H.2] - Human       71152 -
, and the technician informed members of a work crew of the whereabouts of an NRC radiation protection inspection team without being requested to do so; this impacts the NRC's ability to regulate and perform unannounced inspections. Failure to Maintain Adequate Pressurization of the Control Room Envelope Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems  Green NCV 05000482/2018002
Events          NCV 05000482/2018002-03                      Performance,       Problem Closed                                        Field Presence      Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings, was identified when the licensee failed to adequately implement surveillance procedures that affected safety-related equipment and plant stability. Specifically, the licensee failed to adequately implement testing and calibration procedures for pressurizer level instrumentation. This resulted in two letdown isolation signals, securing of pressurizer heaters, and a pressurizer level transient on March 29, 2018.
-0 2 Closed [H.3] - Human Performance , Change Management 71152 - Problem Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion III, "Design Control," was identified when the licensee failed to adequately recognize that the cable spreading room floor was a control building ventilation isolation boundary. Specifically, the licensee cut openings in the floor/ceiling between the 2
,032 foot and 2
,016 foot elevations of the control building and the impact on the control room envelope's ability to pressurize was not recognized. This was a primary contributor to the train B control room emergency ventilation system being unable to maintain the appropriate pressure in the control room envelope.


3 Failure to Adequately Implement Instrumentation and Controls Surveillance Procedures Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events  Green NCV 05000482/2018002
=PLANT STATUS=
-0 3 Closed [H.2] - Human Performance , Field Presence 71152 - Problem Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion V , "Instructions, Procedures, and Drawings," was identified when the licensee failed to adequately implement surveillance procedures that affected safety-related equipment and plant stability. Specifically, the licensee failed to adequately implement testing and calibration procedures for pressurizer level instrumentation. This resulted in two letdown isolation signals, securing of pressurizer heaters , and a pressurizer level transient on March 29, 2018.


4
Wolf Creek Generating Station began the inspection period shutdown for Refueling Outage 22.


=PLANT STATUS=
The reactor was restarted on May 17, 2018, and power ascension was commenced. The unit was returned to approximately rated thermal power on May 21, 2018, and remained at or near rated thermal power for the remainder of the inspection period.


Wolf Creek Generating Station began the inspection period shutdown for Refueling Outage 22. The reactor was restarted on May 17, 2018, and power ascension was commenced. The unit was returned to approximately rated thermal power on May 21, 2018, and remained at or near rated thermal power for the remainder of the inspection period. INSPECTION SCOPES Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/
==INSPECTION SCOPES==
reading-rm/doc-collections/insp
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/
-manual/inspection
reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program
-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, "Light
- Operations Phase. The inspectors performed plant status activities described in Inspection Manual Chapter 2515 Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
-Water Reactor Inspection Program  
- Operations Phase.The inspectors performed plant status activities described in Inspection Manual Chapter 2515 Appendix D, "Plant Status
," and conducted routine reviews using IP 71152, "Problem Identification and Resolution.The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.


==REACTOR SAFETY==
==REACTOR SAFETY==
71111.01-Adverse Weather Protection Summer Readiness (1 Sample)
The inspectors evaluated summer readiness of offsite and alternate alternating current (AC) power systems
. 71111.04-Equipment Alignment Partial Walkdown (2 Samples)  The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
  (1) Essential service water train B on June 20, 2018 (2) Auxiliary feedwater train B on June 26, 2018
. Complete Walkdown (1 Sample)  The inspectors evaluated system configurations during a complete walkdown of the spent fuel pool cooling system April 8 through April 15, 2018
.


5 71111.05AQ
===71111.01Adverse Weather Protection    Summer Readiness ===
-Fire Protection Annual/Quarterly Quarterly Inspection (6 Samples)  The inspectors evaluated fire protection program implementation in the following selected areas: (1) Volume control tank and volume control tank valve compartment, fire area A
{{IP sample|IP=IP 71111.01|count=1}}
-8 on April 21, 2018 (2) Reactor building, elevation 2,000 feet, fire areas RB
The inspectors evaluated summer readiness of offsite and alternate alternating current (AC)power systems.
-1 and RB-2 on May 16, 2018 (3) Reactor building, elevation 2,026 feet, fire areas RB
 
-2, RB-3, RB-4, RB-7, and RB-8 on May 16, 2018 (4) Reactor building, elevation 2,047 feet, fire areas RB
===71111.04Equipment Alignment    Partial Walkdown ===
-5 and RB-10 on May 16, 2018 (5) Reactor building, elevation 2,068 feet 8 inches, fire areas RB
{{IP sample|IP=IP 71111.04|count=2}}
-6 and RB-10 on May 16, 2018 (6) Fuel pool heat exchanger rooms and general area, elevation 2,000 feet, fire areas F
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
-1, F-2, and F-3 on May 31, 2018
: (1) Essential service water train B on June 20, 2018
. 71111.06-Flood Protection Measures Cables (Partial Sampl e) The inspectors evaluated cable submergence protection in essential service water electrical manhole MHE1A on June 18, 2018
: (2) Auxiliary feedwater train B on June 26, 2018.
. 71111.08-Inservice Inspection Activities (1 Sample)
 
  (1) Nondestructive Examination Activities and Welding Activities The inspector directly observed the following nondestructive examinations:
===Complete Walkdown (1 Sample)===
SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Reactor Vessel Head Control Rod Drive Mechanism Penetration Numbers 1, 2, 3, 4, 10, 14, 17, 18, 24, 25, 26, 27, 30, 32, 33, 35, 38, 43, 54, 66, 71, and 74.
The inspectors evaluated system configurations during a complete walkdown of the spent    fuel pool cooling system April 8 through April 15, 2018.
 
===71111.05AQFire Protection Annual/Quarterly Quarterly Inspection ===
{{IP sample|IP=IP 71111.05|count=6}}
The inspectors evaluated fire protection program implementation in the following selected areas:
: (1) Volume control tank and volume control tank valve compartment, fire area A-8 on April 21, 2018
: (2) Reactor building, elevation 2,000 feet, fire areas RB-1 and RB-2 on May 16, 2018
: (3) Reactor building, elevation 2,026 feet, fire areas RB-2, RB-3, RB-4, RB-7, and RB-8 on May 16, 2018
: (4) Reactor building, elevation 2,047 feet, fire areas RB-5 and RB-10 on May 16, 2018
: (5) Reactor building, elevation 2,068 feet 8 inches, fire areas RB-6 and RB-10 on May 16, 2018
: (6) Fuel pool heat exchanger rooms and general area, elevation 2,000 feet, fire areas F-1, F-2, and F-3 on May 31, 2018.
 
===71111.06Flood Protection Measures Cables (Partial Sample)
The inspectors evaluated cable submergence protection in essential service water electrical manhole MHE1A on June 18, 2018.
 
71111.08Inservice Inspection Activities ===
{{IP sample|IP=IP 71111.06|count=1}}
: (1) Nondestructive Examination Activities and Welding Activities The inspector directly observed the following nondestructive examinations:
SYSTEM             WELD IDENTIFICATION                     EXAMINATION TYPE Reactor Vessel Control Rod Drive Mechanism                 Visual (VE)
Head              Penetration Numbers 1, 2, 3, 4, 10, 14, 17, 18, 24, 25, 26, 27, 30, 32, 33, 35, 38, 43, 54, 66, 71, and 74.


Visual (VE)
The inspector reviewed records for the following nondestructive examinations:
The inspector reviewed records for the following nondestructive examinations:
SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Feedwater System Weld Number AE F015 and AE-04-S010-C (Data Sheet Number AGF_012) Ultrasonic
SYSTEM           WELD IDENTIFICATION                     EXAMINATION TYPE Feedwater         Weld Number AE-04-F015 and             Ultrasonic System            AE-04-S010-C (Data Sheet Number AGF_012)
SYSTEM            WELD IDENTIFICATION                      EXAMINATION TYPE Feedwater        Steam Generator A Inner Radius -      Ultrasonic System            Weld Number EBB01A-11-IR (Data Sheet Number AJS_010)
Steam            Steam Weld Number EBB01A-                Ultrasonic Generator        STEAM-3-W (Data Sheet Number RAL_002)
Steam            Steam Weld Number EBB01A-                Ultrasonic Generator        STEAM-6-W (Data Sheet Number RAL_003)
Steam            Weld Number EBB01A-11-W                  Ultrasonic Generator        (Data Sheet Number RAL_004)
Steam            Steam Weld Number EBB01A-                Ultrasonic Generator        STEAM-2-W (Data Sheet Number RAL_005)
: (2) Vessel Upper Head Penetration Inspection Activities The inspector reviewed the results of the licensees bare metal visual inspection of the reactor vessel upper head penetrations. The inspector also reviewed whether the required inspection coverage was achieved and whether limitations were properly recorded. The inspector reviewed whether the personnel performing the inspection were certified examiners to their respective nondestructive examination method.


6 SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Feedwater System Steam Generator "A" Inner Radius
On May 10, 2018, the licensee was granted verbal approval for performing an alternative volumetric examination and leak path assessment in lieu of the visual examination requirements of Note 1 of Table 1, American Society of Mechanical Engineers Code Case N-729-4. Although not indicative of possible nozzle leakage, the licensee was not able to perform the required visual examination of penetration number one due to a hard substance obstructing the annulus. At the time of the inspection, the licensee had satisfactorily completed the ultrasonic inspection and leak path assessment. The licensee had also cleaned the annulus of penetration number one.
- Weld Number EBB01A IR  (Data Sheet Number AJS_010) Ultrasonic Steam Generator Steam Weld Number EBB01A-STEAM-3-W (Data Sheet Number RAL_002) Ultrasonic Steam Generator Steam Weld Number EBB01A-STEAM-6-W (Data Sheet Number RAL_003) Ultrasonic Steam Generator Weld Number EBB01A W (Data Sheet Number RAL_004) Ultrasonic Steam Generator Steam Weld Number EBB01A-STEAM-2-W (Data Sheet Number RAL_005) Ultrasonic (2) Vessel Upper Head Penetration Inspection Activities The inspector reviewed the results of the licensee's bare metal visual inspection of the reactor vessel upper head penetrations. The inspector also reviewed whether the required inspection coverage was achieved and whether limitations were properly recorded.
: (3) Boric Acid Corrosion Control Inspection Activities The Inspector evaluated the licensees boric acid control program performance.
: (4) Steam Generator (SG) Tube Inspection Activities The inspector reviewed the SG tube eddy current examination scope and expansion criteria to determine whether these criteria met technical specification requirements, Electric Power Research Institute (EPRI) guidelines, and commitments made to the NRC. The inspector also reviewed whether the eddy current inspection scope included areas of degradations that were known to represent potential eddy current test challenges such as the top of tube sheet, tube support plates, and U-bends. The inspector confirmed that no repairs were required at the time of the inspection and that the licensees inspection scope was appropriate.
: (5) Identification and Resolution of Problems (71111.08-02.05)
The inspector reviewed 14 condition reports, which dealt with inservice inspection activities, and found the corrective actions for inservice inspection issues were appropriate.


The inspector reviewed whether the personnel performing the inspection were certified examiners to their respective nondestructive examination method.
===71111.11Licensed Operator Requalification Program and Licensed Operator Performance    Operator Requalification ===
{{IP sample|IP=IP 71111.11|count=1}}
The inspectors observed and evaluated licensed operator simulator requalification exams on


On May 10, 2018, the licensee was granted verbal approval for performing an alternative volumetric examination and leak path assessment in lieu of the visual examination requirements of Note 1 of Table 1, American Society of Mechanical Engineers Code  Case N-729-4. Although not indicative of possible nozzle leakage, the licensee was not able to perform the required visual examination of penetration number one due to a hard substance obstructing the annulus. At the time of the inspection, the licensee had satisfactorily completed the ultrasonic inspection and leak path assessment. The licensee had also cleaned the annulus of penetration number one.
===May 31, 2018.
Operator Performance (1 Sample)===
The inspectors observed and evaluated operator performance during energization of the XNB01 transformer and NB01 safety-related bus on May 2, 2018, and performance of STS AE-211, Main Feed Reg Valve Inservice Valve Test, during startup activities on May 17, 2018.


  (3) Boric Acid Corrosion Control Inspection Activities The Inspector evaluated the licensee's boric acid control program performanc e.  (4) Steam Generator (SG) Tube Inspection Activities The inspector reviewed the SG tube eddy current examination scope and expansion criteria to determine whether these criteria met technical specification requirements, Electric Power Research Institute (EPRI) guidelines, and commitments made to the NRC.
===71111.12Maintenance Effectiveness    Routine Maintenance Effectiveness ===
{{IP sample|IP=IP 71111.12|count=1}}
The inspectors evaluated the effectiveness of routine maintenance activities associated with the spent fuel pool cooling and cleanup system level instrumentation reading erratically on May 24, 2017.


The inspector also reviewed whether the eddy current inspection scope included areas of degradations that were known to represent potential eddy current test challenges such as the top of tube sheet, tube support plates, and U
===71111.13Maintenance Risk Assessments and Emergent Work Control ===
-bends. The inspector confirmed that no repairs were required at the time of the inspection and that the licensee's inspection scope was appropriate.
{{IP sample|IP=IP 71111.13|count=3}}
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
: (1) Elevated risk during lowered inventory and preparations for reactor head lift on April 6, 2018, and refueling water storage tank unavailability on April 7, 2018
: (2) Elevated spent fuel pool cooling risk while defueled on April 19 and April 21, 2018
: (3) Elevated risk during Mode 5 while implementing low temperature overpressure protection controls and emergency core cooling pump testing on May 8 and 9, 2018.


(5) Identification and Resolution of Problems (71111.08
===71111.15Operability Determinations and Functionality Assessments ===
-02.05)  The inspector reviewed 14 condition reports
{{IP sample|IP=IP 71111.15|count=4}}
, which dealt with inservice inspection activities
The inspectors evaluated the following operability determinations and functionality assessments:
, and found the corrective actions for inservice inspection issues were appropriate
: (1) Operability evaluation of safety injection and accumulator to loop 1 check valve bonnet bolting issues on April 22, 2018
. 71111.11-Licensed Operator Requalification Program and Licensed Operator Performance Operator Requalification (1 Sample) The inspectors observed and evaluated licensed operator simulator requalification exams on May 31, 2018
: (2) Operability evaluation of start-up transformer XMR01 power factor testing on April 25, 2018
. Operator Performance (1 Sample) The inspectors observed and evaluated operator performance during energization of the XNB01 transformer and NB01 safety
: (3) Operability evaluation of thermal sleeve inspection results on May 8, 2018
-related bus on May 2, 2018, and performance of STS AE
: (4) Operability evaluation of train A safety injection pump for motor current reading higher than name plate rating on May 11, 2018.
-211, "Main Feed Reg Valve Inservice Valve Test," during startup activities on May 17, 2018.


71111.12-Maintenance Effectiveness Routine Maintenance Effectiveness (1 Sample)  The inspectors evaluated the effectiveness of routine maintenance activities associated with the spent fuel pool cooling and cleanup system level instrumentation reading erratically on May 24, 2017
===71111.18Plant Modifications ===
. 71111.13-Maintenance Risk Assessments and Emergent Work Control (3 Samples)  The inspectors evaluated the risk assessments for the following planned and emergent work activities
{{IP sample|IP=IP 71111.18|count=1}}
:  (1) Elevated risk during lowered inventory and preparations for reactor head lift on April 6, 2018, and refueling water storage tank unavailability on April 7, 2018 (2) Elevated spent fuel pool cooling risk while defueled on April 19 and April 21, 2018 (3) Elevated risk during Mode 5 while implementing low temperature overpressur e protection controls and emergency core cooling pump testing on May 8 and 9, 2018. 71111.15-Operability Determinations and Functionality Assessments (4 Samples)  The inspectors evaluated the following operability determinations and functionality assessments:
The inspectors evaluated the spent fuel pool alternate decay heat removal permanent modification.
  (1) Operability evaluation of safety injection and accumulator to loop 1 check valve bonnet bolting issues on April 22, 2018 (2) Operability evaluation of start-u p transformer XMR01 power factor testing on April 25, 2018 8 (3) Operability evaluation of thermal sleeve inspection results on May 8, 2018 (4) Operability evaluation of train A safety injection pump for motor current reading higher than name plate rating on May 11, 2018
.


71111.18-Plant Modifications (1 Sample) The inspectors evaluated the s pen t fuel pool alternate decay heat removal permanent modification
===71111.19Post Maintenance Testing ===
.
{{IP sample|IP=IP 71111.19|count=6}}
The inspectors evaluated the following post maintenance tests:
: (1) Start-up transformer XMR01 testing after switchyard modification and transmission line modification on April 27, 2018
: (2) Emergency diesel generator train B 24-hour testing following outage maintenance on May 1, 2018
: (3) Centrifugal charging pump train A testing after completion of seal maintenance on May 9, 2018
: (4) STS EM-100A, Safety Injection Pump A Inservice Pump Test, following A safety injection pump replacement work on May 11, 2018
: (5) Train B spent fuel pool cooling pump testing after boric acid cleaning and oil sample on May 31, 2018
: (6) STS IC-503B, Channel Calibration Pressurizer Level, following emergent bistable card replacement on June 19, 2018.


71111.19-Post Maintenance Testing (6 Samples)  The inspectors evaluated the following post maintenance tests:  (1) Start-u p transformer XMR01 testing after switchyard modification and transmission line modification on April 27, 2018  (2) Emergency diesel generator train B 24-hour testing following outage maintenance on May 1, 2018 (3) Centrifugal charging pump train A testing after completion of seal maintenance on May 9, 2018  (4) STS EM-100A, "Safety Injection Pump 'A' Inservice Pump Test," following A safety injection pump replacement work on May 11, 2018  (5) Train B spent fuel pool cooling pump testing after boric acid cleaning and oil sample on May 31, 2018 (6) STS IC-503B, "Channel Calibration Pressurizer Level," following emergent bistable card replacement on June 19, 2018
===71111.20Refueling and Other Outage Activities ===
. 71111.20-Refueling and Other Outage Activities (1 Sample)  The inspectors evaluated Refueling Outage 22 activities from April 1 to May 18 , 2018.
{{IP sample|IP=IP 71111.20|count=1}}
The inspectors evaluated Refueling Outage 22 activities from April 1 to May 18, 2018.


The inspectors completed inspection procedure Sections 03.01.d and 03.01.e.
The inspectors completed inspection procedure Sections 03.01.d and 03.01.e.


71111.22-Surveillance Testing The inspectors evaluated the following surveillance tests:
===71111.22Surveillance Testing The inspectors evaluated the following surveillance tests:   Routine ===
Routine (1 Sample)  (1) STS KJ-001B, "Integrated D/G and Safeguard Actuation Test  
{{IP sample|IP=IP 71111.22|count=1}}
- Train B," on May 11, 2018 In-service (1 Sample) (1) STS EM-003A, "ECCS (CCP) Flow Balance and CCP Comprehensive Test," on May 2, 2018 Reactor Coolant System Leak Detection (1 Sample) (1) STS BB-006, "RCS Water Inventory Balance Using the NPIS Computer
: (1) STS KJ-001B, Integrated D/G and Safeguard Actuation Test - Train B, on May 11, 2018
," on June 27, 2018 Containment Isolation Valve (1 Sample) (1) STS PE-128, "Local Leak Rate Test (LLRT) of Penetration P-29 ," on April 24, 2018
 
===In-service (1 Sample)===
: (1) STS EM-003A, ECCS (CCP) Flow Balance and CCP Comprehensive Test, on
 
===May 2, 2018 Reactor Coolant System Leak Detection (1 Sample)===
: (1) STS BB-006, RCS Water Inventory Balance Using the NPIS Computer, on June 27, 2018
 
===Containment Isolation Valve (1 Sample)===
: (1) STS PE-128, Local Leak Rate Test (LLRT) of Penetration P-29, on April 24,


==RADIATION SAFETY==
==RADIATION SAFETY==
71124.01-Radiological Hazard Assessment and Exposure Controls Radiological Hazard Assessment (1 Sample)
 
The inspectors evaluated radiological hazards assessments and controls
===71124.01Radiological Hazard Assessment and Exposure Controls   Radiological Hazard Assessment ===
. Instructions to Workers (1 Sample)
{{IP sample|IP=IP 71124.01|count=1}}
The inspectors evaluated worker instructions
The inspectors evaluated radiological hazards assessments and controls.
. Contamination and Radioactive Material Control (1 Sample)
 
The inspectors evaluated contamination and radioactive material controls
===Instructions to Workers (1 Sample)===
. Radiological Hazards Control and Work Coverage (1 Sample)
The inspectors evaluated worker instructions.
The inspectors evaluated radiological hazards control and work coverage
 
. High Radiation Area and Very High Radiation Area Controls (1 Sample)
===Contamination and Radioactive Material Control (1 Sample)===
The inspectors evaluated risk
The inspectors evaluated contamination and radioactive material controls.
-significant high radiation area and very high radiation area controls. Radiation Worker Performance and Radiation Protection Technician Proficiency (1 Sample)
 
The inspectors evaluated radiation worker performance and radiation protection technician proficiency
===Radiological Hazards Control and Work Coverage (1 Sample)===
. 71124.02-Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls Implementation of ALARA and Radiological Work Controls (1 Sample)
The inspectors evaluated radiological hazards control and work coverage.
 
High Radiation Area and Very High Radiation Area Controls (1 Sample)
The inspectors evaluated risk-significant high radiation area and very high radiation area controls.
 
Radiation Worker Performance and Radiation Protection Technician Proficiency (1 Sample)
The inspectors evaluated radiation worker performance and radiation protection technician proficiency.
 
===71124.02Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls   Implementation of ALARA and Radiological Work Controls ===
{{IP sample|IP=IP 71124.02|count=1}}
The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:
The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:
  (1) RWP 180021, "Cartridge Filter Change
: (1) RWP 180021, Cartridge Filter Change-Out in Aux and RW Buildings
-Out in Aux and RW Buildings" (2) RWP 182601, "Routine Outage Access (No Locked High Radiation Areas)"
: (2) RWP 182601, Routine Outage Access (No Locked High Radiation Areas)
(3) RWP 182300, "Maintenance Support" 10 (4) RWP 183220, "Primary S/G Eddy Current RWP" (5) RWP 184207, "RCP Team Seal Replacement on C & D RCP's" (6) RWP 184420, "Scaffolding Activities RF22" (7) RWP 184482, "Canopy Seal Clamp Activities Disassembly" Radiation Worker Performance (1 Sample)
: (3) RWP 182300, Maintenance Support
: (4) RWP 183220, Primary S/G Eddy Current RWP
: (5) RWP 184207, RCP Team Seal Replacement on C & D RCPs
: (6) RWP 184420, Scaffolding Activities RF22
: (7) RWP 184482, Canopy Seal Clamp Activities Disassembly
 
===Radiation Worker Performance (1 Sample)===
The inspectors evaluated radiation worker and radiation protection technician performance.
The inspectors evaluated radiation worker and radiation protection technician performance.


==OTHER ACTIVITIES==
==OTHER ACTIVITIES - BASELINE==
- BASELINE  71151-Performance Indicator Verification (4 Samples)  The inspectors verified licensee performance indicators submittals listed below:   (1) BI01: Reactor Coolant System (RCS) Specific Activity Sample (04/01/2017-03/31/2018) (2) BI02: RCS Leak Rate Sample (04/01/2017
 
-03/31/2018)
===71151Performance Indicator Verification ===
  (3) OR01: Occupational Exposure Control Effectiveness Sample (04/01/2017
{{IP sample|IP=IP 71151|count=4}}
-3/30/2018)
The inspectors verified licensee performance indicators submittals listed below:
  (4) PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (04/01/2017
: (1) BI01: Reactor Coolant System (RCS) Specific Activity Sample (04/01/2017-03/31/2018)
-03/30/2018
: (2) BI02: RCS Leak Rate Sample (04/01/2017-03/31/2018)
). 71152-Problem Identification and Resolution Semiannual Trend Review (1 Sample)
: (3) OR01: Occupational Exposure Control Effectiveness Sample (04/01/2017-3/30/2018)
The inspectors reviewed the licensee's corrective action program for trends that might be indicative of a more significant safety issue.
: (4) PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (04/01/2017-03/30/2018).


Annual Follow
===71152Problem Identification and Resolution    Semiannual Trend Review ===
-up of Selected Issue s (2 Samples)  The inspectors reviewed the licensee's implementation of its corrective action program related to the following issues:
{{IP sample|IP=IP 71152|count=1}}
  (1) On March 5, 2018, Condition Report 120056 documented that the required control room pressurization could not be developed
The inspectors reviewed the licensees corrective action program for trends that might be indicative of a more significant safety issue.
.  (2) On March 29, 2018, Condition Report 120807 documented that incorrect test switches were operated during a performance of STS IC
-503B, "Channel Calibration Pressurizer Level."


INSPECTION RESULTS Announcement of an NRC Inspector's Presence by Station Personnel Cornerstone Severity Cross-cutting Aspect Report Section Not Applicable Severity Level IV NCV  05000482/2018002
===Annual Follow-up of Selected Issues (2 Samples)===
-0 1  Closed  Not Applicable 71111.20 - Refueling and Other Outage Activities The inspectors identified a Severity Level IV NCV of 10 CFR 50.70(b)(4), "Inspections," associated with the licensee's failure to ensure the arrival and presence of NRC Inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility without a specific request by the NRC inspector.
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
: (1) On March 5, 2018, Condition Report 120056 documented that the required control room pressurization could not be developed.
: (2) On March 29, 2018, Condition Report 120807 documented that incorrect test switches were operated during a performance of STS IC-503B, Channel Calibration Pressurizer Level.


Specifically, a contract radiation protection technician entered the spent fuel pool building where the resident inspector was present and observing core offload activities
==INSPECTION RESULTS==
, and the technician informed members of a work crew of the whereabouts of an NRC radiation protection inspection team without being requested to do so; this impact ed the NRC's ability to regulate and perform unannounced inspections.
Announcement of an NRC Inspectors Presence by Station Personnel Cornerstone              Severity                  Cross-cutting Aspect    Report Section Not Applicable          Severity Level IV        Not Applicable


Description
==71111.20 - Refueling                          NCV                                            ==
:  On April 10, 2018, the resident inspector was in the spent fuel pool building observing fuel movement activities in support of core off
and Other Outage 05000482/2018002-01                              Activities Closed The inspectors identified a Severity Level IV NCV of 10 CFR 50.70(b)(4), Inspections, associated with the licensees failure to ensure the arrival and presence of NRC Inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility without a specific request by the NRC inspector. Specifically, a contract radiation protection technician entered the spent fuel pool building where the resident inspector was present and observing core offload activities, and the technician informed members of a work crew of the whereabouts of an NRC radiation protection inspection team without being requested to do so; this impacted the NRCs ability to regulate and perform unannounced inspections.
-load for Refueling Outage 22. NRC radiation protection inspectors were also onsite conducting inspection activities. At approximately 11: 00 a.m., the resident inspector observed a BHI contractor enter the spent fuel pool building and announce to members of a work crew that NRC inspectors had entered the radiologically controlled area (containment) and to be "mindful and careful."


The resident inspector spoke with the visiting NRC radiation protection inspectors later that afternoon and confirmed they had entered containment at approximately 10
=====Description:=====
: 30 a.m. on April 10, 2018, and had not requested that their presence be announced. The resident inspector noted that his location in the spent fuel pool building
On April 10, 2018, the resident inspector was in the spent fuel pool building observing fuel movement activities in support of core off-load for Refueling Outage 22. NRC radiation protection inspectors were also onsite conducting inspection activities. At approximately 11:00 a.m., the resident inspector observed a BHI contractor enter the spent fuel pool building and announce to members of a work crew that NRC inspectors had entered the radiologically controlled area (containment) and to be mindful and careful.
, where the announcement of NRC inspectors had occurred
, was in close proximity to where the other NRC inspectors were entering containment.


Corrective Actions: On April 25, 2018, the licensee entered this issue into the corrective action program. Additional corrective actions included the performance of a stand down with all BHI employees to inform them that conduct that alerts workers to the presence of the NRC, or any oversight group, is prohibited; the licensee also published an article in a site newsletter explaining the requirements of 10 CFR 50.70. The article informed site personnel that a violation had occurred and described site management expectations regarding appropriate conduct.
The resident inspector spoke with the visiting NRC radiation protection inspectors later that afternoon and confirmed they had entered containment at approximately 10:30 a.m. on April 10, 2018, and had not requested that their presence be announced. The resident inspector noted that his location in the spent fuel pool building, where the announcement of NRC inspectors had occurred, was in close proximity to where the other NRC inspectors were entering containment.


Corrective Action References: Condition Reports 122359 and 122375.
Corrective Actions: On April 25, 2018, the licensee entered this issue into the corrective action program. Additional corrective actions included the performance of a stand down with all BHI employees to inform them that conduct that alerts workers to the presence of the NRC, or any oversight group, is prohibited; the licensee also published an article in a site newsletter explaining the requirements of 10 CFR 50.70. The article informed site personnel that a violation had occurred and described site management expectations regarding appropriate conduct.


Performance Assessment: The inspectors determined this violation was associated with a minor performance deficiency.
Corrective Action References: Condition Reports 122359 and 122375.
 
=====Performance Assessment:=====
The inspectors determined this violation was associated with a minor performance deficiency.


=====Enforcement:=====
=====Enforcement:=====
The Reactor Oversight Process's significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance. Therefore, it is necessary to address this violation, which impedes the NRC's ability to regulate, using traditional enforcement to adequately deter non
The Reactor Oversight Processs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance.
-compliance.
 
Therefore, it is necessary to address this violation, which impedes the NRCs ability to regulate, using traditional enforcement to adequately deter non-compliance.
 
Severity: The finding was evaluated in accordance with the NRC's Enforcement Policy. The finding was reviewed by NRC management and because the violation was of very low safety significance, was not repetitive or willful, and was entered into the corrective action program, this violation is being treated as a Severity Level IV NCV, consistent with the NRC Enforcement Policy.


12 Severity: The finding was evaluated in accordance with the NRC's Enforcement Policy. The finding was reviewed by NRC management and because the violation was of very low safety significance, was not repetitive or willful, and was entered into the corrective action program, this violation is being treated as a Severity Level IV NCV, consistent with the NRC Enforcement Policy.
Violation: Title 10 CFR 50.70(b)(4), Inspections, requires, in part, that the licensee shall ensure that the arrival and presence of an NRC inspector, who has been properly authorized facility access as described in 10 CFR 50.70(b)(3), is not announced or otherwise communicated by its employees or contractors to other persons at the facility unless specifically requested by the NRC inspector.


Violation:  Title 10 CFR 50.70(b)(4), "Inspections," requires, in part, that the licensee shall ensure that the arrival and presence of an NRC inspector, who has been properly authorized facility access as described in 10 CFR 50.70(b)(3), is not announced or otherwise communicated by its employees or contractors to other persons at the facility unless specifically requested by the NRC inspector.
Contrary to the above, on April 10, 2018, the licensee failed to ensure that the arrival and presence of NRC inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility unless specifically requested by the NRC inspectors. Specifically, a radiation protection technician entered the spent fuel pool building and informed members of a work crew of the whereabouts of NRC radiation protection inspectors without being requested to do so.


Contrary to the above, on April 10, 2018, the licensee failed to ensure that the arrival and presence of NRC inspector s, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility unless specifically requested by the NRC inspector s. Specifically, a radiation protection technician entered the spent fuel pool building and informed members of a work crew of the whereabouts of NRC radiation protection inspectors without being requested to do so.
Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.


Enforcement Action:  This violation is being treated as a n NCV , consistent with Section 2.3.2 of the Enforcement Policy.
Observation


Observation 71152 - Problem Identification and Resolution The inspectors reviewed the licensee's progress in addressing the cross-cutting theme in the SCWE area, as discussed in the 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006, ADAMS ML18052A345). The NRC's review of the licensee's progress in addressing the SCWE theme was accomplished within the scope of the biennial problem identification and resolution inspection, which was completed on June 28, 2018. NRC Inspection Report 05000482/201800 7 (ADAMS ML18218A265), dated August 8 , 2018, discusses the results of this inspection, which concluded that actions taken to address the work environment challenges in the maintenance support group had not yet been effective.
==71152 - Problem                                                                             ==
Identification and Resolution The inspectors reviewed the licensees progress in addressing the cross-cutting theme in the SCWE area, as discussed in the 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006, ADAMS ML18052A345). The NRCs review of the licensees progress in addressing the SCWE theme was accomplished within the scope of the biennial problem identification and resolution inspection, which was completed on June 28, 2018. NRC Inspection Report 05000482/2018007 (ADAMS ML18218A265), dated August 8, 2018, discusses the results of this inspection, which concluded that actions taken to address the work environment challenges in the maintenance support group had not yet been effective.


The inspectors also considered whether there was an emerging trend associated wit h impacting the regulatory process. The inspectors noted NCV 05000482/2018002
The inspectors also considered whether there was an emerging trend associated with impacting the regulatory process. The inspectors noted NCV 05000482/2018002-01, as documented in this report, which involved announcement of an NRC inspectors presence by station personnel. The inspectors also noted that the announcement of an inspectors presence was not an isolated event. Specifically, the presence of an NRC inspector was announced by a Wolf Creek employee to a state official during a drill on February 27, 2018.
-01, as documented in this report, which involved announcement of an NRC inspector's presence by station personnel. The inspectors also noted that the announcement of an inspector's presence was not an isolated event. Specifically, the presence of an NRC inspector was announced by a Wolf Creek employee to a state official during a drill on February 27, 2018. However, the inspectors determined that no violation occurred in this case because the announcement, which was not requested by the inspector, was not made to licensee personnel and was thereby outside the NRC's regulatory authority. These issues and other reportability questions being evaluated by ongoing inspections were considered, and no emerging trend has been identified at this time.


13 The inspectors noted that four NCVs that occurred within an approximate 1 year time period relate to the licensee's understanding of the design basis and design basis implementing documents. Specifically
However, the inspectors determined that no violation occurred in this case because the announcement, which was not requested by the inspector, was not made to licensee personnel and was thereby outside the NRCs regulatory authority. These issues and other reportability questions being evaluated by ongoing inspections were considered, and no emerging trend has been identified at this time.
:  NCV 05000482/2018002
-02, "Failure to Maintain Adequate Pressurization of the Control Room Envelope
," involved a failure to ensure an implementing document
-the boundary matrix
-identified all boundary functions; this led to a failure to control a boundary and was a primary contributor to the failure to pressurize the control room envelope.


NCV 05000482/2018001
The inspectors noted that four NCVs that occurred within an approximate 1 year time period relate to the licensees understanding of the design basis and design basis implementing documents. Specifically:
-01, "Inadequate Functionality Assessment Associated with the Emergency Excess Letdown Flowpath," involved discrepancies between th e Technical Specification Bases, procedures, and the updated safety analysis report
* NCV 05000482/2018002-02, Failure to Maintain Adequate Pressurization of the Control Room Envelope, involved a failure to ensure an implementing documentthe boundary matrixidentified all boundary functions; this led to a failure to control a boundary and was a primary contributor to the failure to pressurize the control room envelope.
; these discrepancies contributed to an inadequate functionality assessment
* NCV 05000482/2018001-01, Inadequate Functionality Assessment Associated with the Emergency Excess Letdown Flowpath, involved discrepancies between the Technical Specification Bases, procedures, and the updated safety analysis report; these discrepancies contributed to an inadequate functionality assessment.
.
* NCV 05000482/2017003-02, Failure to Ensure the Design Basis was Adequately Represented in the Technical Specification Bases, involved discrepancies between the auxiliary feedwater Technical Specification Bases and the updated safety analysis report; as a result, inoperability of an auxiliary feedwater train was not recognized.
* NCV 05000482/2017002-02, Failure to Declare Train A Component Cooling Water Inoperable, related to the Technical Specification Bases not specifically identifying specific valves importance to the safety-related design functions as outlined in the updated safety analysis report; as a result, inoperability of safety-related equipment was not recognized.


NCV 05000482/2017003
In each of these cases the inspectors observed that the updated safety analysis report was not consistently being referenced when questions about the adequacy or completeness of the Technical Specification Bases were identified. The inspectors also observed that each of these NCVs represented some organizational knowledge gap concerning the design basis as outlined in the updated safety analysis report.
-02, "Failure to Ensure the Design Basis was Adequately Represented in the Technical Specification Bases
," involved discrepancies between the auxiliary feedwater Technical Specification Bases and the updated safety analysis report; as a result, inoperability of an auxiliary feedwater train was not recognized
.


NCV 05000482/2017002
Failure to Maintain Adequate Pressurization of the Control Room Envelope Cornerstone        Significance                                  Cross-cutting      Report Section Aspect Mitigating        Green                                        [H.3] - Human
-02, "Failure to Declare Train A Component Cooling Water Inoperable," related to the Technical Specification Bases not specifically identifying specific valves' importance to the safety
-related design functions as outlined in the updated safety analysis report; as a result, inoperability of safety
-related equipment was not recognized.


In each of these cases the inspectors observed that the updated safety analysis report was not consistently being referenced when questions about the adequacy or completeness of the Technical Specification Bases were identified
==71152 - Systems           NCV 05000482/2018002-02                      Performance,       Problem          ==
. The inspectors also observed that each of these NCVs represented some organizational knowledge gap concerning the design basis as outlined in the updated safety analysis report
Closed                                        Change             Identification Management         and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion III, Design Control, was identified when the licensee failed to adequately recognize that the cable spreading room floor was a control building ventilation isolation boundary. Specifically, the licensee cut openings in the floor/ceiling between the 2,032 foot and 2,016 foot elevations of the control building and the impact on the control room envelopes ability to pressurize was not recognized. This was a primary contributor to the train B control room emergency ventilation system being unable to maintain the appropriate pressure in the control room envelope.
. Failure to Maintain Adequate Pressurization of the Control Room Envelope Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2018002
-0 2 Closed [H.3] - Human Performance , Change Management 71152 - Problem Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion III, "Design Control,"
was identified when the licensee failed to adequately recognize that the cable spreading room floor was a control building ventilation isolation boundary. Specifically, the licensee cut openings in the floor/ceiling between the 2
,032 foot and 2
,016 foot elevations of the control building and the impact on the control room envelope's ability to pressurize was not recognized. This was a primary contributor to the train B control room emergency ventilation system being unable to maintain the appropriate pressure in the control room envelope.


Description
=====Description:=====
On March 5, 2018, the licensee performed Procedure STS PE
On March 5, 2018, the licensee performed Procedure STS PE-004, Aux Building and Control Room Pressure Test, Revision 16, and the train B control room emergency ventilation systems ability to pressurize the control room envelope and maintain pressure greater than or equal to 0.25 inches water gauge failed. Readings varied from nearly no measurable differential pressurerelative to outside airto approximately 0.15 inches water gauge. During this test, control building doors were not controlled.
-004, "Aux Building and Control Room Pressure Test," Revision 16, and the train B control room emergency ventilation system's ability to pressurize the control room envelope and maintain pressure greater than or equal to 0.25 inches water gauge failed. Readings varied from 14 nearly no measurable differential pressure
-relative to outside air
-to approximately 0.15 inches water gauge. During this test, control building doors were not controlled.


Later tests on March 5, 2018, which maintained control of control building doors, had results that varied between 0.18 and 0.26 inches water gauge, with an average of 0.2258 inches water gauge. Troubleshooting was performed and
Later tests on March 5, 2018, which maintained control of control building doors, had results that varied between 0.18 and 0.26 inches water gauge, with an average of 0.2258 inches water gauge. Troubleshooting was performed and, on March 6, 2018, an interim configuration associated with Design Change Package 14269, SGK05 Tech Spec Addition and Compensatory Modifications, was found to be impacting readings. Specifically, between September 17, 2017, and January 17, 2018, four approximately 2 foot by 2 foot openings were cut in the floor/ceiling between the 2,032 foot and 2,016 foot elevations of the control building to support ongoing ductwork installation.
, on March 6, 2018, an interim configuration associated with Design Change Package 14269, "SGK05 Tech Spec Addition and Compensatory Modifications," was found to be impacting readings. Specifically, between September 17, 2017, and January 17, 2018, four approximately 2 foot by 2 foot openings were cut in the floor/ceiling between the 2
,032 foot and 2
,016 foot elevations of the control building to support ongoing ductwork installation
.


On January 17, 2018, after penetrations for the modification were completed, compensatory measures consisting of steel plates covering the four floor openings were in place until ductwork installation began on February 19, 2018. These compensatory measures were put in place for fire, flood, and other functional concerns. On February 12, 2018, while t he compensatory measures were in place, the train A control room emergency ventilation system successfully pressurized the control room envelope to 0.38 inches water gauge , demonstrating that the compensatory measures were adequate for maintaining control room envelope pressurization capability when in place.
On January 17, 2018, after penetrations for the modification were completed, compensatory measures consisting of steel plates covering the four floor openings were in place until ductwork installation began on February 19, 2018. These compensatory measures were put in place for fire, flood, and other functional concerns. On February 12, 2018, while the compensatory measures were in place, the train A control room emergency ventilation system successfully pressurized the control room envelope to 0.38 inches water gauge, demonstrating that the compensatory measures were adequate for maintaining control room envelope pressurization capability when in place.


Surveillance testing was performed for trains A and B of the control room emergency ventilation system on March 15, 2018, and the control room envelope was pressurized to 0.3448 and 0.3695 inches water gauge, respectively, which met surveillance requirements. The system was restored to operable on March 16, 2018.
Surveillance testing was performed for trains A and B of the control room emergency ventilation system on March 15, 2018, and the control room envelope was pressurized to 0.3448 and 0.3695 inches water gauge, respectively, which met surveillance requirements.


The inspectors reviewed the licensee's cause evaluation, which determined that the probable causes of the issue were inadequate identification of control building ventilation isolation boundaries in WCRE
The system was restored to operable on March 16, 2018.
-35, "Boundary Matrix," Revision 0, and control of conditions during STS PE-004. Specifically, the inspectors also determined that the 2
,016 foot to 2
,032 foot elevation breaches were a primary contributor to the failure of the control room emergency ventilation system to maintain adequate control room envelope pressure. The inspectors noted that WCRE
-35, which was referenced during modification work for Design Change Package 14269, did not identify the barriers between the 2
,016 and 2 ,032 foot elevations of the control building as control building ventilation isolation boundaries.


WCRE-35 was a new document that was first approved on November 30, 2016, and was created from Attachment A, "Boundary Matrix," of AP 10-104, "Breach Authorization," Revision 35. WCRE-35 notes, "The information in the attachment has been copied directly from the procedure Attachment A, but when there were discrepancies identified the information has been verified and updated."  The inspectors determined that the creation of the new WCRE-35 document was an opportunity for the licensee to recognize the subject boundary's importance and categorize the barrier as a control building ventilation isolation boundary.
The inspectors reviewed the licensees cause evaluation, which determined that the probable causes of the issue were inadequate identification of control building ventilation isolation boundaries in WCRE-35, Boundary Matrix, Revision 0, and control of conditions during STS PE-004. Specifically, the inspectors also determined that the 2,016 foot to 2,032 foot elevation breaches were a primary contributor to the failure of the control room emergency ventilation system to maintain adequate control room envelope pressure. The inspectors noted that WCRE-35, which was referenced during modification work for Design Change Package 14269, did not identify the barriers between the 2,016 and 2,032 foot elevations of the control building as control building ventilation isolation boundaries. WCRE-35 was a new document that was first approved on November 30, 2016, and was created from A, Boundary Matrix, of AP 10-104, Breach Authorization, Revision 35.


Corrective Actions:  The licensee completed Revision 3 of WCRE
WCRE-35 notes, The information in the attachment has been copied directly from the procedure Attachment A, but when there were discrepancies identified the information has been verified and updated. The inspectors determined that the creation of the new WCRE-35 document was an opportunity for the licensee to recognize the subject boundarys importance and categorize the barrier as a control building ventilation isolation boundary.
-35 on April 16, 2018, which reflects additional control building ventilation isolation boundaries, essential reading was issued, and other actions were performed to improve control room envelope pressurization margin. Corrective Action Reference
:  Condition Report 120056.


15 Performance Assessment
Corrective Actions: The licensee completed Revision 3 of WCRE-35 on April 16, 2018, which reflects additional control building ventilation isolation boundaries, essential reading was issued, and other actions were performed to improve control room envelope pressurization margin.
: Performance Deficiency:  The failure to recognize control building ventilation isolation boundaries and meet the requirements of 10 CFR Part 50, Criterion III, "Design Control," is a performance deficiency.


Screening: The inspectors determined the performance deficiency was more than minor because it adversely affected the design control attribute of the Barrier Integrity Cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding, reactor coolant system, and containment) protect the public from radionuclide releases caused by accidents or events. Specifically, the control room emergency ventilation system's ability to maintain adequate pressurization of the control room envelope was adversely impacted after an ongoing ventilation modification breached the floor with out compensatory measures in place.
Corrective Action Reference: Condition Report 120056.


Significance: The inspectors assessed the significance of the finding using Exhibit 3, "Barrier Integrity Screening Questions," of Inspection Manual Chapter 0609, Appendix A, "Significance Determination Process (SDP) for Findings At
=====Performance Assessment:=====
-Power," issued June 19, 2012, and determined this finding represents a degradation of the radiological barrier function provided for the control room and represents a degradation of the barrier function of th e control room against smoke or a toxic atmosphere.
Performance Deficiency: The failure to recognize control building ventilation isolation boundaries and meet the requirements of 10 CFR Part 50, Criterion III, Design Control, is a performance deficiency.


Thus, a detailed risk evaluation is required. The senior reactor analyst evaluated the subject performance deficiency and resulting plant conditions to determine the risk impact on the plant. The analyst identified that the control room emergency ventilation system is not a significant risk contributor, because it does not directly affect the core damage frequency, provided operators have a habitable environment. Although the control room boundary was significantly degraded in the as
Screening: The inspectors determined the performance deficiency was more than minor because it adversely affected the design control attribute of the Barrier Integrity Cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding, reactor coolant system, and containment) protect the public from radionuclide releases caused by accidents or events. Specifically, the control room emergency ventilation systems ability to maintain adequate pressurization of the control room envelope was adversely impacted after an ongoing ventilation modification breached the floor without compensatory measures in place.
-found condition, either train of the control room emergency ventilation system was capable of maintaining the control room envelope with some level of pressurization, based on multiple test results. Therefore, while some deterioration of the control room environment could be expected, the control room emergency ventilation system appeared to be capable of maintaining a habitable environment throughout the relatively limited exposure period of the performance deficiency.
 
Significance: The inspectors assessed the significance of the finding using Exhibit 3, Barrier Integrity Screening Questions, of Inspection Manual Chapter 0609, Appendix A, Significance Determination Process (SDP) for Findings At-Power, issued June 19, 2012, and determined this finding represents a degradation of the radiological barrier function provided for the control room and represents a degradation of the barrier function of the control room against smoke or a toxic atmosphere. Thus, a detailed risk evaluation is required.
 
The senior reactor analyst evaluated the subject performance deficiency and resulting plant conditions to determine the risk impact on the plant. The analyst identified that the control room emergency ventilation system is not a significant risk contributor, because it does not directly affect the core damage frequency, provided operators have a habitable environment.
 
Although the control room boundary was significantly degraded in the as-found condition, either train of the control room emergency ventilation system was capable of maintaining the control room envelope with some level of pressurization, based on multiple test results.
 
Therefore, while some deterioration of the control room environment could be expected, the control room emergency ventilation system appeared to be capable of maintaining a habitable environment throughout the relatively limited exposure period of the performance deficiency.


As a result, the increase in risk caused by the degraded condition of the control room envelope was negligible, and the finding was of very low safety significance (Green).
As a result, the increase in risk caused by the degraded condition of the control room envelope was negligible, and the finding was of very low safety significance (Green).


Cross-cutting Aspect: The inspectors determined that the finding has a human performance cross-cutting aspect in the area of change management in that leaders did not use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority.
Cross-cutting Aspect: The inspectors determined that the finding has a human performance cross-cutting aspect in the area of change management in that leaders did not use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority. Specifically, managers did not ensure that individuals understood the importance of, and their role in, the change management process when WCRE-35 was recently revised and implemented. As a result, WCRE-35 did not identify all control building ventilation isolation boundaries.
 
=====Enforcement:=====
Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that for those structures, systems, and components to which this appendix applies, measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in 50.2 and as specified in the license application, are correctly translated into specifications, drawings, procedures, and instructions.
 
Contrary to the above, until April 16, 2018, for quality-related components associated with the control building, to which 10 CFR Part 50, Appendix B, applies, the licensee failed to assure that applicable regulatory requirements and the design basis, as defined in 50.2 and as specified in the license application, are correctly translated into specifications, drawings, procedures, and instructions. Specifically, the licensee failed to ensure that all control building ventilation isolation boundaries were adequately identified in WCRE-35, Boundary Matrix, which the station uses to identify boundary functions, such that the control room envelope could be adequately pressurized in accordance with design basis requirements.
 
Disposition: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.


Specifically, managers did not ensure that individuals understood the importance of, and their role in, the change management process when WCRE
Failure to Adequately Implement Instrumentation and Controls Surveillance Procedures Cornerstone        Significance                                Cross-cutting      Report Section Aspect Initiating          Green                                        [H.2] - Human
-35 was recently revised and implemented
. As a result, WCRE
-35 did not identify all control building ventilation isolation boundaries
. Enforcement
:  Violation:  Title 10 CFR Part 50, Appendix B, Criterion III, "Design Control," requires, in part, that for those structures, systems
, and comp o nents to which this appendix applies, measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in 50.2 and as specified in the license application, are correctly translated into specifications, drawings, procedures, and instructions.


16 Contrary to the above, until April 16, 2018, for quality
==71152 - Events              NCV 05000482/2018002-03                      Performance,       Problem          ==
-related components associated with the control building, to which 10 CFR Part 50, Appendix B
Closed                                      Field Presence    Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings, was identified when the licensee failed to adequately implement surveillance procedures that affected safety-related equipment and plant stability. Specifically, the licensee failed to adequately implement testing and calibration procedures for pressurizer level instrumentation. This resulted in two letdown isolation signals, securing of pressurizer heaters, and a pressurizer level transient on March 29, 2018.
, applies, the licensee failed to assure that applicable regulatory requirements and the design basis, as defined in 50.2 and as specified in the license application, are correctly translated into specifications, drawings, procedures, and instructions. Specifically, the licensee failed to ensure that all control building ventilation isolation boundaries were adequately identified in WCRE
-35, "Boundary Matrix," which the station uses to identify boundary functions, such that the control room envelope could be adequately pressurized in accordance with design basis requirements.


Disposition:
=====Description:=====
This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy. Failure to Adequately Implement Instrumentation and Controls Surveillance Procedures Cornerstone Significance Cross-cutting Aspect Report Section Initiating Events  Green NCV 05000482/2018002
On March 29, 2018, the licensee was performing Procedure STS IC-503B, Pressurizer Level Instrumentation Channel Calibration, Revision 12. This surveillance procedure performs calibration and testing activities associated with three pressurizer level channels, one-at-a-time. To perform calibration of each channel, a control room operator selects away from the channel to be tested, which ensures the controlling pressurizer level channels are not being tested. This allows maintenance technicians to perform calibration and testing activities associated with the desired channel. Following calibration and testing of each channel, the channel is restored and actions are taken to select away from the next desired channel to be tested, which again ensures the controlling pressurizer level channels are not being tested.
-0 3 Closed [H.2] - Human Performance , Field Presence 71152 - Problem Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion V , "Instructions, Procedures, and Drawings,"
was identified when the licensee failed to adequately implement surveillance procedures that affected safety
-related equipment and plant stability. Specifically, the licensee failed to adequately implement testing and calibration procedures for pressurizer level instrumentation. This resulted in two letdown isolation signals, securing of pressurizer heaters , and a pressurizer level transient on March 29, 2018.


Description
During the testing on March 29, 2018, station personnel successfully completed the calibration of channel 459, which is located in the SB038 cabinet. The technicians then informed the control room operator they were moving to the next section of the procedure associated with channel 460, and the operator selected away from channel 460 in accordance with procedure. The technicians had flagged a switch to be manipulated in cabinet SB038, but had incorrectly flagged the switch for channel 459. As a result, channel 459 was again taken to the test position, but this channel was now a controlling pressurizer level channel since channel 460 was to be tested next. The instrument failed low, which resulted in an actual pressurizer level transientlevel got as high as approximately 63 percent from a normal level of approximately 56.6 percentisolation of letdown, and automatic de-energization of the pressurizer back-up heaters.
:  On March 29, 2018, the licensee was performing Procedure STS IC
-503B, "Pressurizer Level Instrumentation Channel Calibration," Revision 12. This surveillance procedure performs calibration and testing activities associated with three pressurizer level channels, one
-at-a-time. To perform calibration of each channel, a control room operator selects away from the channel to be tested, which ensures the controlling pressurizer level channels are not being tested. This allows maintenance technicians to perform calibration and testing activities associated with the desired channel. Following calibration and testing of each channel, the channel is restored and actions are taken to select away from the next desired channel to be tested, which again ensures the controlling pressurizer level channels are not being tested.


During the testing on March 29, 2018, station personnel successfully completed the calibration of channel 459, which is located in the SB038 cabinet. The technician s then informed the control room operator t hey were moving to the next section of the procedure associated with channel 460, and the operator selected away from channel 460 in accordance with procedure. The technicians had flagged a switch to be manipulated in cabinet SB038, but had incorrectly flagged the switch for channel 459.
Step 8.3.3 of Procedure STS IC-503B stated, At C2-0847 (LS/460), PLACE BS-1 (LS/460A)to TEST position. This procedure step was not followed and the technicians did not adequately use human performance tools to ensure they were in the appropriate cabinet and flagging the appropriate channel, and supervision was not present when the inappropriate cabinet was flagged.


As a result, channel 459 was again taken to the test position, but this channel was now a controlling pressurizer level channel since channel 460 was to be tested next. The instrument failed low, which resulted in an actual pressurizer level transient
Operators responded to the transient using Off-Normal Procedure OFN SB-008, Instrument Malfunctions, Revision 45, reselected channel 460 as the controlling pressurizer level channel in accordance with the off-normal procedure, and an operator stated to the technician that they had received the 459 loop alarms. The technician then restored channel 459 from the test position without supervision and proceeded on in Procedure STS IC-503B.
-level got as high as approximately 63 percent from a normal level of approximately 56.6 perce nt-isolation of letdown, and automatic de
-energization of the pressurizer back
-up heaters.


17 Step 8.3.3 of Procedure STS IC
Procedure OFN SB-008 had ensured that the alternate pressurizer level channel on the pressurizer level control selector switch was selected. The technician did not re-perform Step 8.3.1.b, which states, Place BB LS-459D, PZR LEV CRTL SEL switch to L459/L461 position, before proceeding with channel 460 testing. Thus, when channel 460 was taken to the test position, this caused a second actual pressurizer level transientlevel got as high as 63 percenta second letdown isolation signal (though it had not yet been restored), and a second automatic de-energization of the back-up heaters signal was received. Operators again responded to the transient and stabilized the plant. Additionally, following the second actual pressurizer level transient operators provided the order to the technician to, stop work.
-503B stated, "At C2
-0847 (LS/460), PLACE BS
-1 (LS/460A) to TEST position."  This procedure step was not followed and the technicians did not adequately use human performance tools to ensure they were in the appropriate cabinet and flagging the appropriate channel, and supervision was not present when the inappropriate cabinet was flagged.


Operators responded to the transient using Of f-Normal Procedure OFN SB
The licensees evaluation determined that because of the risk associated with this task, supervisory oversight was required. Specifically, the qualitative risk screening performed for the task identified the need for leadership team member implementation oversight as a risk mitigating action. However, the oversight had not yet made it to the control room. The inspectors agreed with the licensees conclusions that the lack of oversight was the most significant contributor to both failures to follow procedures.
-008, "Instrument Malfunctions," Revision 45, reselected channel 460 as the controlling pressurizer level channel in accordance with the off
-normal procedure, and an operator stated to the technician that they had received the 459 loop alarms. The technician then restored channel 459 from the test position without supervision and proceeded on in Procedure STS IC
-503B. Procedure OFN SB
-008 had ensured that the alternate pressurizer level channel on the pressurizer level control selector switch was selected.


The technician did not re
Corrective Actions: The transient was stabilized, work was stopped following the second event, an event review was conducted, a stand-down was initiated, technician qualifications were removed, communications were made to operations and the site, and an interim action was created to have an operations individual present during two-minute drills for any work performed in the cabinets in the back of the control room.
-perform Step 8.3.1.b, which states, "Place BB LS
-459D, PZR LEV CRTL SEL switch to L459/L461 position," before proceeding with channel 460 testing. Thus, when channel 460 was taken to the test position, this caused a second actual pressurizer level transient
-level got as high as 63 percent
-a second letdown isolation signal (though it had not yet been restored), and a second automatic de
-energization of the back
-up heaters signal was received. Operators again responded to the transient and stabilized the plant. Additionally, following the second actual pressurizer level transient operators provided the order to the technician to, "stop work."  The licensee's evaluation determined that because of the risk associated with this task, supervisory oversight was required. Specifically, the qualitative risk screening performed for the task identified the need for "leadership team member implementation oversight" as a risk mitigating action. However, the oversight had not yet made it to the control room.


The inspectors agreed with the licensee's conclusions that the lack of oversight was the most significant contributor to both failures to follow procedures.
Corrective Action Reference: Condition Report 120807.


Corrective Actions: The transient was stabilized, work was stopped following the second event, an event review was conducted, a stand
=====Performance Assessment:=====
-down was initiated, technician qualifications were removed, communications were made to operations and the site, and an interim action was created to have an operations individual present during two
Performance Deficiency: The failure to adequately implement the testing and calibration procedure for pressurizer level instrumentation on two occasions and meet the requirements of 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings, was a performance deficiency. Specifically, procedures for pressurizer level instrumentation calibration were not followed on two occasions:
-minute drills for any work performed in the cabinets in the back of the control room.
: (1) when an instrumentation and control technician failed to take the appropriate channel to test in accordance with procedure; and
: (2) when the individual failed to adequately verify the appropriate channels were selected in accordance with procedure on March 29, 2018. These actions failed the 459 level transmitter channel low inappropriately and then subsequently failed the 460 level transmitter channel low inappropriately, respectively.


Corrective Action Reference
Screening: The inspectors determined the performance deficiency was more than minor because it affected the human performance attribute of the Initiating Events Cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations.
:  Condition Report 120807. Performance Assessment
:  Performance Deficiency:  The failure to adequately implement the testing and calibration procedure for pressurizer level instrumentation on two occasions and meet the requirements of 10 CFR Part 50, Criterion V, "Instructions, Procedures, and Drawings," was a performance deficienc y. Specifically, procedures for pressurizer level instrumentation calibration were not followed on two occasions
:  (1) when an instrumentation and control technician failed to take the appropriate channel to test in accordance with procedure
; and (2) when the individual failed to adequately verify the appropriate channels were selected in accordance with procedure on March 29, 2018. These actions failed the 459 level transmitter channel low inappropriately and then subsequently failed the 460 level transmitter channel low inappropriately, respectively
. Screening:
The inspectors determined the performance deficiency was more than minor because it affected the human performance attribute of the Initiating Events Cornerstone and 18 adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the performance deficiency resulted in two separate actual pressurizer level transient s, letdown isolation signal s, and signals for automatic de
-energization of the pressurizer back
-up heaters.


Significance:  The inspectors assessed the significance of the finding using Exhibit 1 , "Initiating Events Screening Questions," of Inspection Manual Chapter 0609, Appendix A, "Significance Determination Process (SDP) for Findings At
Specifically, the performance deficiency resulted in two separate actual pressurizer level transients, letdown isolation signals, and signals for automatic de-energization of the pressurizer back-up heaters.
-Power," issued June 19, 2012, and determined th is finding was not a deficienc y that caused a plant trip and did not cause the loss of mitigation equipment relied upon to transition the plant from the onset of a trip to stable plant shutdown (e.g. loss of condenser, loss of feedwater). Furthermore, there were no other events such as a high energy line break, internal flooding, or fire. Therefore, the inspectors determined the finding was of very low safety significance (Green).


Cross-cutting Aspect: The inspectors determined that the finding has a human performance cross-cutting aspect in the area of field presence in that senior managers did not ensure supervisory and management oversight of work activities
Significance: The inspectors assessed the significance of the finding using Exhibit 1, Initiating Events Screening Questions, of Inspection Manual Chapter 0609, Appendix A, Significance Determination Process (SDP) for Findings At-Power, issued June 19, 2012, and determined this finding was not a deficiency that caused a plant trip and did not cause the loss of mitigation equipment relied upon to transition the plant from the onset of a trip to stable plant shutdown (e.g. loss of condenser, loss of feedwater). Furthermore, there were no other events such as a high energy line break, internal flooding, or fire. Therefore, the inspectors determined the finding was of very low safety significance (Green).
. Specifically, managers and supervisors did not practice visible leadership in the field and during safety significant evolutions like performance of Procedure STS IC
-503B by placing "eyes on the problem," coaching, mentoring, reinforcing standards and reinforcing positive decision making practices and behaviors, which led to the multiple examples of failure to follow procedures.


Enforcement
Cross-cutting Aspect: The inspectors determined that the finding has a human performance cross-cutting aspect in the area of field presence in that senior managers did not ensure supervisory and management oversight of work activities. Specifically, managers and supervisors did not practice visible leadership in the field and during safety significant evolutions like performance of Procedure STS IC-503B by placing eyes on the problem, coaching, mentoring, reinforcing standards and reinforcing positive decision making practices and behaviors, which led to the multiple examples of failure to follow procedures.
Violation: Title 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," requires, in part, that activities affecting quality shall be accomplished in accordance with documented instructions, procedures, or drawings of a type appropriate to the circumstances.
 
=====Enforcement:=====
Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality shall be accomplished in accordance with documented instructions, procedures, or drawings of a type appropriate to the circumstances.
: (1) Procedure STS IC-503B, Pressurizer Level Instrumentation Channel Calibration, Revision 12, an Appendix B quality related procedure, provides instructions for performing pressurizer level instrument calibration testing. Procedure STS IC-503B, Step 8.3.3, requires that BS-1 (LS/460A) be placed in the test position. Contrary to the above, on March 29, 2018, BS-1 (LS/460A) was not placed in the test position.


  (1) Procedure STS IC
Specifically, the 459 channel was placed in the test position inappropriately.
-503B, "Pressurizer Level Instrumentation Channel Calibration," Revision 12, an Appendix B quality related procedure, provides instructions for performing pressurizer level instrument calibration testing. Procedure STS IC-503B, Step 8.3.3, requires that BS
: (2) Procedure STS IC-503B, Step 8.3.1.b, requires, in part, verification that BB LS-459D, the pressurizer level control selector switch, be placed in the L459/L461 position for channel 460 testing and calibration. Contrary to the above, on March 29, 2018, verification that BB LS-459D, the pressurizer level control selector switch, was placed in the L459/L461 position for channel 460 testing and calibration was not performed.
-1 (LS/460A) be placed in the test position. Contrary to the above, on March 29, 2018, BS
-1 (LS/460A) was not placed in the test position. Specifically, the 459 channel was placed in the test position inappropriately.


(2) Procedure STS IC
Specifically, testing and calibration of channel 460 occurred while channel 460 was selected as the controlling channel.
-503B, Step 8.3.1.b, requires, in part, verification that BB LS
-459D, the pressurizer level control selector switch, be placed in the L459/L461 position for channel 460 testing and calibration. Contrary to the above, on March 29, 2018, verification that BB LS
-459D, the pressurizer level control selector switch, was placed in the L459/L461 position for channel 460 testing and calibration was not performed. Specifically, testing and calibration of channel 460 occurred while channel 460 was selected as the controlling channel.


Disposition:
Disposition: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.
This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.


19 EXIT MEETIN GS AND DEBRIEFS On April 13, 2018, the inspector presented the occupational radiation safety inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.
==EXIT MEETINGS AND DEBRIEFS==
On April 13, 2018, the inspector presented the occupational radiation safety inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.


On May 8, 2018, the inspector presented the inservice inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President , and other members of the licensee staff.
On May 8, 2018, the inspector presented the inservice inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.


On July 17, 2018, the inspector presented the quarterly resident inspector inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.
On July 17, 2018, the inspector presented the quarterly resident inspector inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.


The inspectors verified no proprietary information was retained or documented in this report
The inspectors verified no proprietary information was retained or documented in this report.
.
1


=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=


71111.01-Adverse Weather Protection
71111.01Adverse Weather Protection
Procedures
Procedures
Number Title Revision OFN AF-025 Unit Limitations
Number           Title                                                 Revision
Drawings Number Title Revision KD-7496 One Line Diagram
OFN AF-025       Unit Limitations                                       55
Drawings
Number           Title                                                 Revision
KD-7496           One Line Diagram                                       67
Condition Reports
Condition Reports
23867 123954 123955 123956 123957 123958 123959 123961 123962 123963 123968 123969     Miscellaneous
23867           123954             123955             123956         123957
Documents Number Title Date Temporary Operating Guide
23958            123959             123961             123962         123963
Waverly-LaCygne 345 kV line outages
23968            123969
Expires December 31, 2018 Transmission Operating Directive 0300
Miscellaneous Documents
Outage of the Wolf Creek
Number           Title                                                 Date
-Benton 345 kV Line
Temporary         Waverly-LaCygne 345 kV line outages                   Expires
February 28, 2018 Transmission Operating Directive 0301
Operating Guide                                                          December 31,
Outage of the Wolf Creek
2018
-Rose Hill 345 kV Line
Transmission     Outage of the Wolf Creek-Benton 345 kV Line           February 28,
February 28, 2018 Transmission Operating Directive 0306
Operating                                                                2018
Outage of Wolf Creek 345 kV Breaker 345
Directive 0300
-40 or 345-60 February 28, 2018 Transmission Operating Directive 0307
Transmission      Outage of the Wolf Creek-Rose Hill 345 kV Line         February 28,
Outage of the Wolf Creek
Operating                                                                2018
-Waverly 345 kV Line
Directive 0301
February 28, 2018 Transmission Operating Directive 0308
Transmission      Outage of Wolf Creek 345 kV Breaker 345-40 or 345-60   February 28,
Outage of the Waverly
Operating                                                                2018
-LaCygne 345 kV Line
Directive 0306
February 28, 2018
Transmission      Outage of the Wolf Creek-Waverly 345 kV Line           February 28,
71111.04-Equipment Alignment
Operating                                                                2018
Directive 0307
Transmission      Outage of the Waverly-LaCygne 345 kV Line             February 28,
Operating                                                                2018
Directive 0308
71111.04Equipment Alignment
Procedures
Procedures
Number Title Revision CKL AL-120 Auxiliary Feedwater Normal Lineup
Number           Title                                                     Revision
CKL EC-120 Fuel Pool Cooling and Cleanup System Normal Valve Lineup/Breaker Checklist
CKL AL-120       Auxiliary Feedwater Normal Lineup                         42
CKL EF-120 Essential Service Water Valve, Breaker and Switch Lineup
CKL EC-120       Fuel Pool Cooling and Cleanup System Normal Valve         17
Drawings Number Title Revision E-13EC09 Schematic Diagram Spent Fuel Pool Alternate Power Supply Motor Controller
Lineup/Breaker Checklist
E-13GG02 Schematic Diagram Spent Fuel Pool Pump Room Coolers
CKL EF-120       Essential Service Water Valve, Breaker and Switch Lineup   54
KD-7496 One-Line Diagram
Drawings
M-12AL01 Piping & Instrumentation Diagram Auxiliary Feedwater System 28 M-12EC01 Piping & Instrumentation Diagram Fuel Pool Cooling
Number           Title                                                     Revision
and Clean-up System 23 M-12EC02 Piping & Instrumentation Diagram Fuel Pool Cooling and Clean-up System 7 M-12EF01 Piping & Instrumentation Diagram Essential SVC Water System 29 M-12EF02 Piping & Instrumentation Diagram Essential Service Water System 42 M-K2EF01 Piping & Instrumentation Diagram Essential Service Water System 70 M-K2EF01A Abandoned ESW Equipment
E-13EC09         Schematic Diagram Spent Fuel Pool Alternate Power         1
M-K2EF03 Piping & Instrumentation Diagram Essential Service Water System 19 M-K2EF03A Abandoned ESW Equipment
Supply Motor Controller
E-13GG02         Schematic Diagram Spent Fuel Pool Pump Room Coolers       3
KD-7496           One-Line Diagram                                           61
M-12AL01         Piping & Instrumentation Diagram Auxiliary Feedwater       28
System
M-12EC01         Piping & Instrumentation Diagram Fuel Pool Cooling and    23
Clean-up System
M-12EC02         Piping & Instrumentation Diagram Fuel Pool Cooling and     7
Clean-up System
M-12EF01         Piping & Instrumentation Diagram Essential SVC Water       29
System
M-12EF02         Piping & Instrumentation Diagram Essential Service Water   42
System
M-K2EF01         Piping & Instrumentation Diagram Essential Service Water   70
System
M-K2EF01A         Abandoned ESW Equipment                                   2
M-K2EF03         Piping & Instrumentation Diagram Essential Service Water   19
System
M-K2EF03A         Abandoned ESW Equipment                                   1
Condition Reports
Condition Reports
2669 121872 122213 122233 124453
2669           121872             122213             122233           124453
71111.05AQ
71111.05AQFire Protection Annual/Quarterly
-Fire Protection Annual/Quarterly
Procedures
Procedures
Number Title Revision AP 10-106 Fire Preplans
Number           Title                                                       Revision
18A  Drawings Number Title Revision E-1F9905 Fire Hazard Analysis
AP 10-106         Fire Preplans                                               18A
Drawings
Number           Title                                                       Revision
E-1F9905         Fire Hazard Analysis                                       8
Condition Reports
Condition Reports
21946 122915 122944 123429 123446 123920 123921     71111.06-Flood Protection Measures
21946           122915             122944             123429             123446
Drawings Number Title Revision C-K201 E.S.
23920            123921
: [[contact::W.S. Yard Pipelines & Elect. Duct Banks Plan]], Sections & Schedules SHT.1
71111.06Flood Protection Measures
C-K201 E.S.
Drawings
: [[contact::W.S. Yard Pipelines & Elect. Duct Banks Plan]], Sections  
Number           Title                                                       Revision
& Schedules SHT.1
C-K201           E.S.
C-K202 E.S.
: [[contact::W.S. Yard Pipelines & Elect. Duct Banks Plan]], Sections 10
: [[contact::W.S. Yard Pipelines & Electrical Duct Banks Plan]], Sections & Schedules SH
                  & Schedules SHT.1
: [[contact::T.
C-K201           E.S.
-2 10 C-K202 E.S.W.S. Yard Pipelines & Electrical Duct Banks Plan]], Sections & Schedules SHT.
: [[contact::W.S. Yard Pipelines & Elect. Duct Banks Plan]], Sections 12
-2 11 C-K209 E.S.W.S. Electrical Manholes Plans Sections
                  & Schedules SHT.1
& Details 9 C-K212 E.S.W.S Yard Pipelines & Elec. Duct Banks Plan & Sections
C-K202           E.S.
: [[contact::W.S. Yard Pipelines & Electrical Duct Banks Plan]],       10
Sections & Schedules SHT.-2
C-K202           E.S.
: [[contact::W.S. Yard Pipelines & Electrical Duct Banks Plan]],       11
Sections & Schedules SHT.-2
C-K209           E.S.W.S. Electrical Manholes Plans Sections & Details       9
C-K212           E.S.W.S Yard Pipelines & Elec. Duct Banks Plan & Sections 4
Condition Reports
Condition Reports
24380 124381 124382 124383 124397 124409
24380           124381             124382             124383             124397
71111.08-Inservice Inspection Activities
24409
71111.08Inservice Inspection Activities
Procedures
Procedures
Number Title Revision 54-ISI-603-009 Automated Ultrasonic Examination of Reactor Pressure Vessel Closure Head Penetration Containing Thermal Sleeves 9 AP-16F-001 Boric Acid Corrosion Control Program
Number               Title                                                     Revision
I-ENG-023 Steam Generator Data Analysis Guidelines
54-ISI-603-009       Automated Ultrasonic Examination of Reactor Pressure       9
LMT-08-PDI-UT-1 Ultrasonic Examination of Ferritic Piping Welds
Vessel Closure Head Penetration Containing Thermal
LMT-08-PDI-UT-11 Ultrasonic Examination of Nozzle Inner Radius Area at Wolf Creek Generating Station
Sleeves
LMT-08-UT-004 Ultrasonic Examination of Vessel Welds and Adjacent Base Material > 2.0" in Thickness
AP-16F-001           Boric Acid Corrosion Control Program                       9
SG-SGMP-15-4 Wolf Creek Generating Station RF20 Condition Monitoring and Operational Assessment
I-ENG-023           Steam Generator Data Analysis Guidelines                   16
SG-SGMP-16-18 Wolf Creek Generating Station RF21 Condition Monitoring and Operational Assessment
LMT-08-PDI-UT-1     Ultrasonic Examination of Ferritic Piping Welds           0
SG-SGMP-18-9 Wolf Creek Generating Station RF22 Condition Monitoring and Operational Assessment for
LMT-08-PDI-UT-11 Ultrasonic Examination of Nozzle Inner Radius Area at Wolf     0
Creek Generating Station
LMT-08-UT-004       Ultrasonic Examination of Vessel Welds and Adjacent Base   0
Material > 2.0 in Thickness
SG-SGMP-15-4         Wolf Creek Generating Station RF20 Condition Monitoring   0
and Operational Assessment
SG-SGMP-16-18       Wolf Creek Generating Station RF21 Condition Monitoring   0
and Operational Assessment
SG-SGMP-18-9         Wolf Creek Generating Station RF22 Condition Monitoring   0
and Operational Assessment for
Cycle 23 and Cycle 24
Cycle 23 and Cycle 24
STS PE-040E Reactor Pressure Vessel
STS PE-040E         Reactor Pressure Vessel Head Visual Inspection             7
Head Visual Inspection
WCRE-30             Inservice Inspection Program Plan Wolf Creek Generating   2
WCRE-30 Inservice Inspection Program Plan Wolf Creek Generating Station Interval 4
Station Interval 4
Condition Reports
Condition Reports
93748 93749 107686 108888 109175 111055 112584 113666 114073 117639 117827 121438 121439   71111.11-Licensed Operator Requalification Program and Licensed Operator Performance
93748             93749                 107686             108888         109175
111055           112584               113666             114073         117639
117827           121438               121439
71111.11Licensed Operator Requalification Program and Licensed Operator Performance
Procedures
Procedures
Number Title Revision STS AE-211 Main Feed Reg Valve Inservice Valve Test
Number           Title                                                     Revision
SYS NB-201 Transferring NB01 Power Sources
STS AE-211       Main Feed Reg Valve Inservice Valve Test                   3
SYS NB-320 Deenergizing and Energizing ESF Transformers
SYS NB-201       Transferring NB01 Power Sources                           61
SYS NB-320       Deenergizing and Energizing ESF Transformers               12
Condition Reports
Condition Reports
23853 12395 0 123951   Miscellaneous
23853           123950            123951
Documents Number Title Revision/ Date 17-01 (IC342) 2018 Biennial Requalification Exam Scenario
Miscellaneous Documents
18-01 (340) 2018 Annual Requalification Exam
Number           Title                                               Revision/
STS AE-211 Main Feed Reg Valve Inservice Valve Test
Date
Completed May 17, 2018
17-01 (IC342)     2018 Biennial Requalification Exam Scenario         1
SYS NB-201 Transferring NB01 Power Sources
18-01 (340)       2018 Annual Requalification Exam                     0
Completed May 2, 2018
STS AE-211       Main Feed Reg Valve Inservice Valve Test             Completed
SYS NB-320 Deenergizing and Energizing ESF Transformers
May 17, 2018
Completed May 2, 2018
SYS NB-201       Transferring NB01 Power Sources                     Completed
71111.12-Maintenance Effectiveness
May 2, 2018
SYS NB-320       Deenergizing and Energizing ESF Transformers         Completed
May 2, 2018
71111.12Maintenance Effectiveness
Condition Reports
Condition Reports
113227 122957     Work Orders
113227           122957
17-428387-001     Miscellaneous
Work Orders
Documents Number Title Date System Health Report: Fuel Pool Cooling
17-428387-001
April 1, 2015 through June 30, 2015
Miscellaneous Documents
System Health Report: Fuel Pool Cooling
Number           Title                                       Date
October 1, 2015 through December 31, 2015 System Health Report: Fuel Pool Cooling
System Health Report: Fuel Pool Cooling     April 1, 2015
April 1, 2016 through December, 2016 System Health Report: Fuel Pool Cooling
through
July 1, 2016 through June 30, 2017
June 30, 2015
System Health Report: Fuel Pool Cooling
System Health Report: Fuel Pool Cooling     October 1, 2015
January 1, 2017 through June 30, 2017
through December
Miscellaneous
31, 2015
Documents Number Title Date System Health Report: Fuel Pool Cooling
System Health Report: Fuel Pool Cooling     April 1, 2016
July 1, 2017 through December 31, 2017
through December,
EC Maintenance Rule Final Scope Evaluation:
2016
Spent Fuel Pool Cooling and Cleanup  
System Health Report: Fuel Pool Cooling     July 1, 2016 through
- EC-01 EC Maintenance Rule Final Scope Evaluation:
June 30, 2017
Spent Fuel Pool Cooling and Cleanup  
System Health Report: Fuel Pool Cooling     January 1, 2017
- EC-02 EC Maintenance Rule Final Scope Evaluation:
through June 30,
Spent Fuel Pool Cooling and Cleanup  
2017
- EC-03 EC Maintenance Rule Final Scope Evaluation:
Miscellaneous Documents
Spent Fuel Pool Cooling and Cleanup  
Number           Title                                               Date
- EC-04 EC Maintenance Rule Final Scope Evaluation:
System Health Report: Fuel Pool Cooling             July 1, 2017 through
Spent Fuel Pool Cooling and Cleanup  
December 31, 2017
- EC-05 EC Maintenance Rule Final Scope Evaluation:
EC               Maintenance Rule Final Scope Evaluation:
Fuel Pool Cooling and Cleanup
Spent Fuel Pool Cooling and Cleanup - EC-01
- EC-06 EC Maintenance Rule Final Scope Evaluation:
EC               Maintenance Rule Final Scope Evaluation:
Spent Fuel Pool Cooling and Cleanup  
Spent Fuel Pool Cooling and Cleanup - EC-02
- EC-07   71111.13-Maintenance Risk Assessments and Emergent Work Control
EC               Maintenance Rule Final Scope Evaluation:
Spent Fuel Pool Cooling and Cleanup - EC-03
EC               Maintenance Rule Final Scope Evaluation:
Spent Fuel Pool Cooling and Cleanup - EC-04
EC               Maintenance Rule Final Scope Evaluation:
Spent Fuel Pool Cooling and Cleanup - EC-05
EC               Maintenance Rule Final Scope Evaluation:
Fuel Pool Cooling and Cleanup - EC-06
EC               Maintenance Rule Final Scope Evaluation:
Spent Fuel Pool Cooling and Cleanup - EC-07
71111.13Maintenance Risk Assessments and Emergent Work Control
Procedures
Procedures
Number Title Revision AP 21C-001 Wolf Creek Substation
Number           Title                                                     Revision
AP 21D-004 Control of Containment Penetrations During Shutdown Operations
AP 21C-001       Wolf Creek Substation                                     20
11A AP 22C-008 Qualitative Risk Management
AP 21D-004       Control of Containment Penetrations During Shutdown       11A
4B FHP 02-001 Refueling Operations
Operations
FHP 02-007A Reactor Vessel Closure Head Removal
AP 22C-008       Qualitative Risk Management                               4B
2A FHP 05-001 Equipment Hatch Operations
FHP 02-001       Refueling Operations                                       46
GEN 00-008 RCS Level Less Than Reactor Vessel Flange Operations
FHP 02-007A     Reactor Vessel Closure Head Removal                       12A
STS GP-001 Containment Purge Valves Actuation Test
FHP 05-001       Equipment Hatch Operations                                 0
STS GP-006 CTMT Closure Verification
GEN 00-008       RCS Level Less Than Reactor Vessel Flange Operations       32
STS GP-006 CTMT Closure Verification
STS GP-001       Containment Purge Valves Actuation Test                   27
24A SYS BB-215 RCS Drain Down With Fuel In Reactor
STS GP-006       CTMT Closure Verification                                 14
Drawings Number Title Revision M-12BB01 Piping and Instrumentation Diagram Reactor Coolant System 36 M-12BB02 Piping and Instrumentation Diagram Reactor Coolant System 28 M-12BB04 Piping and Instrumentation Diagram Reactor Coolant System 23 M-12EJ01 Piping and
STS GP-006       CTMT Closure Verification                                 24A
Instrumentation Diagram Residual Heat Removal System
SYS BB-215       RCS Drain Down With Fuel In Reactor                       48
M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant Injection System
Drawings
M-12EM02 Piping and Instrumentation Diagram High Pressure Coolant Injection System
Number           Title                                                   Revision
M-12EM03 Piping and Instrumentation Diagram High Pressure Coolant Injection System Test Line
M-12BB01         Piping and Instrumentation Diagram Reactor Coolant       36
System
M-12BB02         Piping and Instrumentation Diagram Reactor Coolant       28
System
M-12BB04         Piping and Instrumentation Diagram Reactor Coolant       23
System
M-12EJ01         Piping and Instrumentation Diagram Residual Heat         54
Removal System
M-12EM01         Piping and Instrumentation Diagram High Pressure Coolant 44
Injection System
M-12EM02         Piping and Instrumentation Diagram High Pressure Coolant 22
Injection System
M-12EM03         Piping and Instrumentation Diagram High Pressure Coolant 3
Injection System Test Line
Condition Reports
Condition Reports
21353     Miscellaneous
21353
Documents Number Title Date APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary Shift: Nights, Mode: 5
Miscellaneous Documents
April 5, 2018 APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary
Number           Title                                                   Date
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       April 5, 2018
Shift: Nights, Mode: 5
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       April 6, 2018
Shift: Days, Mode 6
Shift: Days, Mode 6
April 6, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       April 7, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary Shift: Nights, Mode 6
Shift: Nights, Mode 6
April 7, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       April 12, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary Shift: Nights, Defueled
Shift: Nights, Defueled
April 12, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       April 19, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary Shift: Nights, Defueled
Shift: Nights, Defueled
April 19, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       April 24, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary Shift: Days, Defueled April 24, 2018
Shift: Days, Defueled
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary Shift: Nights, Mode: 6
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary       May 8, 2018
May 8, 2018
Shift: Nights, Mode: 6
ET 88-0193 Docket No. 50
ET 88-0193       Docket No. 50-482: Generic Letter 88-17 - Loss of Decay December 23,
-482: Generic Letter 88
Heat Removal                                            1988
-17 - Loss of Decay Heat Removal
Miscellaneous Documents
December 23, 1988
Number           Title                                                     Date
Miscellaneous
ET 92-0001       Docket No. 50-482: Change in Commitment Associated       January 2,
Documents Number Title Date ET 92-0001 Docket No.
with Generic Letter 88-17                                 1992
50-482: Change in Commitment Associated with Generic Letter 88
STS CR-002       Shift Log for Modes 4, 5, and 6                           Completed
-17 January 2, 1992 STS CR-002 Shift Log for Modes 4, 5, and 6
May 9, 2018
Completed May 9, 2018
WM 89-0041       Docket No. 50-482: Generic Letter 88-17 - Loss of Decay   February 2,
WM 89-0041 Docket No. 50
Heat Removal                                              1989
-482: Generic Letter 88
71111.15Operability Determinations and Functionality Assessments
-17 - Loss of Decay Heat Removal
February 2, 1989 71111.15-Operability Determinations and Functionality Assessments
Procedures
Procedures
Number Title Revision AP 22A-001 Screening, Prioritization and Pre
Number           Title                                                     Revision
-Approval 21 AP 26C-004 Operability Determination and Functionality Assessment
AP 22A-001       Screening, Prioritization and Pre-Approval               21
AP 28-001 Operability Evaluations
AP 26C-004       Operability Determination and Functionality Assessment   35
Drawings Number Title Revision   Westinghouse Drawing 1464F11
AP 28-001         Operability Evaluations                                   25
M-703-00055 Closure Head (SAP) General Assembly
Drawings
W02 M-709-00099 Control Rod Mechanism Housing Details  
Number           Title                                                     Revision
- Sheet 1 W01 Condition Reports
Westinghouse Drawing 1464F11
2207 122351 122581 123083 123084 123567 123902 123903 123905 123906 123907 123908 123914   Work Orders
M-703-00055       Closure Head (SAP) General Assembly                       W02
18-438919-000 18-438984-000 18-439282-000   Miscellaneous
M-709-00099       Control Rod Mechanism Housing Details - Sheet 1           W01
Documents Number Title Revision/Date APF 05-013-01 M-721-00096 - Instruction Manual for Safety Injection Pump W25
Condition Reports
Miscellaneous
2207           122351               122581           123083           123084
Documents Number Title Revision/Date APF 05C-004-01 WCNOC - Basic Engineering Disposition  
23567            123902               123903           123905           123906
- DPEM01A Current Reading Higher Than Name Plate Rating
23907            123908               123914
- CR 122518 May 1, 2018
Work Orders
APF 05C-004-01 WCNOC - Basic Engineering Disposition  
18-438919-000     18-438984-000       18-439282-000
- DPEM01A Current Reading Higher Than Name Plate Rating  
Miscellaneous Documents
- CR 122581 May 3, 2018 APF 05C-004-01 WCNOC - Basic Engineering Disposition  
Number           Title                                                   Revision/Date
- PEM01A RF22 Rework Hydraulic Performance Impact
APF 05-013-01     M-721-00096 - Instruction Manual for Safety Injection   W25
May 9, 2018
Pump
MRP 2018-010 Electric Power Research Institute  
Miscellaneous Documents
- Notification of Recent PWR CRDM Thermal Sleeve Flange Wear and Control Rod Motion Stoppage Operating Experience and Recommended Plant Actions
Number           Title                                                     Revision/Date
April 20, 2018
APF 05C-004-01 WCNOC - Basic Engineering Disposition - DPEM01A             May 1, 2018
XX-E-006 Calculation XX
Current Reading Higher Than Name Plate Rating - CR
-E-006 AC System Analysis Rev. 7  
2518
- Appendix 31  
APF 05C-004-01 WCNOC - Basic Engineering Disposition - DPEM01A             May 3, 2018
- Scenario L1 (LOCA) Motor Starting Analysis - Output Report
Current Reading Higher Than Name Plate Rating - CR
71111.18-Plant Modifications
2581
Drawings Number Title Revision/Date E-13GG02 Schematic Diagram Spent Fuel Pool Pump Room Coolers
APF 05C-004-01 WCNOC - Basic Engineering Disposition - PEM01A RF22         May 9, 2018
E-13EC09 Schematic Diagram Spent Fuel Pool Alternate Power Supply Motor Controller
Rework Hydraulic Performance Impact
M-084A-00010 8539 SGG45 Wiring Diagram
MRP 2018-010     Electric Power Research Institute - Notification of Recent April 20, 2018
January 31, 2018 WIP-E-12EC09-000-A-1 Schematic Diagram Spent Fuel Pool Alternate Power Supply Motor Controller
PWR CRDM Thermal Sleeve Flange Wear and Control
WIP-E-IR0211A-002B-1 Raceway Plan Plant Site Southwest Quadrant Underground Duct Bank EL. [Elevation] 2000'
Rod Motion Stoppage Operating Experience and
-0" 00 WIP-M-1X6906-000-A-1 Fuel Building Penetration Closure Wall Elevations
Recommended Plant Actions
WIP-M-1X6906-001-A-1 Fuel Building Penetration Closure Wall Elevations
XX-E-006         Calculation XX-E-006 AC System Analysis Rev. 7 -          7
WIP-M-13EG29-000-A-1 Piping Isometric Drawing Alternate Spent Fuel Pool Cooling Fuel Building
Appendix 31 - Scenario L1 (LOCA) Motor Starting
Analysis - Output Report
71111.18Plant Modifications
Drawings
Number           Title                                                       Revision/Date
E-13GG02         Schematic Diagram Spent Fuel Pool Pump Room Coolers         3
E-13EC09         Schematic Diagram Spent Fuel Pool Alternate Power           1
Supply Motor Controller
M-084A-00010     8539 SGG45 Wiring Diagram                                   January 31,
2018
WIP-E-12EC09-   Schematic Diagram Spent Fuel Pool Alternate Power           1
000-A-1          Supply Motor Controller
WIP-E-IR0211A-   Raceway Plan Plant Site Southwest Quadrant Underground 00
2B-1          Duct Bank EL. [Elevation] 2000-0
WIP-M-1X6906-   Fuel Building Penetration Closure Wall Elevations           00
000-A-1
WIP-M-1X6906-   Fuel Building Penetration Closure Wall Elevations           00
001-A-1
WIP-M-13EG29- Piping Isometric Drawing Alternate Spent Fuel Pool Cooling 00
000-A-1          Fuel Building
Condition Reports
Condition Reports
2629 122684 122959 123060 123146 123193 123195 123259 123584 123592 Miscellaneous
2629           122684             122959             123060         123146
Documents Number Title Date 14403 Field Change Notice: Spent Fuel Pool Instrumentation System April 30, 2015
23193            123195             123259             123584         123592
14496 Field Change Notice: Fukushima Spent Fuel Pool Makeup
Miscellaneous Documents
August 30, 2016 15241 Change Package Engineering
Number           Title                                                   Date
Disposition: Spent Fuel Pool Alternate Cooling Modification
14403             Field Change Notice: Spent Fuel Pool Instrumentation     April 30, 2015
November 29, 2017 15273 Field Change Notice: Spent Fuel Pool Alternate Cooling Electrical
System
March 3, 2018 71111.19-Post Maintenance Testing
14496             Field Change Notice: Fukushima Spent Fuel Pool Makeup   August 30,
2016
241            Change Package Engineering Disposition: Spent Fuel Pool November 29,
Alternate Cooling Modification                           2017
273            Field Change Notice: Spent Fuel Pool Alternate Cooling   March 3,
Electrical                                              2018
71111.19Post Maintenance Testing
Procedures
Procedures
Number Title Revision STN EC-201 Fuel Pool Cooling and Clean
Number           Title                                                   Revision
-Up System Valve Test
STN EC-201       Fuel Pool Cooling and Clean-Up System Valve Test         2
STN XMR-001 XMR01 Control Alarm and Trip Circuit Verification
STN XMR-001       XMR01 Control Alarm and Trip Circuit Verification       3
STS BG-100A Centrifugal Charging System "A" Train Inservice Pump
STS BG-100A       Centrifugal Charging System A Train Inservice Pump     48
STS CR-002 Shift Log for Modes 4, 5, and 6
STS CR-002       Shift Log for Modes 4, 5, and 6                         84
STS EM-100A Safety Injection Pump "A" Inservice Pump Test
STS EM-100A       Safety Injection Pump A Inservice Pump Test           41
STS IC-503B Channel Calibration pressurizer Level
STS IC-503B       Channel Calibration pressurizer Level                   12
STS IC-503B Channel Calibration pressurizer Level
STS IC-503B       Channel Calibration pressurizer Level                   12A
2A STS KJ-015B Manual/Auto Fast Start, Sync & Loading of EDG NE02
STS KJ-015B       Manual/Auto Fast Start, Sync & Loading of EDG NE02       44
SYS EC-120 Fuel Pool Cooling and Cleanup System Startup
SYS EC-120       Fuel Pool Cooling and Cleanup System Startup             56
Drawings Number Title Revision E-0033.3-009-03 Power Tran
Drawings
sformer, Class, OA/FA/FOA, Shell Form, Outdoor, Three Phase, KVA 60000/80000/100000,  
Number           Title                                                   Revision
: [[contact::H. V. 345000]],  
E-0033.3-009-03 Power Transformer, Class, OA/FA/FOA, Shell Form,           3
Outdoor, Three Phase, KVA 60000/80000/100000, H.
: [[contact::V.
345000]],  
: [[contact::L.V. 13800]],  
: [[contact::L.V. 13800]],  
: [[contact::Y. Y.]], 13800, 60 Hertz
: [[contact::Y. Y.]], 13800, 60 Hertz
E-003.3-00008 CA/FA/FOA Transformer Control Schematic Wiring Diagram
E-003.3-00008     CA/FA/FOA Transformer Control Schematic Wiring Diagram W10
W10
Drawings
Drawings Number Title Revision E-003.3-00022 Power Transformer, Class OA/FA/FOA, Shell Form, Outdoor, Three Phase, KVA 60000/80000/100000,  
Number           Title                                                     Revision
: [[contact::H. V. 345000]], L  
E-003.3-00022     Power Transformer, Class OA/FA/FOA, Shell Form,           W09
Outdoor, Three Phase, KVA 60000/80000/100000, H.
: [[contact::V.
345000]], L  
: [[contact::V. 13800]],  
: [[contact::V. 13800]],  
: [[contact::Y. Y. 13800]], 60 Hertz
: [[contact::Y. Y. 13800]], 60 Hertz
W09 E-11MR01 Startup Transformer Single Line Metering and Relaying Diagram 7 M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant Injection System
E-11MR01         Startup Transformer Single Line Metering and Relaying     7
M-761-00076-06 Process Control Block Diagram SNUPPS
Diagram
M-12EM01         Piping and Instrumentation Diagram High Pressure Coolant 45
Injection System
M-761-00076-06 Process Control Block Diagram SNUPPS                         6
Condition Reports
Condition Reports
2520 122524 122526 122527 122784 122954 124387 124400 124405   Work Orders
2520             122524             122526             122527           122784
13-366290-005 15-403582-002 17-427200-023 17-432721-000 17-432722-000 18-438909-000 18-438919-001 18-438923-001   Miscellaneous
2954            124387             124400             124405
Number Title Date APF 29B-003-01 Surveillance Test Routing Sheet (STRS)  
Work Orders
- Fuel Pool Cooling and Cleanup System Valve Test
13-366290-005     15-403582-002     17-427200-023     17-432721-000   17-432722-000
April 23, 2018 STN EM-100A SI Pump A Reference Pump
18-438909-000     18-438919-001     18-438923-001
Completed April 29, 2018 STS EM-100A Safety Injection Pump "A" Inservice Pump Test
Miscellaneous
Completed May 11, 2018
Number           Title                                                     Date
STS KJ-015B Manual/Auto Fast Start, Sync & Loading of EDG NE02
APF 29B-003-01 Surveillance Test Routing Sheet (STRS) - Fuel Pool           April 23,
Completed May 1, 2018
Cooling and Cleanup System Valve Test                     2018
71111.20-Refueling and Other Outage Activities
STN EM-100A       SI Pump A Reference Pump                                 Completed
April 29,
2018
STS EM-100A       Safety Injection Pump A Inservice Pump Test             Completed
May 11, 2018
STS KJ-015B       Manual/Auto Fast Start, Sync & Loading of EDG NE02       Completed
May 1, 2018
71111.20Refueling and Other Outage Activities
Procedures
Procedures
Number Title Revision AI-07B-024 Instructions For Containment Purge Permits
Number           Title                                                     Revision
FHP 05-001 Equipment Hatch Operations
AI-07B-024       Instructions For Containment Purge Permits               18
GEN 00-002 Cold Shutdown to Hot Standby
FHP 05-001       Equipment Hatch Operations                               0
101
GEN 00-002       Cold Shutdown to Hot Standby                             101
Procedures
Procedures
Number Title Revision GEN 00-003 Hot Standby to Minimum Load
Number     Title                                                   Revision
101 GEN 00-008 RCS Level Less Than Reactor Vessel Flange Operations
GEN 00-003 Hot Standby to Minimum Load                             101
INC C-0044 Functional Check of 7300 Process Power Supply
GEN 00-008 RCS Level Less Than Reactor Vessel Flange Operations     32
RXE 01-002 Reload Low Power Physics Testing
INC C-0044 Functional Check of 7300 Process Power Supply           7
STS CR-002 Shift Log for Modes 4, 5, and
RXE 01-002 Reload Low Power Physics Testing                         26
84 STS GP-006 CTMT Closure Verification
STS CR-002 Shift Log for Modes 4, 5, and 6                          84
24A SYS BB-112 Vacuum Fill of the RCS
STS GP-006 CTMT Closure Verification                               24A
SYS BB-215 RCS Drain Down With Fuel In Reactor
SYS BB-112 Vacuum Fill of the RCS                                   43
47A SYS BB-215 RCS Drain Down With Fuel In Reactor
SYS BB-215 RCS Drain Down With Fuel In Reactor                     47A
SYS SB-300 Deenergizing SB Protection Sets
SYS BB-215 RCS Drain Down With Fuel In Reactor                     48
Drawings Number Title Revision E-13NN01 Class IE Instrument AC Schematic
SYS SB-300 Deenergizing SB Protection Sets                         5
E-13SB09 Schematic Diagram Process Protection Cabinets 1,2,3,4 Safeguards Test Cabinets and Fire Isolation Cabinets
Drawings
M-12BB01 Piping and Instrumentation Diagram Reactor Coolant System 36 M-12BB02 Piping and Instrumentation Diagram Reactor Coolant System 28 M-12BB04 Piping and Instrumentation Diagram Reactor Coolant System 23 M-12EJ01 Piping and Instrumentation Diagram Residual Heat Removal System
Number     Title                                                   Revision
M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant Injection System
E-13NN01   Class IE Instrument AC Schematic                         9
M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant Injection System
E-13SB09   Schematic Diagram Process Protection Cabinets 1,2,3,4   00
M-12EM02 Piping and Instrumentation Diagram High Pressure Coolant Injection System
Safeguards Test Cabinets and Fire Isolation Cabinets
M-12EM03 Piping and Instrumentation Diagram High Pressure Coolant Injection System Test Line
M-12BB01   Piping and Instrumentation Diagram Reactor Coolant       36
System
M-12BB02   Piping and Instrumentation Diagram Reactor Coolant       28
System
M-12BB04   Piping and Instrumentation Diagram Reactor Coolant       23
System
M-12EJ01   Piping and Instrumentation Diagram Residual Heat         54
Removal System
M-12EM01   Piping and Instrumentation Diagram High Pressure Coolant 44
Injection System
M-12EM01   Piping and Instrumentation Diagram High Pressure Coolant 45
Injection System
M-12EM02   Piping and Instrumentation Diagram High Pressure Coolant 22
Injection System
M-12EM03   Piping and Instrumentation Diagram High Pressure Coolant 3
Injection System Test Line
Condition Reports
Condition Reports
20865 120906 120917 120934 120963 121467 121469 121507 121575 121710 121779 121825 121881 121901 121938 121953 122359 122375 122571 122593 122787 122798 122837 123075 123087 123221 123429 123434 123440 123444 123446 123448 123488 123500 123517 123752 123767     Work Orders
20865           120906               120917             120934         120963
17-426098-000 18-437026-000     Miscellaneous
21467            121469               121507             121575         121710
Documents Number Title Revision/Date Foreign Material Inspections During Wolf Creek RF 22 Failed Fuel Mitigation  
21779            121825               121881             121901         121938
- Presenter Daljit Mand
21953            122359               122375             122571         122593
2787            122798               122837             123075         123087
23221            123429               123434             123440         123444
23446            123448               123488             123500         123517
23752            123767
Work Orders
17-426098-000     18-437026-000
Miscellaneous Documents
Number           Title                                                   Revision/Date
Foreign Material Inspections During Wolf Creek RF 22
Failed Fuel Mitigation - Presenter Daljit Mand
OPS RF-22 Rotation Schedule
OPS RF-22 Rotation Schedule
Refuel 22: Failed Fuel Action Matrix for Completion Core Testing January 4, 2018 RF22 OCC Shift Update
Refuel 22: Failed Fuel Action Matrix for Completion Core January 4,
- Nights April 6, 2018
Testing                                                  2018
RF22 OCC Shift Update
RF22 OCC Shift Update - Nights                           April 6, 2018
- Days April 11, 2018
RF22 OCC Shift Update - Days                             April 11, 2018
RF22 OCC Shift Update
RF22 OCC Shift Update - Nights                           April 11, 2018
- Nights April 11, 2018
RF22 OCC Shift Update - Nights                           April 12, 2018
RF22 OCC Shift Update
RF22 OCC Shift Update - Nights                           April 13, 2018
- Nights April 12, 2018
RF22 OCC Shift Update - Days                            April 15, 2018
RF22 OCC Shift Update
RF22 OCC Shift Update - Nights                          April 16, 2018
- Nights April 13, 2018
RF22 OCC Shift Update - Days                            April 17, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                          April 18, 2018
- Day s April 15, 2018
RF22 OCC Shift Update - Nights                           April 19, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Days                            April 25, 2018
- Night s April 16, 2018
RF22 OCC Shift Update - Nights                          April 26, 2018
RF22 OCC Shift Update - Day s April 17, 2018
RF22 OCC Shift Update - Days                            April 29, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                          April 29, 2018
- Night s April 18, 2018
Miscellaneous Documents
RF22 OCC Shift Update
Number           Title                                             Revision/Date
- Nights April 19, 2018
RF22 OCC Shift Update - Days                      April 30, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    April 30, 2018
- Day s April 25, 2018
RF22 OCC Shift Update - Days                      May 1, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    May 1, 2018
- Night s April 26, 2018
RF22 OCC Shift Update - Days                      May 2, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    May 2, 2018
- Day s April 29, 2018 RF22 OCC Shift Update  
RF22 OCC Shift Update - Days                      May 3, 2018
- Night s April 29, 2018
RF22 OCC Shift Update - Nights                    May 4, 2018
 
RF22 OCC Shift Update - Nights                    May 4, 2018
Miscellaneous
RF22 OCC Shift Update - Days                      May 6, 2018
Documents Number Title Revision/Date RF22 OCC Shift Update  
RF22 OCC Shift Update - Days                      May 7, 2018
- Day s April 30, 2018
RF22 OCC Shift Update - Nights                    May 7, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Days                      May 8, 2018
- Night s April 30, 2018
RF22 OCC Shift Update - Nights                    May 8, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Days                      May 9, 2018
- Day s May 1, 2018
RF22 OCC Shift Update - Nights                    May 9, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    May 10, 2018
- Night s May 1, 2018
RF22 OCC Shift Update - Days                      May 13, 2018
RF22 OCC Shift Update - Day s May 2, 2018
RF22 OCC Shift Update - Days                      May 14, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    May 14, 2018
- Night s May 2, 2018
RF22 OCC Shift Update - Days                      May 15, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    May 15, 2018
- Day s May 3, 2018 RF22 OCC Shift Update  
RF22 OCC Shift Update - Days                      May 16, 2018
- Night s May 4, 2018
RF22 OCC Shift Update - Days                      May 17, 2018
RF22 OCC Shift Update  
RF22 OCC Shift Update - Nights                    May 17, 2018
- Night s May 4, 2018
RF22 OCC Shift Update  
- Day s May 6, 2018
RF22 OCC Shift Update  
- D ay s May 7, 2018
RF22 OCC Shift Update
- Night s May 7, 2018
RF22 OCC Shift Update
- Day s May 8, 2018
RF22 OCC Shift Update
- Night s May 8, 2018
RF22 OCC Shift Update  
- Day s May 9, 2018 RF22 OCC Shift Update  
- Night s May 9, 2018
RF22 OCC Shift Update  
- Night s May 10, 2018
RF22 OCC Shift Update
- Day s May 13, 2018
RF22 OCC Shift Update
- Day s May 14, 2018
RF22 OCC Shift Update
- Night s May 14, 2018
RF22 OCC Shift Update
  - Day s May 15, 2018
RF22 OCC Shift Update
- Night s May 15, 2018
RF22 OCC Shift Update
- Day s May 16, 2018
RF22 OCC Shift Update
- Day s May 17, 2018
RF22 OCC Shift Update
- Night s May 17, 2018
RF2[2] FIN Team Schedule
RF2[2] FIN Team Schedule
AIF 21-016-02 Time Verification Form  
AIF 21-016-02   Time Verification Form - Days - Credited         April 3, 2018
- Days - Credited April 3, 2018
AIF 21-016-02   Time Verification Form - Nights - Credited       April 3, 2018
AIF 21-016-02 Time Verification Form  
AIF 21-016-02   Time Verification Form - Nights - No Credit Taken April 3, 2018
- Nights - Credited April 3, 2018
AIF 22D-008-02   Mode 2 (M2U)/Mode 1 (M1U) Restart Checklist       Completed
AIF 21-016-02 Time Verification Form  
- Nights - No Credit Taken
April 3, 2018
AIF 22D-008-02 Mode 2 (M2U)/Mode 1 (M1U) Restart Checklist
Completed
May 17, 2108
May 17, 2108
 
Miscellaneous Documents
Miscellaneous
Number           Title                                             Revision/Date
Documents Number Title Revision/Date APF 15C-002-01 Procedure Cover Sheet  
APF 15C-002-01 Procedure Cover Sheet - Vacuum Fill of the RCS       Completed
- Vacuum Fill of the RCS
Completed
May 11, 2018
May 11, 2018
APF 21-001-02 Control Room Turnover Checklist  
APF 21-001-02   Control Room Turnover Checklist - On-Coming CRS/WC May 7, 2018
- On-Coming CRS/WC SRO/RO/BOP Review
SRO/RO/BOP Review
May 7, 2018
APF 22B-001-08 Shutdown Risk Assessment Mode 6 Refueling Operations 12
APF 22B-001-08 Shutdown Risk Assessment
                >23 Ft. Above Vessel Flange
Mode 6 Refueling Operations  
APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled         April 4, 2018
>23 Ft. Above Vessel
APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled          April 7, 2018
Flange 12 APF 22B-001-09 Shutdown Risk Assessment No Mode  
APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled         April 11, 2018
- Defueled April 4, 2018
APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled         April 14, 2018
APF 22B-001-09 Shutdown Risk Assessment
APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled         April 15, 2018
No Mode - Defu eled April 7, 2018
APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled         April 17, 2018
APF 22B-001-09 Shutdown Risk Assessment No Mode  
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 1, 2018
- Defueled April 11, 2018
Summary - Shift: Days, Mode 5
APF 22B-001-09 Shutdown Risk Assessment No Mode  
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 3, 2018
- Defueled April 14, 2018
Summary - Shift: Days, Mode 5
APF 22B-001-09 Shutdown Risk Assessment No Mode  
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 4, 2018
- Defueled April 15, 2018
Summary - Shift: Days, Mode 5
APF 22B-001-09 Shutdown Risk Assessment No Mode  
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 5, 2018
- Defueled April 17, 2018
Summary - Shift: Nights, Mode: 5
APF 22B-001-10 Shutdown Safety Function Status
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 6, 2018
& Assessment Summary - Shift: Days, Mode 5
Summary - Shift Days, Mode 6
April 1, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 7, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode 5
Summary - Shift: Days, Mode: 6
April 3, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 7, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode 5
Summary - Shift: Nights, Mode: 6
April 4, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         May 8, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Nights, Mode: 5
Summary - Shift: Nights, Mode: 6
April 5, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 11, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift Days, Mode 6
Summary - Shift: Days, Mode: Defueled
April 6, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 14, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode: 6
Summary - Shift: Nights, Mode: Defueled
April 7, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 15, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Nights, Mode: 6
Summary - Shift: Days, Mode: Defueled
April 7, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 15, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Nights, Mode: 6
Summary - Shift: Nights, Mode: Defueled
May 8, 2018
Miscellaneous Documents
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode: Defueled
Number           Title                                             Revision/Date
April 11, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment         April 17, 2018
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Nights, Mode: Defueled
Summary - Shift: Days, Mode: Defueled
April 14, 2018 APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode: Defueled
APF 22B-001-10 Shutdown Safety Function Status & Assessment         May 8, 2018
April 15, 2018
Summary - Shift: Days, Mode: Defueled
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Nights, Mode: Defueled
APF 25A-401-01 ALARA Review Package - RWP Number 181102             January 18,
April 15, 2018
2018
 
APF 25A-401-01 ALARA Review Package - RWP Number 182602             15
Miscellaneous
APF 25A-401-01 ALARA Review Package - RWP Number 183000             March 7, 2018
Documents Number Title Revision/Date APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode: Defueled
APF 25A-401-01 ALARA Review Package - RWP Number 182602             March 8, 2018
April 17, 2018
APF 25A-401-04 Pre-Job Briefing Form - RWP Number: 182601           10A
APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary - Shift: Days, Mode: Defueled
BGV0365         Mixed Bed Demins Inlet Line Upstrm Drain           20
May 8, 2018
C22: R-EN-A-     Clearance Order                                   April 2, 2018
APF 25A-401-01 ALARA Review Package  
2A
- RWP Number 181102 January 18, 2018 APF 25A-401-01 ALARA Review Package  
C22: R-EN-B-     Clearance Order                                   March 31, 2018
- RWP Number 182602
2A
APF 25A-401-01 ALARA Review Package  
C22: R-OP-S-     Clearance Order                                   May 4, 2018
- RWP Number 183000
001B
March 7, 2018
C22: R-OP-S-     Clearance Order                                   May 9, 2018
APF 25A-401-01 ALARA Review Package  
2A
- RWP Number 182602
C22: R-OP-S-     Clearance Order                                   May 11, 2018
March 8, 2018
2B
APF 25A-401-04 Pre-Job Briefing Form
C22: R-OP-S-     Clearance Order                                   May 6, 2018
- RWP Number: 182601
003A
10A BGV0365 Mixed Bed Demins Inlet Line Upstrm Drain
ET 88-0193       Docket No. 50-482: Generic Letter 88-17 - Loss of December 23,
C22: R-EN-A-002A Clearance Order
Decay Heat Removal                                 1988
April 2, 2018
ET 92-0001       Docket No. 50-482: Change in Commitment Associated January 2,
C22: R-EN-B-002A Clearance Order
with Generic Letter 88-17                         1992
March 31, 2018
GTRE 32         Wolf Creek Generating Station Chemistry Department Report Created
C22: R-OP-S-001B Clearance Order
Radiochemistry Lab                                 April 18, 2018,
May 4, 2018
2:36
C22: R-OP-S-002A Clearance Order
GTRE 32         Wolf Creek Generating Station Chemistry Department Report Created
May 9, 2018
Radiochemistry Lab                                 April 18, 2018,
C22: R-OP-S-002B Clearance Order
08:43
May 11, 2018
GTRE 32 Char     Wolf Creek Generating Station Chemistry Department Report Created
C22: R-OP-S-003A Clearance Order
Radiochemistry Lab                                 April 15, 2018,
May 6, 2018
14:59
ET 88-0193 Docket No. 50
Miscellaneous Documents
-482: Generic Letter 88
Number           Title                                               Revision/Date
-17 - Loss of Decay Heat Removal
GTRE 33         Wolf Creek Generating Station Chemistry Department   Report Created
December 23, 1988 ET 92-0001 Docket No. 50
Radiochemistry Lab                                   April 18, 2018,
-482: Change in Commitment Associated with Generic Letter 88
07:04
-17 January 2, 1992 GTRE 32 Wolf Creek Generating Station Chemistry Department Radiochemistry Lab
GTRE 33         Wolf Creek Generating Station Chemistry Department   Report Created
Report Created April 18, 2018, 02:36 GTRE 32 Wolf Creek Generating Station Chemistry Department Radiochemistry Lab
Radiochemistry Lab                                   April 18, 2018,
Report Created April 18, 2018, 08:43 GTRE 32 Char
07:05
Wolf Creek Generating Station Chemistry Department Radiochemistry Lab
K04-013         Gas Effluent Release Report                         April 16, 2018
Report Created April 15, 2018, 14:59
RA 18-0032       Minor Corrections to Refuel 22 Risk Assessment Team March 20, 2018
Miscellaneous
Report RA 18-0021 - Schedule Level 1 Rev. C 2/1/2018
Documents Number Title Revision/Date GTRE 33 Wolf Creek Generating Station Chemistry Department Radiochemistry Lab
RPF 02-105-01   Radiation Work Permit - 181102                       000
Report Created April 18, 2018, 07:04 GTRE 33 Wolf Creek Generating Station Chemistry Department Radiochemistry Lab
RPF 02-105-01   Radiation Work Permit - 182601                       000
Report Created April 18, 2018, 07:05 K04-013 Gas Effluent Release Report
RPF 02-105-01   Radiation Work Permit - 182602                       000
April 16, 2018
RPF 02-105-01   Radiation Work Permit - 182602                       002
RA 18-0032 Minor Corrections to Refuel 22 Risk Assessment Team Report RA 18
RFP 02-105-01   Radiation Work Permit - 184206                       000
-0021 - Schedule Level 1 Rev. C 2/1/2018
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180225-3 February 25,
March 20, 2018
2018
RPF 02-105-01 Radiation Work Permit  
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180320-   March 20, 2018
- 181102 000 RPF 02-105-01 Radiation Work Permit  
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180405-   April 5, 2018
- 182601 000 RPF 02-105-01 Radiation Work Permit  
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180416-1 April 16, 2018
- 182602 000 RPF 02-105-01 Radiation Work Permit  
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180407-6 April 7, 2018
- 182602 002 RFP 02-105-01 Radiation Work Permit  
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180421-   April 21, 2018
- 184206 000 RPF 02-210-01 WCGS Radiological Survey Map  
RPF 02-210-01   WCGS Radiological Survey Map - Survey M-20180406-   April 6, 2018
- Survey M-20180225-3 February 25, 2018 RPF 02-210-01 WCGS Radiological Survey Map  
RXE 01-002       Reload Low Power Physics Testing                     Completed
- Survey M-20180320-15 March 20, 2018
RPF 02-210-01 WCGS Radiological Survey Map  
- Survey M-20180405-26 April 5, 2018
RPF 02-210-01 WCGS Radiological Survey Map  
- Survey M-20180416-1 April 16, 2018
RPF 02-210-01 WCGS Radiological Survey Map  
- Survey M-20180407-6 April 7, 2018
RPF 02-210-01 WCGS Radiological Survey Map  
- Survey M-20180421-21 April 21, 2018
RPF 02-210-01 WCGS Radiological Survey Map  
- Survey M-20180406-27 April 6, 2018
RXE 01-002 Reload Low Power Physics Testing
Completed
May 17, 2018
May 17, 2018
STS CR-002 Shift Log for Modes 4, 5, and 6
STS CR-002       Shift Log for Modes 4, 5, and 6                     Completed
Completed
May 11, 2018
May 11, 2018
STS GP-006 Containment Closure Verification
STS GP-006       Containment Closure Verification                     Completed
Completed
April 6, 2018
April 6, 2018
WM 26-0034 Docket No. 50
WM 26-0034       Docket No. 50-482: Foreign Ownership, Control or     April 26, 2018
-482: Foreign Ownership, Control or Influence (FOCI) Information  
Influence (FOCI) Information - Change to Lists of
- Change to Lists of Owners, Officers, Directors and Executive Personne
Owners, Officers, Directors and Executive Personnel
l April 26, 2018
Miscellaneous Documents
 
Number            Title                                                    Revision/Date
WM 89-0041        Docket No. 50-482: Generic Letter 88-17 - Loss of        February 2,
Decay Heat Removal                                        1989
71111.22Surveillance Testing
Procedures
Number            Title                                                      Revision
STS BB-004        RCS Water Inventory Balance                                49
STS BB-006        RCS Water Inventory Balance Using the NPIS Computer        19
STS BB-010        Manual RCS Water Inventory Balance                          2
STS CV-210A      ECCS SI Pump Comprehensive and Inservice Check Valve        27
Test
STS EM-003A      ECCS (CCP) Flow Balance and CCP Comprehensive Test          23
STS KJ-001B      Integrated D/G and Safeguard Actuation Test - Train B      61
STS PE-128        LLRT [Local Leak Rate Test] Valve Lineup for Penetrations  6
and 29
Condition Reports
2451            122757            122783            123223
Miscellaneous
Miscellaneous
Documents Number Title Revision/Date WM 89-0041 Docket No. 50
Number           Title                                                     Revision/Date
-482:  Generic Letter 88
STS CV-210A      ECCS SI Pump Comprehensive and Inservice Check Valve      Completed
-17 - Loss of Decay Heat Removal
Test                                                      April 29, 2018
February 2, 1989  71111.22-Surveillance Testing
STS CV-210A      ECCS SI Pump Comprehensive and Inservice Check Valve      Completed
Test                                                      May 1, 2018
STS EM-003A      ECCS (CCP) Flow Balance and CCP Comprehensive Test        Completed
May 2, 2018
WCRE-03          Wolf Creek Tank Document                                  22
71124.01Radiological Hazard Assessment and Exposure Controls
Procedures
Procedures
Number Title Revision STS BB-004 RCS Water Inventory Balance
Number           Title                                                       Revision
STS BB-006 RCS Water Inventory Balance Using the NPIS Computer
AP 19D-100        Radioactive Source Program                                  5
STS BB-010 Manual RCS Water Inventory Balance
STS CV-210A ECCS SI Pump Comprehensive and Inservice Check Valve Test 27 STS EM-003A ECCS (CCP) Flow Balance and CCP Comprehensive Test
STS KJ-001B Integrated D/G and Safeguard Actuation Test
- Train B 61 STS PE-128 LLRT [Local Leak Rate Test] Valve Lineup for Penetrations
and 29 6  Condition Reports
2451 122757 122783 123223  Miscellaneous
Number Title Revision/Date STS CV-210A ECCS SI Pump Comprehensive and Inservice Check Valve Test Completed April 29, 2018
STS CV-210A ECCS SI Pump Comprehensive and Inservice Check Valve Test Completed May 1, 2018
STS EM-003A ECCS (CCP) Flow Balance and CCP Comprehensive Test
Completed May 2, 2018
WCRE-03 Wolf Creek Tank Document
71124.01-Radiological Hazard Assessment and Exposure Controls
Procedures
Procedures
Number Title Revision AP 19D-100 Radioactive Source Program
Number           Title                                                     Revision
Procedures
AP 25A-001       Radiation Protection Manual                               17B
Number Title Revision AP 25A-001 Radiation Protection Manual
AP 25A-100       Access to Locked High or Very High Rad Areas             29
17B AP 25A-100 Access to Locked
AP 25A-100       Containment Entry                                         18A
High or Very High Rad Areas
AP 25B-100       Radiation Worker Guidelines                               51
AP 25A-100 Containment Entry
AP 25B-300       RWP Program                                               24A
18A AP 25B-100 Radiation Worker Guidelines
Radiation Protection Organization, Responsibilities and
AP 25B-300 RWP Program
RPP 01-105                                                                  21
24A RPP 01-105 Radiation Protection Or ganization, Responsibilities and Code of Conduct
Code of Conduct
RPP 02-105 Radiation Work Permit 48 RPP 02-215 Posting of Radiological Controlled Areas
RPP 02-105       Radiation Work Permit                                     48
4A RPP 02-405 RCA Access Control
RPP 02-215       Posting of Radiological Controlled Areas                 34A
RPP 02-515 Release of Material from the RCA
RPP 02-405       RCA Access Control                                       20
RPP 02-605 Control and Inventory of Radioactive Sources
RPP 02-515       Release of Material from the RCA                         34
RPP 02-605       Control and Inventory of Radioactive Sources             18
Condition Reports
Condition Reports
2244 112935 112973 113053 113055 113627 113631 114261 116377 116509 116510 117296 119183 119223 120975 121159 121171 121281 121282 121568 Radiation Work Permits
2244           112935             112973             113053           113055
Number Title Revision 180021 Cartridge Filter Change
113627           113631             114261             116377           116509
-Out in Aux and RW Buildings
116510           117296             119183             119223           120975
182601 Routine Outage Access (No LHRA Access)
21159            121171             121281             121282           121568
183220 Primary S/G Eddy Current Testing
Radiation Work Permits
184199 Secondary Side S/G FOSAR
Number           Title                                                     Revision
184200 Secondary Side S/G Sludge Lance
180021           Cartridge Filter Change-Out in Aux and RW Buildings       0
184420 Scaffolding
2601            Routine Outage Access (No LHRA Access)                   0
184482 RV Head Disassembly  
183220           Primary S/G Eddy Current Testing                         1
- Canopy Seal Clamp Activities
184199           Secondary Side S/G FOSAR                                 0
184483 RV Head Reassembly  
184200           Secondary Side S/G Sludge Lance                           0
- Canopy Seal Clamp Activities
184420           Scaffolding                                               0
186020 Reactor Vessel Head Preparation
184482           RV Head Disassembly - Canopy Seal Clamp Activities       0
184483           RV Head Reassembly - Canopy Seal Clamp Activities         0
186020           Reactor Vessel Head Preparation                           1
Radiation Surveys
Radiation Surveys
Number Title Date M-20180305-17 1306 and 1308C
Number             Title                                           Date
March 5, 2018
M-20180305-17       1306 and 1308C                                   March 5, 2018
M-20180305-4 Resin Bed, Demin Alley, Filter Pit
M-20180305-4       Resin Bed, Demin Alley, Filter Pit               March 4, 2018
March 4, 2018
M-20180307-16       Seal Water HX & VCT Valve Room                   March 7, 2018
M-20180307-16 Seal Water HX & VCT Valve Room
M-20180307-2       B RHR HX Room                                   March 7, 2018
March 7, 2018
M-20180308-12       North and South Pipe Pen                         March 8, 2018
M-20180307-2 B RHR HX Room
M-20180324-6       SJ 143 Sample Panel                             March 24, 2018
March 7, 2018
M-20180329-1       B RHR Pump                                       March 29, 2018
M-20180308-12 North and South Pipe Pen
M-20180402-20       S/G A&D Secondary                               April 2, 2018
March 8, 2018
M-20180403-2       S/G A&D Secondary                               April 3, 2018
M-20180324-6 SJ 143 Sample Panel
M-20180409-19       2000 Aux South                                   April 9, 2018
March 24, 2018
M-20180411-11       S/G A&D Secondary                               April 11, 2018
M-20180329-1 B RHR Pump
M-20180411-21       2047 Containment                                 April 11, 2018
March 29, 2018
M-20180402-20 S/G A&D Secondary
April 2, 2018
M-20180403-2 S/G A&D Secondary
April 3, 2018
M-20180409-19 2000 Aux South
April 9, 2018
M-20180411-11 S/G A&D Secondary
April 11, 2018
M-20180411-21 2047 Containment
April 11, 2018
Air Sample Surveys
Air Sample Surveys
Number Title Date 18-0129 Containment RX Cavity April 1, 2018
Number       Title                                                 Date
18-0131 CTMT 2000' O/S Bio
18-0129       Containment RX Cavity                                 April 1, 2018
-shield April 1, 2018
18-0131       CTMT 2000' O/S Bio-shield                             April 1, 2018
18-0147 Fuel Building 2047' & above
18-0147       Fuel Building 2047 & above                           April 2, 2018
April 2, 2018
18-0154       CTMT 2047'                                             April 3, 2018
18-0154 CTMT 2047'
18-0181       CTMT 2047 (Marinelli Grab Sample)                     April 4, 2018
April 3, 2018
18-0182       CTMT 2047 (Follow-up West of Cavity)                   April 4, 2018
18-0181 CTMT 2047 (Marinelli Grab Sample)
18-0182       CTMT 2047 (Follow-up West of Cavity)                   April 4, 2018
April 4, 2018
Audits and Self-Assessments
18-0182 CTMT 2047 (Follow
Number             Title                                             Date
-up West of Cavity) April 4, 2018
QA Audit Report:
18-0182 CTMT 2047 (Follow
18-01-RP/PC                                                         March 12, 2018
-up West of Cavity)
Radiation Protection And Process Control
April 4, 2018
Self-Assessment:
Audits and Self
QH-2017-1476       Radiation Protection Procedures and Radiation     May 4, 2017
-Assessments
Worker Behavior Observations
Number Title Date 18-01-RP/PC QA Audit Report: Radiation Protection And Process Control
Radiation Protection Programmatic Review as
March 12, 2018
QH-2017-1481       delineated in NRC Inspection Procedures 71124.01, April 24, 2017
QH-2017-1476 Se lf-Assessment:
71124.03, and 71151.OR01
Radiation Protection Procedures and Radiation Worker Behavior Observations
Miscellaneous Documents
May 4, 2017
Number           Title                                         Date
QH-2017-1481 Radiation Protection Programmatic Review as delineated in NRC Inspection Procedures 71124.01, 71124.03, and 71151.OR01
18-0181           Skin Dose From Noble Gas Calculation Sheet     April 4, 2018
April 24, 2017
K 03-70           Air Sample Log                                 April 4, 2018
 
RPF 02-605-03     Sealed Source Inventory                       January 29, 2018
Miscellaneous Documents Number Title Date 18-0181 Skin Dose From Noble Gas Calculation Sheet
STS HP-001       Sealed Source Contamination Surveillance Test January 29, 2018
April 4, 2018
71124.02Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls
K 03-70 Air Sample Log
April 4, 2018
RPF 02-605-03 Sealed Source Inventory January 29, 2018
STS HP-001 Sealed Source Contamination Surveillance Test
January 29, 2018 71124.02-Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls
Procedures
Procedures
Number Title Revision AP 25A-401 ALARA Program
Number           Title                                                 Revision
AP 25A-410 ALARA Committee
AP 25A-401       ALARA Program                                         25
AP 25B-300 RWP Program
AP 25A-410       ALARA Committee                                       23
24A APF 25A-401-01 ALARA Review Package
AP 25B-300       RWP Program                                           24A
APF 25A-401-04 Pre-Job Briefing Form
APF 25A-401-01 ALARA Review Package                                     15
10A APF 25A-401-07 In-Progress ALARA Review
APF 25A-401-04 Pre-Job Briefing Form                                     10A
APF 25A-401-08 Post-Job ALARA Review
APF 25A-401-07 In-Progress ALARA Review                                 1
RPF 02-105-05 RWP Risk Assessment
APF 25A-401-08 Post-Job ALARA Review                                     1
16A RPP 02-105 RWP 48 RPP 02-605 Control & Inventory of Radioactive Sources
RPF 02-105-05     RWP Risk Assessment                                   16A
Condition Reports 112973 113052 113056 113057 113058 113627 113631 113708 113736 113762 114261 114915 115344 115564 115795 116952 117296 118610 119253 119743 119745 120919 120921 121089 121091 121099 121197 121217 121266 121270 121341 121375 121420 121422 121447 121482
RPP 02-105       RWP                                                   48
Audits and Self
RPP 02-605       Control & Inventory of Radioactive Sources             18
-Assessments
Condition Reports
Number Title Date 18-01-RP/PC Quality Assurance Audit Report
2973            113052             113056           113057       113058
113627           113631             113708           113736       113762
114261           114915             115344           115564       115795
116952           117296             118610           119253       119743
119745           120919             120921           121089       121091
21099            121197             121217           121266       121270
21341            121375             121420           121422       121447
21482
Audits and Self-Assessments
Number           Title                                               Date
Quality Assurance Audit Report
18-01-RP/PC                                                           March 12, 2018
Radiation Protection and Process Control
Radiation Protection and Process Control
March 12, 2018
Radiation Protection Programmatic Review as
QH-2017-1481 Radiation Protection Programmatic Review as delineated in NRC Inspection Procedures 71124.01, 71124.03, and 71151.OR01
QH-2017-1481     delineated in NRC Inspection Procedures 71124.01,   April 24, 2017
April 24, 2017
71124.03, and 71151.OR01
QH-2017-1505 NRC Inspection Procedure 71124.04, Occupational Dose Assessment and NRC 71124.02 Occupational ALARA Planning and Controls
NRC Inspection Procedure 71124.04, Occupational
May 22, 2017
QH-2017-1505      Dose Assessment and NRC 71124.02 Occupational       May 22, 2017
ALARA Planning and Controls
Radiation Work Permit Packages
Radiation Work Permit Packages
Number Title Revision 180021 Cartridge Filter Change
Number           Title                                                       Revision
-Out in Aux and RW Buildings
180021           Cartridge Filter Change-Out in Aux and RW Buildings         A
A 182300 Maintenance Support
2300            Maintenance Support                                         0
182601 Routine Outage Access (No Locked High Radiation Areas)
2601            Routine Outage Access (No Locked High Radiation Areas)     0
183220 Primary S/G Eddy Current RWP
183220           Primary S/G Eddy Current RWP                               1
184207 RCP Team Seal Replacement on C & D RCP's
184207           RCP Team Seal Replacement on C & D RCPs                    0
184207 RCP Team Seal Replacement on C & D RCP's
184207           RCP Team Seal Replacement on C & D RCPs                    1
184207 RCP Team Seal Replacement on C & D RCP's
184207           RCP Team Seal Replacement on C & D RCPs                    2
184420 Scaffolding Activities RF22
184420           Scaffolding Activities RF22                                 0
184482 Canopy Seal Clamp Activities Disassembly
184482           Canopy Seal Clamp Activities Disassembly                   0
Miscellaneous Documents
Miscellaneous Documents
Title Date RF 21 & Pre RF21 Forced Outage Radiation Protection Summary
Title                                                                 Date
January 9, 2017 71151-Performance Indicator Verification
RF 21 & Pre RF21 Forced Outage Radiation Protection Summary           January 9, 2017
71151Performance Indicator Verification
Procedures
Procedures
Number Title Revision AP 02A-001 Primary Chemistry Control
Number           Title                                                     Revision
CHS SJ-143B RCS/CVCS/RHR Sampling at SJ
AP 02A-001       Primary Chemistry Control                                 21
-143 Panel 2 STS BB-006 RCS Water Inventory Balance Using the NPIS Computer
CHS SJ-143B       RCS/CVCS/RHR Sampling at SJ-143 Panel                     2
STS BB-006       RCS Water Inventory Balance Using the NPIS Computer       18
Condition Reports
Condition Reports
23874 123885 124426 124427   Miscellaneous
23874             123885             124426             124427
Number Title Date RCS Measurement Reports June 2017 through June 2018
Miscellaneous
Printed June 20, 2018 STS PE-019B RHR Suction Valve Leak Test
Number           Title                                                   Date
Completed November 18, 2016 STS PE-109E RCS Isolation Check Valve Leak Test
RCS               June 2017 through June 2018                             Printed June 20,
Completed November 19, 2016 71152-Problem Identification and Resolution
Measurement                                                                2018
Reports
STS PE-019B       RHR Suction Valve Leak Test                             Completed
November 18,
2016
STS PE-109E       RCS Isolation Check Valve Leak Test                     Completed
November 19,
2016
71152Problem Identification and Resolution
Procedures
Procedures
Number Title Revision AP 10-104 Breach Authorization
Number           Title                                                       Revision
AP 10-104 Breach Authorization
AP 10-104         Breach Authorization                                       35
37A AP 23-009 Control Room Envelope Habitability Program
AP 10-104         Breach Authorization                                       37A
OFN SB-008 Instrument Malfunctions
AP 23-009         Control Room Envelope Habitability Program                 2
STS IC-503B Pressurizer Level Instrumentation Channel Calibration
OFN SB-008       Instrument Malfunctions                                     45
STS PE-004 Aux Building and Control Room Pressure Test
STS IC-503B       Pressurizer Level Instrumentation Channel Calibration       12
STS PE-004       Aux Building and Control Room Pressure Test                 16
Condition Reports
Condition Reports
20056 120807 122587 123642 123823 Work Orders
20056             120807             122587             123642           123823
18-437033-006     Miscellaneous
Work Orders
Number Title Revision/ Date QA-2018-0421 Oversight of Operations During the First Quarter of 2018 from 12/21/17 to 3/29/18
18-437033-006
April 20, 2018
Miscellaneous
Number           Title                                                       Revision/
Date
QA-2018-0421     Oversight of Operations During the First Quarter of 2018   April 20,
from 12/21/17 to 3/29/18                                   2018
Miscellaneous
Miscellaneous
Number Title Revision/ Date QA-2018-0425 QA Assessment of the Maintenance 2018 First Quarter FAO Report on 4/2/19
Number       Title                                                       Revision/
April 22, 2018 QA-2018-0426 Provide QA Oversight of Engineering for the First Quarter of
Date
2018 April 20, 2018 QA-2018-0434 RF22 QA Assessment of Refuel Pool Overfill on 4
QA-2018-0425 QA Assessment of the Maintenance 2018 First Quarter FAO April 22,
-7-18 April 29, 2018 QH-2018-1628 FME Quick Hit Self-Assessment
Report on 4/2/19                                             2018
May 23, 2018
QA-2018-0426 Provide QA Oversight of Engineering for the First Quarter of April 20,
QS-2018-2504 QA Surveillance of Clearance Order Removal
2018                                                        2018
February 5, 2018 QS-2018-2510 Surveillance of CARB Meeting 1
QA-2018-0434 RF22 QA Assessment of Refuel Pool Overfill on 4-7-18         April 29,
-17-18 February 5, 2018 QS-2018-2517 QA Observation of Question About Compensatory Measure Fire Watch on 1/22/18 February 5, 2018 QS-2018-2530 Power Block Roof Leaks
2018
February 7, 2018 QS-2018-2587 Attended and Observed Meeting on Effects of Modifications
QH-2018-1628 FME Quick Hit Self-Assessment                               May 23, 2018
269 March 26, 2018 QS-2018-2597 QA Walkdown of Turbine and Control Buildings
QS-2018-2504 QA Surveillance of Clearance Order Removal                   February 5,
March 28, 2018 QS-2018-2 601 RF22 Observation of Operations Just In Time Training for Plant Cooldown
2018
April 2, 2018
QS-2018-2510 Surveillance of CARB Meeting 1-17-18                         February 5,
QS-2018-2646 RF22 QA Observation of Holes Being Drilled for SGK05 Modification Work on 4/8/18
2018
April 8, 2018
QS-2018-2517 QA Observation of Question About Compensatory Measure       February 5,
QS-2018-2649 RF 22 QA Review of FME Monitor Logs in Containment on 4/8/18 April 9, 2018
Fire Watch on 1/22/18                                       2018
QS-2018-2679 RF22 QA Observation of BHI Workers 4
QS-2018-2530 Power Block Roof Leaks                                       February 7,
-12-18 April 13, 2018 RA 18-0054 Docket No. 50
2018
-482: Wolf Creek Generating Station Cycle 22 and Cycle 23 Core Operating Limits Report
QS-2018-2587 Attended and Observed Meeting on Effects of Modifications   March 26,
April 29, 2018 STS PE-004 Aux Building and Control Room Pressure Test
269                                                        2018
Completed March 7, 2018 STS PE-004 Aux Building and Control Room Pressure Test
QS-2018-2597 QA Walkdown of Turbine and Control Buildings                 March 28,
Completed March 15, 2018 WCRE-35 Boundary Matrix
2018
QS-2018-2601  RF22 Observation of Operations Just In Time Training for     April 2, 2018
Plant Cooldown
QS-2018-2646 RF22 QA Observation of Holes Being Drilled for SGK05         April 8, 2018
Modification Work on 4/8/18
QS-2018-2649 RF 22 QA Review of FME Monitor Logs in Containment on       April 9, 2018
4/8/18
QS-2018-2679 RF22 QA Observation of BHI Workers 4-12-18                   April 13,
2018
RA 18-0054   Docket No. 50-482: Wolf Creek Generating Station Cycle       April 29,
and Cycle 23 Core Operating Limits Report                 2018
STS PE-004   Aux Building and Control Room Pressure Test                 Completed
March 7,
2018
STS PE-004   Aux Building and Control Room Pressure Test                 Completed
March 15,
2018
WCRE-35       Boundary Matrix                                             0
Miscellaneous
Miscellaneous
Number Title Revision/ Date WCRE-35 Boundary Matrix
Number       Title                 Revision/
Date
WCRE-35       Boundary Matrix       3
PAPERWORK REDUCTION ACT STATEMENT
PAPERWORK REDUCTION ACT STATEMENT
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.
This letter does not contain new or amended information collection requirements subject to the
: [[contact::S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget]], Control Number 31500011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number. This letter and
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading
requirements were approved by the Office of Management and Budget, Control
-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, and Requests for Withholding."
Number 31500011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, and Requests for
Withholding.
Information Request
Information Request
January 24, 2018 Notification of Inspection and Request for Information
January 24, 2018
Notification of Inspection and Request for Information
Wolf Creek Nuclear Operating Station
Wolf Creek Nuclear Operating Station
NRC Inspection Report 05000482/2018002
NRC Inspection Report 05000482/2018002
INSERVICE INSPECTION DOCUMENT REQUEST
INSERVICE INSPECTION DOCUMENT REQUEST
A. Information Requested for the In
A. Information Requested for the In-Office Preparation Week
-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
The following information should be sent to the Region IV office in hard copy or electronic format (ims.certrec.com preferred), in care of
format (ims.certrec.com preferred), in care of Isaac Anchondo, by March 26, 2018, to
Isaac Anchondo, by March 26, 2018, to facilitate the selection of specific items that will be reviewed during the onsite inspection week. The inspector will select specific items from the information requested below and then request from your staff additional documents needed
facilitate the selection of specific items that will be reviewed during the onsite inspection
during the onsite inspection week (Section B of this enclosure). We ask that the specific items selected from the lists be available and ready for review on the first day of inspection. Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the inspector(s), and provide subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the inspector as soon as possible.
week. The inspector will select specific items from the information requested below and then
On April 16, 2018, a reactor inspector from the Nuclear Regulatory Commission's
request from your staff additional documents needed during the onsite inspection week
(NRC) Region IV office will perform the baseline inservice inspection at Wolf Creek Nuclear Operating Station, using NRC Inspection Procedure 71111.08, "Inservice Inspection Activities.Experience has shown that this inspection is a resource intensive inspection both for the NRC inspector and your staff. The date of this inspection may change dependent on the outage schedule you provide. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. These documents have been divided into two groups. The first group (Section
    (Section B of this enclosure). We ask that the specific items selected from the lists be
A of the enclosure) identified information to be provided prior to the inspection to ensure that the inspector is adequately prepared. The second group (Section
available and ready for review on the first day of inspection. Please provide requested
B of the enclosure) identifies the information the inspector will need upon
documentation electronically if possible. If requested documents are large and only hard
arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the onsite portions of the inspection.
copy formats are available, please inform the inspector(s), and provide subject
We have discussed the schedule for these inspection
documentation during the first day of the onsite inspection.
activities with your staff and understand that our regulatory contact for this inspection will
If you have any questions regarding this information request, please call the inspector as
be William Muilenburg
soon as possible.
of your licensing organization. The tentative inspection schedule is as follows:
On April 16, 2018, a reactor inspector from the Nuclear Regulatory Commissions (NRC)
Region IV office will perform the baseline inservice inspection at Wolf Creek Nuclear
Operating Station, using NRC Inspection Procedure 71111.08, "Inservice Inspection
Activities. Experience has shown that this inspection is a resource intensive inspection
both for the NRC inspector and your staff. The date of this inspection may change
dependent on the outage schedule you provide. In order to minimize the impact to your
onsite resources and to ensure a productive inspection, we have enclosed a request for
documents needed for this inspection. These documents have been divided into two
groups. The first group (Section A of the enclosure) identified information to be provided
prior to the inspection to ensure that the inspector is adequately prepared. The second
group (Section B of the enclosure) identifies the information the inspector will need upon
arrival at the site. It is important that all of these documents are up to date and complete in
order to minimize the number of additional documents requested during the preparation
and/or the onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and
understand that our regulatory contact for this inspection will be William Muilenburg of your
licensing organization. The tentative inspection schedule is as follows:
Preparation week: March 26, 2018
Preparation week: March 26, 2018
Onsite weeks: April
Onsite weeks: April 16-27, 2018
16-27, 2018 Our inspection dates are subject to change based on your updated schedule of outage activities. If there are any questions about this inspection or the material requested, please contact Isaac Anchondo at (817) 200
Our inspection dates are subject to change based on your updated schedule of outage
-1152. (email to: Isaac.Anchondo@nrc.gov
activities. If there are any questions about this inspection or the material requested, please
). A.1 ISI/Welding Programs and Schedule Information
contact Isaac Anchondo at (817) 200-1152. (email to: Isaac.Anchondo@nrc.gov).
A.1     ISI/Welding Programs and Schedule Information
1. A detailed schedule (including preliminary dates) of:
1. A detailed schedule (including preliminary dates) of:
1.1. Nondestructive examinations planned for ASME Code Class Components performed as part of your ASME Section XI, risk informed (if applicable), and augmented inservice inspection programs during the upcoming outage.
1.1. Nondestructive examinations planned for ASME Code Class Components
1.2. Examinations planned for Alloy 82/182/600 components that are not included in the Section XI scope (If applicable)
performed as part of your ASME Section XI, risk informed (if applicable), and
1.3. Examinations planned as part of your boric acid corrosion control program (Mode 3 walkdowns, bolted connection walkdowns, etc.)
augmented inservice inspection programs during the upcoming outage.
1.4. Welding activities that are scheduled to be completed during the upcoming outage (ASME Class 1, 2, or 3 structures, systems, or components)
1.2. Examinations planned for Alloy 82/182/600 components that are not included in
2. A copy of ASME Section XI Code Relief Requests and associated NRC safety evaluations applicable to the examinations identified above.
the Section XI scope (If applicable)
2.1. A list of ASME Code Cases currently being used to include the system and/or component the Code Case is being applied to.
1.3. Examinations planned as part of your boric acid corrosion control program
3. A list of nondestructive examination reports which have identified recordable or rejectable indications on any ASME Code Class components since the beginning of the last refueling outage. This should include the previous Section XI pressure test(s) conducted during start up and any evaluations
                  (Mode 3 walkdowns, bolted connection walkdowns, etc.)
associated with the results of the pressure tests.
1.4. Welding activities that are scheduled to be completed during the upcoming
4. A list including a brief description (e.g., system, code class, weld category, nondestructive examination performed) associated with the repair/replacement activities of any ASME Code Class component since the beginning of the last outage and/or planned this refueling outage.
outage (ASME Class 1, 2, or 3 structures, systems, or components)
5. If reactor vessel weld examinations required by the ASME Code are scheduled to occur during the upcoming outage, provide a detailed description of the welds to be
2. A copy of ASME Section XI Code Relief Requests and associated NRC safety
examined and the extent of the planned examination. Please also provide reference numbers for applicable procedures that will be used to conduct these examinations.
evaluations applicable to the examinations identified above.
6. Copy of any 10 CFR Part 21 reports applicable to structures, systems, or components within the scope of Section XI of the ASME Code that have been identified since the beginning of the last refueling outage.
2.1. A list of ASME Code Cases currently being used to include the system and/or
7. A list of any temporary non
component the Code Case is being applied to.
-code repairs in service (e.g., pinhole leaks).
3. A list of nondestructive examination reports which have identified recordable or
8. Please provide copies of the most recent self
rejectable indications on any ASME Code Class components since the beginning of
-assessments for the inservice inspection, welding, and Alloy 600 programs.
the last refueling outage. This should include the previous Section XI pressure test(s)
9. Copy of the procedures for welding techniques, and NDE that will be used during the outage. A.2 Reactor Pressure Vessel Head
conducted during start up and any evaluations associated with the results of the
1. Provide a detailed scope of the planned bare metal visual examinations (e.g., volum
pressure tests.
e coverage, limitations, etc.) of the vessel upper head penetrations and/or any nonvisual nondestructive examination of the reactor vessel head including the examination procedures to be used.
4. A list including a brief description (e.g., system, code class, weld category,
nondestructive examination performed) associated with the repair/replacement
activities of any ASME Code Class component since the beginning of the last outage
and/or planned this refueling outage.
5. If reactor vessel weld examinations required by the ASME Code are scheduled to
occur during the upcoming outage, provide a detailed description of the welds to be
examined and the extent of the planned examination. Please also provide reference
numbers for applicable procedures that will be used to conduct these examinations.
6. Copy of any 10 CFR Part 21 reports applicable to structures, systems, or
components within the scope of Section XI of the ASME Code that have been
identified since the beginning of the last refueling outage.
7. A list of any temporary non-code repairs in service (e.g., pinhole leaks).
8. Please provide copies of the most recent self-assessments for the inservice
inspection, welding, and Alloy 600 programs.
9. Copy of the procedures for welding techniques, and NDE that will be used during the
outage.
A.2 Reactor Pressure Vessel Head
1. Provide a detailed scope of the planned bare metal visual examinations (e.g., volume
coverage, limitations, etc.) of the vessel upper head penetrations and/or any
nonvisual nondestructive examination of the reactor vessel head including the
examination procedures to be used.
A.3 Boric Acid Corrosion Control Program
A.3 Boric Acid Corrosion Control Program
1. Copy of the procedures that govern the scope, equipment and implementation of the inspections required to identify boric acid leakage and the procedures for boric acid leakage/corrosion evaluation.
1. Copy of the procedures that govern the scope, equipment and implementation of the
2. Please provide a list of leaks (including code class of the components) that
inspections required to identify boric acid leakage and the procedures for boric acid
have been identified since the last refueling outage and associated corrective action documentation. If during the last cycle, the unit was shutdown, please provide documentation of containment walkdown inspections performed as part of the boric acid corrosion control program.
leakage/corrosion evaluation.
2. Please provide a list of leaks (including code class of the components) that have
been identified since the last refueling outage and associated corrective action
documentation. If during the last cycle, the unit was shutdown, please provide
documentation of containment walkdown inspections performed as part of the boric
acid corrosion control program.
A.4 Steam Generator Tube Inspections
A.4 Steam Generator Tube Inspections
1. A detailed schedule of:
1. A detailed schedule of:
Steam generator tube inspection, data analyses, and repair activities for the upcoming outage.
          *  Steam generator tube inspection, data analyses, and repair activities for the
Steam generator secondary side inspection activities for the upcoming outage (if occurring).
upcoming outage.
2. Copy of SG history documentation given to vendors performing eddy current (ET) testing of the SGs during the upcoming outage.
          *  Steam generator secondary side inspection activities for the upcoming outage
3. Copy of procedure containing screening criteria used for selecting tubes for in
              (if occurring).
-situ pressure testing and
2. Copy of SG history documentation given to vendors performing eddy current (ET)
the procedure to be used for in
testing of the SGs during the upcoming outage.
-situ pressure testing.
3. Copy of procedure containing screening criteria used for selecting tubes for in-situ
 
pressure testing and the procedure to be used for in-situ pressure testing.
4. Copy of previous outage SG tube operational assessment. Also include a copy of the following documents as they become available:
4. Copy of previous outage SG tube operational assessment. Also include a copy of
Degradation assessment
the following documents as they become available:
Condition monitoring assessment
          *  Degradation assessment
5. Copy of the document defining the planned SG ET scope (e.g., 100 percent of unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion transition regions with rotating probe) and identify the scope expansion criteria, which will be applied. Also identify and describe any deviations in this scope or expansion criteria from the EPRI Guidelines.
          *  Condition monitoring assessment
6. Copy of the document describing the ET acquisition equipment to be applied including ET probe types. Also identify the extent of planned tube examination
5. Copy of the document defining the planned SG ET scope (e.g., 100 percent of
coverage with each probe type (e.g. rotating probe  
unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion
-0.080 inches, 0.115 inches pancake coils and mid
transition regions with rotating probe) and identify the scope expansion criteria,
-range +point coil applied at the top
which will be applied. Also identify and describe any deviations in this scope or
-of-tube-sheet plus 3 inches to minus 12 inches).
expansion criteria from the EPRI Guidelines.
7. Identify and quantify any SG tube leakage experienced during the previous operating cycle. Also provide documentation identifying which SG was leaking and corrective actions completed and planned for this condition.
6. Copy of the document describing the ET acquisition equipment to be applied
8. Copy of steam generator eddy current data analyst guidelines and site validated eddy current technique specification sheets. Additionally, please provide a copy of EPRI Appendix H, "Examination Technique Specification Sheets," qualification records. 9. Provide past history of the condition and issues pertaining to the secondary side of the steam generators (including items such as loose parts, fouling, top of tube sheet condition, crud removal amounts, etc.).
including ET probe types. Also identify the extent of planned tube examination
Indicate where the primary, secondary, and resolution analyses are scheduled to take place.
coverage with each probe type (e.g. rotating probe -0.080 inches, 0.115 inches
pancake coils and mid-range +point coil applied at the top-of-tube-sheet plus 3
inches to minus 12 inches).
7. Identify and quantify any SG tube leakage experienced during the previous operating
cycle. Also provide documentation identifying which SG was leaking and corrective
actions completed and planned for this condition.
8. Copy of steam generator eddy current data analyst guidelines and site validated
eddy current technique specification sheets. Additionally, please provide a copy of
EPRI Appendix H, Examination Technique Specification Sheets, qualification
records.
9. Provide past history of the condition and issues pertaining to the secondary side of
the steam generators (including items such as loose parts, fouling, top of tube sheet
condition, crud removal amounts, etc.).
Indicate where the primary, secondary, and resolution analyses are scheduled to
take place.
A.5 Additional Information Related to all Inservice Inspection Activities
A.5 Additional Information Related to all Inservice Inspection Activities
1. A list with a brief description of inservice inspection, and boric acid corrosion control program related issues (e.g., CR) entered into your corrective action program since the beginning of the last refueling outage. For example, a list based upon data base searches using key words related to piping such as: inservice inspection, ASME Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or errors in piping examinations.
1. A list with a brief description of inservice inspection, and boric acid corrosion control
2. Provide training (e.g. Scaffolding, Fall Protection, FME, Confined Space) if they are required for the activities described in A.1 through A.3.
program related issues (e.g., CR) entered into your corrective action program since
the beginning of the last refueling outage. For example, a list based upon data base
searches using key words related to piping such as: inservice inspection, ASME
Code, Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or
errors in piping examinations.
2. Provide training (e.g. Scaffolding, Fall Protection, FME, Confined Space) if they are
required for the activities described in A.1 through A.3.
3. Please provide names and phone numbers for the following program leads:
3. Please provide names and phone numbers for the following program leads:
Inservice inspection (examination, planning)
Inservice inspection (examination, planning)
Containment exams
Containment exams
Reactor pressure vessel head exams
Reactor pressure vessel head exams
Snubbers and supports
Snubbers and supports
Line 1,163: Line 1,348:
Boric acid corrosion control program
Boric acid corrosion control program
Steam generator inspection activities (site lead and vendor contact)
Steam generator inspection activities (site lead and vendor contact)
: [[contact::B. Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting (April 16]], 2018): B.1 Inservice Inspection / Welding Programs and Schedule Information
: [[contact::B. Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting (April 16]],
1. Updated schedules for inservice inspection/nondestructive examination activities, including planned welding activities, and
2018):
schedule showing contingency repair plans, if available.
B.1   Inservice Inspection / Welding Programs and Schedule Information
2. For ASME Code Class welds selected by the inspector from the lists provided from section A of this enclosure, please provide copies of the following documentation for each subject weld:
1. Updated schedules for inservice inspection/nondestructive examination activities,
Weld data sheet (traveler).
including planned welding activities, and schedule showing contingency repair
Weld configuration and system location.
plans, if available.
Applicable Code Edition and Addenda for weldment.
2. For ASME Code Class welds selected by the inspector from the lists provided from
Applicable Code Edition and Addenda for welding procedures.
section A of this enclosure, please provide copies of the following documentation for
Applicable welding procedures used to fabricate the welds.
each subject weld:
Copies of procedure qualification records (PQRs) supporting the weld procedures from B.1.b.v.
                  *  Weld data sheet (traveler).
Copies of welder's performance qualification records (WPQ).
                  *  Weld configuration and system location.
Copies of the nonconformance reports for the selected welds (If applicable).
                  *  Applicable Code Edition and Addenda for weldment.
Radiographs of the selected welds and access to equipment to allow viewing radiographs (if radiographic testing was performed).
                  *  Applicable Code Edition and Addenda for welding procedures.
Copies of the preservice examination records for the selected welds.
                  *  Applicable welding procedures used to fabricate the welds.
Readily accessible copies of nondestructive examination personnel qualifications records for reviewing. 3. For the inservice inspection related corrective action issues selected by the inspector from section A of this enclosure, provide a copy of the corrective actions and supporting documentation.
                  *  Copies of procedure qualification records (PQRs) supporting the weld
 
procedures from B.1.b.v.
4. For the nondestructive examination reports with relevant
                  *  Copies of welders performance qualification records (WPQ).
conditions on an ASME Code Class components selected by the inspector from Section A above, provide a copy of the examination records, examiner qualification records, and associated corrective action documents.
                  *  Copies of the nonconformance reports for the selected welds (If
5. A copy of (or ready access to) most current
applicable).
revision of the inservice inspection program manual and plan for the current interval.
                  *  Radiographs of the selected welds and access to equipment to allow
6. For the nondestructive examinations selected by the inspector from section A of this enclosure, provide a copy of the nondestructive examination procedures used to
viewing radiographs (if radiographic testing was performed).
perform the examinations (including calibration and flaw characterization/sizing procedures). For ultrasonic examination procedures qualified in accordance with ASME Code, Section XI, Appendix VIII, provide documentation supporting the procedure qualification (e.g. the EPRI performance demonstration qualification summary sheets). Also, include qualification documentation of the specific equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and nondestructive examination personnel qualification records.
                  *  Copies of the preservice examination records for the selected welds.
B.2 Reactor Pressure Vessel Head
                  *  Readily accessible copies of nondestructive examination personnel
1. Provide the nondestructive personnel qualification records for the examiners who will perform examinations of the reactor pressure vessel head replacement.
qualifications records for reviewing.
2. Provide drawings showing the
3. For the inservice inspection related corrective action issues selected by the inspector
following:
from section A of this enclosure, provide a copy of the corrective actions and
Reactor pressure vessel head and control rod drive mechanism nozzle configurations
supporting documentation.
Reactor pressure vessel head insulation configuration
4. For the nondestructive examination reports with relevant conditions on an ASME Code
Note: The drawings listed above should include fabrication drawings for the nozzle attachment welds as applicable.
Class components selected by the inspector from Section A above, provide a copy of
B.3 Boric Acid Corrosion Control Program
the examination records, examiner qualification records, and associated corrective
1. Please provide boric acid walk down inspection results, an updated list of boric acid leaks identified so far this outage, associated corrective action documentation, and overall status of planned boric acid inspections.
action documents.
2. Please provide any engineering evaluations completed for boric acid leaks identified since the end of the last refueling outage. Please include a status of corrective actions to repair and/or clean these boric acid leaks. Please identify specifically which known leaks, if any, have remained in service or will remain in service as active leaks.  
5. A copy of (or ready access to) most current revision of the inservice inspection
 
program manual and plan for the current interval.
B.4 Steam Generator Tube Inspections
6. For the nondestructive examinations selected by the inspector from section A of this
1. Copies of the Examination Technique Specification Sheets and associated justification for any revisions.
enclosure, provide a copy of the nondestructive examination procedures used to
2. Please provide a copy of the eddy current testing procedures used to perform the steam generator tube inspections (specifically calibration and flaw characterization/sizing procedures, etc.).
perform the examinations (including calibration and flaw characterization/sizing
3. Copy of the guidance to be followed if a loose part
procedures). For ultrasonic examination procedures qualified in accordance with
or foreign material is identified in the steam generators.
ASME Code, Section XI, Appendix VIII, provide documentation supporting the
4. Identify the types of SG tube repair processes which will be implemented for defective SG tubes (including any NRC reviews/evaluations/approvals of this repair process). Provide the flaw depth sizing criteria to be applied for ET indications identified in the SG tubes. 5. Copy of documents describing actions to be taken if a new SG tube degradation mechanism is identified.
procedure qualification (e.g. the EPRI performance demonstration qualification
6. Provide procedures with guidance/instructions for identifying (e.g. physically locating the tubes that require plugging) and plugging SG tubes.
summary sheets). Also, include qualification documentation of the specific equipment
7. List of corrective action documents generated by the vendor and/or site with respect to steam generator inspection activities.
to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and
B.5 Codes and Standards
nondestructive examination personnel qualification records.
1. Ready access to (i.e., copies provided to the inspector(s) for use during the inspection at the onsite inspection location, or room number and location where available):
B.2   Reactor Pressure Vessel Head
Applicable Editions of the ASME Code (Sections V, IX, and XI) for the inservice inspection program and the repair/replacement program.
1. Provide the nondestructive personnel qualification records for the examiners who will
2. Copy of the performance demonstration initiative (PDI) generic procedures with the latest applicable revisions that support site qualified ultrasonic examinations of piping welds and components (e.g., PDI
perform examinations of the reactor pressure vessel head replacement.
-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-10, etc.).
2. Provide drawings showing the following:
3. Boric Acid Corrosion Guidebook Revision 1  
                  *    Reactor pressure vessel head and control rod drive mechanism nozzle
- EPRI Technical Report 1000975.  
configurations
 
                  *    Reactor pressure vessel head insulation configuration
Note: The drawings listed above should include fabrication drawings for the nozzle
attachment welds as applicable.
B.3   Boric Acid Corrosion Control Program
1. Please provide boric acid walk down inspection results, an updated list of boric acid
leaks identified so far this outage, associated corrective action documentation, and
overall status of planned boric acid inspections.
2. Please provide any engineering evaluations completed for boric acid leaks identified
since the end of the last refueling outage. Please include a status of corrective actions
to repair and/or clean these boric acid leaks. Please identify specifically which known
leaks, if any, have remained in service or will remain in service as active leaks.
B.4 Steam Generator Tube Inspections
1. Copies of the Examination Technique Specification Sheets and associated
justification for any revisions.
2. Please provide a copy of the eddy current testing procedures used to perform the
steam generator tube inspections (specifically calibration and flaw
characterization/sizing procedures, etc.).
3. Copy of the guidance to be followed if a loose part or foreign material is identified in
the steam generators.
4. Identify the types of SG tube repair processes which will be implemented for defective
SG tubes (including any NRC reviews/evaluations/approvals of this repair process).
Provide the flaw depth sizing criteria to be applied for ET indications identified in the
SG tubes.
5. Copy of documents describing actions to be taken if a new SG tube degradation
mechanism is identified.
6. Provide procedures with guidance/instructions for identifying (e.g. physically locating
the tubes that require plugging) and plugging SG tubes.
7. List of corrective action documents generated by the vendor and/or site with respect
to steam generator inspection activities.
B.5 Codes and Standards
1. Ready access to (i.e., copies provided to the inspector(s) for use during the inspection
at the onsite inspection location, or room number and location where available):
                  *  Applicable Editions of the ASME Code (Sections V, IX, and XI) for the
inservice inspection program and the repair/replacement program.
2. Copy of the performance demonstration initiative (PDI) generic procedures with the
latest applicable revisions that support site qualified ultrasonic examinations of piping
welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-10, etc.).
3. Boric Acid Corrosion Guidebook Revision 1 - EPRI Technical Report 1000975.
The following items are requested for the
The following items are requested for the
Occupational Radiation Safety Inspection
Occupational Radiation Safety Inspection
Wolf Creek
Wolf Creek
April 9-13, 2018 Integrated Report 2018002
April 9-13, 2018
Integrated Report 2018002
Inspection areas are listed in the attachments below.
Inspection areas are listed in the attachments below.
Please provide the requested information on or before March 22, 2018
Please provide the requested information on or before March 22, 2018.
. Please submit this information using the same lettering system as below. For example, all contacts and phone numbers for Inspection Procedure 71124.0
Please submit this information using the same lettering system as below. For example, all
should be in a file/folder titled  
contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled
"1- A," applicable organization charts in file/folder "
1- A, applicable organization charts in file/folder 1- B, etc.
1- B," etc. If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at least 30 days later than the onsite inspection dates, so the inspectors will have access to the information while writing the report.
If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at
In addition to the corrective action document lists provided for each inspection procedure listed below, please provide updated lists of corrective action documents at the entrance meeting. The dates for these lists should range from the end dates of the original lists to the day of the entrance meeting.
least 30 days later than the onsite inspection dates, so the inspectors will have access to the
If more than one inspection procedure is to be conducted and the information requests appear to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which file the information can be found.
information while writing the report.
If you have any questions or comments, please contact Natasha Greene at (817) 200
In addition to the corrective action document lists provided for each inspection procedure listed
-1154 or natasha.greene@nrc.gov.
below, please provide updated lists of corrective action documents at the entrance meeting.
The dates for these lists should range from the end dates of the original lists to the day of the
entrance meeting.
If more than one inspection procedure is to be conducted and the information requests appear
to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which
file the information can be found.
If you have any questions or comments, please contact Natasha Greene at (817) 200-1154 or
natasha.greene@nrc.gov.
PAPERWORK REDUCTION ACT STATEMENT
PAPERWORK REDUCTION ACT STATEMENT
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.
This letter does not contain new or amended information collection requirements subject
: [[contact::S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget]], control number 3150
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
-0011.
collection requirements were approved by the Office of Management and Budget,
1. Radiological Hazard Assessment and Exposure Controls (71124.01) and Performance Indicator Verification (71151)
control number 3150-0011.
Date of Last Inspection:
1. Radiological Hazard Assessment and Exposure Controls (71124.01) and
May 8, 2017
Performance Indicator Verification (71151)
A. List of contacts and telephone numbers for the Radiation Protection Organization Staff and Technicians
Date of Last Inspection:         May 8, 2017
A. List of contacts and telephone numbers for the Radiation Protection Organization Staff
and Technicians
B. Applicable organization charts
B. Applicable organization charts
: [[contact::C. Audits]], self
: [[contact::C. Audits]], self-assessments, and LERs written since date of last inspection, related to this
-assessments, and LERs written since date of last inspection
inspection area
, related to this inspection area
D. Procedure indexes for the radiation protection procedures
D. Procedure indexes for the radiation protection procedures
E. Please provide specific procedures related to the following areas noted below. Additional Specific Procedures may be requested by number after the inspector reviews the procedure indexes.
E. Please provide specific procedures related to the following areas noted below.
Additional Specific Procedures may be requested by number after the inspector reviews
the procedure indexes.
1. Radiation Protection Program Description
1. Radiation Protection Program Description
2. Radiation Protection Conduct of Operations
2. Radiation Protection Conduct of Operations
Line 1,247: Line 1,480:
6. RCA Access Controls and Radiation Worker Instructions
6. RCA Access Controls and Radiation Worker Instructions
7. Conduct of Radiological Surveys
7. Conduct of Radiological Surveys
8. Radioactive
8. Radioactive Source Inventory and Control
Source Inventory and Control
9. Declared Pregnant Worker Program
9. Declared Pregnant Worker Program
F. List of corrective action documents (including corporate and sub
F. List of corrective action documents (including corporate and sub-tiered systems) since
-tiered systems) since date of last inspection
date of last inspection
a. Initiated by the radiation protection organization
a. Initiated by the radiation protection organization
b. Assigned to the radiation protection organization
b. Assigned to the radiation protection organization
NOTE: The lists should indicate the significance level
NOTE: The lists should indicate the significance level of each issue and the search
of each issue and the search criteria used. Please provide in document formats which are "searchable" so that the inspector can perform word searches. If not covered above, a summary of corrective action documents since date of last inspection
criteria used. Please provide in document formats which are searchable so that
involving unmonitored releases, unplanned releases, or releases in which any dose limit or administrative dose limit was exceeded (for Public Radiation Safety Performance Indicator verification in accordance with IP 71151)
the inspector can perform word searches.
: [[contact::G. List of radiologically significant work activities scheduled to be conducted during the inspection period (If the inspection is scheduled during an outage]], please also include a list of work activities greater than 1 rem, scheduled during the outage with the dose estimate for the work activity.)
If not covered above, a summary of corrective action documents since date of last
inspection involving unmonitored releases, unplanned releases, or releases in which any
dose limit or administrative dose limit was exceeded (for Public Radiation Safety
Performance Indicator verification in accordance with IP 71151)
G. List of radiologically significant work activities scheduled to be conducted during the
inspection period (If the inspection is scheduled during an outage, please also include a
list of work activities greater than 1 rem, scheduled during the outage with the dose
estimate for the work activity.)
H. List of active radiation work permits
H. List of active radiation work permits
I. Radioactive source inventory list
I. Radioactive source inventory list
a. All radioactive sources that are required to be leak tested
a.       All radioactive sources that are required to be leak tested
b. All radioactive sources that meet the 10 CFR Part 20, Appendix E, Category 2 and above threshold. Please indicate the radioisotope, initial and current activity (w/assay date), and storage location for each applicable source.
b.       All radioactive sources that meet the 10 CFR Part 20, Appendix E, Category 2
 
and above threshold. Please indicate the radioisotope, initial and current activity
J. The last two leak test results for the radioactive sources inventoried and required to be leak tested.
            (w/assay date), and storage location for each applicable source.
If applicable, specifically provide a list of all radioactive source(s) that have failed its leak test within the last two years
J. The last two leak test results for the radioactive sources inventoried and required to be
K. A current listing of any non
leak tested. If applicable, specifically provide a list of all radioactive source(s) that have
-fuel items stored within your pools, and if available, their appropriate dose rates (Contact / @ 30cm)
failed its leak test within the last two years
: [[contact::L. Computer printout of radiological controlled area entries greater than 100 millirem since the previous inspection to the current inspection entrance date. The printout should include the date of entry]], some form of worker identification, the radiation work permit used by the worker, dose accrued by the worker, and the electronic dosimeter dose alarm set-point used during the entry (for Occupational Radiation Safety Performance Indicator verification in accordance with IP 71151).
: [[contact::K. A current listing of any non-fuel items stored within your pools]], and if available, their
 
appropriate dose rates (Contact / @ 30cm)
L. Computer printout of radiological controlled area entries greater than 100 millirem since
the previous inspection to the current inspection entrance date. The printout should
include the date of entry, some form of worker identification, the radiation work permit
used by the worker, dose accrued by the worker, and the electronic dosimeter dose
alarm set-point used during the entry (for Occupational Radiation Safety Performance
Indicator verification in accordance with IP 71151).
Initial Request for Information
Initial Request for Information
Integrated
Integrated Inspection
Inspection
Wolf Creek Nuclear Generating Station
Wolf Creek Nuclear Generating
Inspection Report:               05000482/2018002
Station  Inspection
Inspection Dates:                 April 1 - June 30, 2018
Report:
Inspection Procedure:             Integrated Inspection Procedures
05000482/201
Lead Inspector:                   Douglas Dodson, Senior Resident Inspector
00 2  Inspection
: [[contact::I.     Information Requested Prior to March 22]], 2018
Dates:
The following information should be provided in electronic format (Certrec IMS preferred),
April 1 - June 30, 201 8  Inspection
to the attention of Douglas Dodson by March 22, 2018, to facilitate the reduction in the
Procedure:
items to be selected for a final list during inspection preparation. The inspection team
Integrated
will finalize its sample selections and will provide an additional information request with
Inspection Procedures
specific items. This information shall be made available by March 22, 2018. The specific
Lead Inspector:
items selected from the lists shall be available and ready for review on the day indicated
Douglas Dodson, Senior
in this request. *Please provide requested documentation electronically in pdf files,
Resident Inspector
Excel, or other searchable formats, if possible. The information should contain descriptive
I. Information
names, and be indexed and hyperlinked to facilitate ease of use. Information in lists
Requested Prior to March 22, 2018
should contain enough information to be easily understood by someone who has
The following information should
knowledge of pressurized water reactor technology. If requested documents are large
be provided in electronic format (Certrec IMS
and/or only hard copy formats are available, please inform the inspector(s), and provide
preferred), to the attention of Douglas Dodson by March 22, 201 8, to facilitate the reduction in the items to be selected for a final list during
subject documentation.
inspection
1. Any pre-existing evaluation or list of spent fuel pool cooling and cleanup system
preparation.
components and associated calculations with low design margins.
The inspection team
2. A list of high risk spent fuel pool cooling and cleanup system maintenance rule
will finalize its sample selections and will
components and functions based on engineering or expert panel judgment.
provide an additional
3. A list of spent fuel pool cooling and cleanup system related operating experience
information request with specific items.
evaluations for the last 3 years.
This information shall
4. A list of all spent fuel pool cooling and cleanup system time-critical operator actions in
be made available
procedures.
by March 22, 201 8. The specific items selected from the lists shall
5. A list of permanent and temporary modifications related to spent fuel pool cooling
be available
and cleanup system sorted by component.
and ready for review on the day indicated
6. A list of current spent fuel pool cooling and cleanup system related operator work
in this request.
arounds/burdens.
  *Please provide requested documentation
7. A list of the spent fuel pool cooling and cleanup system design calculations, which
electronically
provide the design margin information for components.
in "pdf" files, Excel, or other searchable formats, if possible. The information
8. List of spent fuel pool cooling and cleanup system root cause evaluations
should contain descriptive
associated with component failures or design issues initiated/completed in the
names, and
last 5 years.
be indexed and hyperlinked
9. A list of any spent fuel pool cooling and cleanup system common-cause failures of
to facilitate
components in the last 3 years.
ease of use. Information
10. An electronic copy of the spent fuel pool cooling and cleanup system design bases
in "lists" should contain enough information
documents and any open, pending, or recently completed changes. Although not an
to be easily understood
exhaustive list, please include any open, pending, or recently completed (last 3 years)
by someone who has knowledge of pressurized
changes to temporary modifications, permanent modifications, engineering change
water reactor technology.
packages, and/or procedure change packages. Specifically, please include any open,
If requested documents are large and/or only
pending, or recently completed changes to emergency operating, abnormal operating,
hard copy formats are available, please inform the inspector(s), and
normal operating, alarm response, system alignment, surveillance, or other procedure.
provide subject documentation
11. An electronic copy of the spent fuel pool cooling and cleanup system System Health
. 1. Any pre-existing evaluation
notebook.
or list of spent fuel pool cooling and cleanup
2. A copy of spent fuel pool cooling and cleanup system related audits completed in the
system components and
last 2 years.
associated calculations with
13. A list of spent fuel pool cooling and cleanup system motor operated valves
low design margins.
    (MOVs) in the program, design margin and risk ranking.
2. A list of high risk spent fuel pool cooling and cleanup system maintenance rule components
14. A list of spent fuel pool cooling and cleanup system air operated valves (AOVs) in
and functions based on engineering or expert panel judgment
the valve program, design margin and risk ranking.
. 3. A list of spent fuel pool cooling and cleanup system related operatin g experience
15. Spent fuel pool cooling and cleanup system structure, system, and components
evaluations for the last 3 years. 4. A list of all spent fuel pool cooling and cleanup system time-critical operator actions in procedures.
maintenance rule category, scoping, unavailability data, unreliability data, functional
5. A list of permanent and temporary modifications
failure evaluations, (a)(1) determinations, (a)(1) goals, and any supporting basis
related to spent fuel pool cooling and cleanup system sorted by component. 6. A list of current spent fuel pool cooling and cleanup system related "operator work arounds/burdens."
documentation.
7. A list of the spent fuel pool cooling and cleanup system design calculations, which provide the design margin information for components
16. A list of spent fuel pool cooling and cleanup system licensee contacts for the
.
inspection team with pager or phone numbers.
8. List of spent fuel pool cooling and cleanup
17. An excel spreadsheet of spent fuel pool cooling and cleanup system related PRA
system root cause evaluations
human action basic events or risk ranking of operator actions from your site specific
associated
PSA sorted by RAW and FV. Provide copies of your human reliability worksheets
with component failures
for these items.
or design issues initiated/completed
18. In so far as there are recent or pending changes, please provide an Excel
in the last 5 years. 9. A list of any spent fuel pool cooling and cleanup
spreadsheet of spent fuel pool cooling and cleanup system related equipment basic
system common-cause failures of components
events (with definitions) including importance measures sorted by risk achievement
in the last 3 years. 10. An electronic copy of the spent fuel pool cooling and cleanup
worth (RAW) and Fussell-Vesely (FV) from your internal events probabilistic risk
system design bases documents and any open, pending, or recently completed changes. Although not an exhaustive list, please include any open, pending, or recently completed (last 3 years) changes to temporary modifications, permanent modifications, engineering change packages, and/or procedure change packages. Specifically, please include any open, pending, or recently completed changes to emergency operating, abnormal operating, normal operating, alarm response, system alignment, surveillance, or other procedure.
assessment (PRA). Include basic events with RAW value of 1.3 or greater.
11. An electronic
19. In so far as there are recent or pending changes, please provide a list of the top 50
copy of the spent fuel pool cooling and cleanup
cut-sets from your PRA.
system System Health notebook. 12. A copy of spent fuel pool cooling and cleanup system related audits completed in the last 2 years. 13. A list of spent fuel pool cooling and cleanup system motor operated valves (MOVs) in the program, design margin and risk ranking. 14. A list of spent fuel pool cooling and cleanup system air operated valves
20. In so far as there are recent or pending changes, please provide copies of PRA
(AOVs) in the valve program, design margin
system notebooks, and the latest PRA summary document.
and risk ranking
21. In so far as there are recent or pending changes, and if you have an external events
. 15. Spent fuel pool cooling and cleanup
or fire PSA model, provide the information requested in items 17-19 for external
system structure, system, and components
events and fire, as it relates to the spent fuel pool cooling and cleanup system.
' maintenance
2. In so far as there are recent or pending changes, please provide a copy of the Wolf
rule category, scoping, unavailability data, unreliability data, functional failure evaluations, (a)(1) determinations, (a)(1) goals, and any supporting basis documentation
Creek Nuclear Generating Station IPEEE changes, if available electronically.
. 16. A list of spent fuel pool cooling and cleanup
system licensee
contacts for the inspection team with
pager or phone numbers
. 17. An excel spreadsheet of spent fuel pool cooling and cleanup
system related PRA
human action basic events or risk ranking
of operator actions from your site specific
PSA sorted by RAW and
F
: [[contact::V. Provide copies of your human reliability worksheets for these items. 18. In so far as there are recent or pending changes]], please provide an Excel spreadsheet of spent fuel pool cooling and cleanup
system related equipment basic events (with definitions) including importance measures sorted by risk achievement worth (RAW) and Fussell
-Vesely (FV) from your internal events probabilistic risk assessment (PRA).
Include basic events with RAW value of 1.3 or greater.
19. In so far as there are recent or pending changes, please provide a
list of the top 50 cut-sets from your PRA.
 
20. In so far as there are recent or pending changes, please provide copies of PRA "system notebooks," and the latest PRA summary document.
21. In so far as there are recent or pending changes, and if you have an external events or fire PSA model, provide the information requested in items
17-19 for external events and fire, as it relates to the spent fuel pool cooling and cleanup
system. 22. In so far as there are recent or pending changes, please provide a
copy of the Wolf Creek Nuclear Generating Station IPEEE
changes, if available electronically.


ML18226A175
ML18226A175
SUNSI Review
SUNSI Review           ADAMS:           Non-Publicly Available       Non-Sensitive Keyword:
ADAMS:   Non-Publicly Available
By: NHTaylor           Yes No       Publicly Available           Sensitive     NRC-002
Non-Sensitive Keyword: By: NHTaylor  Yes    No Publicly Available
OFFICE         SRI:DRP/B     RI: DRP/B     C:DRS/OB         C:DRS/PSB2   C:DRS/EB1   C:DRS/EB2
Sensitive
NAME           DDodson       FThomas       VGaddy           HGepford     TFarnholtz   JDrake
NRC-002 OFFICE SRI:DRP/B RI: DRP/B C:DRS/OB C:DRS/PSB2
SIGNATURE       ded           fdt           vgg             hjg           WcS for     jfd
C:DRS/EB1 C:DRS/EB2 NAME DDodson FThomas VGaddy HGepford TFarnholtz
DATE           8/3/2018       08/03/18       8/1/2018         8/1/2018     8/1/18       8/1/18
JDrake SIGNATURE ded fdt vgg hjg WcS for jfd DATE 8/3/2018 08/03/18 8/1/2018 8/1/2018 8/1/18 8/1/18 OFFICE PE:DRP/B BC:DRP/B     NAME JMelfi NTaylor     SIGNATURE jfm NHT     DATE 8/3/18 8/12/18
OFFICE         PE:DRP/B       BC:DRP/B
NAME           JMelfi         NTaylor
SIGNATURE       jfm           NHT
DATE           8/3/18         8/12/18
}}
}}

Latest revision as of 17:58, 18 December 2019

NRC Integrated Inspection Report 05000482/2018002 and Assessment Follow-Up Letter
ML18226A175
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 08/12/2018
From: Nick Taylor
NRC Region 4
To: Heflin A
Wolf Creek
References
Download: ML18226A175 (60)


Text

ust 12, 2018

SUBJECT:

WOLF CREEK GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000482/2018002 AND ASSESSMENT FOLLOW-UP LETTER

Dear Mr. Heflin:

On June 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Wolf Creek Generating Station. On July 17, 2018, the NRC inspectors discussed the results of this inspection with Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

NRC inspectors documented two findings of very low safety significance (Green) in this report.

Both of these findings involved violations of NRC requirements. Additionally, NRC inspectors documented one Severity Level IV violation with no associated finding. The NRC is treating these violations as non-cited violations (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspector at the Wolf Creek Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Wolf Creek Generating Station.

In the 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006, Agencywide Documents Access and Management System (ADAMS) ML18052A345), the NRC identified a cross-cutting theme in the safety conscious work environment (SCWE) area. On August 8, 2018, the NRC documented an assessment of the licensees progress in addressing the SCWE theme in NRC Inspection Report 05000482/2018007 (ADAMS ML18218A265). The inspectors determined that while the licensee had taken some corrective actions to address the work environment challenges on site, these actions had not yet been effective to improve the SCWE in the maintenance support group.

Based on this conclusion and the previously documented finding with a cross-cutting aspect related to the inconsistent implementation of SCWE policy (S.1), as discussed in NRC Inspection Report 05000482/2017004 (ADAMS ML18043A114), the NRC determined that a theme in the SCWE area continues to exist. The NRC will continue to monitor your staffs progress in implementing corrective actions for this theme.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Nicholas H. Taylor, Chief Project Branch B Division of Reactor Projects Docket No. 50-482 License No. NPF-42

Enclosure:

Inspection Report 05000482/2018002 w/Attachments:

1. Documents Reviewed 2 Request for Information Inservice Inspection 3. Request for Information O

Inspection Report

Docket Number: 05000482 License Number: NPF-42 Report Number: 05000482/2018002 Enterprise Identifier: I-2018-002-0012 Licensee: Wolf Creek Nuclear Operating Corporation Facility: Wolf Creek Generating Station Location: Burlington, Kansas Inspection Dates: April 1, 2018 to June 30, 2018 Inspectors: D. Dodson, Senior Resident Inspector F. Thomas, Resident Inspector C. Alldredge, Health Physicist I. Anchondo, Reactor Inspector J. Melfi, Project Engineer J. ODonnell, CHP, Health Physicist Approved By: N. Taylor Chief, Project Branch B Division of Reactor Projects 1 Enclosure

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an Integrated Inspection at Wolf Creek Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC-identified and self-revealed findings, violations, and additional items are summarized in the table below.

List of Findings and Violations Announcement of an NRC Inspectors Presence by Station Personnel Cornerstone Significance Cross-cutting Report Aspect Section Not Severity Level IV Not 71111.20 -

Applicable NCV Applicable Refueling 05000482/2018002-01 and Other Closed Outage Activities The inspectors identified a Severity Level IV non-cited violation (NCV) of 10 CFR 50.70(b)(4),

Inspections, associated with the licensees failure to ensure the arrival and presence of NRC Inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility without a specific request by the NRC inspector.

Specifically, a contract radiation protection technician entered the spent fuel pool building where the resident inspector was present and observing core offload activities, and the technician informed members of a work crew of the whereabouts of an NRC radiation protection inspection team without being requested to do so; this impacts the NRCs ability to regulate and perform unannounced inspections.

Failure to Maintain Adequate Pressurization of the Control Room Envelope Cornerstone Significance Cross-cutting Report Aspect Section Mitigating Green [H.3] - 71152 -

Systems NCV 05000482/2018002-02 Human Problem Closed Performance, Identification Change and Management Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion III, Design Control, was identified when the licensee failed to adequately recognize that the cable spreading room floor was a control building ventilation isolation boundary. Specifically, the licensee cut openings in the floor/ceiling between the 2,032 foot and 2,016 foot elevations of the control building and the impact on the control room envelopes ability to pressurize was not recognized. This was a primary contributor to the train B control room emergency ventilation system being unable to maintain the appropriate pressure in the control room envelope.

Failure to Adequately Implement Instrumentation and Controls Surveillance Procedures Cornerstone Significance Cross-cutting Report Aspect Section Initiating Green [H.2] - Human 71152 -

Events NCV 05000482/2018002-03 Performance, Problem Closed Field Presence Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings, was identified when the licensee failed to adequately implement surveillance procedures that affected safety-related equipment and plant stability. Specifically, the licensee failed to adequately implement testing and calibration procedures for pressurizer level instrumentation. This resulted in two letdown isolation signals, securing of pressurizer heaters, and a pressurizer level transient on March 29, 2018.

PLANT STATUS

Wolf Creek Generating Station began the inspection period shutdown for Refueling Outage 22.

The reactor was restarted on May 17, 2018, and power ascension was commenced. The unit was returned to approximately rated thermal power on May 21, 2018, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/

reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program

- Operations Phase. The inspectors performed plant status activities described in Inspection Manual Chapter 2515 Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01Adverse Weather Protection Summer Readiness

The inspectors evaluated summer readiness of offsite and alternate alternating current (AC)power systems.

71111.04Equipment Alignment Partial Walkdown

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Essential service water train B on June 20, 2018
(2) Auxiliary feedwater train B on June 26, 2018.

Complete Walkdown (1 Sample)

The inspectors evaluated system configurations during a complete walkdown of the spent fuel pool cooling system April 8 through April 15, 2018.

71111.05AQFire Protection Annual/Quarterly Quarterly Inspection

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Volume control tank and volume control tank valve compartment, fire area A-8 on April 21, 2018
(2) Reactor building, elevation 2,000 feet, fire areas RB-1 and RB-2 on May 16, 2018
(3) Reactor building, elevation 2,026 feet, fire areas RB-2, RB-3, RB-4, RB-7, and RB-8 on May 16, 2018
(4) Reactor building, elevation 2,047 feet, fire areas RB-5 and RB-10 on May 16, 2018
(5) Reactor building, elevation 2,068 feet 8 inches, fire areas RB-6 and RB-10 on May 16, 2018
(6) Fuel pool heat exchanger rooms and general area, elevation 2,000 feet, fire areas F-1, F-2, and F-3 on May 31, 2018.

===71111.06Flood Protection Measures Cables (Partial Sample)

The inspectors evaluated cable submergence protection in essential service water electrical manhole MHE1A on June 18, 2018.

71111.08Inservice Inspection Activities ===

(1) Nondestructive Examination Activities and Welding Activities The inspector directly observed the following nondestructive examinations:

SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Reactor Vessel Control Rod Drive Mechanism Visual (VE)

Head Penetration Numbers 1, 2, 3, 4, 10, 14, 17, 18, 24, 25, 26, 27, 30, 32, 33, 35, 38, 43, 54, 66, 71, and 74.

The inspector reviewed records for the following nondestructive examinations:

SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Feedwater Weld Number AE-04-F015 and Ultrasonic System AE-04-S010-C (Data Sheet Number AGF_012)

SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Feedwater Steam Generator A Inner Radius - Ultrasonic System Weld Number EBB01A-11-IR (Data Sheet Number AJS_010)

Steam Steam Weld Number EBB01A- Ultrasonic Generator STEAM-3-W (Data Sheet Number RAL_002)

Steam Steam Weld Number EBB01A- Ultrasonic Generator STEAM-6-W (Data Sheet Number RAL_003)

Steam Weld Number EBB01A-11-W Ultrasonic Generator (Data Sheet Number RAL_004)

Steam Steam Weld Number EBB01A- Ultrasonic Generator STEAM-2-W (Data Sheet Number RAL_005)

(2) Vessel Upper Head Penetration Inspection Activities The inspector reviewed the results of the licensees bare metal visual inspection of the reactor vessel upper head penetrations. The inspector also reviewed whether the required inspection coverage was achieved and whether limitations were properly recorded. The inspector reviewed whether the personnel performing the inspection were certified examiners to their respective nondestructive examination method.

On May 10, 2018, the licensee was granted verbal approval for performing an alternative volumetric examination and leak path assessment in lieu of the visual examination requirements of Note 1 of Table 1, American Society of Mechanical Engineers Code Case N-729-4. Although not indicative of possible nozzle leakage, the licensee was not able to perform the required visual examination of penetration number one due to a hard substance obstructing the annulus. At the time of the inspection, the licensee had satisfactorily completed the ultrasonic inspection and leak path assessment. The licensee had also cleaned the annulus of penetration number one.

(3) Boric Acid Corrosion Control Inspection Activities The Inspector evaluated the licensees boric acid control program performance.
(4) Steam Generator (SG) Tube Inspection Activities The inspector reviewed the SG tube eddy current examination scope and expansion criteria to determine whether these criteria met technical specification requirements, Electric Power Research Institute (EPRI) guidelines, and commitments made to the NRC. The inspector also reviewed whether the eddy current inspection scope included areas of degradations that were known to represent potential eddy current test challenges such as the top of tube sheet, tube support plates, and U-bends. The inspector confirmed that no repairs were required at the time of the inspection and that the licensees inspection scope was appropriate.
(5) Identification and Resolution of Problems (71111.08-02.05)

The inspector reviewed 14 condition reports, which dealt with inservice inspection activities, and found the corrective actions for inservice inspection issues were appropriate.

71111.11Licensed Operator Requalification Program and Licensed Operator Performance Operator Requalification

The inspectors observed and evaluated licensed operator simulator requalification exams on

===May 31, 2018.

Operator Performance (1 Sample)===

The inspectors observed and evaluated operator performance during energization of the XNB01 transformer and NB01 safety-related bus on May 2, 2018, and performance of STS AE-211, Main Feed Reg Valve Inservice Valve Test, during startup activities on May 17, 2018.

71111.12Maintenance Effectiveness Routine Maintenance Effectiveness

The inspectors evaluated the effectiveness of routine maintenance activities associated with the spent fuel pool cooling and cleanup system level instrumentation reading erratically on May 24, 2017.

71111.13Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Elevated risk during lowered inventory and preparations for reactor head lift on April 6, 2018, and refueling water storage tank unavailability on April 7, 2018
(2) Elevated spent fuel pool cooling risk while defueled on April 19 and April 21, 2018
(3) Elevated risk during Mode 5 while implementing low temperature overpressure protection controls and emergency core cooling pump testing on May 8 and 9, 2018.

71111.15Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Operability evaluation of safety injection and accumulator to loop 1 check valve bonnet bolting issues on April 22, 2018
(2) Operability evaluation of start-up transformer XMR01 power factor testing on April 25, 2018
(3) Operability evaluation of thermal sleeve inspection results on May 8, 2018
(4) Operability evaluation of train A safety injection pump for motor current reading higher than name plate rating on May 11, 2018.

71111.18Plant Modifications

The inspectors evaluated the spent fuel pool alternate decay heat removal permanent modification.

71111.19Post Maintenance Testing

The inspectors evaluated the following post maintenance tests:

(1) Start-up transformer XMR01 testing after switchyard modification and transmission line modification on April 27, 2018
(2) Emergency diesel generator train B 24-hour testing following outage maintenance on May 1, 2018
(3) Centrifugal charging pump train A testing after completion of seal maintenance on May 9, 2018
(4) STS EM-100A, Safety Injection Pump A Inservice Pump Test, following A safety injection pump replacement work on May 11, 2018
(5) Train B spent fuel pool cooling pump testing after boric acid cleaning and oil sample on May 31, 2018
(6) STS IC-503B, Channel Calibration Pressurizer Level, following emergent bistable card replacement on June 19, 2018.

71111.20Refueling and Other Outage Activities

The inspectors evaluated Refueling Outage 22 activities from April 1 to May 18, 2018.

The inspectors completed inspection procedure Sections 03.01.d and 03.01.e.

71111.22Surveillance Testing The inspectors evaluated the following surveillance tests: Routine

(1) STS KJ-001B, Integrated D/G and Safeguard Actuation Test - Train B, on May 11, 2018

In-service (1 Sample)

(1) STS EM-003A, ECCS (CCP) Flow Balance and CCP Comprehensive Test, on

May 2, 2018 Reactor Coolant System Leak Detection (1 Sample)

(1) STS BB-006, RCS Water Inventory Balance Using the NPIS Computer, on June 27, 2018

Containment Isolation Valve (1 Sample)

(1) STS PE-128, Local Leak Rate Test (LLRT) of Penetration P-29, on April 24,

RADIATION SAFETY

71124.01Radiological Hazard Assessment and Exposure Controls Radiological Hazard Assessment

The inspectors evaluated radiological hazards assessments and controls.

Instructions to Workers (1 Sample)

The inspectors evaluated worker instructions.

Contamination and Radioactive Material Control (1 Sample)

The inspectors evaluated contamination and radioactive material controls.

Radiological Hazards Control and Work Coverage (1 Sample)

The inspectors evaluated radiological hazards control and work coverage.

High Radiation Area and Very High Radiation Area Controls (1 Sample)

The inspectors evaluated risk-significant high radiation area and very high radiation area controls.

Radiation Worker Performance and Radiation Protection Technician Proficiency (1 Sample)

The inspectors evaluated radiation worker performance and radiation protection technician proficiency.

71124.02Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls Implementation of ALARA and Radiological Work Controls

The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:

(1) RWP 180021, Cartridge Filter Change-Out in Aux and RW Buildings
(2) RWP 182601, Routine Outage Access (No Locked High Radiation Areas)
(3) RWP 182300, Maintenance Support
(4) RWP 183220, Primary S/G Eddy Current RWP
(5) RWP 184207, RCP Team Seal Replacement on C & D RCPs
(6) RWP 184420, Scaffolding Activities RF22
(7) RWP 184482, Canopy Seal Clamp Activities Disassembly

Radiation Worker Performance (1 Sample)

The inspectors evaluated radiation worker and radiation protection technician performance.

OTHER ACTIVITIES - BASELINE

71151Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

(1) BI01: Reactor Coolant System (RCS) Specific Activity Sample (04/01/2017-03/31/2018)
(2) BI02: RCS Leak Rate Sample (04/01/2017-03/31/2018)
(3) OR01: Occupational Exposure Control Effectiveness Sample (04/01/2017-3/30/2018)
(4) PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (04/01/2017-03/30/2018).

71152Problem Identification and Resolution Semiannual Trend Review

The inspectors reviewed the licensees corrective action program for trends that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) On March 5, 2018, Condition Report 120056 documented that the required control room pressurization could not be developed.
(2) On March 29, 2018, Condition Report 120807 documented that incorrect test switches were operated during a performance of STS IC-503B, Channel Calibration Pressurizer Level.

INSPECTION RESULTS

Announcement of an NRC Inspectors Presence by Station Personnel Cornerstone Severity Cross-cutting Aspect Report Section Not Applicable Severity Level IV Not Applicable

71111.20 - Refueling NCV

and Other Outage 05000482/2018002-01 Activities Closed The inspectors identified a Severity Level IV NCV of 10 CFR 50.70(b)(4), Inspections, associated with the licensees failure to ensure the arrival and presence of NRC Inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility without a specific request by the NRC inspector. Specifically, a contract radiation protection technician entered the spent fuel pool building where the resident inspector was present and observing core offload activities, and the technician informed members of a work crew of the whereabouts of an NRC radiation protection inspection team without being requested to do so; this impacted the NRCs ability to regulate and perform unannounced inspections.

Description:

On April 10, 2018, the resident inspector was in the spent fuel pool building observing fuel movement activities in support of core off-load for Refueling Outage 22. NRC radiation protection inspectors were also onsite conducting inspection activities. At approximately 11:00 a.m., the resident inspector observed a BHI contractor enter the spent fuel pool building and announce to members of a work crew that NRC inspectors had entered the radiologically controlled area (containment) and to be mindful and careful.

The resident inspector spoke with the visiting NRC radiation protection inspectors later that afternoon and confirmed they had entered containment at approximately 10:30 a.m. on April 10, 2018, and had not requested that their presence be announced. The resident inspector noted that his location in the spent fuel pool building, where the announcement of NRC inspectors had occurred, was in close proximity to where the other NRC inspectors were entering containment.

Corrective Actions: On April 25, 2018, the licensee entered this issue into the corrective action program. Additional corrective actions included the performance of a stand down with all BHI employees to inform them that conduct that alerts workers to the presence of the NRC, or any oversight group, is prohibited; the licensee also published an article in a site newsletter explaining the requirements of 10 CFR 50.70. The article informed site personnel that a violation had occurred and described site management expectations regarding appropriate conduct.

Corrective Action References: Condition Reports 122359 and 122375.

Performance Assessment:

The inspectors determined this violation was associated with a minor performance deficiency.

Enforcement:

The Reactor Oversight Processs significance determination process does not specifically consider the regulatory process impact in its assessment of licensee performance.

Therefore, it is necessary to address this violation, which impedes the NRCs ability to regulate, using traditional enforcement to adequately deter non-compliance.

Severity: The finding was evaluated in accordance with the NRC's Enforcement Policy. The finding was reviewed by NRC management and because the violation was of very low safety significance, was not repetitive or willful, and was entered into the corrective action program, this violation is being treated as a Severity Level IV NCV, consistent with the NRC Enforcement Policy.

Violation: Title 10 CFR 50.70(b)(4), Inspections, requires, in part, that the licensee shall ensure that the arrival and presence of an NRC inspector, who has been properly authorized facility access as described in 10 CFR 50.70(b)(3), is not announced or otherwise communicated by its employees or contractors to other persons at the facility unless specifically requested by the NRC inspector.

Contrary to the above, on April 10, 2018, the licensee failed to ensure that the arrival and presence of NRC inspectors, who had been properly authorized facility access as described in 10 CFR 50.70(b)(3), were not announced or otherwise communicated by its employees or contractors to other persons at the facility unless specifically requested by the NRC inspectors. Specifically, a radiation protection technician entered the spent fuel pool building and informed members of a work crew of the whereabouts of NRC radiation protection inspectors without being requested to do so.

Enforcement Action: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Observation

71152 - Problem

Identification and Resolution The inspectors reviewed the licensees progress in addressing the cross-cutting theme in the SCWE area, as discussed in the 2017 Annual Assessment Letter for Wolf Creek Generating Station (Report 05000482/2017006, ADAMS ML18052A345). The NRCs review of the licensees progress in addressing the SCWE theme was accomplished within the scope of the biennial problem identification and resolution inspection, which was completed on June 28, 2018. NRC Inspection Report 05000482/2018007 (ADAMS ML18218A265), dated August 8, 2018, discusses the results of this inspection, which concluded that actions taken to address the work environment challenges in the maintenance support group had not yet been effective.

The inspectors also considered whether there was an emerging trend associated with impacting the regulatory process. The inspectors noted NCV 05000482/2018002-01, as documented in this report, which involved announcement of an NRC inspectors presence by station personnel. The inspectors also noted that the announcement of an inspectors presence was not an isolated event. Specifically, the presence of an NRC inspector was announced by a Wolf Creek employee to a state official during a drill on February 27, 2018.

However, the inspectors determined that no violation occurred in this case because the announcement, which was not requested by the inspector, was not made to licensee personnel and was thereby outside the NRCs regulatory authority. These issues and other reportability questions being evaluated by ongoing inspections were considered, and no emerging trend has been identified at this time.

The inspectors noted that four NCVs that occurred within an approximate 1 year time period relate to the licensees understanding of the design basis and design basis implementing documents. Specifically:

  • NCV 05000482/2018002-02, Failure to Maintain Adequate Pressurization of the Control Room Envelope, involved a failure to ensure an implementing documentthe boundary matrixidentified all boundary functions; this led to a failure to control a boundary and was a primary contributor to the failure to pressurize the control room envelope.
  • NCV 05000482/2017003-02, Failure to Ensure the Design Basis was Adequately Represented in the Technical Specification Bases, involved discrepancies between the auxiliary feedwater Technical Specification Bases and the updated safety analysis report; as a result, inoperability of an auxiliary feedwater train was not recognized.
  • NCV 05000482/2017002-02, Failure to Declare Train A Component Cooling Water Inoperable, related to the Technical Specification Bases not specifically identifying specific valves importance to the safety-related design functions as outlined in the updated safety analysis report; as a result, inoperability of safety-related equipment was not recognized.

In each of these cases the inspectors observed that the updated safety analysis report was not consistently being referenced when questions about the adequacy or completeness of the Technical Specification Bases were identified. The inspectors also observed that each of these NCVs represented some organizational knowledge gap concerning the design basis as outlined in the updated safety analysis report.

Failure to Maintain Adequate Pressurization of the Control Room Envelope Cornerstone Significance Cross-cutting Report Section Aspect Mitigating Green [H.3] - Human

71152 - Systems NCV 05000482/2018002-02 Performance, Problem

Closed Change Identification Management and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion III, Design Control, was identified when the licensee failed to adequately recognize that the cable spreading room floor was a control building ventilation isolation boundary. Specifically, the licensee cut openings in the floor/ceiling between the 2,032 foot and 2,016 foot elevations of the control building and the impact on the control room envelopes ability to pressurize was not recognized. This was a primary contributor to the train B control room emergency ventilation system being unable to maintain the appropriate pressure in the control room envelope.

Description:

On March 5, 2018, the licensee performed Procedure STS PE-004, Aux Building and Control Room Pressure Test, Revision 16, and the train B control room emergency ventilation systems ability to pressurize the control room envelope and maintain pressure greater than or equal to 0.25 inches water gauge failed. Readings varied from nearly no measurable differential pressurerelative to outside airto approximately 0.15 inches water gauge. During this test, control building doors were not controlled.

Later tests on March 5, 2018, which maintained control of control building doors, had results that varied between 0.18 and 0.26 inches water gauge, with an average of 0.2258 inches water gauge. Troubleshooting was performed and, on March 6, 2018, an interim configuration associated with Design Change Package 14269, SGK05 Tech Spec Addition and Compensatory Modifications, was found to be impacting readings. Specifically, between September 17, 2017, and January 17, 2018, four approximately 2 foot by 2 foot openings were cut in the floor/ceiling between the 2,032 foot and 2,016 foot elevations of the control building to support ongoing ductwork installation.

On January 17, 2018, after penetrations for the modification were completed, compensatory measures consisting of steel plates covering the four floor openings were in place until ductwork installation began on February 19, 2018. These compensatory measures were put in place for fire, flood, and other functional concerns. On February 12, 2018, while the compensatory measures were in place, the train A control room emergency ventilation system successfully pressurized the control room envelope to 0.38 inches water gauge, demonstrating that the compensatory measures were adequate for maintaining control room envelope pressurization capability when in place.

Surveillance testing was performed for trains A and B of the control room emergency ventilation system on March 15, 2018, and the control room envelope was pressurized to 0.3448 and 0.3695 inches water gauge, respectively, which met surveillance requirements.

The system was restored to operable on March 16, 2018.

The inspectors reviewed the licensees cause evaluation, which determined that the probable causes of the issue were inadequate identification of control building ventilation isolation boundaries in WCRE-35, Boundary Matrix, Revision 0, and control of conditions during STS PE-004. Specifically, the inspectors also determined that the 2,016 foot to 2,032 foot elevation breaches were a primary contributor to the failure of the control room emergency ventilation system to maintain adequate control room envelope pressure. The inspectors noted that WCRE-35, which was referenced during modification work for Design Change Package 14269, did not identify the barriers between the 2,016 and 2,032 foot elevations of the control building as control building ventilation isolation boundaries. WCRE-35 was a new document that was first approved on November 30, 2016, and was created from A, Boundary Matrix, of AP 10-104, Breach Authorization, Revision 35.

WCRE-35 notes, The information in the attachment has been copied directly from the procedure Attachment A, but when there were discrepancies identified the information has been verified and updated. The inspectors determined that the creation of the new WCRE-35 document was an opportunity for the licensee to recognize the subject boundarys importance and categorize the barrier as a control building ventilation isolation boundary.

Corrective Actions: The licensee completed Revision 3 of WCRE-35 on April 16, 2018, which reflects additional control building ventilation isolation boundaries, essential reading was issued, and other actions were performed to improve control room envelope pressurization margin.

Corrective Action Reference: Condition Report 120056.

Performance Assessment:

Performance Deficiency: The failure to recognize control building ventilation isolation boundaries and meet the requirements of 10 CFR Part 50, Criterion III, Design Control, is a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it adversely affected the design control attribute of the Barrier Integrity Cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding, reactor coolant system, and containment) protect the public from radionuclide releases caused by accidents or events. Specifically, the control room emergency ventilation systems ability to maintain adequate pressurization of the control room envelope was adversely impacted after an ongoing ventilation modification breached the floor without compensatory measures in place.

Significance: The inspectors assessed the significance of the finding using Exhibit 3, Barrier Integrity Screening Questions, of Inspection Manual Chapter 0609, Appendix A, Significance Determination Process (SDP) for Findings At-Power, issued June 19, 2012, and determined this finding represents a degradation of the radiological barrier function provided for the control room and represents a degradation of the barrier function of the control room against smoke or a toxic atmosphere. Thus, a detailed risk evaluation is required.

The senior reactor analyst evaluated the subject performance deficiency and resulting plant conditions to determine the risk impact on the plant. The analyst identified that the control room emergency ventilation system is not a significant risk contributor, because it does not directly affect the core damage frequency, provided operators have a habitable environment.

Although the control room boundary was significantly degraded in the as-found condition, either train of the control room emergency ventilation system was capable of maintaining the control room envelope with some level of pressurization, based on multiple test results.

Therefore, while some deterioration of the control room environment could be expected, the control room emergency ventilation system appeared to be capable of maintaining a habitable environment throughout the relatively limited exposure period of the performance deficiency.

As a result, the increase in risk caused by the degraded condition of the control room envelope was negligible, and the finding was of very low safety significance (Green).

Cross-cutting Aspect: The inspectors determined that the finding has a human performance cross-cutting aspect in the area of change management in that leaders did not use a systematic process for evaluating and implementing change so that nuclear safety remains the overriding priority. Specifically, managers did not ensure that individuals understood the importance of, and their role in, the change management process when WCRE-35 was recently revised and implemented. As a result, WCRE-35 did not identify all control building ventilation isolation boundaries.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, requires, in part, that for those structures, systems, and components to which this appendix applies, measures shall be established to assure that applicable regulatory requirements and the design basis, as defined in 50.2 and as specified in the license application, are correctly translated into specifications, drawings, procedures, and instructions.

Contrary to the above, until April 16, 2018, for quality-related components associated with the control building, to which 10 CFR Part 50, Appendix B, applies, the licensee failed to assure that applicable regulatory requirements and the design basis, as defined in 50.2 and as specified in the license application, are correctly translated into specifications, drawings, procedures, and instructions. Specifically, the licensee failed to ensure that all control building ventilation isolation boundaries were adequately identified in WCRE-35, Boundary Matrix, which the station uses to identify boundary functions, such that the control room envelope could be adequately pressurized in accordance with design basis requirements.

Disposition: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Adequately Implement Instrumentation and Controls Surveillance Procedures Cornerstone Significance Cross-cutting Report Section Aspect Initiating Green [H.2] - Human

71152 - Events NCV 05000482/2018002-03 Performance, Problem

Closed Field Presence Identification and Resolution A self-revealed Green NCV of 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings, was identified when the licensee failed to adequately implement surveillance procedures that affected safety-related equipment and plant stability. Specifically, the licensee failed to adequately implement testing and calibration procedures for pressurizer level instrumentation. This resulted in two letdown isolation signals, securing of pressurizer heaters, and a pressurizer level transient on March 29, 2018.

Description:

On March 29, 2018, the licensee was performing Procedure STS IC-503B, Pressurizer Level Instrumentation Channel Calibration, Revision 12. This surveillance procedure performs calibration and testing activities associated with three pressurizer level channels, one-at-a-time. To perform calibration of each channel, a control room operator selects away from the channel to be tested, which ensures the controlling pressurizer level channels are not being tested. This allows maintenance technicians to perform calibration and testing activities associated with the desired channel. Following calibration and testing of each channel, the channel is restored and actions are taken to select away from the next desired channel to be tested, which again ensures the controlling pressurizer level channels are not being tested.

During the testing on March 29, 2018, station personnel successfully completed the calibration of channel 459, which is located in the SB038 cabinet. The technicians then informed the control room operator they were moving to the next section of the procedure associated with channel 460, and the operator selected away from channel 460 in accordance with procedure. The technicians had flagged a switch to be manipulated in cabinet SB038, but had incorrectly flagged the switch for channel 459. As a result, channel 459 was again taken to the test position, but this channel was now a controlling pressurizer level channel since channel 460 was to be tested next. The instrument failed low, which resulted in an actual pressurizer level transientlevel got as high as approximately 63 percent from a normal level of approximately 56.6 percentisolation of letdown, and automatic de-energization of the pressurizer back-up heaters.

Step 8.3.3 of Procedure STS IC-503B stated, At C2-0847 (LS/460), PLACE BS-1 (LS/460A)to TEST position. This procedure step was not followed and the technicians did not adequately use human performance tools to ensure they were in the appropriate cabinet and flagging the appropriate channel, and supervision was not present when the inappropriate cabinet was flagged.

Operators responded to the transient using Off-Normal Procedure OFN SB-008, Instrument Malfunctions, Revision 45, reselected channel 460 as the controlling pressurizer level channel in accordance with the off-normal procedure, and an operator stated to the technician that they had received the 459 loop alarms. The technician then restored channel 459 from the test position without supervision and proceeded on in Procedure STS IC-503B.

Procedure OFN SB-008 had ensured that the alternate pressurizer level channel on the pressurizer level control selector switch was selected. The technician did not re-perform Step 8.3.1.b, which states, Place BB LS-459D, PZR LEV CRTL SEL switch to L459/L461 position, before proceeding with channel 460 testing. Thus, when channel 460 was taken to the test position, this caused a second actual pressurizer level transientlevel got as high as 63 percenta second letdown isolation signal (though it had not yet been restored), and a second automatic de-energization of the back-up heaters signal was received. Operators again responded to the transient and stabilized the plant. Additionally, following the second actual pressurizer level transient operators provided the order to the technician to, stop work.

The licensees evaluation determined that because of the risk associated with this task, supervisory oversight was required. Specifically, the qualitative risk screening performed for the task identified the need for leadership team member implementation oversight as a risk mitigating action. However, the oversight had not yet made it to the control room. The inspectors agreed with the licensees conclusions that the lack of oversight was the most significant contributor to both failures to follow procedures.

Corrective Actions: The transient was stabilized, work was stopped following the second event, an event review was conducted, a stand-down was initiated, technician qualifications were removed, communications were made to operations and the site, and an interim action was created to have an operations individual present during two-minute drills for any work performed in the cabinets in the back of the control room.

Corrective Action Reference: Condition Report 120807.

Performance Assessment:

Performance Deficiency: The failure to adequately implement the testing and calibration procedure for pressurizer level instrumentation on two occasions and meet the requirements of 10 CFR Part 50, Criterion V, Instructions, Procedures, and Drawings, was a performance deficiency. Specifically, procedures for pressurizer level instrumentation calibration were not followed on two occasions:

(1) when an instrumentation and control technician failed to take the appropriate channel to test in accordance with procedure; and
(2) when the individual failed to adequately verify the appropriate channels were selected in accordance with procedure on March 29, 2018. These actions failed the 459 level transmitter channel low inappropriately and then subsequently failed the 460 level transmitter channel low inappropriately, respectively.

Screening: The inspectors determined the performance deficiency was more than minor because it affected the human performance attribute of the Initiating Events Cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations.

Specifically, the performance deficiency resulted in two separate actual pressurizer level transients, letdown isolation signals, and signals for automatic de-energization of the pressurizer back-up heaters.

Significance: The inspectors assessed the significance of the finding using Exhibit 1, Initiating Events Screening Questions, of Inspection Manual Chapter 0609, Appendix A, Significance Determination Process (SDP) for Findings At-Power, issued June 19, 2012, and determined this finding was not a deficiency that caused a plant trip and did not cause the loss of mitigation equipment relied upon to transition the plant from the onset of a trip to stable plant shutdown (e.g. loss of condenser, loss of feedwater). Furthermore, there were no other events such as a high energy line break, internal flooding, or fire. Therefore, the inspectors determined the finding was of very low safety significance (Green).

Cross-cutting Aspect: The inspectors determined that the finding has a human performance cross-cutting aspect in the area of field presence in that senior managers did not ensure supervisory and management oversight of work activities. Specifically, managers and supervisors did not practice visible leadership in the field and during safety significant evolutions like performance of Procedure STS IC-503B by placing eyes on the problem, coaching, mentoring, reinforcing standards and reinforcing positive decision making practices and behaviors, which led to the multiple examples of failure to follow procedures.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality shall be accomplished in accordance with documented instructions, procedures, or drawings of a type appropriate to the circumstances.

(1) Procedure STS IC-503B, Pressurizer Level Instrumentation Channel Calibration, Revision 12, an Appendix B quality related procedure, provides instructions for performing pressurizer level instrument calibration testing. Procedure STS IC-503B, Step 8.3.3, requires that BS-1 (LS/460A) be placed in the test position. Contrary to the above, on March 29, 2018, BS-1 (LS/460A) was not placed in the test position.

Specifically, the 459 channel was placed in the test position inappropriately.

(2) Procedure STS IC-503B, Step 8.3.1.b, requires, in part, verification that BB LS-459D, the pressurizer level control selector switch, be placed in the L459/L461 position for channel 460 testing and calibration. Contrary to the above, on March 29, 2018, verification that BB LS-459D, the pressurizer level control selector switch, was placed in the L459/L461 position for channel 460 testing and calibration was not performed.

Specifically, testing and calibration of channel 460 occurred while channel 460 was selected as the controlling channel.

Disposition: This violation is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

On April 13, 2018, the inspector presented the occupational radiation safety inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.

On May 8, 2018, the inspector presented the inservice inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.

On July 17, 2018, the inspector presented the quarterly resident inspector inspection results to Mr. C. Reasoner, Chief Nuclear Officer and Senior Vice President, and other members of the licensee staff.

The inspectors verified no proprietary information was retained or documented in this report.

DOCUMENTS REVIEWED

71111.01Adverse Weather Protection

Procedures

Number Title Revision

OFN AF-025 Unit Limitations 55

Drawings

Number Title Revision

KD-7496 One Line Diagram 67

Condition Reports

23867 123954 123955 123956 123957

23958 123959 123961 123962 123963

23968 123969

Miscellaneous Documents

Number Title Date

Temporary Waverly-LaCygne 345 kV line outages Expires

Operating Guide December 31,

2018

Transmission Outage of the Wolf Creek-Benton 345 kV Line February 28,

Operating 2018

Directive 0300

Transmission Outage of the Wolf Creek-Rose Hill 345 kV Line February 28,

Operating 2018

Directive 0301

Transmission Outage of Wolf Creek 345 kV Breaker 345-40 or 345-60 February 28,

Operating 2018

Directive 0306

Transmission Outage of the Wolf Creek-Waverly 345 kV Line February 28,

Operating 2018

Directive 0307

Transmission Outage of the Waverly-LaCygne 345 kV Line February 28,

Operating 2018

Directive 0308

71111.04Equipment Alignment

Procedures

Number Title Revision

CKL AL-120 Auxiliary Feedwater Normal Lineup 42

CKL EC-120 Fuel Pool Cooling and Cleanup System Normal Valve 17

Lineup/Breaker Checklist

CKL EF-120 Essential Service Water Valve, Breaker and Switch Lineup 54

Drawings

Number Title Revision

E-13EC09 Schematic Diagram Spent Fuel Pool Alternate Power 1

Supply Motor Controller

E-13GG02 Schematic Diagram Spent Fuel Pool Pump Room Coolers 3

KD-7496 One-Line Diagram 61

M-12AL01 Piping & Instrumentation Diagram Auxiliary Feedwater 28

System

M-12EC01 Piping & Instrumentation Diagram Fuel Pool Cooling and 23

Clean-up System

M-12EC02 Piping & Instrumentation Diagram Fuel Pool Cooling and 7

Clean-up System

M-12EF01 Piping & Instrumentation Diagram Essential SVC Water 29

System

M-12EF02 Piping & Instrumentation Diagram Essential Service Water 42

System

M-K2EF01 Piping & Instrumentation Diagram Essential Service Water 70

System

M-K2EF01A Abandoned ESW Equipment 2

M-K2EF03 Piping & Instrumentation Diagram Essential Service Water 19

System

M-K2EF03A Abandoned ESW Equipment 1

Condition Reports

2669 121872 122213 122233 124453

71111.05AQFire Protection Annual/Quarterly

Procedures

Number Title Revision

AP 10-106 Fire Preplans 18A

Drawings

Number Title Revision

E-1F9905 Fire Hazard Analysis 8

Condition Reports

21946 122915 122944 123429 123446

23920 123921

71111.06Flood Protection Measures

Drawings

Number Title Revision

C-K201 E.S.

W.S. Yard Pipelines & Elect. Duct Banks Plan, Sections 10

& Schedules SHT.1

C-K201 E.S.

W.S. Yard Pipelines & Elect. Duct Banks Plan, Sections 12

& Schedules SHT.1

C-K202 E.S.

W.S. Yard Pipelines & Electrical Duct Banks Plan, 10

Sections & Schedules SHT.-2

C-K202 E.S.

W.S. Yard Pipelines & Electrical Duct Banks Plan, 11

Sections & Schedules SHT.-2

C-K209 E.S.W.S. Electrical Manholes Plans Sections & Details 9

C-K212 E.S.W.S Yard Pipelines & Elec. Duct Banks Plan & Sections 4

Condition Reports

24380 124381 124382 124383 124397

24409

71111.08Inservice Inspection Activities

Procedures

Number Title Revision

54-ISI-603-009 Automated Ultrasonic Examination of Reactor Pressure 9

Vessel Closure Head Penetration Containing Thermal

Sleeves

AP-16F-001 Boric Acid Corrosion Control Program 9

I-ENG-023 Steam Generator Data Analysis Guidelines 16

LMT-08-PDI-UT-1 Ultrasonic Examination of Ferritic Piping Welds 0

LMT-08-PDI-UT-11 Ultrasonic Examination of Nozzle Inner Radius Area at Wolf 0

Creek Generating Station

LMT-08-UT-004 Ultrasonic Examination of Vessel Welds and Adjacent Base 0

Material > 2.0 in Thickness

SG-SGMP-15-4 Wolf Creek Generating Station RF20 Condition Monitoring 0

and Operational Assessment

SG-SGMP-16-18 Wolf Creek Generating Station RF21 Condition Monitoring 0

and Operational Assessment

SG-SGMP-18-9 Wolf Creek Generating Station RF22 Condition Monitoring 0

and Operational Assessment for

Cycle 23 and Cycle 24

STS PE-040E Reactor Pressure Vessel Head Visual Inspection 7

WCRE-30 Inservice Inspection Program Plan Wolf Creek Generating 2

Station Interval 4

Condition Reports

93748 93749 107686 108888 109175

111055 112584 113666 114073 117639

117827 121438 121439

71111.11Licensed Operator Requalification Program and Licensed Operator Performance

Procedures

Number Title Revision

STS AE-211 Main Feed Reg Valve Inservice Valve Test 3

SYS NB-201 Transferring NB01 Power Sources 61

SYS NB-320 Deenergizing and Energizing ESF Transformers 12

Condition Reports

23853 123950 123951

Miscellaneous Documents

Number Title Revision/

Date

17-01 (IC342) 2018 Biennial Requalification Exam Scenario 1

18-01 (340) 2018 Annual Requalification Exam 0

STS AE-211 Main Feed Reg Valve Inservice Valve Test Completed

May 17, 2018

SYS NB-201 Transferring NB01 Power Sources Completed

May 2, 2018

SYS NB-320 Deenergizing and Energizing ESF Transformers Completed

May 2, 2018

71111.12Maintenance Effectiveness

Condition Reports

113227 122957

Work Orders

17-428387-001

Miscellaneous Documents

Number Title Date

System Health Report: Fuel Pool Cooling April 1, 2015

through

June 30, 2015

System Health Report: Fuel Pool Cooling October 1, 2015

through December

31, 2015

System Health Report: Fuel Pool Cooling April 1, 2016

through December,

2016

System Health Report: Fuel Pool Cooling July 1, 2016 through

June 30, 2017

System Health Report: Fuel Pool Cooling January 1, 2017

through June 30,

2017

Miscellaneous Documents

Number Title Date

System Health Report: Fuel Pool Cooling July 1, 2017 through

December 31, 2017

EC Maintenance Rule Final Scope Evaluation:

Spent Fuel Pool Cooling and Cleanup - EC-01

EC Maintenance Rule Final Scope Evaluation:

Spent Fuel Pool Cooling and Cleanup - EC-02

EC Maintenance Rule Final Scope Evaluation:

Spent Fuel Pool Cooling and Cleanup - EC-03

EC Maintenance Rule Final Scope Evaluation:

Spent Fuel Pool Cooling and Cleanup - EC-04

EC Maintenance Rule Final Scope Evaluation:

Spent Fuel Pool Cooling and Cleanup - EC-05

EC Maintenance Rule Final Scope Evaluation:

Fuel Pool Cooling and Cleanup - EC-06

EC Maintenance Rule Final Scope Evaluation:

Spent Fuel Pool Cooling and Cleanup - EC-07

71111.13Maintenance Risk Assessments and Emergent Work Control

Procedures

Number Title Revision

AP 21C-001 Wolf Creek Substation 20

AP 21D-004 Control of Containment Penetrations During Shutdown 11A

Operations

AP 22C-008 Qualitative Risk Management 4B

FHP 02-001 Refueling Operations 46

FHP 02-007A Reactor Vessel Closure Head Removal 12A

FHP 05-001 Equipment Hatch Operations 0

GEN 00-008 RCS Level Less Than Reactor Vessel Flange Operations 32

STS GP-001 Containment Purge Valves Actuation Test 27

STS GP-006 CTMT Closure Verification 14

STS GP-006 CTMT Closure Verification 24A

SYS BB-215 RCS Drain Down With Fuel In Reactor 48

Drawings

Number Title Revision

M-12BB01 Piping and Instrumentation Diagram Reactor Coolant 36

System

M-12BB02 Piping and Instrumentation Diagram Reactor Coolant 28

System

M-12BB04 Piping and Instrumentation Diagram Reactor Coolant 23

System

M-12EJ01 Piping and Instrumentation Diagram Residual Heat 54

Removal System

M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant 44

Injection System

M-12EM02 Piping and Instrumentation Diagram High Pressure Coolant 22

Injection System

M-12EM03 Piping and Instrumentation Diagram High Pressure Coolant 3

Injection System Test Line

Condition Reports

21353

Miscellaneous Documents

Number Title Date

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary April 5, 2018

Shift: Nights, Mode: 5

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary April 6, 2018

Shift: Days, Mode 6

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary April 7, 2018

Shift: Nights, Mode 6

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary April 12, 2018

Shift: Nights, Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary April 19, 2018

Shift: Nights, Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary April 24, 2018

Shift: Days, Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment Summary May 8, 2018

Shift: Nights, Mode: 6

ET 88-0193 Docket No. 50-482: Generic Letter 88-17 - Loss of Decay December 23,

Heat Removal 1988

Miscellaneous Documents

Number Title Date

ET 92-0001 Docket No. 50-482: Change in Commitment Associated January 2,

with Generic Letter 88-17 1992

STS CR-002 Shift Log for Modes 4, 5, and 6 Completed

May 9, 2018

WM 89-0041 Docket No. 50-482: Generic Letter 88-17 - Loss of Decay February 2,

Heat Removal 1989

71111.15Operability Determinations and Functionality Assessments

Procedures

Number Title Revision

AP 22A-001 Screening, Prioritization and Pre-Approval 21

AP 26C-004 Operability Determination and Functionality Assessment 35

AP 28-001 Operability Evaluations 25

Drawings

Number Title Revision

Westinghouse Drawing 1464F11

M-703-00055 Closure Head (SAP) General Assembly W02

M-709-00099 Control Rod Mechanism Housing Details - Sheet 1 W01

Condition Reports

2207 122351 122581 123083 123084

23567 123902 123903 123905 123906

23907 123908 123914

Work Orders

18-438919-000 18-438984-000 18-439282-000

Miscellaneous Documents

Number Title Revision/Date

APF 05-013-01 M-721-00096 - Instruction Manual for Safety Injection W25

Pump

Miscellaneous Documents

Number Title Revision/Date

APF 05C-004-01 WCNOC - Basic Engineering Disposition - DPEM01A May 1, 2018

Current Reading Higher Than Name Plate Rating - CR

2518

APF 05C-004-01 WCNOC - Basic Engineering Disposition - DPEM01A May 3, 2018

Current Reading Higher Than Name Plate Rating - CR

2581

APF 05C-004-01 WCNOC - Basic Engineering Disposition - PEM01A RF22 May 9, 2018

Rework Hydraulic Performance Impact

MRP 2018-010 Electric Power Research Institute - Notification of Recent April 20, 2018

PWR CRDM Thermal Sleeve Flange Wear and Control

Rod Motion Stoppage Operating Experience and

Recommended Plant Actions

XX-E-006 Calculation XX-E-006 AC System Analysis Rev. 7 - 7

Appendix 31 - Scenario L1 (LOCA) Motor Starting

Analysis - Output Report

71111.18Plant Modifications

Drawings

Number Title Revision/Date

E-13GG02 Schematic Diagram Spent Fuel Pool Pump Room Coolers 3

E-13EC09 Schematic Diagram Spent Fuel Pool Alternate Power 1

Supply Motor Controller

M-084A-00010 8539 SGG45 Wiring Diagram January 31,

2018

WIP-E-12EC09- Schematic Diagram Spent Fuel Pool Alternate Power 1

000-A-1 Supply Motor Controller

WIP-E-IR0211A- Raceway Plan Plant Site Southwest Quadrant Underground 00

2B-1 Duct Bank EL. [Elevation] 2000-0

WIP-M-1X6906- Fuel Building Penetration Closure Wall Elevations 00

000-A-1

WIP-M-1X6906- Fuel Building Penetration Closure Wall Elevations 00

001-A-1

WIP-M-13EG29- Piping Isometric Drawing Alternate Spent Fuel Pool Cooling 00

000-A-1 Fuel Building

Condition Reports

2629 122684 122959 123060 123146

23193 123195 123259 123584 123592

Miscellaneous Documents

Number Title Date

14403 Field Change Notice: Spent Fuel Pool Instrumentation April 30, 2015

System

14496 Field Change Notice: Fukushima Spent Fuel Pool Makeup August 30,

2016

241 Change Package Engineering Disposition: Spent Fuel Pool November 29,

Alternate Cooling Modification 2017

273 Field Change Notice: Spent Fuel Pool Alternate Cooling March 3,

Electrical 2018

71111.19Post Maintenance Testing

Procedures

Number Title Revision

STN EC-201 Fuel Pool Cooling and Clean-Up System Valve Test 2

STN XMR-001 XMR01 Control Alarm and Trip Circuit Verification 3

STS BG-100A Centrifugal Charging System A Train Inservice Pump 48

STS CR-002 Shift Log for Modes 4, 5, and 6 84

STS EM-100A Safety Injection Pump A Inservice Pump Test 41

STS IC-503B Channel Calibration pressurizer Level 12

STS IC-503B Channel Calibration pressurizer Level 12A

STS KJ-015B Manual/Auto Fast Start, Sync & Loading of EDG NE02 44

SYS EC-120 Fuel Pool Cooling and Cleanup System Startup 56

Drawings

Number Title Revision

E-0033.3-009-03 Power Transformer, Class, OA/FA/FOA, Shell Form, 3

Outdoor, Three Phase, KVA 60000/80000/100000, H.

V.

345000,

L.V. 13800,
Y. Y., 13800, 60 Hertz

E-003.3-00008 CA/FA/FOA Transformer Control Schematic Wiring Diagram W10

Drawings

Number Title Revision

E-003.3-00022 Power Transformer, Class OA/FA/FOA, Shell Form, W09

Outdoor, Three Phase, KVA 60000/80000/100000, H.

V.

345000, L

V. 13800,
Y. Y. 13800, 60 Hertz

E-11MR01 Startup Transformer Single Line Metering and Relaying 7

Diagram

M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant 45

Injection System

M-761-00076-06 Process Control Block Diagram SNUPPS 6

Condition Reports

2520 122524 122526 122527 122784

2954 124387 124400 124405

Work Orders

13-366290-005 15-403582-002 17-427200-023 17-432721-000 17-432722-000

18-438909-000 18-438919-001 18-438923-001

Miscellaneous

Number Title Date

APF 29B-003-01 Surveillance Test Routing Sheet (STRS) - Fuel Pool April 23,

Cooling and Cleanup System Valve Test 2018

STN EM-100A SI Pump A Reference Pump Completed

April 29,

2018

STS EM-100A Safety Injection Pump A Inservice Pump Test Completed

May 11, 2018

STS KJ-015B Manual/Auto Fast Start, Sync & Loading of EDG NE02 Completed

May 1, 2018

71111.20Refueling and Other Outage Activities

Procedures

Number Title Revision

AI-07B-024 Instructions For Containment Purge Permits 18

FHP 05-001 Equipment Hatch Operations 0

GEN 00-002 Cold Shutdown to Hot Standby 101

Procedures

Number Title Revision

GEN 00-003 Hot Standby to Minimum Load 101

GEN 00-008 RCS Level Less Than Reactor Vessel Flange Operations 32

INC C-0044 Functional Check of 7300 Process Power Supply 7

RXE 01-002 Reload Low Power Physics Testing 26

STS CR-002 Shift Log for Modes 4, 5, and 6 84

STS GP-006 CTMT Closure Verification 24A

SYS BB-112 Vacuum Fill of the RCS 43

SYS BB-215 RCS Drain Down With Fuel In Reactor 47A

SYS BB-215 RCS Drain Down With Fuel In Reactor 48

SYS SB-300 Deenergizing SB Protection Sets 5

Drawings

Number Title Revision

E-13NN01 Class IE Instrument AC Schematic 9

E-13SB09 Schematic Diagram Process Protection Cabinets 1,2,3,4 00

Safeguards Test Cabinets and Fire Isolation Cabinets

M-12BB01 Piping and Instrumentation Diagram Reactor Coolant 36

System

M-12BB02 Piping and Instrumentation Diagram Reactor Coolant 28

System

M-12BB04 Piping and Instrumentation Diagram Reactor Coolant 23

System

M-12EJ01 Piping and Instrumentation Diagram Residual Heat 54

Removal System

M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant 44

Injection System

M-12EM01 Piping and Instrumentation Diagram High Pressure Coolant 45

Injection System

M-12EM02 Piping and Instrumentation Diagram High Pressure Coolant 22

Injection System

M-12EM03 Piping and Instrumentation Diagram High Pressure Coolant 3

Injection System Test Line

Condition Reports

20865 120906 120917 120934 120963

21467 121469 121507 121575 121710

21779 121825 121881 121901 121938

21953 122359 122375 122571 122593

2787 122798 122837 123075 123087

23221 123429 123434 123440 123444

23446 123448 123488 123500 123517

23752 123767

Work Orders

17-426098-000 18-437026-000

Miscellaneous Documents

Number Title Revision/Date

Foreign Material Inspections During Wolf Creek RF 22

Failed Fuel Mitigation - Presenter Daljit Mand

OPS RF-22 Rotation Schedule

Refuel 22: Failed Fuel Action Matrix for Completion Core January 4,

Testing 2018

RF22 OCC Shift Update - Nights April 6, 2018

RF22 OCC Shift Update - Days April 11, 2018

RF22 OCC Shift Update - Nights April 11, 2018

RF22 OCC Shift Update - Nights April 12, 2018

RF22 OCC Shift Update - Nights April 13, 2018

RF22 OCC Shift Update - Days April 15, 2018

RF22 OCC Shift Update - Nights April 16, 2018

RF22 OCC Shift Update - Days April 17, 2018

RF22 OCC Shift Update - Nights April 18, 2018

RF22 OCC Shift Update - Nights April 19, 2018

RF22 OCC Shift Update - Days April 25, 2018

RF22 OCC Shift Update - Nights April 26, 2018

RF22 OCC Shift Update - Days April 29, 2018

RF22 OCC Shift Update - Nights April 29, 2018

Miscellaneous Documents

Number Title Revision/Date

RF22 OCC Shift Update - Days April 30, 2018

RF22 OCC Shift Update - Nights April 30, 2018

RF22 OCC Shift Update - Days May 1, 2018

RF22 OCC Shift Update - Nights May 1, 2018

RF22 OCC Shift Update - Days May 2, 2018

RF22 OCC Shift Update - Nights May 2, 2018

RF22 OCC Shift Update - Days May 3, 2018

RF22 OCC Shift Update - Nights May 4, 2018

RF22 OCC Shift Update - Nights May 4, 2018

RF22 OCC Shift Update - Days May 6, 2018

RF22 OCC Shift Update - Days May 7, 2018

RF22 OCC Shift Update - Nights May 7, 2018

RF22 OCC Shift Update - Days May 8, 2018

RF22 OCC Shift Update - Nights May 8, 2018

RF22 OCC Shift Update - Days May 9, 2018

RF22 OCC Shift Update - Nights May 9, 2018

RF22 OCC Shift Update - Nights May 10, 2018

RF22 OCC Shift Update - Days May 13, 2018

RF22 OCC Shift Update - Days May 14, 2018

RF22 OCC Shift Update - Nights May 14, 2018

RF22 OCC Shift Update - Days May 15, 2018

RF22 OCC Shift Update - Nights May 15, 2018

RF22 OCC Shift Update - Days May 16, 2018

RF22 OCC Shift Update - Days May 17, 2018

RF22 OCC Shift Update - Nights May 17, 2018

RF2[2] FIN Team Schedule

AIF 21-016-02 Time Verification Form - Days - Credited April 3, 2018

AIF 21-016-02 Time Verification Form - Nights - Credited April 3, 2018

AIF 21-016-02 Time Verification Form - Nights - No Credit Taken April 3, 2018

AIF 22D-008-02 Mode 2 (M2U)/Mode 1 (M1U) Restart Checklist Completed

May 17, 2108

Miscellaneous Documents

Number Title Revision/Date

APF 15C-002-01 Procedure Cover Sheet - Vacuum Fill of the RCS Completed

May 11, 2018

APF 21-001-02 Control Room Turnover Checklist - On-Coming CRS/WC May 7, 2018

SRO/RO/BOP Review

APF 22B-001-08 Shutdown Risk Assessment Mode 6 Refueling Operations 12

>23 Ft. Above Vessel Flange

APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled April 4, 2018

APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled April 7, 2018

APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled April 11, 2018

APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled April 14, 2018

APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled April 15, 2018

APF 22B-001-09 Shutdown Risk Assessment No Mode - Defueled April 17, 2018

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 1, 2018

Summary - Shift: Days, Mode 5

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 3, 2018

Summary - Shift: Days, Mode 5

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 4, 2018

Summary - Shift: Days, Mode 5

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 5, 2018

Summary - Shift: Nights, Mode: 5

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 6, 2018

Summary - Shift Days, Mode 6

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 7, 2018

Summary - Shift: Days, Mode: 6

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 7, 2018

Summary - Shift: Nights, Mode: 6

APF 22B-001-10 Shutdown Safety Function Status & Assessment May 8, 2018

Summary - Shift: Nights, Mode: 6

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 11, 2018

Summary - Shift: Days, Mode: Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 14, 2018

Summary - Shift: Nights, Mode: Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 15, 2018

Summary - Shift: Days, Mode: Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 15, 2018

Summary - Shift: Nights, Mode: Defueled

Miscellaneous Documents

Number Title Revision/Date

APF 22B-001-10 Shutdown Safety Function Status & Assessment April 17, 2018

Summary - Shift: Days, Mode: Defueled

APF 22B-001-10 Shutdown Safety Function Status & Assessment May 8, 2018

Summary - Shift: Days, Mode: Defueled

APF 25A-401-01 ALARA Review Package - RWP Number 181102 January 18,

2018

APF 25A-401-01 ALARA Review Package - RWP Number 182602 15

APF 25A-401-01 ALARA Review Package - RWP Number 183000 March 7, 2018

APF 25A-401-01 ALARA Review Package - RWP Number 182602 March 8, 2018

APF 25A-401-04 Pre-Job Briefing Form - RWP Number: 182601 10A

BGV0365 Mixed Bed Demins Inlet Line Upstrm Drain 20

C22: R-EN-A- Clearance Order April 2, 2018

2A

C22: R-EN-B- Clearance Order March 31, 2018

2A

C22: R-OP-S- Clearance Order May 4, 2018

001B

C22: R-OP-S- Clearance Order May 9, 2018

2A

C22: R-OP-S- Clearance Order May 11, 2018

2B

C22: R-OP-S- Clearance Order May 6, 2018

003A

ET 88-0193 Docket No. 50-482: Generic Letter 88-17 - Loss of December 23,

Decay Heat Removal 1988

ET 92-0001 Docket No. 50-482: Change in Commitment Associated January 2,

with Generic Letter 88-17 1992

GTRE 32 Wolf Creek Generating Station Chemistry Department Report Created

Radiochemistry Lab April 18, 2018,

2:36

GTRE 32 Wolf Creek Generating Station Chemistry Department Report Created

Radiochemistry Lab April 18, 2018,

08:43

GTRE 32 Char Wolf Creek Generating Station Chemistry Department Report Created

Radiochemistry Lab April 15, 2018,

14:59

Miscellaneous Documents

Number Title Revision/Date

GTRE 33 Wolf Creek Generating Station Chemistry Department Report Created

Radiochemistry Lab April 18, 2018,

07:04

GTRE 33 Wolf Creek Generating Station Chemistry Department Report Created

Radiochemistry Lab April 18, 2018,

07:05

K04-013 Gas Effluent Release Report April 16, 2018

RA 18-0032 Minor Corrections to Refuel 22 Risk Assessment Team March 20, 2018

Report RA 18-0021 - Schedule Level 1 Rev. C 2/1/2018

RPF 02-105-01 Radiation Work Permit - 181102 000

RPF 02-105-01 Radiation Work Permit - 182601 000

RPF 02-105-01 Radiation Work Permit - 182602 000

RPF 02-105-01 Radiation Work Permit - 182602 002

RFP 02-105-01 Radiation Work Permit - 184206 000

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180225-3 February 25,

2018

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180320- March 20, 2018

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180405- April 5, 2018

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180416-1 April 16, 2018

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180407-6 April 7, 2018

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180421- April 21, 2018

RPF 02-210-01 WCGS Radiological Survey Map - Survey M-20180406- April 6, 2018

RXE 01-002 Reload Low Power Physics Testing Completed

May 17, 2018

STS CR-002 Shift Log for Modes 4, 5, and 6 Completed

May 11, 2018

STS GP-006 Containment Closure Verification Completed

April 6, 2018

WM 26-0034 Docket No. 50-482: Foreign Ownership, Control or April 26, 2018

Influence (FOCI) Information - Change to Lists of

Owners, Officers, Directors and Executive Personnel

Miscellaneous Documents

Number Title Revision/Date

WM 89-0041 Docket No. 50-482: Generic Letter 88-17 - Loss of February 2,

Decay Heat Removal 1989

71111.22Surveillance Testing

Procedures

Number Title Revision

STS BB-004 RCS Water Inventory Balance 49

STS BB-006 RCS Water Inventory Balance Using the NPIS Computer 19

STS BB-010 Manual RCS Water Inventory Balance 2

STS CV-210A ECCS SI Pump Comprehensive and Inservice Check Valve 27

Test

STS EM-003A ECCS (CCP) Flow Balance and CCP Comprehensive Test 23

STS KJ-001B Integrated D/G and Safeguard Actuation Test - Train B 61

STS PE-128 LLRT [Local Leak Rate Test] Valve Lineup for Penetrations 6

and 29

Condition Reports

2451 122757 122783 123223

Miscellaneous

Number Title Revision/Date

STS CV-210A ECCS SI Pump Comprehensive and Inservice Check Valve Completed

Test April 29, 2018

STS CV-210A ECCS SI Pump Comprehensive and Inservice Check Valve Completed

Test May 1, 2018

STS EM-003A ECCS (CCP) Flow Balance and CCP Comprehensive Test Completed

May 2, 2018

WCRE-03 Wolf Creek Tank Document 22

71124.01Radiological Hazard Assessment and Exposure Controls

Procedures

Number Title Revision

AP 19D-100 Radioactive Source Program 5

Procedures

Number Title Revision

AP 25A-001 Radiation Protection Manual 17B

AP 25A-100 Access to Locked High or Very High Rad Areas 29

AP 25A-100 Containment Entry 18A

AP 25B-100 Radiation Worker Guidelines 51

AP 25B-300 RWP Program 24A

Radiation Protection Organization, Responsibilities and

RPP 01-105 21

Code of Conduct

RPP 02-105 Radiation Work Permit 48

RPP 02-215 Posting of Radiological Controlled Areas 34A

RPP 02-405 RCA Access Control 20

RPP 02-515 Release of Material from the RCA 34

RPP 02-605 Control and Inventory of Radioactive Sources 18

Condition Reports

2244 112935 112973 113053 113055

113627 113631 114261 116377 116509

116510 117296 119183 119223 120975

21159 121171 121281 121282 121568

Radiation Work Permits

Number Title Revision

180021 Cartridge Filter Change-Out in Aux and RW Buildings 0

2601 Routine Outage Access (No LHRA Access) 0

183220 Primary S/G Eddy Current Testing 1

184199 Secondary Side S/G FOSAR 0

184200 Secondary Side S/G Sludge Lance 0

184420 Scaffolding 0

184482 RV Head Disassembly - Canopy Seal Clamp Activities 0

184483 RV Head Reassembly - Canopy Seal Clamp Activities 0

186020 Reactor Vessel Head Preparation 1

Radiation Surveys

Number Title Date

M-20180305-17 1306 and 1308C March 5, 2018

M-20180305-4 Resin Bed, Demin Alley, Filter Pit March 4, 2018

M-20180307-16 Seal Water HX & VCT Valve Room March 7, 2018

M-20180307-2 B RHR HX Room March 7, 2018

M-20180308-12 North and South Pipe Pen March 8, 2018

M-20180324-6 SJ 143 Sample Panel March 24, 2018

M-20180329-1 B RHR Pump March 29, 2018

M-20180402-20 S/G A&D Secondary April 2, 2018

M-20180403-2 S/G A&D Secondary April 3, 2018

M-20180409-19 2000 Aux South April 9, 2018

M-20180411-11 S/G A&D Secondary April 11, 2018

M-20180411-21 2047 Containment April 11, 2018

Air Sample Surveys

Number Title Date

18-0129 Containment RX Cavity April 1, 2018

18-0131 CTMT 2000' O/S Bio-shield April 1, 2018

18-0147 Fuel Building 2047 & above April 2, 2018

18-0154 CTMT 2047' April 3, 2018

18-0181 CTMT 2047 (Marinelli Grab Sample) April 4, 2018

18-0182 CTMT 2047 (Follow-up West of Cavity) April 4, 2018

18-0182 CTMT 2047 (Follow-up West of Cavity) April 4, 2018

Audits and Self-Assessments

Number Title Date

QA Audit Report:

18-01-RP/PC March 12, 2018

Radiation Protection And Process Control

Self-Assessment:

QH-2017-1476 Radiation Protection Procedures and Radiation May 4, 2017

Worker Behavior Observations

Radiation Protection Programmatic Review as

QH-2017-1481 delineated in NRC Inspection Procedures 71124.01, April 24, 2017

71124.03, and 71151.OR01

Miscellaneous Documents

Number Title Date

18-0181 Skin Dose From Noble Gas Calculation Sheet April 4, 2018

K 03-70 Air Sample Log April 4, 2018

RPF 02-605-03 Sealed Source Inventory January 29, 2018

STS HP-001 Sealed Source Contamination Surveillance Test January 29, 2018

71124.02Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls

Procedures

Number Title Revision

AP 25A-401 ALARA Program 25

AP 25A-410 ALARA Committee 23

AP 25B-300 RWP Program 24A

APF 25A-401-01 ALARA Review Package 15

APF 25A-401-04 Pre-Job Briefing Form 10A

APF 25A-401-07 In-Progress ALARA Review 1

APF 25A-401-08 Post-Job ALARA Review 1

RPF 02-105-05 RWP Risk Assessment 16A

RPP 02-105 RWP 48

RPP 02-605 Control & Inventory of Radioactive Sources 18

Condition Reports

2973 113052 113056 113057 113058

113627 113631 113708 113736 113762

114261 114915 115344 115564 115795

116952 117296 118610 119253 119743

119745 120919 120921 121089 121091

21099 121197 121217 121266 121270

21341 121375 121420 121422 121447

21482

Audits and Self-Assessments

Number Title Date

Quality Assurance Audit Report

18-01-RP/PC March 12, 2018

Radiation Protection and Process Control

Radiation Protection Programmatic Review as

QH-2017-1481 delineated in NRC Inspection Procedures 71124.01, April 24, 2017

71124.03, and 71151.OR01

NRC Inspection Procedure 71124.04, Occupational

QH-2017-1505 Dose Assessment and NRC 71124.02 Occupational May 22, 2017

ALARA Planning and Controls

Radiation Work Permit Packages

Number Title Revision

180021 Cartridge Filter Change-Out in Aux and RW Buildings A

2300 Maintenance Support 0

2601 Routine Outage Access (No Locked High Radiation Areas) 0

183220 Primary S/G Eddy Current RWP 1

184207 RCP Team Seal Replacement on C & D RCPs 0

184207 RCP Team Seal Replacement on C & D RCPs 1

184207 RCP Team Seal Replacement on C & D RCPs 2

184420 Scaffolding Activities RF22 0

184482 Canopy Seal Clamp Activities Disassembly 0

Miscellaneous Documents

Title Date

RF 21 & Pre RF21 Forced Outage Radiation Protection Summary January 9, 2017

71151Performance Indicator Verification

Procedures

Number Title Revision

AP 02A-001 Primary Chemistry Control 21

CHS SJ-143B RCS/CVCS/RHR Sampling at SJ-143 Panel 2

STS BB-006 RCS Water Inventory Balance Using the NPIS Computer 18

Condition Reports

23874 123885 124426 124427

Miscellaneous

Number Title Date

RCS June 2017 through June 2018 Printed June 20,

Measurement 2018

Reports

STS PE-019B RHR Suction Valve Leak Test Completed

November 18,

2016

STS PE-109E RCS Isolation Check Valve Leak Test Completed

November 19,

2016

71152Problem Identification and Resolution

Procedures

Number Title Revision

AP 10-104 Breach Authorization 35

AP 10-104 Breach Authorization 37A

AP 23-009 Control Room Envelope Habitability Program 2

OFN SB-008 Instrument Malfunctions 45

STS IC-503B Pressurizer Level Instrumentation Channel Calibration 12

STS PE-004 Aux Building and Control Room Pressure Test 16

Condition Reports

20056 120807 122587 123642 123823

Work Orders

18-437033-006

Miscellaneous

Number Title Revision/

Date

QA-2018-0421 Oversight of Operations During the First Quarter of 2018 April 20,

from 12/21/17 to 3/29/18 2018

Miscellaneous

Number Title Revision/

Date

QA-2018-0425 QA Assessment of the Maintenance 2018 First Quarter FAO April 22,

Report on 4/2/19 2018

QA-2018-0426 Provide QA Oversight of Engineering for the First Quarter of April 20,

2018 2018

QA-2018-0434 RF22 QA Assessment of Refuel Pool Overfill on 4-7-18 April 29,

2018

QH-2018-1628 FME Quick Hit Self-Assessment May 23, 2018

QS-2018-2504 QA Surveillance of Clearance Order Removal February 5,

2018

QS-2018-2510 Surveillance of CARB Meeting 1-17-18 February 5,

2018

QS-2018-2517 QA Observation of Question About Compensatory Measure February 5,

Fire Watch on 1/22/18 2018

QS-2018-2530 Power Block Roof Leaks February 7,

2018

QS-2018-2587 Attended and Observed Meeting on Effects of Modifications March 26,

269 2018

QS-2018-2597 QA Walkdown of Turbine and Control Buildings March 28,

2018

QS-2018-2601 RF22 Observation of Operations Just In Time Training for April 2, 2018

Plant Cooldown

QS-2018-2646 RF22 QA Observation of Holes Being Drilled for SGK05 April 8, 2018

Modification Work on 4/8/18

QS-2018-2649 RF 22 QA Review of FME Monitor Logs in Containment on April 9, 2018

4/8/18

QS-2018-2679 RF22 QA Observation of BHI Workers 4-12-18 April 13,

2018

RA 18-0054 Docket No. 50-482: Wolf Creek Generating Station Cycle April 29,

and Cycle 23 Core Operating Limits Report 2018

STS PE-004 Aux Building and Control Room Pressure Test Completed

March 7,

2018

STS PE-004 Aux Building and Control Room Pressure Test Completed

March 15,

2018

WCRE-35 Boundary Matrix 0

Miscellaneous

Number Title Revision/

Date

WCRE-35 Boundary Matrix 3

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

Number 31500011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, and Requests for

Withholding.

Information Request

January 24, 2018

Notification of Inspection and Request for Information

Wolf Creek Nuclear Operating Station

NRC Inspection Report 05000482/2018002

INSERVICE INSPECTION DOCUMENT REQUEST

A. Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (ims.certrec.com preferred), in care of Isaac Anchondo, by March 26, 2018, to

facilitate the selection of specific items that will be reviewed during the onsite inspection

week. The inspector will select specific items from the information requested below and then

request from your staff additional documents needed during the onsite inspection week

(Section B of this enclosure). We ask that the specific items selected from the lists be

available and ready for review on the first day of inspection. Please provide requested

documentation electronically if possible. If requested documents are large and only hard

copy formats are available, please inform the inspector(s), and provide subject

documentation during the first day of the onsite inspection.

If you have any questions regarding this information request, please call the inspector as

soon as possible.

On April 16, 2018, a reactor inspector from the Nuclear Regulatory Commissions (NRC)

Region IV office will perform the baseline inservice inspection at Wolf Creek Nuclear

Operating Station, using NRC Inspection Procedure 71111.08, "Inservice Inspection

Activities. Experience has shown that this inspection is a resource intensive inspection

both for the NRC inspector and your staff. The date of this inspection may change

dependent on the outage schedule you provide. In order to minimize the impact to your

onsite resources and to ensure a productive inspection, we have enclosed a request for

documents needed for this inspection. These documents have been divided into two

groups. The first group (Section A of the enclosure) identified information to be provided

prior to the inspection to ensure that the inspector is adequately prepared. The second

group (Section B of the enclosure) identifies the information the inspector will need upon

arrival at the site. It is important that all of these documents are up to date and complete in

order to minimize the number of additional documents requested during the preparation

and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and

understand that our regulatory contact for this inspection will be William Muilenburg of your

licensing organization. The tentative inspection schedule is as follows:

Preparation week: March 26, 2018

Onsite weeks: April 16-27, 2018

Our inspection dates are subject to change based on your updated schedule of outage

activities. If there are any questions about this inspection or the material requested, please

contact Isaac Anchondo at (817) 200-1152. (email to: Isaac.Anchondo@nrc.gov).

A.1 ISI/Welding Programs and Schedule Information

1. A detailed schedule (including preliminary dates) of:

1.1. Nondestructive examinations planned for ASME Code Class Components

performed as part of your ASME Section XI, risk informed (if applicable), and

augmented inservice inspection programs during the upcoming outage.

1.2. Examinations planned for Alloy 82/182/600 components that are not included in

the Section XI scope (If applicable)

1.3. Examinations planned as part of your boric acid corrosion control program

(Mode 3 walkdowns, bolted connection walkdowns, etc.)

1.4. Welding activities that are scheduled to be completed during the upcoming

outage (ASME Class 1, 2, or 3 structures, systems, or components)

2. A copy of ASME Section XI Code Relief Requests and associated NRC safety

evaluations applicable to the examinations identified above.

2.1. A list of ASME Code Cases currently being used to include the system and/or

component the Code Case is being applied to.

3. A list of nondestructive examination reports which have identified recordable or

rejectable indications on any ASME Code Class components since the beginning of

the last refueling outage. This should include the previousSection XI pressure test(s)

conducted during start up and any evaluations associated with the results of the

pressure tests.

4. A list including a brief description (e.g., system, code class, weld category,

nondestructive examination performed) associated with the repair/replacement

activities of any ASME Code Class component since the beginning of the last outage

and/or planned this refueling outage.

5. If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the upcoming outage, provide a detailed description of the welds to be

examined and the extent of the planned examination. Please also provide reference

numbers for applicable procedures that will be used to conduct these examinations.

6. Copy of any 10 CFR Part 21 reports applicable to structures, systems, or

components within the scope of Section XI of the ASME Code that have been

identified since the beginning of the last refueling outage.

7. A list of any temporary non-code repairs in service (e.g., pinhole leaks).

8. Please provide copies of the most recent self-assessments for the inservice

inspection, welding, and Alloy 600 programs.

9. Copy of the procedures for welding techniques, and NDE that will be used during the

outage.

A.2 Reactor Pressure Vessel Head

1. Provide a detailed scope of the planned bare metal visual examinations (e.g., volume

coverage, limitations, etc.) of the vessel upper head penetrations and/or any

nonvisual nondestructive examination of the reactor vessel head including the

examination procedures to be used.

A.3 Boric Acid Corrosion Control Program

1. Copy of the procedures that govern the scope, equipment and implementation of the

inspections required to identify boric acid leakage and the procedures for boric acid

leakage/corrosion evaluation.

2. Please provide a list of leaks (including code class of the components) that have

been identified since the last refueling outage and associated corrective action

documentation. If during the last cycle, the unit was shutdown, please provide

documentation of containment walkdown inspections performed as part of the boric

acid corrosion control program.

A.4 Steam Generator Tube Inspections

1. A detailed schedule of:

  • Steam generator tube inspection, data analyses, and repair activities for the

upcoming outage.

  • Steam generator secondary side inspection activities for the upcoming outage

(if occurring).

2. Copy of SG history documentation given to vendors performing eddy current (ET)

testing of the SGs during the upcoming outage.

3. Copy of procedure containing screening criteria used for selecting tubes for in-situ

pressure testing and the procedure to be used for in-situ pressure testing.

4. Copy of previous outage SG tube operational assessment. Also include a copy of

the following documents as they become available:

  • Degradation assessment
  • Condition monitoring assessment

5. Copy of the document defining the planned SG ET scope (e.g., 100 percent of

unrepaired tubes with bobbin probe and 20 percent sample of hot leg expansion

transition regions with rotating probe) and identify the scope expansion criteria,

which will be applied. Also identify and describe any deviations in this scope or

expansion criteria from the EPRI Guidelines.

6. Copy of the document describing the ET acquisition equipment to be applied

including ET probe types. Also identify the extent of planned tube examination

coverage with each probe type (e.g. rotating probe -0.080 inches, 0.115 inches

pancake coils and mid-range +point coil applied at the top-of-tube-sheet plus 3

inches to minus 12 inches).

7. Identify and quantify any SG tube leakage experienced during the previous operating

cycle. Also provide documentation identifying which SG was leaking and corrective

actions completed and planned for this condition.

8. Copy of steam generator eddy current data analyst guidelines and site validated

eddy current technique specification sheets. Additionally, please provide a copy of

EPRI Appendix H, Examination Technique Specification Sheets, qualification

records.

9. Provide past history of the condition and issues pertaining to the secondary side of

the steam generators (including items such as loose parts, fouling, top of tube sheet

condition, crud removal amounts, etc.).

Indicate where the primary, secondary, and resolution analyses are scheduled to

take place.

A.5 Additional Information Related to all Inservice Inspection Activities

1. A list with a brief description of inservice inspection, and boric acid corrosion control

program related issues (e.g., CR) entered into your corrective action program since

the beginning of the last refueling outage. For example, a list based upon data base

searches using key words related to piping such as: inservice inspection, ASME

Code,Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or

errors in piping examinations.

2. Provide training (e.g. Scaffolding, Fall Protection, FME, Confined Space) if they are

required for the activities described in A.1 through A.3.

3. Please provide names and phone numbers for the following program leads:

Inservice inspection (examination, planning)

Containment exams

Reactor pressure vessel head exams

Snubbers and supports

Repair and replacement program

Licensing

Site welding engineer

Boric acid corrosion control program

Steam generator inspection activities (site lead and vendor contact)

B. Information to be Provided Onsite to the Inspector(s) at the Entrance Meeting (April 16,

2018):

B.1 Inservice Inspection / Welding Programs and Schedule Information

1. Updated schedules for inservice inspection/nondestructive examination activities,

including planned welding activities, and schedule showing contingency repair

plans, if available.

2. For ASME Code Class welds selected by the inspector from the lists provided from

section A of this enclosure, please provide copies of the following documentation for

each subject weld:

  • Weld data sheet (traveler).
  • Weld configuration and system location.
  • Applicable Code Edition and Addenda for weldment.
  • Applicable Code Edition and Addenda for welding procedures.
  • Applicable welding procedures used to fabricate the welds.
  • Copies of procedure qualification records (PQRs) supporting the weld

procedures from B.1.b.v.

  • Copies of welders performance qualification records (WPQ).
  • Copies of the nonconformance reports for the selected welds (If

applicable).

  • Radiographs of the selected welds and access to equipment to allow

viewing radiographs (if radiographic testing was performed).

  • Copies of the preservice examination records for the selected welds.

qualifications records for reviewing.

3. For the inservice inspection related corrective action issues selected by the inspector

from section A of this enclosure, provide a copy of the corrective actions and

supporting documentation.

4. For the nondestructive examination reports with relevant conditions on an ASME Code

Class components selected by the inspector from Section A above, provide a copy of

the examination records, examiner qualification records, and associated corrective

action documents.

5. A copy of (or ready access to) most current revision of the inservice inspection

program manual and plan for the current interval.

6. For the nondestructive examinations selected by the inspector from section A of this

enclosure, provide a copy of the nondestructive examination procedures used to

perform the examinations (including calibration and flaw characterization/sizing

procedures). For ultrasonic examination procedures qualified in accordance with

ASME Code,Section XI, Appendix VIII, provide documentation supporting the

procedure qualification (e.g. the EPRI performance demonstration qualification

summary sheets). Also, include qualification documentation of the specific equipment

to be used (e.g., ultrasonic unit, cables, and transducers including serial numbers) and

nondestructive examination personnel qualification records.

B.2 Reactor Pressure Vessel Head

1. Provide the nondestructive personnel qualification records for the examiners who will

perform examinations of the reactor pressure vessel head replacement.

2. Provide drawings showing the following:

configurations

Note: The drawings listed above should include fabrication drawings for the nozzle

attachment welds as applicable.

B.3 Boric Acid Corrosion Control Program

1. Please provide boric acid walk down inspection results, an updated list of boric acid

leaks identified so far this outage, associated corrective action documentation, and

overall status of planned boric acid inspections.

2. Please provide any engineering evaluations completed for boric acid leaks identified

since the end of the last refueling outage. Please include a status of corrective actions

to repair and/or clean these boric acid leaks. Please identify specifically which known

leaks, if any, have remained in service or will remain in service as active leaks.

B.4 Steam Generator Tube Inspections

1. Copies of the Examination Technique Specification Sheets and associated

justification for any revisions.

2. Please provide a copy of the eddy current testing procedures used to perform the

steam generator tube inspections (specifically calibration and flaw

characterization/sizing procedures, etc.).

3. Copy of the guidance to be followed if a loose part or foreign material is identified in

the steam generators.

4. Identify the types of SG tube repair processes which will be implemented for defective

SG tubes (including any NRC reviews/evaluations/approvals of this repair process).

Provide the flaw depth sizing criteria to be applied for ET indications identified in the

SG tubes.

5. Copy of documents describing actions to be taken if a new SG tube degradation

mechanism is identified.

6. Provide procedures with guidance/instructions for identifying (e.g. physically locating

the tubes that require plugging) and plugging SG tubes.

7. List of corrective action documents generated by the vendor and/or site with respect

to steam generator inspection activities.

B.5 Codes and Standards

1. Ready access to (i.e., copies provided to the inspector(s) for use during the inspection

at the onsite inspection location, or room number and location where available):

  • Applicable Editions of the ASME Code (Sections V, IX, and XI) for the

inservice inspection program and the repair/replacement program.

2. Copy of the performance demonstration initiative (PDI) generic procedures with the

latest applicable revisions that support site qualified ultrasonic examinations of piping

welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-10, etc.).

3. Boric Acid Corrosion Guidebook Revision 1 - EPRI Technical Report 1000975.

The following items are requested for the

Occupational Radiation Safety Inspection

Wolf Creek

April 9-13, 2018

Integrated Report 2018002

Inspection areas are listed in the attachments below.

Please provide the requested information on or before March 22, 2018.

Please submit this information using the same lettering system as below. For example, all

contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled

1- A, applicable organization charts in file/folder 1- B, etc.

If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at

least 30 days later than the onsite inspection dates, so the inspectors will have access to the

information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed

below, please provide updated lists of corrective action documents at the entrance meeting.

The dates for these lists should range from the end dates of the original lists to the day of the

entrance meeting.

If more than one inspection procedure is to be conducted and the information requests appear

to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which

file the information can be found.

If you have any questions or comments, please contact Natasha Greene at (817) 200-1154 or

natasha.greene@nrc.gov.

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

control number 3150-0011.

1. Radiological Hazard Assessment and Exposure Controls (71124.01) and

Performance Indicator Verification (71151)

Date of Last Inspection: May 8, 2017

A. List of contacts and telephone numbers for the Radiation Protection Organization Staff

and Technicians

B. Applicable organization charts

C. Audits, self-assessments, and LERs written since date of last inspection, related to this

inspection area

D. Procedure indexes for the radiation protection procedures

E. Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. Radiation Protection Program Description

2. Radiation Protection Conduct of Operations

3. Personnel Dosimetry Program

4. Posting of Radiological Areas

5. High Radiation Area Controls

6. RCA Access Controls and Radiation Worker Instructions

7. Conduct of Radiological Surveys

8. Radioactive Source Inventory and Control

9. Declared Pregnant Worker Program

F. List of corrective action documents (including corporate and sub-tiered systems) since

date of last inspection

a. Initiated by the radiation protection organization

b. Assigned to the radiation protection organization

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that

the inspector can perform word searches.

If not covered above, a summary of corrective action documents since date of last

inspection involving unmonitored releases, unplanned releases, or releases in which any

dose limit or administrative dose limit was exceeded (for Public Radiation Safety

Performance Indicator verification in accordance with IP 71151)

G. List of radiologically significant work activities scheduled to be conducted during the

inspection period (If the inspection is scheduled during an outage, please also include a

list of work activities greater than 1 rem, scheduled during the outage with the dose

estimate for the work activity.)

H. List of active radiation work permits

I. Radioactive source inventory list

a. All radioactive sources that are required to be leak tested

b. All radioactive sources that meet the 10 CFR Part 20, Appendix E, Category 2

and above threshold. Please indicate the radioisotope, initial and current activity

(w/assay date), and storage location for each applicable source.

J. The last two leak test results for the radioactive sources inventoried and required to be

leak tested. If applicable, specifically provide a list of all radioactive source(s) that have

failed its leak test within the last two years

K. A current listing of any non-fuel items stored within your pools, and if available, their

appropriate dose rates (Contact / @ 30cm)

L. Computer printout of radiological controlled area entries greater than 100 millirem since

the previous inspection to the current inspection entrance date. The printout should

include the date of entry, some form of worker identification, the radiation work permit

used by the worker, dose accrued by the worker, and the electronic dosimeter dose

alarm set-point used during the entry (for Occupational Radiation Safety Performance

Indicator verification in accordance with IP 71151).

Initial Request for Information

Integrated Inspection

Wolf Creek Nuclear Generating Station

Inspection Report: 05000482/2018002

Inspection Dates: April 1 - June 30, 2018

Inspection Procedure: Integrated Inspection Procedures

Lead Inspector: Douglas Dodson, Senior Resident Inspector

I. Information Requested Prior to March 22, 2018

The following information should be provided in electronic format (Certrec IMS preferred),

to the attention of Douglas Dodson by March 22, 2018, to facilitate the reduction in the

items to be selected for a final list during inspection preparation. The inspection team

will finalize its sample selections and will provide an additional information request with

specific items. This information shall be made available by March 22, 2018. The specific

items selected from the lists shall be available and ready for review on the day indicated

in this request. *Please provide requested documentation electronically in pdf files,

Excel, or other searchable formats, if possible. The information should contain descriptive

names, and be indexed and hyperlinked to facilitate ease of use. Information in lists

should contain enough information to be easily understood by someone who has

knowledge of pressurized water reactor technology. If requested documents are large

and/or only hard copy formats are available, please inform the inspector(s), and provide

subject documentation.

1. Any pre-existing evaluation or list of spent fuel pool cooling and cleanup system

components and associated calculations with low design margins.

2. A list of high risk spent fuel pool cooling and cleanup system maintenance rule

components and functions based on engineering or expert panel judgment.

3. A list of spent fuel pool cooling and cleanup system related operating experience

evaluations for the last 3 years.

4. A list of all spent fuel pool cooling and cleanup system time-critical operator actions in

procedures.

5. A list of permanent and temporary modifications related to spent fuel pool cooling

and cleanup system sorted by component.

6. A list of current spent fuel pool cooling and cleanup system related operator work

arounds/burdens.

7. A list of the spent fuel pool cooling and cleanup system design calculations, which

provide the design margin information for components.

8. List of spent fuel pool cooling and cleanup system root cause evaluations

associated with component failures or design issues initiated/completed in the

last 5 years.

9. A list of any spent fuel pool cooling and cleanup system common-cause failures of

components in the last 3 years.

10. An electronic copy of the spent fuel pool cooling and cleanup system design bases

documents and any open, pending, or recently completed changes. Although not an

exhaustive list, please include any open, pending, or recently completed (last 3 years)

changes to temporary modifications, permanent modifications, engineering change

packages, and/or procedure change packages. Specifically, please include any open,

pending, or recently completed changes to emergency operating, abnormal operating,

normal operating, alarm response, system alignment, surveillance, or other procedure.

11. An electronic copy of the spent fuel pool cooling and cleanup system System Health

notebook.

2. A copy of spent fuel pool cooling and cleanup system related audits completed in the

last 2 years.

13. A list of spent fuel pool cooling and cleanup system motor operated valves

(MOVs) in the program, design margin and risk ranking.

14. A list of spent fuel pool cooling and cleanup system air operated valves (AOVs) in

the valve program, design margin and risk ranking.

15. Spent fuel pool cooling and cleanup system structure, system, and components

maintenance rule category, scoping, unavailability data, unreliability data, functional

failure evaluations, (a)(1) determinations, (a)(1) goals, and any supporting basis

documentation.

16. A list of spent fuel pool cooling and cleanup system licensee contacts for the

inspection team with pager or phone numbers.

17. An excel spreadsheet of spent fuel pool cooling and cleanup system related PRA

human action basic events or risk ranking of operator actions from your site specific

PSA sorted by RAW and FV. Provide copies of your human reliability worksheets

for these items.

18. In so far as there are recent or pending changes, please provide an Excel

spreadsheet of spent fuel pool cooling and cleanup system related equipment basic

events (with definitions) including importance measures sorted by risk achievement

worth (RAW) and Fussell-Vesely (FV) from your internal events probabilistic risk

assessment (PRA). Include basic events with RAW value of 1.3 or greater.

19. In so far as there are recent or pending changes, please provide a list of the top 50

cut-sets from your PRA.

20. In so far as there are recent or pending changes, please provide copies of PRA

system notebooks, and the latest PRA summary document.

21. In so far as there are recent or pending changes, and if you have an external events

or fire PSA model, provide the information requested in items 17-19 for external

events and fire, as it relates to the spent fuel pool cooling and cleanup system.

2. In so far as there are recent or pending changes, please provide a copy of the Wolf

Creek Nuclear Generating Station IPEEE changes, if available electronically.

ML18226A175

SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:

By: NHTaylor Yes No Publicly Available Sensitive NRC-002

OFFICE SRI:DRP/B RI: DRP/B C:DRS/OB C:DRS/PSB2 C:DRS/EB1 C:DRS/EB2

NAME DDodson FThomas VGaddy HGepford TFarnholtz JDrake

SIGNATURE ded fdt vgg hjg WcS for jfd

DATE 8/3/2018 08/03/18 8/1/2018 8/1/2018 8/1/18 8/1/18

OFFICE PE:DRP/B BC:DRP/B

NAME JMelfi NTaylor

SIGNATURE jfm NHT

DATE 8/3/18 8/12/18