05000293/FIN-2018003-01 | 2018Q3 | Pilgrim | Failure to Identify an Adverse Condition Associated with Elevated Standby Gas Treatment System Accumulator Leakage |
05000456/FIN-2018002-03 | 2018Q2 | Braidwood | Inadequate Test Activity Coordination Results in Unintended Valve Actuation and Reactor Coolant System Pressure Drop |
05000348/FIN-2018002-02 | 2018Q2 | Farley | Failure to develop adequate PM for diesel generator relays |
05000410/FIN-2018002-01 | 2018Q2 | Nine Mile Point | Failure to Ensure Proper Control of the Standby Gas Treatment System Damper Valve, 2GTS*V2000B, Within Procedures, Materials, and Design Control Measures |
05000277/FIN-2018002-01 | 2018Q2 | Peach Bottom | Failure to Identify and Promptly Correct a Condition Adverse to Quality Concerning Battery Charger 2B-003-1 |
05000416/FIN-2018002-03 | 2018Q2 | Grand Gulf | Failure to Adequately Test NUS Temperature Switch |
05000250/FIN-2018001-01 | 2018Q1 | Turkey Point | Failure to conduct post maintenance testing in accordance with ASME OM code |
05000259/FIN-2018001-01 | 2018Q1 | Browns Ferry | Inadequate Post-Maintenance Testing of 4kV Breaker Stationary Switches |
05000265/FIN-2018001-02 | 2018Q1 | Quad Cities | Failure to Establish Design Standard for Unit 2 Residual Heat Removal Service Water Pumps |
05000341/FIN-2018001-01 | 2018Q1 | Fermi | Failure to Incorporate Vendor Recommendations into Maintenance Instructions on the Division 1 Control Complex Heating Ventilation and Air Conditioning Supply Fan Motor |