IR 05000482/2021003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000482/2021003 and Independent Spent Fuel Storage Installation Inspection Report 07200079/2021001, WC2021003 IR Ch
ML21302A194
Person / Time
Site: Peach Bottom, Wolf Creek  
Issue date: 11/05/2021
From: Greg Werner
NRC/RGN-IV/DRP
To: Reasoner C
Wolf Creek
References
IR 2021001
Download: ML21302A194 (25)


Text

SUBJECT:

WOLF CREEK GENERATING STATION - INTEGRATED INSPECTION REPORT 05000482/2021003 AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT 07200079/2021001

Dear Mr. Reasoner:

On September 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station. On October 7, 2021, the NRC inspectors discussed the results of this inspection with Mr. Jaime McCoy, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

NRC inspectors documented one finding of very low safety significance (Green) in the report that did not involve a violation of NRC requirements.

If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Wolf Creek Generating Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document November 5, 2021 Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gregory E. Werner, Chief Reactor Projects Branch B Division of Reactor Projects Docket Nos. 05000482 and 07200079 License No. NPF-42

Enclosure:

As stated

Inspection Report

Docket Number:

05000482 and 07200079

License Number:

NPF-42

Report Number:

05000482/2021003 and 07200079/2021001

Enterprise Identifier:

I-2021-003-0031 and I-2021-001-0007

Licensee:

Wolf Creek Nuclear Operating Corporation

Facility:

Wolf Creek Generating Station and Independent Spent Fuel Storage

Installation

Location:

Burlington, KS

Inspection Dates:

July 1, 2021 to September 30, 2021

Inspectors:

L. Brookhart, Senior Spent Fuel Storage Inspector

M. Davis, Trans And Storage Safety Inspector

M. Doyle, Operations Engineer

C. Henderson, Senior Resident Inspector

J. Melfi, Project Engineer

P. Patel, Structural Engineer

G. Pick, Senior Reactor Inspector

R. Rodriguez, Structural Engineer

E. Simpson, Health Physicist

C. Smith, Health Physicist

J. Vera, Resident Inspector

Approved By:

Gregory E. Werner, Chief

Reactor Projects Branch B

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection and an independent spent fuel storage installation inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Implement Critical Design Parameters for the Main Feedwater System During Digital Control System Modifications Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green FIN 05000482/2021003-01 Open/Closed

[H.12] - Avoid Complacency 71153 The inspectors reviewed a self-revealed, Green finding associated with the licensees failure to ensure balance of plant control system vendor used critical design parameters for the nonsafety-related main feedwater system bypass regulating valves in accordance with Procedure AI 05-005, Modifications to Non-Controlled [structures, systems, and components], Revision 5. Procedure AI 05-005 implemented the licensee self--imposed standard to control the main feedwater system as controlled plant equipment which required configuration-control to conform with Title 10 Code of Federal Regulations Part 50,

Appendix B rules and regulations. As a result, operators observed oscillating and divergent water levels in all four steam generators that caused an automatic reactor trip.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000482/2021-003-00 Automatic Reactor Trip Due to Low Steam Generator Level 71153 Closed

PLANT STATUS

Wolf Creek Generating Station began the inspection period at full power. On August 18, 2021, an automatic reactor trip from 100 percent reactor occurred due to a loss of main feedwater flow to the B steam generator caused by a stem separation of the B main feedwater regulating valve.

The licensee commenced Forced Outage 25-02 to repair the B main feedwater regulating valve and performed extent of condition reviews of the remaining three main feedwater regulating valves. On August 21, 2021, the unit commenced reactor startup, and the reactor was made critical. The unit was returned to full power on August 22,

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time onsite as local COVID-19 conditions permitted.

As part of their onsite activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D; conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk significant activities; and completed onsite portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and onsite. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Train B essential service water to emergency diesel generator jacket water and lube oil heat exchangers on July 9, 2021
(2) Train A electrical penetration cooling unit SGL15A on July 21, 2021
(3) Train A safety injection on September 23, 2021

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the component cooling water system on September 28, 2021.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Electrical penetration room A, fire area A-18, on July 21, 2021
(2) Electrical penetration room B, fire area A-17, on July 21, 2021
(3) Essential service water pump house pump room B, fire area essential service water B, on August 4, 2021
(4) Safety injection pump room B, fire area A-4, on September 8, 2021
(5) Safety injection pump room A, fire Area A-2, on September 23, 2021

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on July 20, 2021.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Train B engineering safety feature 4160volt switchgear (NB02) room on August 5, 2021

Cable Degradation (IP Section 03.02) (1 Sample)

The inspectors evaluated cable submergence protection in:

(1) Train B essential service water electrical cable manhole MHE5B inspection on August 31, 2021

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (2 Samples)

The inspectors evaluated readiness and performance of:

(1) Train B emergency diesel generator jacket water heat exchanger on July 16, 2021
(2) Train A component cooling water heat exchanger on September 10, 2021

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered on September 14, 2021.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during control rod movement and parking on August 12, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the annual licensed operator requalification exam on September 8, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Containment fan cooler supply breaker starter relay failures on August 5, 2021
(2) Adverse trend in valve program issues on September 7, 2021
(3) Safety injection system maintenance effectiveness review on September 23, 2021

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Train A essential service water manhole MHE3A and safety injection planned maintenance window on July 14, 2021
(2) Turbine driven auxiliary feedwater pump planned maintenance window on August 24, 2021
(3) Emergent work activities for a partial loss of power to train B balance of plant engineered safety feature actuation system cabinet SA036E during control room radiation monitor testing on September 3, 2021
(4) Emergency diesel generator A, 7-day planned maintenance window on September 14, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Train B turbine drive auxiliary feedwater essential feedwater suction check valve operability determination on July 7, 2021
(2) Trains A and B containment coolers with support system inoperable during maintenance operability determination on August 4, 2021
(3) Train B battery charger momentary voltage drop when starting emergency diesel generator B supply fan operability determination on September 10, 2021
(4) Emergency exhaust system damper failure to reclutch following maintenance past operability determination on September 16, 2021

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1) Ovation balance of plant digital control upgrade - main feedwater pump trip and turbine runback on September 10, 2021
(2) Manual operator actions with the emergency diesel generator paralleled with offsite power on September 16, 2021

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Train A safety injection pump and breaker maintenance post-maintenance testing on July 16, 2021
(2) Train A safety injection discharge header motor operated valve EMHV8812A post-maintenance testing on July 16, 2021
(3) Train B Emergency exhaust system non-radioactive tunnel supply downstream isolation damper, GLD0037, failure to reclutch following maintenance post-maintenance testing on July 23, 2021.
(4) Train A charging pump discharge header to boron injection tank isolation motor operated valve, EMHV8803A, packing adjustment post-maintenance testing on July 28, 2021.
(5) Main feedwater regulating valve B stem replacement post-maintenance testing on August 20, 2020
(6) Train A auxiliary feedwater pump and valve maintenance post-maintenance testing on September 22, 2021

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Train B component cooling water pumps B and D comprehensive inservice surveillance testing on July 8, 2021
(2) Trains A and B electrical penetration room cooler surveillance testing requirements on August 5, 2021
(3) Train A safety injection solid station protection system logic test on August 12, 2021

FLEX Testing (IP Section 03.02) (1 Sample)

(1) FLEX 500 kW diesel generator and reactor coolant system make up pump testing on September 7, 2021

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Emergency preparedness drill involving a complete loss of core exit thermocouple indication, loss of control room indications, and loss-of-coolant accident on August 18,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) July 1, 2020 through June 30, 2021

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1) July 1, 2020 through June 30, 2021

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) FLEX diesel generator testing operating experience on August 24, 2021
(2) Effectiveness of corrective actions related to the full implementation cyber security program inspection findings as described in NRC Cyber Security Inspection Report 05000482/2019410 (ML19268A037)

71153 - Follow Up of Events and Notices of Enforcement Discretion Event Followup (IP Section 03.01)

(1) The inspectors evaluated the reactor trip from 100 percent reactor power due to a loss of feedwater to steam generator B and licensees response on August 18, 2021.

Event Report (IP Section 03.02) (1 Sample)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000482/2021-003-00, "Automatic Reactor Trip Due to Low Steam Generator Level" (ADAMS Accession No. ML21193A078). The inspection conclusions associated with this LER are documented in this report under Inspection Results Section

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===60856 - Review of 10 CFR 72.212(b) Evaluations The inspection was conducted to determine if Wolf Creek Generating Station met the general license requirements of 10 CFR Part 72 before conducting operations to load their Independent Spent Fuel Storage Installation (ISFSI).

Review of 10 CFR 72.212(b) Evaluations===

(1) On August 16-19, 2021, the NRC conducted a team inspection of Wolf Creek Generating Station's 10 CFR Part 72 program implementation and 10 CFR 72.212 report prior to the licensee's first loading campaign, which is scheduled for the fall of 2021. Wolf Creek Generating Station has elected to become a 10 CFR Part 72 general licensee in accordance with 10 CFR 72.210. The licensee has selected the Transnuclear Americas LLC Nutech Horizontal Modular Storage Extended Optimized Storage (EOS) system. The licensee constructed the ISFSI storage pad in the spring of 2020 and built the EOS NUMHOMS in the fall of 2020, in accordance with the Transnuclear NUHOMS EOS Certificate of Compliance 72-1042, Amendment 1 and Final Safety Analysis Report, Revision 3.

The following programs, procedures, and calculations were inspected:

Site specific analysis that confirmed the licensee met the license conditions for flooding, lightning, blockage of inlet openings, off-normal temperature requirements, and snow and ice

Evaluation to confirm annual dose equivalent would meet 10 CFR 72.104 and 72.106 requirements

Evaluation under 10 CFR 50.59 of ISFSI's impact on the reactor facility and compliance to site's heavy load program Evaluation of the fuel building's crane to meet the criteria of NUREG 0554 Single-Failure-Proof Cranes for Nuclear Power Plants,"

Review of calculations for structural and seismic stability for the transfer cask on the fuel building crane and placement locations within the fuel building

Work orders and procedures that the fuel building's crane meets ASME B30.2 for load testing and annual maintenance requirements

Reviewed site's new Emergency Plan for inclusion of ISFSI specific emergencies

Evaluation of ISFSI impact on the reactor Quality Assurance Plan

Evaluation of the ISFSI's impact on the reactor facility's radiation protection plan

Training program for qualification of Part 72 operations within the fuel building

Training program and procedures for performing 10 CFR 72.48 evaluations

Training program qualification for the updated Emergency Plan with ISFSI specific requirements

Load testing and non-destructive testing records of special lifting devices used during loading operations

Fuel selection procedures to ensure fuel contents meet license conditions

Record retention program implementation for ISFSI records Remaining items that have yet to be fully reviewed include:

Site specific analysis confirming license conditions for tornados, earthquake, fire and explosions, normal environmental temperatures, and soil liquefaction

Matrix loading crane and roller trays structural and seismic analysis

Training documentation for qualification of Part 72 operations outside at the ISFSI pad

Review of site specific 10 CFR 72.48 changes, tests, and experiments

Finalized 10 CFR 72.212 report

INSPECTION RESULTS

Failure to Implement Critical Design Parameters for the Main Feedwater System During Digital Control System Modifications Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green FIN 05000482/2021003-01 Open/Closed

[H.12] - Avoid Complacency 71153 The inspectors reviewed a self-revealed, Green finding associated with the licensees failure to ensure balance of plant control system vendor used critical design parameters for the nonsafety-related main feedwater system bypass regulating valves in accordance with Procedure AI 05-005, Modifications to Non-Controlled SSCs, Revision 5.

Procedure AI 05-005 implemented the licensee self--imposed standard to control the main feedwater system as controlled plant equipment which required configuration-control toconform with Title 10 Code of Federal Regulations Part 50, Appendix B rules and regulations. As a result, operators observed oscillating and divergent water levels in all four steam generators that caused an automatic reactor trip.

Description:

During Refueling Outage (RF) 24, the licensee upgraded multiple nonsafety-related nuclear supply system control systems to the Ovation based distribution control system. These changes included new digital controls for the main feedwater system regulating valves and the associated bypass valves. The main feedwater system was a nonsafety-related SSC that was controlled in accordance with Procedure AI 05-005.

Procedure AI 05-005, Attachment A, classified the main feedwater system as controlled plant equipment. This designation implemented the self-imposed standard that configuration control for the main feedwater system conforms with 10 CFR Part 50, Appendix B rules and regulations. Therefore, the inspectors concluded the licensees self-imposed standard was to ensure modifications of the nonsafety-related main feedwater system to the Ovation based distribution control system was controlled in accordance with 10 CFR Part 50, Appendix B, Criterion III, which states, in part, that measures shall also be established for the selection and review suitability of application of material, parts, equipment, and processes that are essential to the safety-related functions of the structures, systems, and components.

On May 12, 2021, the licensee was performing a reactor startup following the completion of RF 24 when steam generator water levels began oscillating and diverging at approximately 8 percent reactor power while in automatic control. Operators took manual control of the main feedwater regulating bypass valves but were unable to restore levels prior to a steam generator low level automatic reactor trip. The cause of the automatic reactor trip was the low-power controller gains for the main feedwater bypass regulating valves were set too high. This led to a higher feedwater flow to the steam generators than needed for the feedwater system demand. This condition resulted in steam generator water level control instability causing oscillating and diverging water levels. The licensee entered this issue into their corrective action program as Condition Report 10005736, classified this a significant condition adverse to quality and performed a root cause evaluation. The root cause evaluation identified one root cause and one contributing cause associated with the automatic reactor trip that occurred on May 12, 2021. The root cause and contributing cause are as follows:

Root

Cause:

The licensees specific main feedwater bypass regulating valve characteristics and the impact of the feedwater control system designed were not fully recognized. This resulted in the incorrect control system tuning parameters and inadequate risk mitigation strategies for the initial power ascension following the implementation of the Ovation main feedwater digital control system. Specifically, the licensees vendor did not incorporate the stations main feedwater bypass regulating valve critical design parameters of a 4-inch bypass valve with a maximum flow coefficient of 150 for determining the initial tuning parameters for the valves during the Ovation upgrade. Instead, the vendor used a 6-inch bypass valve with a flow coefficient near double the value of the stations bypass valve flow coefficient. This resulted in the low-power controller gain values for the main feedwater bypass regulating valves being set too high. These parameters resulted in the steam generator water level control instability causing oscillating and diverging water levels, resulting in the May 12, 2021, automatic reactor trip.

Contributing cause: Throughout the Ovation modification design and implementation process, there was inadequate risk recognition and advocacy which resulted in missed opportunities for leaders to engage cross-functionally and make key decisions. For example, the licensees initial just-in-time training for the Ovation system modification was based on an analysis of training needs and focused on performing the reactor startup activities with the Ovation system. However, the licensee concluded the possible failures of all main feedwater bypass regulating valves, with oscillating and diverging steam generator water levels at low power, was not determined to be a likely failure even though it occurred on the plant training simulator. This similar event occurring on the plant training simulator provided the licensee with an opportunity to validate the vendor used the correct main feedwater system critical design parameters and their conclusion the plant training simulator was not comparable to the anticipated plant response when implementing the new main feedwater digital control system.

The inspectors reviewed the above information and concluded the licensee failed to implement the self-imposed standard to control the main feedwater system as a controlled plant equipment in accordance with Procedure AI 05-005. Specifically, the licensee failed to ensure the balance of plant control system vendor used critical design parameters for the main feedwater system bypass regulating valves.

Corrective Actions: The licensee implemented the following immediate corrective actions: 1. The initial controller gain values were updated for the main feedwater bypass regulating valves using the stations critical design parameters prior to commencing reactor startup on May 14, 2021; 2. The licensee performed additional just-in-time training to ensure licensed operators were familiar with manual digital control system for the main feedwater bypass regulating valves prior to the May 14, 2021 reactor startup. The corrective action to prevent recurrence was to update design drawings with a caution that a change to the valve critical design parameters could impact the Ovation feedwater control logic.

Corrective Action References: Condition Report 10005736

Performance Assessment:

Performance Deficiency: The licensees failure to ensure balance of plant control system vendor used critical design parameters for the main feedwater system bypass regulating valves was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Design Control attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the licensees failure to use the main feedwater system bypass regulation valve critical design parameters during balance of plant control system modification resulted in oscillating and divergent water levels in all four steam generators resulting in an automatic reactor trip.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 1, Section B.

The inspectors determined the finding was of very low safety significance (Green) because the finding did cause a reactor trip, but not the loss of mitigation equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition (e.g., loss of condenser, loss of feedwater).

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, the licensee failed to validate the vendor design control parameters for the main feedwater system bypass regulating valves and reevaluate the risk associated with oscillating and diverging water levels in all four steam generators, even when plant training simulator indicated the potential of this event to occur.

Enforcement:

Inspectors did not identify a violation of regulatory requirements associated with this finding.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On July 28, 2021, the inspectors presented the cyber security problem identification and resolution inspection results to Mr. L. Lane, Director Strategic Engineering and other members of the licensee staff.

On September 14, 2021, the inspectors presented the Wolf Creek 2021 annual requalification inspection results to Mr. A. Servaes, Regulatory Exam Writer and other members of the licensee staff.

On October 7, 2021, the inspectors presented the integrated inspection results to Mr. J. McCoy, Site Vice President and other members of the licensee staff.

On October 7, 2021, the inspectors presented the Independent Spent Fuel Installation 72.212 Inspection results to Mr. C. Reasoner, Chief Executive Officer and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60856

Engineering

Evaluations

50.59 Document

Number 15044

Cask Handling Crane NUREG 0554/0612 Compliance

Safety Analysis Report

60856

Engineering

Evaluations

BED WO 21-

468230-001

Characterization of Fuel Assemblies and Control

Components Discharged through RF22

07/27/2021

60856

Engineering

Evaluations

Calc 30501-0506

NUHOMS HSM-MX Dose Rates and ISFSI Site Dose

Analysis

60856

Engineering

Evaluations

HG-C-003

Stability of Loaded Transfer Cask in all Planned

Configurations in the Fuel Building

60856

Engineering

Evaluations

HG-C-006

Heavy Loads Summary for Pool-to-Pad Operational

Evolutions

60856

Engineering

Evaluations

KE-C-019

Crane Structural Analysis and Trolley Evaluation

60856

Procedures

AI 19C-001

Dry Cask Storage Loading Plan

60856

Procedures

AP 06-002

Radiological Emergency Response Plan

60856

Procedures

APF 06-002-02

Emergency Action Levels Technical Bases

71111.04

Calculations

GL-M-002

Calculate Tube Plugging Allowance for Aerofin (Cu-Ni) Coils

for Electrical Penetration Room Coolers (SGL15A and

SGL15B)

71111.04

Calculations

KJ-M-015

EKJ06A/B Thermal Performance Calculation

71111.04

Calculations

KJ-M-017

Emergency Diesel Standby Generator (KKJ01 BB) Runtime

without ESW Flow

71111.04

Calculations

XX-M-005

Evaluation of the UHS Maximum Temperature to Exceed

95F Design Basis Temperature Short Periods during the 30

Day Following a DBA

71111.04

Calculations

XX-M-068

Tube Plugging Criteria for Safety-Related Room Cooler

(Aerofin AL6XN) Cooling Coils

71111.04

Corrective Action

Documents

Condition Reports

10006569, 10007097, 10007129, 10007128

71111.04

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10007353

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Drawings

E-13KJ03B

Schematic Diagram Diesel Generator KKJ01B Engine

Control (D/G Trips)

71111.04

Drawings

M-12EF01

Piping Instrumentation Diagram Essential SVC Water

System

71111.04

Drawings

M-12EF02

Piping and Instrumentation Essential SVC Water System

71111.04

Drawings

M-12EG01

Piping & Instrumentation Diagram Component Cooling

Water System

71111.04

Drawings

M-12EG02

Piping & Instrumentation Diagram Component Cooling

Water System

71111.04

Drawings

M-12EG03

Piping & Instrumentation Diagram Component Cooling

Water System

71111.04

Drawings

M-12GL01

Piping and Instrumentation Diagram Auxiliary Building HVAC

71111.04

Drawings

M-12KJ04

Piping and Instrumentation Diagram Standby Diesel

Generator B Cooling Water System

71111.04

Drawings

M-12KJ06

Piping and Instrumentation Diagram Standby Diesel

Generator B Lube Oil System

71111.04

Engineering

Changes

CCP 012774

EKJ06A/B Replacement Jacket Water Heat Exchangers

71111.04

Miscellaneous

E-1F9915

Design Basis Document for OFN PR-017, Control Room

Evacuation

71111.04

Procedures

AP 21G-001

Control of Locked Components Status

78A

71111.04

Procedures

CKL EF-120

Essential Service Water Valve, Breaker and Switch Lineup

56B

71111.04

Procedures

CKL EG-120

Component Cooling Water System Valve Switch and

Breaker Lineup

71111.04

Procedures

OFN RP-017

Control Room Evacuation

71111.04

Procedures

STN EF-022B

ESW Train B Post-LOCA Flow Balance

2A

71111.04

Procedures

STN PE-037B

ESW Train B Heat Exchanger Low and DP Trending

71111.04

Work Orders

WO

17-432437-006

71111.05

Corrective Action

Documents

Condition Report

10007600

71111.05

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10009053

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05

Drawings

M-12LF02

Piping and Instrumentation Diagram Auxiliary Building Floor

and Equipment Drain System

71111.05

Drawings

M-12LF04

Piping and Instrumentation Diagram Auxiliary Building Floor

and Equipment Drain System

71111.05

Miscellaneous

E-1F9905

Fire Hazard Analysis

71111.05

Miscellaneous

E-1F9910

Post Fire Safe Shutdown Area Analysis

71111.05

Procedures

AP 10-106

Fire Preplans

71111.06

Calculations

FL-08

Control Building Flooding

71111.06

Corrective Action

Documents

Condition Reports

10004542, 10005554

71111.06

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10008129

71111.06

Drawings

E-11NG20

Sheet 11

MCC-NG02A

238

71111.06

Drawings

M-12EF01

Piping Instrumentation Diagram Essential SVC Water

System

71111.06

Drawings

M-12KC02

Piping and Instrumentation Diagram Fire Protection System

71111.06

Drawings

M-12LE02

Piping and Instrumentation Diagram Control and Diesel Gen.

Bldg. Oily Waste System

71111.06

Drawings

M-1G051

Equipment Locations Control and Diesel Gens BLDFS and

Comm. Corridor Plan EL. 2000-00 and EL. 2016-00

71111.06

Miscellaneous

BAP-21-0353

Barrier Authorization Permit

71111.06

Miscellaneous

WCRE-035

Boundary Matrix

71111.06

Procedures

AI 21-016

Operator Time Critical Actions Validation

71111.06

Procedures

ALR 00-008B

Serv WTR Press HI LO

71111.06

Procedures

ALR 00-049E

CTRL BLD OW Sump Level Hi

71111.06

Procedures

ALR 00-055A

ESW PMP A Press LO

11A

71111.06

Procedures

AP 21-004

Operator Response Time Program

4C

71111.06

Procedures

OFN SG-003

Natural Events

71111.06

Work Orders

WO

17-427039-000

71111.07A

Calculations

KJ-M-011

EKJ03A/B Thermal Performance Calculation

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.07A

Calculations

KJ-M-015

EKJ06A/B Thermal Performance Calculation

71111.07A

Corrective Action

Documents

Condition Reports

107702, 107706, 137997, 138950, 145929, 145940,

10002803, 10003532, 10003541, 10003543, 10003585,

10003642, 10003654, 10003697, 10003826, 10004111,

10004152, 10004284, 10004325, 10004276, 10004495

71111.07A

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10004457

71111.07A

Drawings

M-1HX001

Heat Exchanger Tube Sheet Maps

71111.07A

Miscellaneous

M-018E

Design Specification for Replacement Jacket Water Heat

Exchangers ASME Code Section III Class 3

71111.07A

Procedures

AP 23L-002

Heat Exchanger Program

71111.07A

Procedures

STN PE-037B

ESW Train B Heat Exchanger Flow and DP Trending

71111.07A

Work Orders

WO

16-418115-000, 17-433842-000, 18-447320-000,

19-440206-000, 19-451425-000, 19-456598-000,

20-457635-000, 20-458813-000, 20-458813-002,

20-461902-000, 20-464226-000

71111.11A

Miscellaneous

Wolf Creek ARQ

exam results

Wolf Creek ARQ exam results

09/14/2021

71111.11Q

Procedures

STN SF-001

Control Rod Parking

21A

71111.11Q

Work Orders

WO

21-468846-000

71111.12

Calculations

SA-88-015

Determination of the SI Flowrate under HL Injection Mode

71111.12

Corrective Action

Documents

Condition Reports

109647, 110725, 123103, 125945, 127042, 134338, 134339,

141615, 10001654, 10005727, 10006141, 10006569,

10007097, 10007128, 10007387, 10007433, 10007439,

10008024, 10008863

71111.12

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

10007665, 10008147, 10009043

71111.12

Drawings

M-12BB01

Piping and Instrumentation Diagram Reactor Coolant

System

71111.12

Drawings

M-12EM01

Piping and Instrumentation Diagram High Pressure Coolant

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Injection System

71111.12

Drawings

M-12EP01

Piping and Instrumentation Diagram Accumulator Safety

Injection

71111.12

Engineering

Changes

DCP 020393

EDG Supply Fan Motor Starters Replacement

71111.12

Miscellaneous

E-018-00189

Qualification and Test Summary Report

11W

71111.12

Miscellaneous

EDSD-I

Equipment Qualification Design Basis Document

71111.12

Miscellaneous

M-000

Mechanical/Nuclear Design Criteria for Wolf Creek

Generating Station

71111.12

Miscellaneous

WCOP-02

Inservice Testing Program for Pumps, Valves, and Snubbers

71111.12

Procedures

AI 29B-002

Check Valve Condition Monitoring Program

8A

71111.12

Procedures

ELE-007

NG001T - NG004T Motor Control Center Inspection,

Cleaning and Testing

71111.12

Procedures

EM-M-036

Establishment of the Safety Injection Pump Comprehensive

Test Error Allowance and Minimum Operability Limit Curve

71111.12

Procedures

STS CV-103

Inservice Testing Check Valve Condition Monitoring for

BB8949A/B/C/D

71111.12

Procedures

STS CV-210A

ECCS SI Comprehensive Pump and Inservice Check Valve

Test

71111.12

Procedures

STS EJ-209A

Train A RHR System Inservice Valve Test

71111.12

Procedures

STS EJ-209B

Train B RHR System Inservice Valve Test

71111.12

Procedures

STS PE-019E

RCS Isolation Check Valve Leak Test

71111.12

Procedures

SYS GN-120

Containment Cooling System Operation

71111.12

Work Orders

WO

13-374331-000, 18-440567-009, 20-462172-000

71111.13

Calculations

NAI-1878-001

Wolf Creek HELB Analysis

71111.13

Corrective Action

Documents

Condition Reports

84848, 10008360, 10008523, 10008827, 10008829,

10009004, 10009065, 10009124

71111.13

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10008652

71111.13

Drawings

J-104-00390

Logic Block Diagram ESFAS

W08

71111.13

Drawings

KD-7496 Sheet 1

One Line Diagram

71111.13

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

System

71111.13

Miscellaneous

BAP-21-0349

Breach Authorization Permit TDAFW TESO Work

71111.13

Miscellaneous

EQSD-I

Equipment Qualification Design Basis Document

71111.13

Miscellaneous

WCRE-35

Boundary Matrix

71111.13

Procedures

AI 22C-013

Protected Equipment Program

23A

71111.13

Procedures

AP 10-104

Breach Authorization

71111.13

Procedures

AP 22C-003

On-Line Nuclear Safety and Generation Risk Assessment

71111.13

Procedures

AP 22C-007

Risk Management and Contingency Planning

71111.13

Procedures

AP 22C-008

Qualitative Risk Management

71111.13

Procedures

EMG C-0

Loss of All AC Power

71111.13

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.13

Procedures

EMG ES-02

Reactor Trip Response

71111.13

Procedures

EMG FR-H1

Response to Loss of Secondary Heat Sink

71111.13

Procedures

OFN NB-030

Loss of AC Emergency Bus NB01 (NB02)

39A

71111.13

Procedures

STS IC-455B

Channel Calibration Control Room Air Intake Radiation

Monitor GK RE-0004

18A

71111.13

Procedures

SYS AP-122

Non-Safety Aux Feed Pump Operation

71111.13

Procedures

SYS SY-120

Sharpe Diesel Operation and Alignment to Site

14A

71111.13

Work Orders

WO

20-466623-001, 20-458883-018, 21-474284-000

71111.15

Calculations

EF-M-80

UHS Inventory Losses form ESW through the AFW System

71111.15

Calculations

GL-M-005

Electrical Penetration Room Temperature with Inoperable

Room Cooler

71111.15

Calculations

HV-288

Loss of Ventilation

71111.15

Corrective Action

Documents

Condition Reports

10007131, 10007263, 10007622

71111.15

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10009180

71111.15

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71111.15

Engineering

Changes

CCP 09816

Inoperable Electrical Penetration Room Cooler (SGL15A/B)

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Miscellaneous

E-018-00189

Qualification and Test Summary Report

11W

71111.15

Miscellaneous

EQSD-I

Equipment Qualification Design Basis Document

71111.15

Miscellaneous

EQSD-II

Equipment Qualification Design Basis Document

71111.15

Miscellaneous

WCRE-34

Fourth 10-Year Interval Inservice Testing Basis Document

71111.15

Procedures

AP 26C-004

Operability Determination and Functionality Assessment

71111.15

Procedures

MPE RC-001

Room Cooler Maintenance

71111.15

Procedures

MPE VD-001

27A Ventilation Damper Maintenance

71111.15

Procedures

SYS GL-200

Inoperable Penetration Room Cooler

13A

71111.15

Procedures

SYS OQT-001B

Operations B Train Quarterly Tasks

71111.15

Work Orders

WO

20-466019-000, 20-466019-001

71111.18

Calculations

GM-M-002

Diesel Generator Building Minimum Room Temperature

71111.18

Calculations

KJ-M-017

Emergency Diesel Standby Generator (KKJ01 BB) Runtime

without ESW Flow

71111.18

Corrective Action

Documents

Condition Reports

10003002, 10003106, 10003334, 10003523, 10003525,

10003731, 10004244, 10004269, 10007567

71111.18

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

10007846, 10008687

71111.18

Miscellaneous

M-018-00155

Operation of Engine without Cooling Water

71111.18

Procedures

ALR 00-120A

MFP A Trip

71111.18

Procedures

ALR 00-123A

MFP B Trip

71111.18

Procedures

ALR 00-123A

MFP B Trip

71111.18

Procedures

BD-EMG E-0

Reactor Trip or Safety Injection

29A

71111.18

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.18

Procedures

MFP A Trip

MFP A Trip

71111.18

Procedures

OFN EF-033

Loss of Essential Service Water

71111.18

Procedures

OFN NB-042

Loss of Offsite Power to NB01 (NB02) with EDG Paralleled

71111.19

Corrective Action

Documents

Condition Reports

10005026, 10007439, 10008456, 10008543

71111.19

Miscellaneous

WCOP-02

Inservice Testing Program for Pumps, Valves, and Snubbers

71111.19

Miscellaneous

WCRE-34

Fourth 10-Year Interval Inservice Testing Program

71111.19

Procedures

AI 23D-002

Motor Operated Valve Calculation Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.19

Procedures

AP 16E-002

Post Maintenance Testing Development

20A

71111.19

Procedures

AP 23D-001

Motor Operated Valve Program

71111.19

Procedures

MPM LT-001

Limitorque Operator Minor Maintenance, Lubrication, and

Inspection

71111.19

Procedures

STN EM-201

Safety Injection Valve Test

71111.19

Procedures

STS AE-211

Main Feed Reg Valve Inservice Test

71111.19

Procedures

STS AL-101

MDAFW Pump A Inservice Pump Test

71111.19

Procedures

STS EM-100A

Safety Injection Pump A Inservice Pump Test

71111.19

Procedures

STS VT-001

Verification of OMN-1, MOV Exercise Requirements

71111.19

Work Orders

WO

15-399593-001, 15-399593-018, 15-399593-021,

20-466803-000, 20-467625-000, 20-467625-001,

21-470469-000, 21-470469-001, 21-473455-007,

21-473455-008, 21-473455-013

71111.22

Calculations

FD-13-008

RCS FLEX Hydraulic Evaluation

71111.22

Corrective Action

Documents

Condition Reports

139748, 142288, 142515, 145234, 10000718, 10006728

71111.22

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10007983

71111.22

Miscellaneous

WCNOC-183

Operations and Maintenance Manual RCS Pump Cat Triplex

353 HS.AIP Plunger Pump rated 20 GPM @ 1650 psig

W01

71111.22

Procedures

AP 16E-002

Post Maintenance Testing Equipment

20A

71111.22

Procedures

AP 21A-002

Diverse and Flexible Coping Mitigating Strategies (FLEX)

Program

71111.22

Procedures

AP 23L-002

Heat Exchanger Program

71111.22

Procedures

STN PE-036

Safety Related Room Cooler Heat Transfer Verification and

Performance Trending

71111.22

Procedures

STN PE-037A

ESW Train A Heat Exchanger Flow and DP Trending

71111.22

Procedures

STN PE-037B

ESW Train A Heat Exchanger Flow and DP Trending

71111.22

Procedures

STS EG-101B

Component Cooling Water Pumps B/D Comprehensive

Pump Test

7B

71111.22

Procedures

STS IC-211

Actuation Logic Test Train A Solid State Protection System

37A

71111.22

Procedures

SYS FD-001

Operations Monthly FLEX Tasks

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.22

Procedures

SYS FD-002

Operations Annual FLEX Tasks

71111.22

Work Orders

WO

10-323422-000, 11-338649-000, 12-357297-000,

18-446961-000, 18-446961-001, 19-457078-005,

19-457425-000, 20-457635-000, 20-463186-002,

20-463186-010, 20-464266-000, 20-465658-000,

20-465658-002, 20-467211-000, 20-467211-001,

20-467213-000, 20-467458-000, 21-468259-000,

21-472930-000

71114.06

Corrective Action

Documents

Condition Reports

10008457, 10008465, 10008468

71114.06

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10008633

71114.06

Procedures

ALR 00-130C

ESF N2 ACC Press LoLo

71114.06

Procedures

ALR 00-130D

ESF N2 ACC Press Lo

71151

Corrective Action

Documents

Condition Report

10001662

71151

Miscellaneous

WCNOC-163

Mitigating System Performance Index Basis Document

71151

Procedures

FSG-05

Initial Assessment and FLEX Equipment Staging

71152

Calculations

DAR-PEUS-12-6

FLEX Electrical Conceptual Design for the Wolf Creek

Nuclear Operating Corporation

71152

Calculations

FD-E-001

FD System Electrical Calculations

71152

Corrective Action

Documents

Condition Reports

139748, 142288, 142515, 145234, 128958, 133406, 133814,

134405, 134406, 134409, 141390, 10003270, 10004822,

10000718

71152

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10007628

71152

Drawings

CYBER-C-0001

Cyber Security Network Block Diagram

E

71152

Miscellaneous

AC-VULN-

10003270

Windows Server 2003 and Windows XP Vulnerabilities

identified through CVEs

05/26/2021

71152

Miscellaneous

AIF 15D-028-08

Critical System Administrative Guide

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71152

Miscellaneous

LCM-20210405

SCS-LCM-202993.00, Security Computer System

71152

Miscellaneous

RC-VULN-

10003270

Windows Server 2003 and Windows XP Vulnerabilities

identified through CVEs

05/26/2021

71152

Miscellaneous

WCNOC-185

Beyond Design Basis Flex Equipment Operations and

Maintenance Manual 500 kW Generator C15 Model

W02

71152

Miscellaneous

WO 11-0019

Cyber Security Plan

71152

Procedures

AI 15D-020

Defense-in-Depth Cyber Security Protective Strategy

71152

Procedures

AI 15D-027

Ongoing Monitoring & Vulnerability Analysis (OM&VA)

71152

Procedures

AP 15D-008

Wolf Creek Cyber Security Program

71152

Procedures

FSG-08

Alternate RCS Boration

71152

Work Orders

WO

18-443033-001, 20-457258-000, 20-458235-000,

20-460439-000, 20-461349-000, 20-463623-000,

20-464828-000, 20-464837-000, 20-464838-000,

20-464839-000, 20-464840-000, 20-464840-000,

20-464842-000, 20-464843-000, 20-464844-000,

20-469726-000

71153

Corrective Action

Documents

Condition Report

10008456

71153

Procedures

EMG E-0

Reactor Trip or Safety Injection

71153

Procedures

EMG ES-02

Reactor Trip Response

71153

Work Orders

WO

21-473455-015, 21-473455-016, 21-473455-017,

21-473455-018