IR 05000482/2018010

From kanterella
Jump to navigation Jump to search
NRC Design Bases Assurance (Teams) Inspection Report 05000482/2018010
ML18318A330
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 11/14/2018
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Heflin A
Wolf Creek
References
IR 2018010
Download: ML18318A330 (35)


Text

November 14, 2018

SUBJECT:

WOLF CREEK GENERATING STATION NRC DESIGN BASES ASSURANCE

(TEAMS) INSPECTION REPORT 05000482/2018010

Dear Mr. Heflin:

On August 3, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Wolf Creek Generating Station. On August 2, 2018, the NRC team held an initial debrief of the results of this inspection with Mr. Jamie McCoy, Site Vice President, and other members of your staff. On October 1, 2018, a phone call was held with Mr. Steve Smith, Vice President, Engineering, and other members of the licensee staff, to clarify the characterization of the identified findings. On November 1, 2018, an additional phone call was held with Mr. Daljit Mand, Director, Engineering, and other members of the licensee staff, to revise the characterization of the identified findings. On November 13, 2018, a final exit phone call was held with Mr. Gabe Fugate, Director, Plant Support, and other members of the licensee staff, to identify changes to the inspection findings as a result of an enforcement policy review. The results of this inspection are documented in the enclosed report.

The NRC team documented four findings of very low safety significance (Green) and one licensee identified finding, in this report. These findings involved violations of NRC requirements. The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or significance of these NCVs, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC resident inspectors at the Wolf Creek Generating Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Thomas R. Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety

Sincerely, Docket No. 50-482 License No. NPF-42

Enclosure:

Inspection Report 05000482/2018010 w/ Attachment:

Supplemental Information

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

05000482

License Number:

NPF-42

Report Number:

05000482/2018010

Enterprise Identifier: I-2018-010-0041

Licensee:

Wolf Creek Nuclear Operating Corporation

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS 66839

Inspection Dates:

July 11, 2018 to August 3, 2018

Inspectors:

R. Kopriva, Senior Resident Inspector, Engineering Branch 1

F. Thomas, Resident Inspector, Branch B

I. Anchondo, Reactor Inspector, Engineering Branch 2

A. Palmer, Senior Reactor Technology Instructor, Technical Training

Center

H. Leake, Contractor, Beckman and Associates

J. Zudans, Contractor, Beckman and Associates

Approved By:

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY

The Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an Integrated Inspection at Wolf Creek Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC-identified and self-revealed findings, violations, and additional items are summarized in the table below.

List of Findings and Violations

Failure to Follow Procedures Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-01 Closed None 71111.21M The team identified two examples of a Green, non-cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for failure to follow procedures.

Failure to Establish an Adequate Procedure for Operator Time Critical/Time Sensitive Actions Validation Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-02 Closed None 71111.21M The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion V,

Instructions, Procedures, and Drawings, for failure to have an adequate Procedure.

Procedure AI 21-016, Operator Time Critical Actions Validation, Revision 14, Attachment B

- Time Sensitive Action List, does not have unique identifiers for cross referencing the records to the procedure.

Failure to Correct Reoccurring Problems with Time Critical/Sensitive Action Activities Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-03 Closed

[P.4] - Problem Identification and Resolution, Trending 71111.21M The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI,

Corrective Action, for the licensees failure to correct reoccurring problems with Time Critical/Time Sensitive Action issues.

Failure to Identify that the 125 VDC Equalizing Voltage had Exceeded Design Requirements Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-04 Closed

[H.13] - Human Performance,

Consistent Process 71111.21M -

The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion III,

Design Control, for the failure to verify or check the adequacy of design calculation NK-E-001, 125 Volt Direct-Current (VDC) Class 1E Battery System Sizing, Voltage Drop and Short Circuit Studies, Revision 4. The licensee failed to recognize that the actual 125 VDC Class 1E bus voltages had exceeded the maximum design limit voltages for downstream equipment identified in the calculation, and they had not placed any limits on voltages which could exceed the design limit of 140 VDC on the Class 1E System components.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21MDesign Bases Assurance Inspection (Teams)

From July 16, 2018 to August 3, 2018, the team reviewed the following design attributes associated with risk-significant components, permanent plant modifications, and operating experience.

Component===

(1) Turbine Driven Auxiliary Feedwater Pump PAL02.

a)

Material condition of pump/turbine and pump room walkdown.

b)

Condition reports and maintenance activities associated with pump and turbine.

c)

Operating procedures for pump operation during a design bases loss-of-coolant accident coincident with a loss-of-offsite power.

d)

Pump testing procedures and test trends associated with in-service testing.

e)

System health, system descriptions, vendor technical manual and corrective action reviews.

f )

Engineering evaluations of pump non-conforming conditions.

(2) Shutdown RCP Seals.

a)

Material condition of seals, maintenance activities and corrective actions.

b)

Operating procedures for pump operation in support of FLEX conditions and conformance to requirements for sealing acceptability.

c)

Condition reports and maintenance activities associated with seals and seal package.

d)

FLEX strategies and their implementation at Wolf Creek and conformance to regulatory requirements.

e)

Reactor coolant pump seal test procedures, test results and test trends.

f )

Evolution of Generation III design and modification changes.

(3) Reactor Coolant Pump A Circuit Breaker PA0107.

a)

Design Basis documents.

b)

Current system health report.

c)

Selected drawings.

d)

Maintenance and test procedures.

e)

Condition Reports associated with the Reactor Coolant Pump Circuit Breaker PA0107.

f )

Component maintenance history and corrective action program reports.

g)

Electrical distribution and system load flow/voltage drop calculations.

(4) 125 VDC Switchboard Bus NK41 a)

Design basis documents.

b)

Current system health report.

c)

Selected drawings.

d)

Maintenance and test procedures.

e)

Condition Reports associated with the 125 Volts Direct Current (VDC) System Inverter Bus NK01.

f )

Battery short circuit calculations, sizing calculations, coordination studies, voltage drop calculations, and switchboard maintenance activities were appropriate for the design of the system.

g)

Input and output operating voltage characteristics to verify the NK41 switchboard and downstream components can perform their design function through all input voltage ranges.

h)

Component maintenance history and corrective action program reports.

I )

Preventive maintenance, inspection, and testing procedures for Class 1E 125 VDC System components.

(5) 13.8KV AC Bus PA01 a)

Component maintenance history and corrective action program reports.

b)

Load flow, voltage drop, and short circuit calculations.

c)

Protective device selection and settings.

d)

Procedures for preventive maintenance, inspection, and testing.

e)

Material condition and configuration (i.e., visual inspection during a walkdown).

(6) 4160 VAC Bus NB02 a)

Component maintenance history and corrective action program reports.

b)

Load flow, voltage drop, and short circuit calculations.

c)

Protective device selection and settings.

d)

Procedures for preventive maintenance, inspection, and testing.

e)

Equipment qualification specifications.

f )

Adequacy of offsite power during design basis events.

g)

Material condition and configuration (i.e., visual inspection during a walkdown).

Component Large Early Release Frequency (LERF) (1 Sample)

(1) Containment Isolation Valve EJHV8701A a)

Procedures and associated testing records for the containment and pressure isolation function.

b)

Operating procedures for manual manipulation of EJHV8701A during accident conditions.

c)

Component maintenance history and corrective action program reports.

Permanent Plant Modification (4 Samples)

(1) DCP 014893, Switchgear Racking Mechanism Chain Repair,
(2) DCP 015251, Emergency Diesel Generator Exciter Power Potential Transformer Protection,
(3) DCP 015214, Essential Service Water - Water Hammer Vacuum Breaker Valves Spring Replacement,
(4) DCP 015040, Nitrogen Backup for EJHCV0606 and EJHCV0607,
(5) DCP 014831, Improved Reactor Coolant Pump Passive Shutdown Seal.
(6) DCP 004637, Residual Heat Removal Heat Exchanger Outlet Valve Nitrogen Backup Port.
(7) DCP 015081, New Residual Heat Removal Pressure Transmitter EJPIT0027 and NPIS Point.

Operating Experience (1 Sample)

(1) NRC Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power

Evaluation of Inspection Related Operator Procedures and Actions

(1) Control room operator actions resulting from a simulated small break Loss of Coolant Accident.

a)

Control room crew was expected to implement procedures to address the loss of coolant accident and trip reactor coolant pumps when conditions were met.

b)

From the time when reactor coolant system pressure drops below setpoint and conditions are met the operators must take actions to secure reactor coolant pumps within five minutes.

(2) Control room operator actions resulted from a loss of coolant accident which emptied the reactor water storage tank water into containment sump.

a)

Control room crew was expected to implement procedures to address the empty reactor water storage tank and transfer the emergency core cooling system pumps from injection mode to cold leg recirculation mode.

b)

From the time the reactor water storage tank level reaches Lo Lo 1 setpoint the operators must take actions to transfer emergency core cooling system equipment from injection mode to cold leg recirculation within eight minutes nine seconds.

(3) Control room operator actions resulted from a loss of coolant accident which emptied the reactor water storage tank water into containment sump.

a)

Control room crew was expected to implement procedures to address the empty reactor water storage tank and transfer the remaining emergency core cooling system pumps from injection mode to cold leg recirculation mode.

b)

From the time the reactor water storage tanks level reaches Lo Lo 2 setpoint the operators must take actions to transfer remaining emergency core cooling system equipment from injection mode to cold leg recirculation within two minutes ten seconds.

(4) Control room operator actions resulted from a loss of component cooling water in one train with the emergency core cooling system pumps running.

a)

Control room crew was expected to implement procedures to address stopping the affected emergency core cooling system pumps during a loss of component cooling water cooling in a single train.

b)

From the time the component cooling water pumps are not running in a single train the operators must take actions to stop the affected emergency core cooling system pumps to prevent damage from loss of cooling within thirty minutes.

All operator action timings were completed on the simulator successfully.

INSPECTION RESULTS

Failure to Follow Procedures Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-01 Closed None 71111.21M

Introduction:

The team identified two examples of a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for failure to follow procedures.

Example 1

Description:

The team reviewed control room time critical and time sensitive activities which are used to validate design bases criteria. Without verification and validation of time critical/sensitive activities, the licensee would not be able to confirm that timing of design bases criteria would be met.

The team selected time critical and time sensitive, non-exempt tasks to be reviewed, which are identified in Attachments A and B of Procedure AI 21-016, Operator Time Critical Actions Validation, revision 14. These nonexempt tasks are required to be validated at least once every five years. The team reviewed approximately forty nine records from 2013 to 2018, and found that when reviewing Time Verification Form AIF 21-016-02, Revision 1, most of the records provided had Block 2 and Block 3 filled out improperly. The errors included the blocks being empty or were filled out with insufficient information. Block 2 is the identification information to link the form back to the task in the Attachments A or B of the procedure.

Block 3 is the reference information to show to how it was validated using other documents.

Without correct information in Block 2, the licensee had difficulty demonstrating which task was validated. Without correct information in Block 3, the licensee had difficulty demonstrating under what conditions the task was validated, which calls into question the validity of the document. With some records left blank in Block 2 or Block 3 the licensee was left to determine how the task was validated using comments or assumptions. The team chose only nonexempt tasks to simplify the inspection. It was not clear from the records provided to the team that the licensees program is being performed as required, and was not being performed as designated in the program procedures.

Corrective Actions: The licensee has acknowledged that the forms had not been filled out properly and that Procedure AI 21-016 had not been followed. The licensee has entered this concern into their corrective action program, and will review the concern of failure to follow station procedures.

Corrective Action Reference: Condition Report CR-00125356.

Example 2

Description:

During a review of Operability Evaluation OE-NK-18-005, dated July 26, 2018, the team questioned whether the downstream components from Class 1E 125 VAC Bus NK01 had been considered in the extent of condition of the evaluation. The operability evaluation did not address the downstream components, as Condition Report CR-00125361 only focused on the NK batteries and chargers, without regard for the downstream components. This does not comply with the licensees procedure AP 26C-004, Operability Determination and Functionality Assessment, Revision 35. Section 6.1.2.1.a requires that operability determinations should include which structures, systems, and components (SSCs) are affected by the degraded or non-conforming condition. The operability determination performed for condition report CR-125361 failed to meet this requirement in that the components downstream of the NK buses had not been considered for overvoltage effects.

Corrective Actions: On August 1, 2018, the licensee completed the revised Operability Evaluation OE NK-18-005, to address the effect of the overvoltage condition on the downstream 125 VDC rated equipment. The licensee determined that reasonable assurance exists that the systems, structures, and components, associated with the operability evaluation remained capable of performing their specified safety function. The licensee has entered this concern into their corrective action program, and will review the concern of failure to follow station procedures.

Corrective Action Reference: Condition Report CR-00125487

Performance Assessment:

Performance Deficiency: The team determined that the licensees failure to follow procedures (Procedure AI-21-016, Operator Time Critical Actions Validation, Revision 14, and Procedure AP 26C-004, Operability Determination and Functionality Assessment, Revision 35) was a performance deficiency.

Screening: The team determined the performance deficiency was more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern. Specifically, for Example 1: the licensee failed to complete Time Verification Form AIF 21-016-02, to accurately validate simulator time critical and time sensitive activities for control room and in plant activities. Without verification of time critical/sensitive activities, the licensee could not confirm the timing of design bases criteria would be met. For Example 2: the operability screening of Condition Report CR-00125361 for the 140 VDC design limit for 125 VDC System components having been exceeded only focused on battery banks NK11, NK12, NK13, NK14, and the battery chargers, but did not address the effects of overvoltage conditions on downstream equipment.

Significance: The team assessed the significance of the findings using NRC Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, issued October 7, 2016. Using Exhibit 2, Mitigating Systems Screening Questions, the team determined the findings to be of very low safety significance (Green)because the findings were a design or qualification deficiency that did not represent a loss of operability or functionality; did not represent an actual loss of safety function of the system or train; did not result in the loss of one or more trains of non-technical specification equipment; and did not screen as potentially risk significant due to seismic, flooding, or severe weather.

Cross-cutting Aspect: The team determined that the finding did not have a cross cutting aspect associated with it.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, which states Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. Instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

Contrary to the above, prior to July 30, 2018, the licensee failed to accomplish activities affecting quality in accordance with station procedures. For Example 1; Procedure AI-21-016, Operator Time Critical Actions Validation, Revision 14, contains Form AIF 21-016-02, Time Verification Form, Revision 1. On AIF 21-016-02, Block 2 is the identification information to link the form back to the task in the Attachments A or B of the procedure. Block 3 is the reference information to show to how it was validated using other documents. On several the forms, Block 2 and Block 3 were not filled out correctly as required by the procedure. For Example 2; licensee Procedure AP 26C-004, Operability Determination and Functionality Assessment, Revision 35, Section 6.1.2, states, in part, that the scope of a Operability Determination must be sufficient to address the capability of systems, structures, and components to perform their specified safety functions. The operability screening of Condition Report CR-00125361 did not follow Procedure AP 26C-004, in that it did not address all of the capabilities of the component to perform its safety function as the effects of overvoltage conditions on downstream equipment were not analyzed.

Disposition: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Establish an Adequate Procedure for Operator Time Critical Actions Validation Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-02 Closed None 71111.21M

Introduction:

The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for failure to have an adequate Procedure.

Procedure AI 21-016, Operator Time Critical Actions Validation, Revision 14, Attachment B

- Time Sensitive Action List, does not have unique identifiers for cross referencing the records to the procedure.

Description:

The Design Basis Assurance inspection procedure 71111.21M, Section 03.01 b.2.b discusses operations margin and refers to components required to be operated during high risk and/or time critical operations. The team elected to review Procedure AI 21-016, Operator Time Critical Actions Validation, Revision 14, to confirm that the licensee was performing design basis time critical and time sensitive actions for operations activities. The team identified a procedure deficiency in that Attachment B, Time Sensitive Action List, did not have unique identifiers in task Block 2 similar to task Block 2 found in Attachment A. This lack of unique identifier prevents cross referencing the records for Time Sensitive Actions listed in Attachment B with the records documenting the required validation. Block 2 of Form AIF AI 21-016-02 would use this information to link the form back to the task in the procedure attachments to prove it had been validated.

As an example, in the Time Critical Action heading, each time critical action in Attachment A starts with a code TCA_SLB_S1. Attachment B just has verbiage. The records that were provided were filled out with a variety of descriptions, usually not matching the description provided in the attachment. Without this unique information identifier, it was difficult to determine which task was validated, and at times impossible to determine what was being validated.

Corrective Actions: The licensee has acknowledged that Form AIF AI 21-016-02, B, Time Sensitive Action List, did not have unique identifiers in task Block 2, and is in the process of reviewing the procedure to identify and correct deficiencies that may exist.

Corrective Action Reference: Condition Reports CR-00125536 and CR-00125350.

Performance Assessment:

Performance Deficiency: The team determined that the licensees failure to have an adequate procedure with unique identifiers for the Time Sensitive Actions in Attachment B of Procedure AI 21-016 was a performance deficiency.

Screening: The team determined that the finding was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.

Specifically, the licensee failed to have unique identifiers for the time sensitive actions so that records could be cross referenced to the procedure to document that the required tasks had been validated successfully.

Significance: The team assessed the significance of the finding using NRC Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, issued October 7, 2016. Using Exhibit 2, Mitigating Systems Screening Questions, the team determined the finding to be of very low safety significance (Green)because the finding was a design or qualification deficiency that did not represent a loss of operability or functionality; did not represent an actual loss of safety function of the system or train; did not result in the loss of one or more trains of non-technical specification equipment; and did not screen as potentially risk significant due to seismic, flooding, or severe weather.

Cross-cutting Aspect: The team determined that this finding did not have a cross cutting aspect associated with it.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, which states, Activities affecting quality shall be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished in accordance with these instructions, procedures, or drawings. Instructions, procedures, or drawings shall include appropriate quantitative or qualitative acceptance criteria for determining that important activities have been satisfactorily accomplished.

Contrary to the above, prior to July 30, 2018, the licensee failed to include appropriate quantitative or qualitative acceptance criteria for determining that important activities had been satisfactorily accomplished. The licensee had failed to establish an adequate procedure for cross referencing Time Sensitive Actions listed in Attachment B with the records documenting the required validation. Specifically, Procedure AI 21-016, Attachment B - Time Sensitive Action List, Revision 14, was inadequate in that each Time Sensitive Action did not have a unique identifier for cross referencing the records to the procedure. (Could not correlate which records were used to validate which task).

Disposition: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Correct Reoccurring Problems with Time Critical/Sensitive Action Activities Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-03 Closed

[P.4] - Problem Identification and Resolution, Trending 71111.21M

Introduction:

The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure to correct reoccurring problems with completing Time Critical/Time Sensitive Action issues.

Description:

The team reviewed corrective actions associated with Procedure AP 21-04, Operator Response Time Program, Revision 4B, and Procedure AI 21-016, Operator Time Critical Actions Validation, Revision 14. The team found that during the five year cycle of the program, the licensee had identified multiple (approximately 18) deficiencies in the program (i.e. source document to the form is not consistently being utilized, several of the time critical actions in AI 21-016 have not been validated, time critical actions not submitted as required, time sensitive action program requires enhancement, operations time sensitive action cannot be satisfied, several operator time critical actions are not validated and could result in operating outside of analyzed limits.) The licensees review pertaining to the identification of the problems, and resolution of the issues had resulted in inadequate identification of reoccurring problems, and problem resolution. The concerns were also identification in a Mid Cycle Self-Assessment (CR-00085924), QA Audits (CR-00104699), and an NRC Component Design Basis Inspection (CR-00103698). The corrective actions derived to answer the concerns had not prevented the problems from reoccurring. The licensee had addressed the concerns in eighteen different condition reports dating back to 2013.

The team found that over the last five years, the corrective actions taken by the licensee for the deficiencies and deviations in the Operator Time Critical Action Validations were ineffective.

Corrective Actions: The licensee has acknowledged that the corrective actions for these issues had not resolved the issues. The licensee has entered this concern into their corrective action program, and will be reviewing the issues.

Corrective Action Reference: Condition Report CR-00125533.

Performance Assessment:

Performance Deficiency: The licensees failure to promptly identify and correct deficiencies with the validation of Time Critical and Time Sensitive Actions, as required by 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, was a performance deficiency.

Screening: The team determined the performance deficiency was more than minor because if left uncorrected, the performance deficiency would have the potential to lead to a more significant safety concern. Specifically, the licensee did not recognize that they had failed to correct reoccurring deficiencies concerning validation of Time Critical/Time Sensitive Actions over the last five years, which could lead to inaccurate design bases assumptions or incorrect operator actions.

Significance: The team assessed the significance of the finding using NRC Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, issued October 7, 2016. Using Exhibit 2, Mitigating Systems Screening Questions, the team determined the finding to be of very low safety significance (Green)because the finding was a design or qualification deficiency that did not represent a loss of operability or functionality; did not represent an actual loss of safety function of the system or train; did not result in the loss of one or more trains of non-technical specification equipment; and did not screen as potentially risk significant due to seismic, flooding, or severe weather.

Cross-cutting Aspect: The team determined that this finding had a cross cutting aspect in the area of Problem Identification and Resolution, Trending, where the organization periodically analyzes information from the corrective action program and other assessments in the aggregate to identify programmatic and common cause issues. The licensee failed to recognize reoccurring concerns pertaining to time critical action, even after these issues had been identified in self-assessment and Quality Control audits. [P.4]

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, states, in part, Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, defective materials and equipment, and nonconformances, are promptly identified and corrected.

Contrary to the above, since May 2012 until August 1, 2018, the licensee failed to assure that conditions adverse to quality, such as failures, deficiencies, and nonconformances, are promptly identified and corrected. Specifically, the licensee had identified multiple (approximately 18) deficiencies with Time Critical and Time Sensitive Actions and the corrective actions had been inadequate to correct the conditions, even after these issues had been identified in self-assessment and Quality Control audits.

Disposition: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Failure to Identify 125 VDC Equalizing Voltage Exceeded Design Requirements Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000482/2018010-04 Closed

[H.13] - Human Performance, Consistent Process 71111.21M -

Introduction:

The team identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion III, Design Control, for the failure to verify or check the adequacy of design calculation NK-E-001, 125 Volt Direct-Current (VDC) Class 1E Battery System Sizing, Voltage Drop and Short Circuit Studies, Revision 4. The licensee failed to recognize that the actual 125 VDC Class 1E bus voltages had exceeded the maximum design limit voltages for downstream equipment identified in the calculation, and they had not placed any limits on voltages which could exceed the design limit of 140 VDC on the Class 1E System components.

Description:

One of the components the team selected to inspect was the 125 VDC Switchboard Bus NK41. The Wolf Creek Updated Safety Analysis Report, Section 1.2.7.2 states that vital alternating current instrumentation and control power supply systems include battery systems, static inverters, and distribution panels. All of the voltages listed in that section of the updated safety analysis report are nominal values, and all electrical Class IE equipment is designed to accept the expected range in voltage. As part of the review for this component, the team reviewed design calculation NK-E-001, 125 Volt Direct-Current (VDC) Class 1E Battery System Sizing, Voltage Drop and Short Circuit Studies, Revision 4. During the review of the calculation, the team identified concerns with the validation of certain criteria specified in the calculation.

The team noted that procedure MPE E050Q-05, Battery Equalizing Procedure, Revision 14, references a battery equalizing voltage range of 139.5 to 140 VDC for the 125 VDC batteries (NK11, NK12, NK13, and NK14); and procedure STS NB-005, Breaker Alignment Verification, Revision 34, Appendix B, references a required voltage range of 130 to 140 VDC for the Class 1E 125 VDC electrical distribution buses NK01, NK02, NK03, and NK04.

The team identified that design calculation NK-E-001 lists several components with maximum voltage limits that are less than the maximum voltages of 140 VDC. The team requested voltage data during the time that the battery equalize charging was in progress. The licensee provided the team data measurements that had been taken between April 10, 2018 and April 18, 2018. The data indicated that the actual NK01 bus voltage exceeded the 140 VDC procedure and calculation limit (up to 143 VDC for approximately 20 minutes during NK11 battery equalize charging). The team identified periods when components downstream of the Class 1E 125 VDC electrical distribution buses (with design limits less than 140 VDC) had been exposed to voltages that exceeded maximum design values for components listed in design calculation NK-E-001. The licensee did not have an analysis to address the concern pertaining to whether the equipment downstream of the NK01 bus could withstand voltages that exceeded design limits. Also, Procedure MPE E050Q-05 references a maximum equalizing voltage of 140 VDC for the battery banks.

According to licensee systems engineering personnel, this condition would only be expected during battery equalize charging activities. Section 7.2 of procedure MPE E050Q-05 requires that battery terminal voltage is measured and that potentiometer adjustments be made to obtain equalize values given in the table for equalize voltage range, but there were no steps that prohibited exceeding the 140 VDC maximum value. Furthermore, procedure STS NB-005, Breaker Alignment Verification, does not reference any specific steps to ensure that the 140 VDC voltage limit would not be exceeded. Neither of the procedures referenced identify any actions to be taken when the voltage limit is exceeded.

Corrective Actions. On August 1, 2018, the licensee completed Operability Evaluation OE NK-18-005, to address the effect of the overvoltage condition on the 125 VDC battery, battery charger, and equalizer. The licensee determined that reasonable assurance exists that the systems, structures, or components associated with the operability evaluation remained capable of performing their specified safety function. According to updated information in Condition Report CR-00125361, a procedure change request (PCR) was initiated to add battery voltage monitoring to procedure MPE E050Q-05 to ensure maximum voltage values are not exceeded. Furthermore, updated information in Condition Report CR-00125468, indicated that an action was initiated to review previous performance of NK buses to determine the historical amount of overvoltage that may have occurred.

Corrective Action References: Condition Reports CR-00125361 and CR-00125468.

Performance Assessment:

Performance Deficiency: The licensees failure to verify or check the adequacy of design calculation NK-E-001, 125 Volt Direct-Current (VDC) Class 1E Battery System Sizing, Voltage Drop and Short Circuit Studies, Revision 4, was a performance deficiency.

Screening: The team determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.

Specifically, the licensee failed to verify or check the adequacy of design calculation NK-E-001, 125 Volt Direct-Current (VDC) Class 1E Battery System Sizing, Voltage Drop and Short Circuit Studies, Revision 4, regarding maximum allowed Class 1E 125 VDC voltage, and procedures involving Class 1E 125 VDC system components. There had been periods of time when components downstream of the Class 1E 125 VDC electrical distribution buses (with design limits less than 140 VDC) had been exposed to voltages that exceeded maximum design values. Furthermore, procedure STS NB-005, Breaker Alignment Verification, does not reference any specific steps to ensure that the 140 VDC voltage is not exceeded, and none of the procedures reference any actions to take when the voltage limit is exceeded.

Significance: The team assessed the significance of the finding using NRC Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, issued October 7, 2016. Using Exhibit 2, Mitigating Systems Screening Questions, the team determined the finding to be of very low safety significance (Green)because the finding was a design or qualification deficiency that did not represent a loss of operability or functionality; did not represent an actual loss of safety function of the system or train; did not result in the loss of one or more trains of non-technical specification equipment; and did not screen as potentially risk significant due to seismic, flooding, or severe weather.

Cross-Cutting Aspect: The team determined that this finding had a crosscutting aspect in the area of Human Performance, Consistent Process, where Individuals use a consistent, systematic approach to make decisions. Risk insights are incorporated as appropriate.

Specifically, the licensee did not use a consistent, systematic approach for reviewing components downstream of the battery chargers for overvoltage conditions as identified in the design basis calculation. [H.13]

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, states in part, Measures shall be established to assure that applicable regulatory requirements and the design basis are correctly translated into specifications, drawings, procedures, and instructions. The design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Contrary to the above, prior to August 1, 2018, the licensee failed to verify or check the adequacy of design, such as by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Specifically, the licensee failed to verify or check the adequacy of design calculation NK-E-001, Revision 4, 125 Volt Direct-Current (VDC) Class 1E Battery System Sizing, Voltage Drop and Short Circuit Studies, and procedures involving Class 1E 125 VDC system components, by not recognizing that the actual 125 VDC Class 1E bus voltages had exceeded the maximum design limit voltages for downstream equipment identified in design calculation NK-E-001. Also, the licensee had not placed any voltage limits in any procedures for the 125 VDC Class 1E System which had actually exceeded the design limit of 140 VDC.

Disposition: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Licensee-Identified Non-Cited Violation 71152Problem Identification and Resolution This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, states, in part, Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and non-conformances are promptly identified and corrected.

Contrary to the above, prior to 2015, the licensee failed to promptly identify and correct a repetitive deficiency or nonconformance. Specifically, the licensee had identified a leaking flange on the residual heat removal heat exchanger since 1997. Prior to 1997 a different data base had been used to record boric acid leakage, and the data was not available during the inspection. Over the years since plant startup, the licensee had been diligent in completing boric acid evaluations on the leaking residual heat removal heat exchanger flange, indicating minimal wastage of the flange closure studs and nuts that had been subjected to boric acid.

Corrective actions included cleaning up the boric acid leakage, and checking or re-torqueing the closure nuts. These measures did not correct the problem of the leaking heat exchanger flange.

In 2015 the licensee completed an in-depth engineering evaluation of the leaking flange, including discussions with the heat exchanger manufacturer. New corrective measures included changing the torque values on the closure studs and nuts. The licensee is still evaluating the results of the corrective actions taken to preclude further leakage.

Significance/Severity Level: The team assessed the significance of the finding using NRC Inspection Manual Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, issued October 7, 2016. The team concluded the finding was of very low safety significance (Green) because all questions in Exhibit 2 could be answered no.

Corrective Action Reference(s): Condition Reports CR-00057242, CR-00057267, and CR-

EXIT MEETINGS AND DEBRIEFS

On August 2, 2018, the team presented the initial results of this design basis assurance inspection to Mr. Jamie McCoy, Site Vice President, and other members of the licensee staff.

On October 1, 2018, a phone call was held with Mr. Steve Smith, Vice President, Engineering, and other members of the licensee staff, to clarify the characterization of the identified findings.

On November 1, 2018, an additional phone call was held with Mr. Daljit Mand, Director, Engineering, and other members of the licensee staff, to revise the characterization of the identified findings. On November 13, 2018, a final exit phone call was held with Mr. Gabe Fugate, Director, Plant Support, and other members of the licensee staff, to identify changes to the inspection findings as a result of an enforcement policy review. The team verified no proprietary information was retained or documented in this report.

A1-1

DOCUMENTS REVIEWED

Calculations

Number

Title

Revision

A-06-W

Thermal Capability of Electrical Penetration

Assemblies (EPA) Versus Dual Short Circuit

Protection to Satisfy Reg. [Regulatory] Guide 1.63

007

H-06

Protective Relays

H-08

System NB Protective Relays

H-15

Provide RCPM Protective Relay Settings (Class 1E)

for UV & UF

NK-E-001

25 VDC Class 1E Battery System Sizing, Voltage

Drop and Short Circuit Studies

NN-E-001

Class 1E NN Inverter Loading

P-009A-010-

CN001

Piping Stress Analysis for Essential Service Water

System, Train B

June 20, 2017

PK-E-001

Non-Class 1E 125 Volt DC System

WCN-023-CALC-

001

Transient water hammer analysis of the essential

service water system following a LOOP with a higher

setpoint for the vacuum breakers at the top of the loop.

XX-E-006

AC System Analysis

Condition Reports (CR-)

00056641

00077640

00098218

00106993

00118952

00057242

00077791

00098844

00107885

00118954

00057267

00077792

00099349

00107915

00119043

00069540

00077794

00099930

00109450

00119167-01

00070051

00082790

00099956

00109656

00120213

00070256

00085924

00099993

00109733

00121267

00070380

00088577

00100863

00109893

00121828

00070718

00088665

00101289

00110094

00122600

00071246

00091857

00101942

00110420

00123328

A1-2

Condition Reports (CR-)

00071977

00092106

00102416-01

00110546

00123329

00072165

00092324

00103150

00111571

00123660

00072426

00093748

00103658

00112981

00123843

00072496

00093748

00103698

00116051

00123902

00073206

00094365

00103918

00116852

00123908

00073240

00094366

00104699

00117311

00124694

00073244

00094627

00105147

00117441

00124822

00073443

00097769

00105480

00117639

00124997

00073445

00098177

00106923

00118853

Condition Reports Generated During the Inspection (CR-)

00125081

00125166

00125310

00125413

00125489

00125111

00125183

00125350

00125414

00125490

00125112

00125184

00125356

00125447

00125492

00125123

00125191

00125361

00125456

00125513

00125136

00125225

00125362

00125457

00125521

00125139

00125227

00125370

00125458

00125533

00125152

00125255

00125405

00125468

00125536

00125158

00125255a

00125406

00125487

00125557

Design Change Packages

Number

Title

Revision

Date

014831

Improved RCP Passive Shutdown Seal

015040

Nitrogen Backup for EJHCV0606 and EJHCV0607

015070

NN Power to GK Damper

015081

New RHR Pressure Transmitter EJPIT0027 and

NPIS [Nuclear Plant Information System] Point

A1-3

Design Change Packages

Number

Title

Revision

Date

015214

ESW Water Hammer Vacuum Breaker Valves Spring

Replacement

14923

Restore Regulatory Compliance for 10 480 V MOVs

CCP 11897

Transformer XNB02 Tap Change

DCP 13271

Turbine Trip Wiring Changes in Support of DCP

011354

FCN 015251

EDG Exciter Power Potential Transformer Protection

MCP 14893

Switchgear Racking Mechanism Chain Repair

PMR 04637

RHR Heat Exchanger Outlet Valve Nitrogen Backup

Port

Drawings

Number

Title

Revision

5736

Vertical Residual H.E. Outline Drawing

5739

Vertical Residual Heat Exchanger Details

5740

Vertical Residual Heat Exchanger Details

E-009B-00025

Breaker Schematic G.E. 13.8KV

W02

E-02PA01

Logic Diagram, Unit Auxiliary Source 13.8kV Bus

Feeder Breakers

E-11001

Main Single Line Diagram

E-11005

List of Loads Supplied by Emergency Diesel

Generator

E-11010

DC [Direct Current] Main Single Line Diagram

E-11010

DC [Direct Current] Main Single Line Diagram

E-11010A

DC [Direct Current] Main Single Line Diagram (PK03

And PK04 Bus)

A1-4

Drawings

Number

Title

Revision

E-11010A

DC [Direct Current] Main Single Line Diagram (PK03

And PK04 Bus)

E-11023

Relay Setting Tabulation & Coordination Curves

System NB

E-11030

Relay Setting Tabulation RCPM UV & UF Monitors

E-11032

Substation and Plant Transformer Tap Settings

E-11MA01

Main Generator Single Line Metering and Relaying

Diagram

E-11NB02

Lower Medium Voltage Sys. Class 1E 4.16 kV Single

Line Meter and Relay Diagram

E-11PA01

Higher Medium Voltage System 13.8 kV Single Line

Meter & Relay Diagram

E-11PK01

Non-Class 1E 125V System Meter & Relay Diagram

E-12NF01

Load Shedding and Emergency Load Sequencing

Logic

E-13BB01

Schematic Diagram Reactor Coolant Pumps

E-13N03

Schematic Diagram RHR Pump MOV

EID-0004

Pool Parameters

IP-M-18EF13-010-

Hanger Details Small Pipes, Essential Water System

KD-7496

One Line Diagram

KD-7496A

Distribution System Equipment Lineup Limitations

KL-1909

Logic Block Diagram, Load Shedding & Emergency

Load Sequencing System (LSELS)

E

M-018-00077

Electrical Schematic Diesel Gen. [Generator] Control

NE107

W01

M-018-00077

Electrical Schematic Diesel Gen. [Generator] Control

NE106

W20

M-018-00301

Interconnection Wiring Diagram (NE107)

W08

A1-5

Drawings

Number

Title

Revision

M-12BB01

Piping & Instrumentation Diagram Reactor Coolant

System

M-12BB04

Piping & Instrumentation Diagram Reactor Coolant

System

M-12EF01

Piping and Instrumentation Diagram, Essential Service

Water System

M-12EF02

Piping and Instrumentation Diagram, Essential Service

Water System

M-12EJ01

Piping & Instrumentation Diagram Residual Heat

Removal System

M-12E-J01

P&ID, Residual Heat Removal System

M-12EM01

Piping & Instrumentation Diagram High Pressure

Coolant Injection System

M-12EP01

Piping & Instrumentation Diagram Accumulator Safety

Injection

M-223F-00003

CRISPIN Model VR-41 Model Relief Check Valve

Flanged Ends Size 4 Fig. 150 - VR

W04

M-724-00761

Motor Operated Gate Valve

WIP-J-110-00660-

W11-A-1

Wiring Diagram Termination Area Rack HF187A

Separation Group 5

WIP-J-110-00671-

W10-A-1

Rack HF187A & 187B Loading Standardized Nuclear

Unit Power Plant System Applicable to Unit 1, Bechtel

P.O. 10466-J-110-1

WIP-J-110-01026-

000-A-1

Instrument Loop Diagram Residual Heat Removal

System RHR Pump Discharge Header Pressure

WIP-J-14EJ08-

2-A-1

Instrument Isometric Drawing RHR [Residual Heat

Removal] HX [Heat Exchanger] 1B to ACCUM

[Accumulator] INJ [Injection] LP [ Loop] 3 & 4

WIP-J-17P39-000-

Instrument Mounting Detail Pressure Transmitter

(Rosemount) Packed Manifold

WIP-M-12EJ01-

053-A-1

Piping and Instrumentation Diagram Residual Heat

Removal System

WIP-M-13EJ10-

2-A-1

Schematic Diagram Instrumentation

A1-6

Procedures

Number

Title

Revision

18-0022

Essential Reading - LBLOCA HL Break

AI 16C-006

Troubleshooting

AI 16C-007

Work Order Planning

AI 16F-001

Evaluation of Boric Acid Leakage

AI 21-016

Operator Time Critical Actions Validation

AI 23O-001

Functional Importance Determination

AI 26C-004

Technical Specification Application for Containment

Isolation Valves

AI 26C-004

Technical Specification Application for Containment

Isolation Valves

7A

AI 28A-010

Screening Condition Reports

29A

AI 28A-010

Screening Condition Reports

AI 28A-100

Condition Report Resolution

AI 28B-005

Evidence and Action Matrix

AI 30B-005

Development and Conduct of Simulator Activities for

Licensed Operator Training

AI 30B-015

Licensed Operator Requalification Examination

Guidelines

ALR 501

Standby Diesel Engine System Control Panel KJ-121

AP 05-002

Disposition and Change Packages

AP 05-002

Disposition and Change Package

AP 05-005

Design, Implementation and Configuration Control of

Modifications

AP 05-005

Design, Implementation and Configuration Control of

Modifications

2, 26

A1-7

Procedures

Number

Title

Revision

AP 05-013

Review of Vendor Technical Documents

AP 05-013

Review of Vendor Technical Documents

AP 05-024

Minor Change Package

AP 05C-004

Basic Engineering Dispositions

0, 1

AP 15C-001

Procedure Writers Guide

AP 15C003

Procedure Users Guide for Abnormal Plant Conditions 37

AP 16C-006

MPAC Work Request/Work Order Process Controls

21A

AP 16F-001

Boric Acid Corrosion Control Program

AP 20E-001

Industry Operating Experience Program

AP 21-001

Conduct of Operations

AP 21-004

Operator Response Time Program

4B

AP 21A-002

Diverse and Flexible Coping Mitigation Strategies

(FLEX) Program

AP 21C-001

Wolf Creek Substation

AP 22A-001

Screening, Prioritization and Pre-Approval

AP 26A-003

CFR 50.59 Reviews

AP 26C-004

Operability Determination and Functionality

Assessment

AP 28-001

Operability Evaluations

AP 28-007

Nonconformance Control

AP 28-011

Resolving Degraded or Nonconforming Conditions

Impacting SSCs

AP 28A-100

Corrective Action Program

A1-8

Procedures

Number

Title

Revision

AP 28A-100

Corrective Action Program

BD EMG E-0

Reactor Trip of Safety Injection

BD EMG E-1

Loss of Reactor or Secondary Coolant

BD EMG E-2

Faulted SG Isolation

BD EMG ES-12

Transfer to Cold Leg Recirculation

EMG E-0

Reactor Trip or Safety Injection

39A

EMG E-1

Loss of Reactor or Secondary Coolant

EMG E-2

Faulted SG Isolation

EMG ES-12

Transfer to Cold Leg Recirculation

EMG FR-C2

Response to Degraded Cooling

EMG FR-P1

Response to Imminent Pressurized Thermal Shock

Conditions

IP-ENG-001

Standard Design Process

KMS-4

Mechanical Standard for Bolting

KMS-6

Fastener Specification for Use at the Wolf Creek

General Station in Both ASME and Non-ASME/ANSI

M-10EJ

System Description Residual Heat Removal

MPE E009-01

Siemens Breaker Cubicle Maintenance, Testing, and

Swapping

MPE E009Q-01

13.8 kV and 4.16 kV Switchgear Inspection and

Testing

MPE E009Q-01

13.8 KV And 4.16 KV Switchgear Inspection and

Testing

33A

MPE E009Q-01

13.8 KV And 4.16 KV Switchgear Inspection and

Testing

A1-9

Procedures

Number

Title

Revision

MPE E050Q-05

Battery Equalizing Procedure

MPM M712Q-01

Reactor Coolant Pump Seal Removal/Installation

MPM M712Q-02

Reactor Coolant Pump Seal Cartridge

Inspection/Rebuild

OFN BB-005

RCP Malfunctions

OFN BB-005

RCP Malfunctions

OFN EG-004

CCW System Malfunctions

18B

OFN EG-004

CCW System Malfunctions

18B

PWROG-14006-P Implementation Guide for Generation III Westinghouse

Seal

0-B

PWROG-16030-

NP

Time Critical Action/Time Sensitive Action Program

Standard PA-PSC-0840

August, 2016

Record of

Completion

Flex Support Guideline (FSG) Validation Process

STN EJ-205

RHR System Valve Test

STN TCA-001

Manual Time Critical Action Timing

STS AL-103

TDAFW Pump Inservice Test

STS AL-104

TDAFW ESF Response Time Test

STS AL-211

TDAFW Comprehensive Pump Testing and System

Flow Path Verification and Inservice Check Valve

STS BB-207

RCP Seal Water Injection Inservice Check Valve Test 8

STS BN-208A

RWST to RHR Pump A Suction Valve Test

3A

STS BN-208B

RWST to RHR Pump B Suction Valve Test

3A

STS IC-740A

RHR Switchover to Recirculation Sump Test - Train A

A1-10

Procedures

Number

Title

Revision

STS IC-740B

RHR Switchover to Recirculation Sump Test - Train B

28C

STS IC-805B

Channel Calibration of NB02 Grid Degraded Voltage,

Time Delay Trip

STS IC-902A

Actuation Logic Test Train A Residual Heat Removal

Suction Isolation Valves

4A

STS MT-019A

25 VDC Class 1E Quarterly Inspection For NK11 and

NK13 Batteries

1B

STS MT-028

Penetration Breaker Inspection

STS MT-028

Penetration Breaker Inspection

STS MT-079

ESW System Water Hammer Inservice Check Valve

Test

STS NB-005

Breaker Alignment Verification

STS NB-005

Breaker Alignment Verification

STS PE-007

Periodic Verification of Motor Operated Valves

STS PE-19B

RHR Suction Valve Leak Test

STS VT-001

Verification of OMN-1, MOV Exercise Requirements

SYS NB-200

Transferring XNB01 Supply Between SL7 and #7

Transformer

SYS NK-331

De-energizing NK Buses

TSO 0101-21

Division of Responsibility of the Wolf Creek Substation July 13, 2018

TSO 0400-02

Wolf Creek 345 kV Bus Voltage

April 30, 2018

TSO 0414-02

Monitoring Wolf Creek Contingency Study 345 kV Bus April 30, 2018

WCAP-16755-NP

Operator Time Critical Action Program Standard

Rev. 0

A1-11

Vendor Technical Document

Number

Title

Revision

Date

6998D62

Colt Industries Type WNR Volt Reg. [Voltage

Regulation] & Excitation System

January 17, 1983

E-009-00223

Instruction Manual for 13.8 kV Switchgear

W33

E-009-00242

Instruction Manual for 4.16 kV Class 1E Switchgear

W31

E-009-00258

IEEE 323 Qualification Program General Electric Co.

July 2, 1984

E-009-00342

Metal-Clad Switchgear

W09

E-009B-00001

Qualification Plan for Siemens 5-AF-GER-350-1200-

and 5-3AF-GER-350-2000-78

W05

E-009B-00006

Third Party Qualification Plan for Siemens 52STA

Switch Mechanisms

W01

E-009B-00009

Instruction Manual for Siemens Type 3AF-GER

Vertical Lift Direct Replacement Circuit Breakers

W06

E-009B-00018

Third Party Qualification Report for Siemens Types 5-

3AF-GER-350-1200-78 and 5-3AF-GER-350-2000-78

Vertical Lift Vacuum Circuit Breakers and 52STA

Switch Mechanisms

W01

E-009B-00029

Siemens Vacuum Circuit Breakers (Vehicle)

W02

E-009B-00029

Siemens Circuit Breakers (Vehicle) Type GER 5kV to

15kV

E-009B-00044

Siemens Type-3AFS Vacuum Circuit Breakers

W01

E-009B-00044

Siemens Type-3AFS Vacuum Circuit Breakers

W01

E-020-00055

Installation and Maintenance Instructions - AV-Line

Switchboards (GEH-2621C)

E-020-00055

Instructions (GEH-3042A) - Mounting and Connecting

Hardware for QMR Double Branch Panelboard Units,30-100 Amperes

E-020-00055

Instructions (GEH-3043) - Mounting and Connecting

Hardware for QMR Double Branch Panelboard Units,30-600 Amperes

E-050A-00011

Lucent Technologies Lineage 2000 Round Cell Battery W03

A1-12

Vendor Technical Document

Number

Title

Revision

Date

M-021-00061

Instruction Manual for Auxiliary Feedwater Pumps

W29

M-072-00024

Operation/Maintenance for Cooling Water Heat

Exchangers

W07

M-072-00052

Instruction Manual for Auxiliary Heat Exchangers

W11

M-223F-00003

Crispin Model VR-41 Model Relief Check Valve

Flanged Ends Size 4 Fig. 150 - VR

W04

M-712-00068

Instruction Manual for Reactor Coolant Pump

W38

WIP-M-223F-

00004-W01-A-1

Crispin Mode VR-41 Relief Check Valve Flanged Size

150 LB Carbon Steel With Resilient Seat.

W02

Work Orders (WO)

2-242150-013

2-359883-000

13-381325-001

15-399466

16-420373-000

05-273137-002

13-364867-000

13-381325-002

15-399467

16-420373-001

05-277630

13-376820-000

14-385969-000

15-401047-002

17-421126-000

07-295699

13-376820-000

14-385969-001

15-401047-005

17-423640-000

2-357898

13-376820-005

14-394162

15-404075-000

17-434455-000

2-357899

13-376846-000

15-396644-000

15-404395-000

17-434455-001

2-359817-000

13-381325-000

15-398783

15-409923-001

Miscellaneous

Number

Title

Revision

Date

NERC Interface Coordination Agreement for the Wolf

Creek Substation

April 28, 2018

015214

Applicability Determination

015214

50.59 Screen

07381

Gaskets and Bolting Change Package

A1-13

Miscellaneous

Number

Title

Revision

Date

14831

Applicability Determination

14831

10CFR 50.59 Screening

15040

Applicability Determination

15040

CFR 50.59 Screening

17-00365

Wolf Creek Generating Station, Unit 1 Safety

Evaluation Regarding Implementation of Mitigating

Strategies and Reliable Spent Fuel Pool

Instrumentation Related to Orders EA-12-049 and EA-

2-051

August 2, 2017

2012-0003

DCP 14016 10 CFR 50.59 Evaluation

BED for CR

46330 Rev. 1

Evaluation of Voids in Suction Piping for Auxiliary Feed

Water Pumps

BED for SWO 15-

401047-002 and

15-401047-005

Expected Life Evaluation for ESW Vacuum Breaker

Valves

March 10, 2016

E-009

Technical Specification for Metal-Clad Switchboard

E-020

Technical Specification for DC Distribution

Switchboards for the Standardized Nuclear Unit Power

Plant System (SNUPPS)

E-020

Specification: DC Distribution Switchboards

E-058

Technical Specification for 600 Volt Single & Multiple

Conductor Copper Power Cable for Wolf Creek Nuclear

Operating Corporation

E-10NB

System Description, Lower Medium Voltage System

4.16 kV (Class 1E Power System

E-10NE

System Description, Standby Power Supply System

E-10NF

System Description, Load Shedding and Emergency

Load Sequencing

E-10NK

System Description for 125-Volt DC System (Class 1E

Power System)

A1-14

Miscellaneous

Number

Title

Revision

Date

E-10PA

System Description, Higher Medium Voltage System

13.8 kV (Non-Class 1E Power System)

E-10PA

System Description for Higher Medium Voltage System

- 13.8 KV (Non-Class IE Power System)

EFV0482

IST Basis Report for Valve EF V0482

N/A

EFV0484

IST Basis Report for Valve EF V0484

N/A

EMG C-12

LOCA Outside Containment

ET-17-0003

Docket no. 50-482: Wolf Creek Nuclear Operating

Corporations Compliance Report for the

Implementation of Order EA-12-049

January 19, 2017

FD-SL-01-WC

Functional Description, Auxiliary Power System

LR1400302

Reactor Coolant Pumps (RCP)

LTR-RES-13-108 Input to an Operability Determination Associated with

the Shutdown Seal (SDS) Failure to Actuate During

Post-Service Testing

M-021-00061

Instruction Manual For Auxiliary Feedwater Pumps

W29

M-10AL

Auxiliary Feedwater System, System Description

M-10BB

Reactor Coolant System

M-10BB

System Description for Reactor Coolant Systems

M-10EF

System Description Essential Service Water System

M-712-00210

Use of Westinghouse Shield Passive Shutdown Seal

for Flex Strategies

MGE LT-006

Maintenance of Limotorque Valve Operators Type

SMB-0 Thru 4

NEI 12-06 [Rev 5] Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide

NEI 16-07

Improving the Effectiveness of Issue Resolution to

Enhance Safety and Efficiency

A1-15

Miscellaneous

Number

Title

Revision

Date

NK

System Health Report for 125 VDC (1E)

(July 1, 2017 -

December 31,

2017)

NRC Final Safety

Evaluation Report

Topical Report WCAP-17100-P/NP, REVISION 1,

PRA Model for the Westinghouse Shut Down Seal AL"

(PA-RMSC-0499) Pressurized Water Reactor Owners

Group, Project no. 694

April 29, 2011

NSAL-13-6

SHIELD Passive Thermal Shutdown Seal (SDS) Failure

to Actuate During Post-Service Test

July 26, 2013

OE NK-18-005

Operability Evaluation: NK001, NK002, NK003, NK004

25 VDC Bus Switchboard and Component

Downstream of the NK Bus Are Listed in Calculation

NK-E-001 Appendix E

July 31, 2018

OFN BB-031

Shutdown LOCA

OFN EJ-15

Loss of RHR Cooling

29B

ONF EJ-40

CL Recirculation During Mode 3, with Accumulator

Isolated in Mode 4, 5, or 6

PA

System Health Report for High-Medium Voltage 13.8

kV

(July 1, 2017 -

December 31,

2017)

PM FILE 49330

A RCP no. 3 Seal Leak-off Flush

n/a

QH-2018-1612

USAR Self-Assessment for 2018 DBAI

July 19,2018

REVISION TO

JLD-ISG-2012-01

Compliance with Order EA-12-049,

Order Modifying Licenses with Regard to

Requirements for Mitigation Strategies for

Beyond-Design-Basis External Events

SCA-05-0028

Safety Classification Analysis, NB Syst. Magna Blast

Breaker Elevating Mechanism Roller Assembly

System Health

Report

Reactor Coolant System (BB)

July 1, 2017 -

December 31,

2017

System Health

Report

Auxiliary Feedwater System AL, AP, FC-1

July 1, 2017 -

December 31,

2017

A1-16

Miscellaneous

Number

Title

Revision

Date

TDAFWP Test

Trends

IST Hydraulic and Vibration Trends for TDAFWP and

Screen Shots from Data Program

Various dates

WO 14-0023

Docket No. 50-482: Request for Schedule Relaxation of

NRC Order EA-12-049, Requirement lV.A.2, at Wolf

Creek Generating Station

March 31, 2014

ML18318A330

SUNSI Review

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: RAK

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

NAME

RKopriva

FThomas

IAnchondo

APalmer

TFarnholtz

NTaylor

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

DATE

11/01/18

10/26/18

10/23/18

11/02/18

11/05/18

11/12/18

OFFICE

NAME

TFarnholtz

SIGNATURE

/RA/

DATE

11/14/18